Pre-cast Steel Pile Bridge Replacement with Male-Female Connectors

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The existing methods for railway bridge replacement are time-consuming, expensive, and require careful construction to avoid disrupting rail traffic, with cast-in-place concrete techniques leading to variable quality and lower bridge elevations that can cause flooding and environmental issues.

Innovation Solution

The use of pre-cast steel piles, steel-reinforced concrete caps, and metallic male and female connectors allows for rapid and robust bridge replacement, enabling precise alignment and quick connection without welding, with the connectors designed for easy maintenance and replacement.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Adaptability or versatility

If cast-in-place construction techniques are used to cast concrete caps at the worksite, then the replacement bridge can be built beneath the existing bridge to allow rail traffic to flow during construction, but the method is time-consuming and expensive due to careful construction requirements and concrete curing time

Engineering Contradiction:
Improveability to build beneath existing bridgeVSAvoidconstruction speed
Core Design Contradiction:
Adaptability or versatilityVSProductivity

Solution Approach 1:

The patent applies preliminary action by pre-casting concrete caps at an off-site location before the actual bridge replacement. The caps are manufactured in advance with precise reinforcement placement and quality control, then transported to the worksite for installation. This eliminates the time-consuming on-site concrete pouring and curing process while maintaining the ability to build the replacement bridge beneath the existing structure.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The patent segments the bridge construction into separate components: pre-casted caps, steel piles, and connection elements. The caps are manufactured independently at a factory, allowing parallel processing and quality control. At the worksite, these pre-fabricated segments are assembled together, significantly reducing construction time compared to monolithic cast-in-place construction.

Inventive Principle:
Principle #1Segmentation

2Ease of operation

If cast-in-place construction techniques are used, then the replacement bridge can be built while avoiding disruption to rail traffic, but the quality of concrete and reinforcing materials is variable from one plant to the next

Engineering Contradiction:
Improvecontinuity of rail trafficVSAvoidquality consistency
Core Design Contradiction:
Ease of operationVSManufacturing precision

Solution Approach 1:

The patent moves the concrete casting operation to an off-site factory environment where quality control can be standardized and maintained consistently. The pre-casting process allows for precise placement of reinforcement bars and concrete mixing under controlled conditions, eliminating the variability associated with multiple on-site concrete plants while maintaining construction flexibility.

Inventive Principle:
Principle #10Preliminary action

3Productivity

If the replacement bridge is built at a lower elevation to allow traffic flow during construction, then rail traffic can continue over the existing bridge, but the clearance between the replacement bridge and the underlying waterway is reduced, potentially interfering with shipping and increasing flooding risk

Engineering Contradiction:
Improvecontinuity of rail trafficVSAvoidflooding risk and shipping interference
Core Design Contradiction:
ProductivityVSObject-affected harmful factors

Solution Approach 1:

The patent uses pre-casted caps that can be manufactured to precise elevations before transport. This allows the replacement bridge to be constructed at the correct final elevation from the beginning, eliminating the need to build lower during construction and then raise it later. The pre-fabricated caps enable accurate elevation control while maintaining traffic flow during the replacement process.

Inventive Principle:
Principle #10Preliminary action

4Ease of manufacture

If traditional timber pile bents are used with successive rows of vertical piles, then the bridge can be constructed using conventional methods, but the area beneath the bridge becomes congested with stubs of old piles over time, making further repairs impossible without significant cost

Engineering Contradiction:
Improveconventional construction methodVSAvoidability to perform future repairs
Core Design Contradiction:
Ease of manufactureVSAdaptability or versatility

Solution Approach 1:

The patent changes the fundamental parameters of the substructure system by replacing timber piles with steel H-piles and traditional concrete caps with pre-casted steel-reinforced concrete caps. This parameter change creates a more durable system with greater clearance beneath the bridge, eliminating the congestion problem of old pile stubs and enabling future repairs and replacements without significant cost or complexity.

Inventive Principle:
Principle #35Parameter changes

Data Source

PatentUS8458839B2Apparatus and method for replacing a bridge using a pre-cast construction techniques
Publication Date: 2013.06.11 ENCON TECHNOLOGIES LLC
  • US8458839B2 patent drawing
  • US8458839B2 patent drawing
  • US8458839B2 patent drawing

AI summary

A method and apparatus for replacing a bridge using pre-cast materials, including steel piles, steel reinforced concrete caps, and metallic male and female connectors. The pre-cast materials can be formed to precise standards in a controlled factory environment before being brought to the worksite for the bridge replacement project. Further, the male and female connectors provide for a quick and robust way to connect the caps to the piles without the use of welding between the piles and the caps.