Problem

Current measurement while drilling (MWD) systems face inefficiencies in transmitting survey data from the drill string to the surface, leading to reduced timeliness and increased costs due to the time-consuming nature of data transmission and potential inaccuracies in drill string positioning.

Innovation Solution

A MWD system comprising a downhole processor and communication module that determines whether the drill string is on or off a predetermined drill plan, transmitting non-compressed data if off the plan and compressed data if on the plan, utilizing optimization compression schemes to reduce data transmission time and improve accuracy.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Measurement precision

If survey data is transmitted continuously without compression, then data accuracy is maintained, but transmission time increases and timeliness deteriorates

Engineering Contradiction:
Improvedata accuracyVSAvoidtransmission time
Core Design Contradiction:
Measurement precisionVSLoss of time

Solution Approach 1:

The system dynamically changes the data transmission parameter (compression level) based on the drill string's position relative to the drill plan. When the drill string is on the drill plan, compressed data is transmitted to reduce transmission time. When off the drill plan, non-compressed data is transmitted to maintain full data accuracy for accurate positioning analysis.

Inventive Principle:
Principle #35Parameter changes

2Productivity

If data transmission is performed frequently to improve timeliness, then data freshness increases, but the time required for each transmission increases

Engineering Contradiction:
Improvedata transmission efficiencyVSAvoidtransmission time
Core Design Contradiction:
ProductivityVSLoss of time

Solution Approach 1:

The system applies partial data transmission by sending only the necessary data at each transmission event. When the drill string is on the drill plan, compressed (reduced) data is sent. When off the drill plan, full non-compressed data is sent. This partial action approach optimizes transmission efficiency while maintaining timeliness by adapting the data volume to the actual operational needs.

Inventive Principle:
Principle #16Partial or excessive action

3Measurement precision

If non-compressed data is transmitted to maintain positioning accuracy, then measurement precision is improved, but transmission duration increases

Engineering Contradiction:
Improvepositioning accuracyVSAvoidtransmission duration
Core Design Contradiction:
Measurement precisionVSDuration of action of moving object

Solution Approach 1:

The system dynamically adjusts the data compression level based on real-time drill string position relative to the drill plan. The downhole processor determines whether the drill string is on or off the drill plan and accordingly selects between compressed and non-compressed data transmission modes, optimizing both positioning accuracy and transmission duration adaptively throughout the drilling operation.

Inventive Principle:
Principle #15Dynamics

Data Source

PatentUS10590757B1Measurement while drilling communication scheme
Publication Date: 2020.03.17 ERDOS MILLER INC
  • US10590757B1 patent drawing
  • US10590757B1 patent drawing
  • US10590757B1 patent drawing

AI summary

A measurement while drilling system including a first module and a second module. The first module situated at a distal end of a drill string and including a downhole processor configured to determine that the drill string is one of on a drill plan and off the drill plan, and a downhole communication module communicatively coupled to the downhole processor to transmit signals. The second module situated at a proximal end of the drill string and including an uphole communication module configured to receive the signals. Where the downhole processor is configured to transmit non-compressed data if the drill string is off the drill plan and compressed data if the drill string is on the drill plan.