Priority Calculation Device for Manufacturing Lots

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The Critical Ratio (CR) method for determining the priority of in-process items in manufacturing is unable to calculate priorities for items that have not been assigned a shipping timing, making it impossible to prioritize in-demand items effectively.

Innovation Solution

A priority calculation system that assigns priorities based on a product-type-basis demand ratio, using a device with a storage unit for demand and process information and a control unit to determine and assign priorities to lots based on their product-type-basis demand ratio, ensuring that lots with ratios closer to the demand ratio are prioritized.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Measurement precision

If the Critical Ratio (CR) method is used to prioritize in-process items, then the priority of in-demand items can be calculated, but it is impossible to calculate the priority of in-process items for which shipping timing has not been assigned

Engineering Contradiction:
Improvepriority calculation capabilityVSAvoidapplicability to non-demand items
Core Design Contradiction:
Measurement precisionVSAdaptability or versatility

Solution Approach 1:

The patent extends the priority calculation system to handle both in-demand items (with shipping timing) and non-demand items (without shipping timing) through a unified demand ratio mechanism. The system calculates demand ratios for all in-process items regardless of whether shipping timing is assigned, making the priority calculation system universally applicable to all items in the manufacturing process.

Inventive Principle:
Principle #6Universality (Multi-functionality)

Solution Approach 2:

The patent introduces a new parameter (demand ratio) to replace or supplement the traditional CR method parameters. By changing the calculation basis from time-based (CR) to demand-based (demand ratio), the system can handle both in-demand and non-demand items uniformly, resolving the limitation of the CR method.

Inventive Principle:
Principle #35Parameter changes

2Productivity

If priority is assigned based on shortest shipping time (CR method), then urgent items are processed first, but items not in demand cannot be prioritized effectively

Engineering Contradiction:
Improveprocessing efficiency of urgent itemsVSAvoiddemand information for non-urgent items
Core Design Contradiction:
ProductivityVSLoss of information

Solution Approach 1:

The patent implements a feedback mechanism where demand information is continuously monitored and used to adjust priority assignments. The system calculates demand ratios based on current demand information and uses this feedback to dynamically prioritize both in-demand and non-demand items, ensuring that demand information is not lost but rather utilized for comprehensive priority management.

Inventive Principle:
Principle #23Feedback

Solution Approach 2:

The patent performs preliminary calculation of demand ratios for all items including those without assigned shipping timing. By pre-calculating demand ratios for non-demand items, the system prepares priority information in advance, enabling effective prioritization when these items need to be processed alongside in-demand items.

Inventive Principle:
Principle #10Preliminary action

Data Source

PatentUS8825190B2Priority calculation device, program, priority calculation system, and priority calculation method
Publication Date: 2014.09.02 HITACHI LTD
  • US8825190B2 patent drawing
  • US8825190B2 patent drawing
  • US8825190B2 patent drawing

AI summary

Priority can be calculated for works-in-process which are not in demand. A priority calculation device (110) comprises a priority calculation unit (124) which specifies a queue of lots in each production stage, a product category wherein the lot is to be used, and the number of components included in the lot, on the basis of information stored in a queue information storage area (115), and allocates priority for each lot so that when the specified lot is supplied to the production stage, a lot, by which a ratio of a component, in each product category, contained in a lot which is in a process subsequent to the process of the production stage is made closer to the ratio of demand in each product category specified by the information stored in a demand information storage area (113), is supplied into the production stage with higher priority.