Precast Concrete Rings for Underground Construction

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Conventional methods for constructing underground structures require temporary shoring systems that are inefficient, leading to duplication of labor, additional soil disturbance, and increased costs, as they need to be erected, disassembled, and removed, complicating the construction process and wasting resources.

Innovation Solution

The use of precast concrete segments forming circular rings that serve as both temporary earth support and permanent structural components, with a waterproofing system and post-tensioning for resistance to lateral soil pressures, allowing for continuous excavation and construction without additional temporary supports.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Reliability

If temporary shoring systems are erected to stabilize excavation sites, then construction safety and soil stability are improved, but construction time and costs increase due to the need to erect, disassemble, and remove these systems

Engineering Contradiction:
Improvesoil stabilityVSAvoidconstruction time
Core Design Contradiction:
ReliabilityVSLoss of time

Solution Approach 1:

The patent merges the temporary shoring function with the permanent structure by using the same precast concrete segments for both purposes. The segments form a continuous wall that provides soil stabilization during excavation and becomes the permanent retaining wall, eliminating the need for separate temporary and permanent structures.

Inventive Principle:
Principle #5Merging (Combining)

Solution Approach 2:

The precast concrete segments serve multiple functions: they act as temporary shoring during excavation, provide permanent structural support, and form the final retaining wall. This multi-functionality eliminates the need for separate temporary structures and reduces overall construction time.

Inventive Principle:
Principle #6Universality (Multi-functionality)

2Reliability

If temporary shoring walls are constructed outside the permanent structure, then soil support is provided during excavation, but additional soil disturbance and excavation are required

Engineering Contradiction:
Improvesoil supportVSAvoidsoil disturbance
Core Design Contradiction:
ReliabilityVSObject-generated harmful factors

Solution Approach 1:

The patent combines the temporary shoring wall and permanent structure into a single integrated system. The precast concrete segments are installed along the excavation perimeter and serve as both temporary support and permanent structure, eliminating the need for separate temporary walls constructed outside the permanent structure.

Inventive Principle:
Principle #5Merging (Combining)

3Reliability

If traditional two-step construction process is used (temporary shoring then permanent structure), then soil stability is maintained, but resource waste and cost increase occur

Engineering Contradiction:
Improvesoil stabilityVSAvoidresource waste
Core Design Contradiction:
ReliabilityVSLoss of substance

Solution Approach 1:

The patent merges the temporary shoring system and permanent structure into a single integrated system using precast concrete segments. These segments provide soil stabilization during excavation and become the permanent retaining wall, eliminating the need to construct and then remove separate temporary structures, thereby reducing material waste and costs.

Inventive Principle:
Principle #5Merging (Combining)

Solution Approach 2:

Instead of discarding temporary shoring structures after use, the patent recovers resources by making the temporary segments permanent. The same segments that provide temporary support during excavation are retained and integrated into the permanent structure, eliminating the need to dispose of temporary materials.

Inventive Principle:
Principle #34Discarding and recovering

Data Source

PatentUS20240376821A1Apparatus and Methods for Underground Structures and Construction Thereof
Publication Date: 2024.11.14 KRUSE GMBH & CO KG
  • US20240376821A1 patent drawing
  • US20240376821A1 patent drawing
  • US20240376821A1 patent drawing

AI summary

Described herein are apparatus, systems and methods useful in forming vertical structures.