Project Evaluation Method for Hidden Critical Path Detection

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

Existing project analysis methods, such as CPM and PERT, are insufficient in providing comprehensive information to project managers, especially for complex projects with many tasks, and do not effectively handle networks with start to start, finish to finish, and finish to start task relationships.

Innovation Solution

A method and computer program product that receive task timing and relationship information to locate hidden critical paths, calculate path duration slack, and estimate project robustness by generating networks representative of different task relationships, including start to start, finish to finish, and finish to start, and computing a robustness score based on critical path and hidden critical path durations.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Loss of information

If traditional CPM and PERT methods are used to analyze projects, then the analysis process is simple and straightforward, but the information provided is insufficient for complex projects with many tasks and multiple task relationship types

Engineering Contradiction:
Improveinformation completenessVSAvoidanalysis complexity
Core Design Contradiction:
Loss of informationVSDevice complexity

Solution Approach 1:

The patent segments the project network analysis into multiple components: identifying critical paths, identifying hidden critical paths, calculating path duration slack, and evaluating robustness. This segmentation allows comprehensive analysis of complex projects by breaking down the overall evaluation into manageable parts that can be processed systematically

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The patent extends traditional project analysis by adding a new dimension - the concept of 'hidden critical paths' alongside the traditional critical path. This dimensional expansion allows project managers to view project risks from multiple perspectives, capturing information that single-dimension methods miss

Inventive Principle:
Principle #17Another dimension (Dimensionality change)

2Adaptability or versatility

If only finish to start relationships are considered in project analysis, then the analysis method is simple, but it cannot effectively handle networks with start to start, finish to finish, and other task relationships

Engineering Contradiction:
Improvetask relationship coverageVSAvoidnetwork complexity
Core Design Contradiction:
Adaptability or versatilityVSDevice complexity

Solution Approach 1:

The patent creates a universal project analysis method that handles multiple task relationship types (finish to start, start to start, finish to finish) through a unified approach. The method calculates path duration slack and identifies hidden critical paths regardless of the specific relationship types involved, making the analysis tool versatile across different project network structures

Inventive Principle:
Principle #6Universality (Multi-functionality)

3Reliability

If comprehensive project analysis is performed to identify all critical paths and evaluate robustness, then project management quality improves, but the computational complexity and time required increase significantly

Engineering Contradiction:
Improveproject evaluation accuracyVSAvoidanalysis time
Core Design Contradiction:
ReliabilityVSLoss of time

Solution Approach 1:

The patent performs preliminary calculations of path duration slack for all paths before identifying hidden critical paths. This preliminary action prepares the data structure in advance, allowing efficient identification of paths with minimal slack that constitute hidden critical paths, thereby reducing overall computation time

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The method uses the path duration slack calculations to automatically identify hidden critical paths without requiring separate complex algorithms. The slack values themselves serve as the criterion for identification, making the system self-sufficient and reducing external computational overhead

Inventive Principle:
Principle #25Self-service

Data Source

PatentUS7769618B2Method and computer program product for evaluating a project
Publication Date: 2010.08.03 LEVANON TAL
  • US7769618B2 patent drawing
  • US7769618B2 patent drawing
  • US7769618B2 patent drawing

AI summary

A method and computer program product, for evaluating a project, the method includes: receiving task timing information and task relationship information; locating at least one hidden critical path; and estimating a robustness of the project in response to at one characteristic of the at least one hidden critical path.