Post-Tension Concrete Slab Splicing Using Segmented Cavity Devices

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Conventional post-tensioned concrete slab construction requires significant gaps between slabs, leading to delays in construction due to access limitations and exposure to weather conditions, as well as inefficiencies in the alignment and connection of rebars.

Innovation Solution

A method and system involving cavity-forming devices that reduce the gap between post-tensioned concrete slabs by allowing rebars to be connected through these devices, which are filled with binding material to secure the slabs together, enabling faster construction and improved structural integrity.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Reliability

If a large gap is maintained between post-tensioned concrete slabs to accommodate tooling and equipment for tensioning, then the tensioning process can be properly performed, but construction time is significantly delayed and workers are exposed to weather conditions

Engineering Contradiction:
Improvetensioning process capabilityVSAvoidconstruction time
Core Design Contradiction:
ReliabilityVSLoss of time

Solution Approach 1:

The gap between slabs is segmented into two functional zones: a first gap portion for accessing rebars during pouring and a second gap portion for tensioning operations. This segmentation allows different equipment and workers to operate simultaneously in different portions of the gap, reducing overall construction time while maintaining necessary access for both pouring and tensioning processes.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

Rebars are positioned and extended into the gap before the slab is poured and cured. This preliminary positioning allows the rebars to be ready for connection before tensioning begins, eliminating the need to wait after pouring before starting tensioning operations, thus reducing construction time delays.

Inventive Principle:
Principle #10Preliminary action

2Reliability

If a large gap is maintained between post-tensioned concrete slabs to allow access for tensioning equipment, then proper tensioning can be achieved, but the gap becomes longer during and after tensioning causing further access problems

Engineering Contradiction:
Improvetensioning process capabilityVSAvoidgap length
Core Design Contradiction:
ReliabilityVSLength of stationary object

Solution Approach 1:

The gap is divided into a first gap portion and a second gap portion, where the first portion maintains relatively stable length for rebar access and the second portion accommodates the lengthening that occurs during tensioning. This segmentation isolates the lengthening effect to a specific zone that does not interfere with rebar access areas.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

Different portions of the gap have different functional requirements: the first gap portion is optimized for rebar access and connection with relatively constrained dimensions, while the second gap portion is designed to accommodate tensioning equipment and the lengthening that occurs during post-tensioning operations.

Inventive Principle:
Principle #3Local quality

3Strength

If rebars from adjacent slabs are to be aligned and connected, then structural continuity is achieved, but the misalignment of rebars due to independent tensioning of each slab creates connection difficulties

Engineering Contradiction:
Improvestructural continuityVSAvoidrebar connection ease
Core Design Contradiction:
StrengthVSEase of manufacture

Solution Approach 1:

Rebars are positioned and extended into the gap before the slab is poured and cured, and before tensioning occurs. This preliminary positioning establishes the rebar locations in advance, ensuring that when the slabs are later tensioned and the gap lengthens, the rebars remain properly aligned and ready for connection without requiring complex adjustment procedures.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The rebar connection process is segmented into distinct phases: positioning during pouring, securing after curing, and final connection after tensioning. This segmentation allows each phase to be optimized independently, making the overall connection process easier despite the independent tensioning of adjacent slabs.

Inventive Principle:
Principle #1Segmentation

4Productivity

If the gap between slabs is reduced to minimize construction delays, then construction time is improved, but adequate access for tensioning equipment and workers is compromised

Engineering Contradiction:
Improveconstruction speedVSAvoidaccess for equipment and workers
Core Design Contradiction:
ProductivityVSEase of operation

Solution Approach 1:

The gap is segmented into a first gap portion providing access for rebar positioning and connection, and a second gap portion providing access for tensioning equipment. This segmentation allows the overall gap to be smaller than traditional gaps while still providing adequate access for both pouring operations and tensioning operations through different portions of the segmented gap.

Inventive Principle:
Principle #1Segmentation

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

This approach reduces construction time by minimizing access delays and weather exposure, while ensuring robust connections between slabs, thus enhancing the efficiency and speed of the construction process.

Implementation Method 1

grout material (e.g., a mixture of cement, sand, aggregate, and water) is pumped into the cavity surrounding the wire. The grout material bonds the wire to the duct, and the duct is bonded to the cured concrete.

Methodology Applied
Scientific EffectGrout material bonding: Adhesive

Data Source

PatentUS10689853B2Post-tension concrete leave out splicing system and method
Publication Date: 2020.06.23 REIGSTAD & ASSOC
  • US10689853B2 patent drawing
  • US10689853B2 patent drawing
  • US10689853B2 patent drawing

AI summary

Devices, systems, and methods for constructing post-tensioned concrete slabs in a new floor construction that has a reduced gap distance between the slabs. The devices, systems, and methods can improve project construction time by reducing the time delay in accessing the floor underneath the slabs due to safety and/or weather conditions.