Problem

Current cryogenic environment test apparatuses for semiconductor devices require frequent changes in temperature and pressure to unload wafers and refill cooling sources, leading to delayed test times and frequent process interruptions.

Innovation Solution

A semiconductor test system comprising a transfer chamber, loadlock chambers, and test chambers configured to maintain consistent pressure and temperature during wafer transfer, allowing for continuous operation under cryogenic conditions by controlling the pressure and temperature of the transfer chamber to match the loadlock and test chambers, enabling efficient wafer handling and testing without disrupting the cryogenic environment.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Ease of operation

If the temperature and pressure of the cryogenic test apparatus are changed to unload wafers and refill cooling sources, then the apparatus can perform necessary maintenance and wafer handling operations, but the test time is delayed and the testing process is frequently interrupted

Engineering Contradiction:
Improvewafer unloading and cooling source refillingVSAvoidtest time delay
Core Design Contradiction:
Ease of operationVSLoss of time

Solution Approach 1:

The system is divided into multiple independent test chambers (first test chamber, second test chamber) that can operate simultaneously. While one chamber undergoes temperature and pressure changes for wafer unloading or cooling source refilling, the other chamber continues testing without interruption. This segmentation allows maintenance operations to occur in parallel with ongoing tests, eliminating test time delays.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

A transfer chamber serves as an intermediary between the loadlock chamber and test chambers. The transfer chamber receives wafers from the loadlock and transfers them to the test chambers without requiring the test chambers to change their temperature and pressure conditions. This intermediary structure enables wafer handling operations to occur in a separate environment, preventing interruptions to the cryogenic testing process.

Inventive Principle:
Principle #24Intermediary (Mediator)

2Quantity of substance

If the cooling source is consumed and the tank needs to be refilled or exchanged, then the cooling source can be replenished, but the temperature and pressure must be changed causing frequent process stoppages

Engineering Contradiction:
Improvecooling source replenishmentVSAvoidtesting continuity
Core Design Contradiction:
Quantity of substanceVSProductivity

Solution Approach 1:

The system employs multiple test chambers that can operate independently. When the cooling source in one chamber is consumed and needs refilling, the other chamber continues testing without interruption. This segmentation of the testing function across multiple chambers ensures that cooling source maintenance does not halt overall productivity.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The system monitors the cooling source level in advance and can prepare for refilling operations before the cooling source is completely consumed. By detecting the cooling source level and initiating refilling procedures proactively, the system minimizes the duration of any necessary interruptions and maintains continuous operation in parallel chambers.

Inventive Principle:
Principle #10Preliminary action

3Adaptability or versatility

If the temperature and pressure are frequently changed for wafer handling and maintenance, then necessary operations can be performed, but the test efficiency and reliability are reduced

Engineering Contradiction:
Improvewafer handling capabilityVSAvoidtesting reliability
Core Design Contradiction:
Adaptability or versatilityVSReliability

Solution Approach 1:

The transfer chamber acts as an intermediary that handles wafer transfer operations between the loadlock and test chambers. By performing wafer handling in the transfer chamber rather than directly in the test chamber, the system maintains the stable cryogenic environment required for reliable testing while still enabling versatile wafer handling operations.

Inventive Principle:
Principle #24Intermediary (Mediator)

Solution Approach 2:

The system separates wafer handling functions from testing functions by using distinct chambers. The loadlock chamber handles wafer loading, the transfer chamber handles wafer transfer, and the test chambers handle testing. This segmentation allows each chamber to maintain its optimal conditions independently, ensuring testing reliability while providing adaptable wafer handling capabilities.

Inventive Principle:
Principle #1Segmentation

Data Source

PatentUS11885846B2System and method of testing a semiconductor device
Publication Date: 2024.01.30 SK HYNIX INC
  • US11885846B2 patent drawing
  • US11885846B2 patent drawing
  • US11885846B2 patent drawing

AI summary

A system for testing a semiconductor may include a transfer chamber, at least one loadlock chamber and at least one test chamber. The transfer chamber may include a plurality of sidewalls. The loadlock chamber may be arranged on a first sidewall of the sidewalls of the transfer chamber. The loadlock chamber may include a carrier configured to receive a plurality of wafers. The test chamber may be arranged on a second sidewall of the sidewalls of the transfer chamber. When the transfer chamber is connected to the loadlock chamber, a pressure of the transfer chamber may be changed into a pressure of the loadlock chamber. When the transfer chamber is connected to the test chamber, the pressure of the transfer chamber may be changed into a pressure of the test chamber.