Prefabricated Offset Shingle With Frangible Lines for Roof Installation

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The installation of offset shingles on pitched roofs is inefficient due to the need for manual measuring and cutting, which results in multiple ladder trips and potential damage to the roof, leading to excess material waste and reduced installation speed and accuracy.

Innovation Solution

Prefabricated offset shingles with transverse cuts and frangible lines of weakness are designed to separate into multiple offset portions of varying widths, allowing for easy separation and installation without cutting on the rooftop, facilitating a stair-step pattern and reducing the need for manual measurement and cutting.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Adaptability or versatility

If manual measuring and cutting is performed on-site, then the shingles can be adapted to the roof, but the installation speed decreases and multiple ladder trips are required

Engineering Contradiction:
Improveadaptability to roofVSAvoidinstallation speed
Core Design Contradiction:
Adaptability or versatilityVSProductivity

Solution Approach 1:

The shingles are pre-cut into specific offset portions with predetermined dimensions during manufacturing, eliminating the need for on-site cutting. The frangible lines of weakness are pre-formed to allow easy separation of the offset portions, enabling installers to simply tear along the pre-formed lines rather than performing manual cutting during installation.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The shingle is divided into multiple offset portions (first offset portion, second offset portion, third offset portion) with different widths, separated by frangible lines of weakness. This segmentation allows the shingle to be pre-configured with the exact offset pattern needed for proper alignment, while the portions can be easily separated by tearing along the pre-formed lines during installation.

Inventive Principle:
Principle #1Segmentation

2Ease of operation

If manual cutting is performed on the rooftop, then the shingles can be fitted, but the risk of damaging the roof increases

Engineering Contradiction:
Improvefitting capabilityVSAvoidroof damage risk
Core Design Contradiction:
Ease of operationVSObject-affected harmful factors

Solution Approach 1:

All cutting operations are performed during manufacturing before the shingles reach the installation site. The frangible lines of weakness are pre-formed through controlled cutting or scoring processes, creating predetermined separation paths that allow installers to simply tear along these lines without using tools that could damage the roof.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The frangible lines of weakness act as intermediaries between the intact shingle and the required offset portions. These pre-formed lines provide a controlled separation path that guides the installer through the separation process, eliminating the need for manual cutting tools and reducing the risk of accidental roof damage.

Inventive Principle:
Principle #24Intermediary (Mediator)

3Manufacturing precision

If offset shingles are cut to varying widths, then proper alignment is achieved, but material waste increases

Engineering Contradiction:
Improvealignment precisionVSAvoidmaterial waste
Core Design Contradiction:
Manufacturing precisionVSLoss of substance

Solution Approach 1:

The shingle is pre-cut during manufacturing into specific offset portions with predetermined widths that are optimized for proper alignment. The frangible lines of weakness are pre-formed at specific locations to separate these portions, ensuring that the correct widths are achieved without requiring wasteful trial-and-error cutting on-site.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The shingle is divided into multiple offset portions with specific widths (first offset portion, second offset portion, third offset portion) separated by frangible lines of weakness. This segmentation allows the shingle to be pre-configured with the exact offset pattern needed for proper alignment, minimizing material waste by ensuring the correct portions are used from the start.

Inventive Principle:
Principle #1Segmentation

4Ease of manufacture

If multiple ladder trips are made for cutting, then the shingles can be prepared, but installation time increases

Engineering Contradiction:
Improveshingle preparationVSAvoidinstallation time
Core Design Contradiction:
Ease of manufactureVSLoss of time

Solution Approach 1:

All cutting and preparation operations are completed during manufacturing before the shingles are installed on the roof. The frangible lines of weakness are pre-formed during this preliminary process, eliminating the need for installers to make multiple ladder trips for cutting operations and significantly reducing installation time.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The shingle is pre-segmented into offset portions with frangible lines of weakness during manufacturing, so that all preparation work is done before installation. This segmentation allows the shingle to be ready for direct installation without requiring multiple trips to the roof for cutting or preparation.

Inventive Principle:
Principle #1Segmentation

Data Source

PatentUS10487508B2Prefabricated offset shingle
Publication Date: 2019.11.26 OWENS CORNING INTELLECTUAL CAPITAL LLC
  • US10487508B2 patent drawing
  • US10487508B2 patent drawing
  • US10487508B2 patent drawing

AI summary

An exemplary prefabricated offset shingle includes a headlap portion extending from a top edge to a nail zone, a tab portion extending from the nail zone to a bottom edge, the headlap portion and the tab portion extending between first and second side edges. Two transverse cuts extend from the bottom edge to the headlap portion, and frangible lines of weakness in line with the transverse cuts extend from the transverse cuts to the top edge. The cuts and lines of weakness separate the shingle into first, second, and third offset portions having first, second, and third widths.