Post-Tension Concrete Splice Device Reduces Slab Gap

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The conventional construction process of post-tensioned concrete slabs involves significant gaps between slabs, leading to delays in accessing and completing floors due to safety and weather conditions, as well as inefficiencies in tooling and equipment access, which prolongs construction time and exposes the area to weather.

Innovation Solution

A splice device is used to connect the rebars of adjacent post-tensioned concrete slabs, reducing the gap between them to a minimum distance equal to the length of the splice device, allowing for earlier access and completion of floors by eliminating the need for extensive waiting periods and protecting the area from weather conditions.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Ease of operation

If a large gap is maintained between post-tensioned concrete slabs to accommodate tooling and equipment for tensioning, then the tensioning process can be completed, but the construction time is prolonged and the area remains exposed to weather conditions

Engineering Contradiction:
Improveaccess to slabs for tensioningVSAvoidconstruction time
Core Design Contradiction:
Ease of operationVSLoss of time

Solution Approach 1:

The construction process is divided into distinct phases: first pouring slabs with protruding rebars, then tensioning them separately while maintaining a gap, and finally connecting them via splicing. This segmentation allows each slab to be tensioned independently without requiring a large continuous gap, reducing the time the area remains exposed.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

Rebars are positioned to protrude from the slabs before tensioning occurs. This preliminary positioning of connection elements allows the slabs to be tensioned independently and then quickly connected afterward, eliminating the need to maintain a large gap throughout the entire construction process.

Inventive Principle:
Principle #10Preliminary action

2Ease of operation

If a large gap is maintained between slabs to allow worker access and equipment operation, then tensioning can be performed, but safety risks and weather exposure increase

Engineering Contradiction:
Improveworker access and equipment operationVSAvoidweather conditions and safety risks
Core Design Contradiction:
Ease of operationVSObject-affected harmful factors

Solution Approach 1:

By dividing the construction into separate slab pours that are tensioned independently and then connected, the gap needed during tensioning is minimized. This reduces the area exposed to weather and safety hazards while still allowing necessary operations to occur.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The protruding rebars serve as intermediary connection elements that allow the slabs to be joined after independent tensioning. This eliminates the need for a large permanent gap, reducing weather exposure and safety risks while maintaining operational capability.

Inventive Principle:
Principle #24Intermediary (Mediator)

3Ease of manufacture

If slabs are poured separately and tensioned independently, then each slab can be constructed autonomously, but the rebars do not align axially and require a longer gap

Engineering Contradiction:
Improveindependent slab constructionVSAvoidgap length
Core Design Contradiction:
Ease of manufactureVSLength of stationary object

Solution Approach 1:

Rebars are positioned to protrude from each slab before tensioning, with their positions predetermined to ensure proper alignment after tensioning. This preliminary positioning allows independent slab construction while maintaining rebar alignment, eliminating the need for an extended gap.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The alignment function is transferred from the gap structure to the protruding rebar positioning system. By using the rebar positions as the alignment mechanism rather than relying on gap width, the slabs can be constructed independently with minimal gap while ensuring proper axial alignment during splicing.

Inventive Principle:
Principle #28Mechanics substitution (Replace mechanical system)

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

This solution reduces construction time by enabling earlier access to all areas of the floor and preventing weather intrusion, thereby streamlining the construction process and enhancing project efficiency.

Implementation Method 1

The applied stress (e.g., forces applied to the wire strand system) in the post-tensioning process causes a volume change (and/or a length change) to the concrete material.

Methodology Applied
Scientific EffectVolume change:

Implementation Method 2

The grout material bonds the wire to the duct, and the duct is bonded to the cured concrete. Thus, the stress applied to the wire can be transferred to the concrete.

Methodology Applied
Scientific EffectBonding: Adhesive

Data Source

PatentUS9404254B2Post-tension concrete leave out splicing system and method
Publication Date: 2016.08.02 3JR LLC
  • US9404254B2 patent drawing
  • US9404254B2 patent drawing
  • US9404254B2 patent drawing

AI summary

Devices, systems, and methods for constructing post-tensioned concrete slabs in a new floor construction that has a reduced gap distance between the slabs. The devices, systems, and methods can improve project construction time by reducing the time delay in accessing the floor underneath the slabs due to safety and/or weather conditions.