Movable Top Track Wall Frames for Faster Multi-Storey Construction

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Existing construction methods for multi-storey buildings require waiting for load-bearing walls and columns to cure before proceeding to the next stage, leading to inefficiencies and delays, especially in systems using precast concrete or permanent formwork, and do not meet fire resistance requirements without using concrete or masonry.

Innovation Solution

A method using a structural steel frame that temporarily supports the building load during curing, allowing simultaneous construction of internal and external walls, with a transfer of load to cured concrete columns once they achieve sufficient strength.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Reliability

If traditional masonry or precast concrete methods are used to meet fire resistance requirements, then fire resistance is improved, but construction time increases due to required curing periods

Engineering Contradiction:
Improvefire resistanceVSAvoidconstruction time
Core Design Contradiction:
ReliabilityVSLoss of time

Solution Approach 1:

The building structure is segmented into temporary steel frame components and permanent concrete column components. The steel frame provides immediate load-bearing capacity and fire resistance, while concrete columns are installed and cured in place to provide permanent structural support, allowing construction to proceed without waiting for full curing of load-bearing elements.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

A temporary steel frame acts as an intermediary load-bearing structure during construction. This steel frame temporarily carries the building loads while concrete columns are being installed and cured, enabling continuous construction progress without compromising structural integrity or fire resistance requirements.

Inventive Principle:
Principle #24Intermediary (Mediator)

2Reliability

If load-bearing walls are constructed using concrete or masonry to meet fire resistance standards, then fire resistance is improved, but construction productivity decreases due to sequential storey construction requirements

Engineering Contradiction:
Improvefire resistanceVSAvoidconstruction speed
Core Design Contradiction:
ReliabilityVSProductivity

Solution Approach 1:

The construction process is segmented into simultaneous activities: steel frame installation, concrete column pouring, and interior wall construction can all proceed concurrently on multiple storeys, eliminating the sequential curing wait times that traditionally limited productivity.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The steel frame is installed preliminarily to provide immediate fire-resistant load-bearing capacity, allowing subsequent concrete column installation and interior wall construction to proceed without delay. This preliminary action eliminates the need to wait for concrete curing before continuing construction.

Inventive Principle:
Principle #10Preliminary action

3Loss of time

If precast concrete panels are used to speed up construction, then construction time is reduced, but transport and handling costs and complexity increase

Engineering Contradiction:
Improveconstruction timeVSAvoidtransport and handling complexity
Core Design Contradiction:
Loss of timeVSDevice complexity

Solution Approach 1:

The structure is divided into lightweight steel frame components that can be easily transported and assembled, eliminating the need to handle heavy precast concrete panels. This segmentation maintains construction speed while reducing transport and handling complexity.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The temporary steel frame components are relatively inexpensive and easy to install/remove compared to heavy precast panels. These components serve their temporary purpose during construction and can be easily replaced or adjusted, reducing overall project complexity.

Inventive Principle:
Principle #27Cheap short-living objects (Disposable)

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

Enables rapid construction by allowing simultaneous work on multiple floors while columns cure, meeting fire resistance standards, and transitioning to concrete columns as the primary load-bearing elements upon completion.

Implementation Method 1

The channels are filled with a curable substance to form load bearing columns within the building frame. The transfer of load from the building frame to the cured columns is complete

Methodology Applied
Scientific EffectCuring:

Data Source

PatentEP3682065B1Building construction method
Publication Date: 2026.02.25 IAVILAER PTY LTD
  • EP3682065B1 patent drawingFigure 1
  • EP3682065B1 patent drawingFigure 2
  • EP3682065B1 patent drawingFigure 3

AI summary

A building construction method uses wall frames having a moveable top track. The track is fixed in a raised position so as to be load-bearing during construction, allowing construction work to progress quickly. When supporting concrete columns have cured, the fixing can be released allowing the track to move into a lowered position and for the building load to transfer to the columns.