Subsea Vessel Riser Storage Horizontal Pre-Assembly

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The existing process for assembling and disassembling riser strings in subsea wellbore operations is time-consuming due to the need for extensive connection-making between riser sections, which slows down the deployment and requires significant effort and testing.

Innovation Solution

The implementation of a vessel with a riser storage system that stores pre-assembled riser stands, allowing connections to be made and tested before loading, significantly reducing the assembly time by storing multiple riser stands connected end-to-end in horizontal orientation, and using a strongback assembly for efficient handling and alignment during deployment.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Adaptability or versatility

If riser sections are stored individually and assembled on-demand, then flexibility in deployment is improved, but assembly time and operational complexity increase significantly

Engineering Contradiction:
Improveflexibility in deploymentVSAvoidassembly time
Core Design Contradiction:
Adaptability or versatilityVSLoss of time

Solution Approach 1:

Riser sections are pre-assembled into complete riser strings onshore before deployment. The pre-assembly process includes connecting multiple riser sections with connector fittings, installing satellite pipes, and performing integrity testing in advance. This preliminary preparation eliminates time-consuming assembly operations at sea, reducing deployment time while maintaining deployment flexibility.

Inventive Principle:
Principle #10Preliminary action

Solution Approach 2:

The riser string is divided into modular sections that can be pre-assembled independently onshore. Each section can be tested and certified separately, then quickly deployed as complete modules. This segmentation allows parallel preparation of multiple sections, improving overall deployment efficiency while maintaining system flexibility.

Inventive Principle:
Principle #1Segmentation

2Loss of time

If riser sections are assembled and tested onshore before deployment, then deployment time is reduced, but storage requirements and logistical complexity increase

Engineering Contradiction:
Improvedeployment timeVSAvoidlogistical complexity
Core Design Contradiction:
Loss of timeVSDevice complexity

Solution Approach 1:

Multiple riser sections are nested within each other in a telescopic arrangement during storage and transport. The sections are stacked vertically or horizontally in a compact configuration, reducing storage space requirements. This nesting approach allows complete pre-assembled riser strings to be stored in a space-efficient manner without requiring complex external support structures.

Inventive Principle:
Principle #7Nested doll (Nesting)

3Productivity

If traditional on-site assembly process is used, then equipment and storage space requirements are reduced, but operational efficiency and productivity decrease

Engineering Contradiction:
Improveoperational efficiencyVSAvoidhandling complexity
Core Design Contradiction:
ProductivityVSEase of operation

Solution Approach 1:

All connection making, satellite pipe installation, and integrity testing are performed in advance onshore where facilities and expertise are readily available. This preliminary action transfers operational complexity from the marine environment to the onshore facility, simplifying on-site operations to merely deploying pre-tested complete assemblies, thereby improving operational efficiency.

Inventive Principle:
Principle #10Preliminary action

Data Source

PatentUS9896167B2Subsea wellbore operations vessel
Publication Date: 2018.02.20 ITREC BV
  • US9896167B2 patent drawing
  • US9896167B2 patent drawing
  • US9896167B2 patent drawing

AI summary

A vessel (1) adapted to perform subsea wellbore related operations involving a riser string between the subsea wellbore and the vessel, e.g. drilling and/or wellbore intervention. The vessel (1) has a hull (2) and a riser storage (40) adapted to store therein of multiple risers in horizontal orientation. The riser storage (40) is adapted to store therein, or has stored therein, multiple pre-assembled riser stands (60), e.g. at least 25 riser stands, each riser stand being assembled from multiple riser sections (60, 61) connected end-to-end, e.g. each riser stand (62) consisting of two riser sections (60, 61), each riser section comprising a riser pipe and optionally one or more satellite pipes on the outside of and along the riser pipe, each riser section (60, 61) comprising a connector fitting arrangement at each end thereof, and each riser section (60, 61) comprising preferably one or more buoyancy members, wherein in a riser stand the connector fitting arrangement of one riser section is connected to a connector fitting arrangement of another riser section.