UHPC Bottom Flange Prestressed Concrete Camber Control

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The existing methods for designing and fabricating prestressed concrete components face challenges such as high costs, inadequate durability due to high permeability and cracking, undesirable tension forces leading to frequent repairs, limitations in maximum prestress application, and unpredictable camber variations, which increase project complexity and time.

Innovation Solution

The introduction of staged fabrication processes and design methodologies that utilize Ultra-High Performance Concrete (UHPC) for critical subcomponents, thinner sections with ribs or stiffeners, and controlled camber induction through geometry modifications, along with innovative connections like epoxy-applied bolted connections and uniquely shaped UHPC connections, to reduce material usage and enhance structural efficiency.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Reliability

If UHPC is used for the entire component, then durability is improved, but cost increases significantly

Engineering Contradiction:
ImprovedurabilityVSAvoidcost
Core Design Contradiction:
ReliabilityVSQuantity of substance

Solution Approach 1:

The patent applies UHPC specifically to the bottom flange subcomponent where it is most needed for durability and crack resistance, while using conventional HPC for the web and top flange. This localized application of expensive material only where required maintains durability benefits while significantly reducing overall cost.

Inventive Principle:
Principle #3Local quality

Solution Approach 2:

The patent creates a hybrid prestressed concrete component combining UHPC and HPC in different subcomponents. The UHPC bottom flange provides enhanced durability and crack resistance, while the HPC web and top flange provide structural support at lower cost, achieving a cost-effective composite material solution.

Inventive Principle:
Principle #40Composite materials

2Stability of the object's composition

If complete fabrication is performed prior to prestressing, then structural integrity is ensured, but project time increases

Engineering Contradiction:
Improvestructural integrityVSAvoidproject time
Core Design Contradiction:
Stability of the object's compositionVSLoss of time

Solution Approach 1:

The patent divides the concrete component into separate subcomponents (bottom flange, web, top flange) that can be fabricated independently before assembly. The bottom flange is fabricated and prestressed as a separate unit, then assembled with the web and top flange, allowing parallel processing and reducing total project time while maintaining structural integrity.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The bottom flange subcomponent is fabricated and prestressed in advance as a separate unit before assembly with the remaining components. This preliminary action allows the critical prestressing to be completed early, and the other subcomponents can be fabricated simultaneously, reducing overall project duration.

Inventive Principle:
Principle #10Preliminary action

3Quantity of substance

If conventional HPC is used, then cost is reduced, but durability deteriorates due to high permeability and cracking

Engineering Contradiction:
ImprovecostVSAvoiddurability
Core Design Contradiction:
Quantity of substanceVSReliability

Solution Approach 1:

The patent uses conventional HPC for the web and top flange where cost control is prioritized, while reserving UHPC for the bottom flange where durability against moisture and corrosive chemicals is most critical. This localized material selection achieves acceptable durability at reduced cost.

Inventive Principle:
Principle #3Local quality

4Loss of time

If staged fabrication is implemented, then project time is reduced, but manufacturing complexity increases

Engineering Contradiction:
Improveproject timeVSAvoidmanufacturing complexity
Core Design Contradiction:
Loss of timeVSDevice complexity

Solution Approach 1:

The patent segments the fabrication process into discrete stages: bottom flange fabrication and prestressing, then assembly with web and top flange. This segmentation allows parallel processing of different subcomponents, reducing total project time. The modular approach actually simplifies manufacturing by allowing standardized fabrication of individual subcomponents that can be assembled later.

Inventive Principle:
Principle #1Segmentation

Data Source

PatentUS11773589B2Refined prestressed concrete elements
Publication Date: 2023.10.03 ADVANCED BRIDGE CONSTR TECH INC
  • US11773589B2 patent drawing
  • US11773589B2 patent drawing
  • US11773589B2 patent drawing

AI summary

Disclosed invention comprises innovations in the fabrication process and the associated design methodology for producing refined prestressed concrete elements/components. The innovations disclosed are fabrication using multiple stages, the use of ultra high strength materials for only critical subcomponents, utilizing thinner sections made of ultra high strength materials, and a unique method of inducing and controlling camber. The embodiments of this invention enable the accelerated construction of concrete structures that are both durable and cost effective. This disclosure demonstrates the significant improvements to the prior art in the areas of durability, constructability, and cost reduction for prestressed concrete components. The embodiments presented in this disclosure are for bridge superstructure applications.