Multilateral Intelligent Well Completion Segmentation

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Current multilateral well completion systems face challenges in independent monitoring and control of flow from lateral and primary boreholes, with potential damage to components and limitations in maximum production rate due to small completion tubing sizes and buckling issues.

Innovation Solution

A new completion architecture is introduced where lower completion equipment is deployed downhole in the lower lateral borehole and primary borehole, followed by intermediate and upper completion deployments, enabling electrical and hydraulic communication and allowing larger tubing sizes to maximize production while minimizing component damage and buckling risks.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Productivity

If smaller sized completion tubing is run downstream of the uppermost multilateral junction interface, then the maximum production rate is limited, but this approach is taken to avoid buckling issues during deployment and/or during the life of the well

Engineering Contradiction:
Improvemaximum production rateVSAvoidbuckling issues
Core Design Contradiction:
ProductivityVSReliability

Solution Approach 1:

The well completion system is divided into multiple segments: a first completion string in the first lateral borehole, a second completion string in the second lateral borehole, and a third completion string in the primary borehole. This segmentation allows each completion string to be independently sized and optimized, enabling larger tubing diameters in each lateral without requiring the entire downstream completion to be sized for the smallest lateral, thereby increasing production capacity while maintaining structural integrity.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The invention transitions from a traditional single-string completion architecture to a multi-string three-dimensional completion architecture. By deploying completion strings in multiple lateral boreholes that converge at a junction and connect to a primary borehole, the system creates additional spatial dimensions for tubing routing. This allows larger diameter tubing to be used in individual laterals without creating buckling issues along the entire downstream path, as each string is independently supported and sized.

Inventive Principle:
Principle #17Another dimension (Dimensionality change)

2Adaptability or versatility

If downhole flow control valves, permanent downhole gauges, downhole cables, and control lines are run through multilateral junctions, then independent monitoring and control is enabled, but this increases the potential for damage to such components due to very little clearance

Engineering Contradiction:
Improveindependent monitoring and controlVSAvoidpotential for damage to components
Core Design Contradiction:
Adaptability or versatilityVSObject-affected harmful factors

Solution Approach 1:

The completion system segments the routing of intelligent completion components into separate, dedicated paths. Flow control valves, gauges, cables, and control lines are installed within individual completion strings rather than being forced through tight multilateral junctions. This segmentation provides adequate clearance and protection for each component while maintaining the capability for independent monitoring and control of each lateral borehole.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The completion strings act as intermediary protective conduits between the intelligent completion components and the harsh well environment. By routing sensitive components through dedicated completion strings with sufficient internal diameter, the system provides mechanical protection and adequate clearance, reducing the potential for damage while still enabling full intelligent completion functionality at the multilateral junction.

Inventive Principle:
Principle #24Intermediary (Mediator)

3Productivity

If a new completion architecture with multiple completion strings is deployed, then larger tubing sizes can be used to maximize production, but this increases the complexity of the completion system

Engineering Contradiction:
Improveproduction ratesVSAvoidcompletion architecture
Core Design Contradiction:
ProductivityVSDevice complexity

Solution Approach 1:

The completion system is segmented into multiple independent completion strings, each optimized for its specific lateral borehole. This segmentation allows each string to use larger tubing sizes appropriate for its production requirements without affecting the other laterals. The modular nature of segmented completion strings simplifies deployment and maintenance compared to a single complex string, as each segment can be independently installed, sized, and replaced.

Inventive Principle:
Principle #1Segmentation

Data Source

PatentUS11959363B2Multilateral intelligent well completion methodology and system
Publication Date: 2024.04.16 SCHLUMBERGER TECH CORP
  • US11959363B2 patent drawing
  • US11959363B2 patent drawing

AI summary

A technique facilitates improving a completion architecture for a multilateral intelligent well completion (IWC). Effectively, a new and enhanced completion design and deployment approach is provided for multilateral IWCs. According to an embodiment, lower completion equipment is initially deployed downhole into a lower lateral borehole and lower section of a primary borehole. An intermediate completion may then be run downhole and into engagement with the lower completion equipment. Subsequently, an upper lateral borehole (or boreholes) may be drilled and completed. After drilling and completing the one or more upper lateral boreholes, an upper completion is deployed downhole and coupled with the intermediate completion in a manner which enables signal communication with downhole sections of the well.