Problem

Conventional wastewater pump stations with two pumps are inefficient due to high energy consumption and maintenance needs, as they require frequent start-stop cycles, leading to kinetic energy loss and increased wear and tear, resulting in shorter pump lifespan and higher operational costs.

Innovation Solution

A three-pump system design where two pumps assist the primary continuously running pump during peak demand and serve as backups, optimizing horsepower usage based on 24-hour flow rates, well capacity, and pipe layout to minimize energy consumption and reduce start-stop cycles, thereby extending pump lifespan and lowering maintenance costs.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Productivity

If a two-pump system is used with one primary pump and one backup pump, then the system can handle peak flow rates and provide backup capability, but the primary pump must frequently start and stop, causing high energy consumption and kinetic energy loss

Engineering Contradiction:
Improvepeak flow rate handling capacityVSAvoidenergy consumption
Core Design Contradiction:
ProductivityVSUse of energy by moving object

Solution Approach 1:

The system divides the pumping function into three separate pumps of equal capacity instead of one large pump and one backup. This segmentation allows the load to be distributed across multiple units, with pumps operating in parallel at optimal points rather than one pump cycling on and off frequently.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

Each pump is designed to operate at its optimal efficiency point under normal conditions. By having three pumps of equal capacity rather than one oversized pump, each unit can maintain local optimal operating conditions, avoiding the inefficiencies of operating far from the design point.

Inventive Principle:
Principle #3Local quality

2Device complexity

If the primary pump operates alone during normal conditions, then the system reduces complexity, but frequent start-stop cycles increase maintenance requirements and reduce pump lifespan

Engineering Contradiction:
Improvesystem complexityVSAvoidpump lifespan
Core Design Contradiction:
Device complexityVSReliability

Solution Approach 1:

The pumping function is segmented into three independent pump units that can operate independently or in combination. This allows the system to maintain simplicity while improving reliability, as each pump experiences reduced cycling stress.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The system is pre-configured with three pumps of equal capacity ready to operate. This preliminary arrangement eliminates the need for complex control logic to manage oversized pumps, while the pumps are positioned to immediately take over if needed, reducing start-stop cycles and extending lifespan.

Inventive Principle:
Principle #10Preliminary action

3Device complexity

If one pump is oversized to handle maximum flow rates alone, then the system reduces the number of pumps needed, but the pump operates inefficiently at partial load and consumes more energy

Engineering Contradiction:
Improvenumber of pumpsVSAvoidenergy inefficiency at partial load
Core Design Contradiction:
Device complexityVSLoss of energy

Solution Approach 1:

Instead of one oversized pump, the system uses three smaller pumps of equal capacity. Each pump is sized to handle approximately one-third of the maximum flow, allowing them to operate efficiently at partial loads when demand is lower, and in parallel when demand is high.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The system uses partial action by operating one or two pumps at a time based on demand, rather than always running one oversized pump at partial efficiency. This approach matches the operating capacity to the actual demand, avoiding energy waste.

Inventive Principle:
Principle #16Partial or excessive action

Data Source

PatentUS8777584B2Energy saving green wastewater pump station design
Publication Date: 2014.07.15 MEHR NASSER FRED
  • US8777584B2 patent drawing
  • US8777584B2 patent drawing
  • US8777584B2 patent drawing

AI summary

An energy saving three pump waste water pump station design that eliminates the high energy usage of traditional waste water pump stations, reduces maintenance costs to the pumps and increases the useful lives of the pumps by having a primary pump running continuously, a second pump mining during high demand periods and a third pump functioning primarily as a back up pump. Unlike conventional pump-station designs, the Energy Saving Green Pump Station Design utilizes a single float switch panel. Whereas independent float switches trigger start-stops in conventional pump station designs, the Green design incorporates a remote controllable panel for rotating the primary, secondary and third pumps on a schedule. This design also provides a process for determining in-flow rates for a pump station and efficiency operating points of pumps so that the most efficient pumps with the lowest horsepower can be selected.