Shallow Sea Outfall Pipeline Mounting with Four-Pontoon Assembly

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The mounting of sea outfall pipelines in shallow sections is challenging due to their long distance, inaccessibility at low tide, and the need for precise construction during high tide, which complicates the installation process and increases costs.

Innovation Solution

A method utilizing four specially-designed pontoon apparatuses with hoisting supports, traction winches, and anchor windlasses to assemble pipeline sections within a pre-excavated foundation trench, allowing for precise positioning and disassembly of pipeline ends, reducing the need for companion ships and minimizing damage.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Productivity

If conventional mounting methods are used for sea outfall pipelines in shallow sections, then the pipeline can be installed, but the construction time is excessive and the available window period during high tide is insufficient

Engineering Contradiction:
Improvemounting efficiencyVSAvoidconstruction time
Core Design Contradiction:
ProductivityVSLoss of time

Solution Approach 1:

The pipeline is divided into multiple sections that can be pre-assembled on land and then mounted in sequence in the shallow sea section. The pontoon apparatus is also segmented into multiple units that can work cooperatively, allowing parallel operations and reducing overall construction time

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

Foundation trenches are pre-excavated in the shallow sea section before pipeline installation. Pipeline sections are pre-assembled with flanges and connection components on land, and the pontoon apparatus is pre-positioned and anchored before the actual pipeline mounting begins, maximizing the utilization of the limited high tide window period

Inventive Principle:
Principle #10Preliminary action

2Ease of operation

If pipeline sections are assembled in the shallow section with long distance, then the pipeline can be installed, but the mounting technique becomes quite difficult and requires high control

Engineering Contradiction:
Improvemounting easeVSAvoidmounting complexity
Core Design Contradiction:
Ease of operationVSDevice complexity

Solution Approach 1:

The pontoon apparatus serves as an intermediary platform between the land-based assembly area and the final pipeline position in the shallow sea. It provides a stable, floating workspace with integrated hoisting, traction, and positioning systems that simplify the complex operation of installing pipelines in difficult-to-reach shallow water areas

Inventive Principle:
Principle #24Intermediary (Mediator)

Solution Approach 2:

The pontoon apparatus is designed as a multi-functional device that combines hoisting support, traction winching, anchor positioning, and pipeline guidance capabilities in a single integrated platform. This universal device can handle various pipeline sections and mounting scenarios, reducing the need for multiple specialized equipment and simplifying the overall mounting process

Inventive Principle:
Principle #6Universality (Multi-functionality)

3Reliability

If the shallow section is inaccessible at low tide, then the pipeline can be protected from exposure, but construction can only be carried out during high tide resulting in a short available window period

Engineering Contradiction:
Improvepipeline protectionVSAvoidavailable window period
Core Design Contradiction:
ReliabilityVSDuration of action of moving object

Solution Approach 1:

Foundation trenches are pre-excavated and prepared before the high tide window begins. All pontoon apparatus are pre-positioned, anchored, and equipped with necessary tools and materials. Pipeline sections are pre-assembled on land with connection components ready, so that when high tide occurs, the mounting operation can begin immediately and be completed efficiently within the limited time window

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The pontoon apparatus enables continuous mounting operations during the high tide period without interruption. Multiple pontoons work in parallel to assemble different pipeline sections simultaneously. The coordinated operation of hoisting, traction, and positioning systems ensures that the pipeline installation process continues smoothly from start to finish within the available window period, maximizing productivity

Inventive Principle:
Principle #20Continuity of useful action

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

The method effectively addresses the installation challenges by ensuring structural safety, reducing construction time and costs, and minimizing environmental impact while maintaining pipeline quality.

Implementation Method 1

two pontoon bodies (10) are disposed in parallel at a spacing greater than a diameter of the sea outfall pipeline, so that there is a pipeline channel between the two pontoon bodies (10)

Methodology Applied
Scientific EffectBuoyancy: Archimedes' Principle (Buoyancy)

Implementation Method 2

the spreader includes two sets of sheave blocks, two hoisting winches, and one hoisting steel wire rope; fixed pulleys of the two sets of sheave blocks are suspended in one-to-one correspondence on the middles of bottom surfaces of the two longitudinal beams of the hoisting support respectively

Methodology Applied
Scientific EffectMechanical Advantage: Mechanical Advantage

Data Source

PatentUS20260036221A1Mounting method for sea outfall pipeline in shallow section
Publication Date: 2026.02.05 CCCC THIRD HARBOR ENGINEERING CO LTD
  • US20260036221A1 patent drawing
  • US20260036221A1 patent drawing
  • US20260036221A1 patent drawing

AI summary

Disclosed is a mounting method for a sea outfall pipeline in a shallow section, including a preparation process and a construction process. The preparation process includes a pipeline pre-submergence preparation step and a pontoon apparatus positioning step. At the pipeline pre-submergence preparation step, a female flange and a male flange are welded in one-to-one correspondence at two ends of a pipeline section, blind flanges are fixed to outer ends of the female flange and the male flange respectively. At the pontoon apparatus positioning step, from front to back, a first pontoon apparatus to a fourth pontoon apparatus are sequentially anchored and positioned at a certain spacing, the first pontoon apparatus and the fourth pontoon apparatus are used in one-to-one correspondence for dismounting the blind flanges at the two ends of the pipeline section, the second pontoon apparatus and the third pontoon apparatus are used for mounting the pipeline section.