Post-Tensioned Concrete Beam Foundation for Wind Turbines

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Conventional wind turbine foundations require excessive amounts of concrete, lead to inefficient construction processes, and are prone to thermal cracking, resulting in high costs, material waste, and compromised structural integrity due to environmental and logistical challenges.

Innovation Solution

A foundation system utilizing pre-cast high-strength beams and soil anchors, which reduces concrete usage, improves heat dissipation, and employs a hub assembly with post-tensioning cables for rapid deployment and enhanced stability, minimizing environmental impact and construction time.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Stability of the object's composition

If conventional spread foundations with massive concrete pours are used, then foundation stability is achieved, but concrete consumption increases excessively and construction time extends significantly

Engineering Contradiction:
Improvefoundation stabilityVSAvoidconcrete consumption
Core Design Contradiction:
Stability of the object's compositionVSQuantity of substance

Solution Approach 1:

The foundation is divided into multiple pre-cast concrete piles (typically 4-8 piles) arranged in a circular or square pattern, replacing the monolithic concrete pour. Each pile is independently manufactured off-site and installed separately, reducing total concrete volume while maintaining stability through distributed load bearing.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

Concrete piles are pre-cast in controlled off-site facilities before delivery to the installation location. This preliminary manufacturing allows for quality control, optimized concrete usage, and parallel production multiple piles simultaneously, reducing on-site construction time and material waste.

Inventive Principle:
Principle #10Preliminary action

2Stability of the object's composition

If massive concrete pours are performed on-site, then foundation mass is achieved for stability, but construction complexity and resource mobilization increase significantly

Engineering Contradiction:
Improvefoundation massVSAvoidconstruction complexity
Core Design Contradiction:
Stability of the object's compositionVSDevice complexity

Solution Approach 1:

The monolithic foundation is segmented into multiple standardized pre-cast piles with uniform dimensions and reinforcement patterns. This standardization simplifies manufacturing, transportation, and installation processes, reducing construction complexity while achieving the required foundation mass through the combined weight of multiple piles.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The pre-cast piles are designed with self-contained reinforcement cages and bearing capacities that do not require complex on-site assembly or additional reinforcement work. Each pile is a complete, ready-to-install unit that requires minimal site preparation and no sophisticated coordination during installation.

Inventive Principle:
Principle #25Self-service

3Stability of the object's composition

If large volumes of concrete are poured in one continuous pour, then foundation integrity is maintained, but logistical coordination and risk of cold joints increase

Engineering Contradiction:
Improvefoundation integrityVSAvoidlogistical efficiency
Core Design Contradiction:
Stability of the object's compositionVSProductivity

Solution Approach 1:

The foundation is divided into multiple separate pre-cast piles rather than one continuous pour. Each pile is manufactured independently in controlled facilities, eliminating the need for complex logistical coordination of multiple concrete trucks and workers simultaneously. The segmented installation process allows for better quality control and eliminates cold joint risks.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

Concrete piles are pre-cast and cured to full strength before delivery to the site. This preliminary action transfers the concrete pouring and curing process from the busy construction site to the manufacturing facility, where logistics can be managed more efficiently and quality can be assured before installation.

Inventive Principle:
Principle #10Preliminary action

4Strength

If rebar assemblies with extremely long bars are installed, then structural reinforcement is achieved, but installation time and labor requirements increase significantly

Engineering Contradiction:
Improvestructural reinforcementVSAvoidinstallation time
Core Design Contradiction:
StrengthVSLoss of time

Solution Approach 1:

The reinforcement system is segmented into pre-assembled steel cages that are integrated into each pre-cast pile during manufacturing. These cages consist of standardized rebar arrangements that are factory-assembled with precision, eliminating the need for time-consuming on-site rebar bending, cutting, and assembly of extremely long bars.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

Reinforcement cages are pre-assembled and attached to the concrete piles in the manufacturing facility before delivery. This preliminary action allows for precise geometric layout and spacing control in a controlled environment, and the completed piles arrive at the site ready for immediate installation without requiring additional rebar work.

Inventive Principle:
Principle #10Preliminary action

5Strength

If massive concrete sections are cast in-place, then foundation capacity is achieved, but risk of thermal cracking from heat of hydration increases

Engineering Contradiction:
Improvefoundation capacityVSAvoidrisk of thermal cracking
Core Design Contradiction:
StrengthVSReliability

Solution Approach 1:

The foundation is divided into multiple smaller pre-cast concrete piles rather than one massive concrete section. This segmentation reduces the volume of concrete in each pour, thereby reducing the heat of hydration and associated thermal gradients that cause cracking. The smaller sections can be cured more uniformly and with lower peak temperatures.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

Concrete piles are pre-cast in controlled manufacturing facilities where temperature and curing conditions can be carefully monitored and regulated. This preliminary action allows for optimized curing regimes that minimize thermal cracking risk, and the piles are cured to full strength before installation, eliminating the thermal cracking risk associated with large on-site pours.

Inventive Principle:
Principle #10Preliminary action

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

The solution significantly reduces concrete consumption, minimizes thermal cracking, and enhances the structural integrity and efficiency of wind turbine foundations, enabling faster and more cost-effective installation while preserving soil integrity.

Implementation Method 1

A foundation system utilizing pre-cast high-strength beams and soil anchors, which reduces concrete usage, improves heat dissipation, and employs a hub assembly with post-tensioning cables for rapid deployment and enhanced stability

Methodology Applied
Scientific EffectLoad transfer: Force

Implementation Method 2

the foundation made according to the methods described herein improves heat dissipation conditions during construction, thus eliminating the risk of thermal cracking due to heat of hydration

Methodology Applied
Scientific EffectHeat dissipation: Conduction (thermal)

Implementation Method 3

employs a hub assembly with post-tensioning cables for rapid deployment and enhanced stability

Methodology Applied
Scientific EffectPost-tensioning: Compression

Data Source

PatentUS9938685B2Beam and pile anchor foundation for towers
Publication Date: 2018.04.10 RUTE FOUNDATION SYSTEMS INC
  • US9938685B2 patent drawing
  • US9938685B2 patent drawing
  • US9938685B2 patent drawing

AI summary

A foundation system for a tower, such as a wind turbine, includes a central hub assembly, a plurality of post-tensioned concrete beams, and an anchoring system associated with each beam. In use the foundation system is arranged so that the bottom surfaces of the concrete beams bear on soil and the anchoring is disposed within the soil. The beams can be inverted bulb-T beams having post-tensioning cables inserted there-through and cooperating with an oppositely disposed related beam. The central hub assembly can include a plurality of stacked disk elements or steel frame elements that are post-tensioned together to form a single hub structure.