Three-Truss Girder Pushing Device with Passive Middle Truss

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The complex construction and high costs associated with building three-truss continuous steel truss girders, particularly due to the complexity and environmental dependencies of existing methods, necessitate a more efficient and cost-effective approach.

Innovation Solution

A three-truss continuous steel truss girder-pushing device comprising left, middle, and right supporting structures, a slideway girder system with vertical and horizontal pushing jacks, and sliding blocks, which allows for synchronized pushing of side trusses while the middle truss slides passively, reducing stress on nodes and facilitating easier river crossings.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Ease of manufacture

If cantilever erection construction is carried out by using the slinging tower, then the steel truss girder can be erected, but the construction process becomes complex and many unsafe factors arise

Engineering Contradiction:
Improveease of erectionVSAvoidconstruction process complexity
Core Design Contradiction:
Ease of manufactureVSDevice complexity

Solution Approach 1:

The patent replaces the complex slinging tower mechanical system with a simpler pushing method that uses horizontal continuous pushing jacks and sliding blocks to move the steel truss girder segments into position, eliminating the need for tall lifting towers and complex rigging operations

Inventive Principle:
Principle #28Mechanics substitution (Replace mechanical system)

Solution Approach 2:

The patent extracts and removes the slinging tower from the construction system entirely, using only the necessary pushing components (jacks, sliding blocks, and reaction forces from bridge piers) to achieve the erection, thereby simplifying the construction process and eliminating associated safety hazards

Inventive Principle:
Principle #2Taking out (Extraction)

2Ease of manufacture

If cantilever erection construction is carried out by adding the temporary pier, then the steel truss girder can be erected, but large investment, high building difficulty, and high costs are incurred

Engineering Contradiction:
Improveease of erectionVSAvoidtemporary pier investment
Core Design Contradiction:
Ease of manufactureVSQuantity of substance

Solution Approach 1:

The patent uses simple, inexpensive sliding blocks and pushing jacks that can be easily assembled and disassembled, replacing the need for expensive temporary piers that require significant material investment and complex construction

Inventive Principle:
Principle #27Cheap short-living objects (Disposable)

Solution Approach 2:

The patent completely eliminates the temporary pier from the construction system, using the existing bridge piers and the pushing mechanism to achieve erection without any additional permanent or temporary support structures

Inventive Principle:
Principle #2Taking out (Extraction)

3Productivity

If pushing method is used, then field occupation is reduced and construction quality is ensured, but it has not been applied in the erection of the three-truss continuous steel truss girder

Engineering Contradiction:
Improveconstruction efficiencyVSAvoidapplicability to three-truss structure
Core Design Contradiction:
ProductivityVSAdaptability or versatility

Solution Approach 1:

The patent divides the three-truss continuous steel truss girder into separate segments (side trusses and middle truss) that can be pushed independently using the same pushing mechanism, making the method adaptable to this specific three-truss configuration

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The patent creates a universal pushing system that can handle different truss configurations (side trusses and middle truss) using the same basic mechanism of horizontal pushing jacks and sliding blocks, demonstrating the method's versatility for three-truss continuous structures

Inventive Principle:
Principle #6Universality (Multi-functionality)

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

This method improves construction efficiency, reduces costs, minimizes temporary pier requirements, enhances flood prevention, and shortens construction periods by ensuring only nodes are stressed during pushing, thus avoiding obstacles and maintaining construction quality.

Implementation Method 1

a stainless steel plate is welded on a top surface of the steel plate

Methodology Applied
Scientific EffectFriction reduction: Friction

Data Source

PatentUS8732882B2Three-truss continuous steel truss girder-pushing device and arrangement method thereof
Publication Date: 2014.05.27 CHINA RAILWAY MAJOR BRIDGE ENG GRP CO LTD
  • US8732882B2 patent drawing
  • US8732882B2 patent drawing
  • US8732882B2 patent drawing

AI summary

The present invention claims a three-truss continuous steel truss girder-pushing device and an arrangement method thereof. The device comprises three supporting structures of left, center and right, the three supporting structures are provided respectively with left and right side truss slideway girders and a middle truss slideway girder. The front ends of the slideway girder are provided with an operating platform where horizontal continuous pushing jacks are installed; the front ends of the left and right slideway girder and the center slideway girder are each provided with four vertical lifting jacks. The three-truss continuous steel truss girder-pushing device simultaneously pushes the two side trusses of the steel truss beam only, while the center truss slides passively, thereby improving construction efficiency and reducing construction costs.