Vertical Shaft Lining Sequence to Reduce Excavation Instability

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The construction of deep and large vertical shafts using the reverse integral inverted-wall method faces challenges such as structural instability, safety risks, and inefficiencies due to the need for precise control over the need for a stable structure, including suspended structures, vibration disturbances, and safety hazards from heavy steel formworks and frequent hoisting operations.

Innovation Solution

A top-down sequential-building construction method for deep and large vertical shafts, involving staged construction from the surface to the contact air channel elevation and then to the vertical shaft bottom, with a lining structure built from bottom to top using single-side cantilever climbing formworks, full-face blasting, and integrated support systems.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Ease of manufacture

If the reverse integral inverted-wall method is used for constructing vertical shafts, then the construction can proceed with suspended structures, but the structure experiences vibration disturbance and instability during excavation

Engineering Contradiction:
Improveconstruction feasibilityVSAvoidstructural stability
Core Design Contradiction:
Ease of manufactureVSStability of the object's composition

Solution Approach 1:

The patent inverts the conventional construction sequence by constructing the lining structure from bottom to top instead of top to bottom. This allows the lining to be built on a stable foundation rather than being suspended during excavation, eliminating vibration disturbance while maintaining construction feasibility through the inverted sequencing approach

Inventive Principle:
Principle #13The other way round (Inversion)

2Ease of manufacture

If large steel formworks are used for constructing the lining structure, then the lining can be built, but the steel formworks are heavy causing frequent hoisting and cross operations with safety risks

Engineering Contradiction:
Improvelining construction capabilityVSAvoidconstruction safety
Core Design Contradiction:
Ease of manufactureVSReliability

Solution Approach 1:

The patent segments the lining construction into multiple sections that can be built sequentially from bottom to top. This segmentation allows smaller, lighter formworks to be used in each section rather than large steel formworks spanning the entire shaft, reducing hoisting frequency and eliminating cross-operation safety risks while maintaining lining construction capability

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

By inverting the construction sequence to build from bottom to top, the patent enables the use of smaller, lighter formworks that can be progressively moved upward as construction progresses, rather than requiring heavy steel formworks to be hoisted and positioned from the top down

Inventive Principle:
Principle #13The other way round (Inversion)

3Productivity

If the vertical shaft is constructed using traditional methods, then construction can proceed, but there is large interference between processes and many risk sources

Engineering Contradiction:
Improveconstruction progressVSAvoidprocess complexity
Core Design Contradiction:
ProductivityVSDevice complexity

Solution Approach 1:

The patent inverts the construction sequence to proceed from bottom to top, which simplifies the construction process by eliminating the need for complex hoisting and cross-operation coordination required in traditional top-down methods. This inversion reduces process interference and risk sources while maintaining construction progress through systematic sequencing

Inventive Principle:
Principle #13The other way round (Inversion)

Solution Approach 2:

The patent applies preliminary action by constructing the lining structure in advance from the bottom up, creating a stable foundation and progressively extending the structure as excavation proceeds. This preliminary construction approach simplifies subsequent operations and reduces process complexity compared to traditional methods where structures must be suspended and assembled in complex sequences

Inventive Principle:
Principle #10Preliminary action

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

This method reduces structural disturbances, enhances safety, improves construction quality, and reduces risks by minimizing structural dead weight, hoisting frequency, and process interference, while ensuring stable and reliable construction.

Implementation Method 1

The blasting adopts a full-face one-time blasting and a layered integral blasting

Methodology Applied
Scientific EffectBlasting: Explosion

Implementation Method 2

A preliminary shotcrete spraying, a steel grid construction, a steel mesh construction, a hollow grouting anchor construction, and a secondary shotcrete spraying are performed

Methodology Applied
Scientific EffectShotcrete spraying: Fluid Spray

Data Source

PatentUS20250389189A1Top-down sequential-building construction method for deep and large vertical shaft cavern group
Publication Date: 2025.12.25 CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD
  • US20250389189A1 patent drawing
  • US20250389189A1 patent drawing
  • US20250389189A1 patent drawing

AI summary

A top-down sequential-building construction method for deep and large vertical shaft cavern groups is provided. The construction method includes the following steps. A preparation is made for a construction. A vertical shaft locking beam is constructed. A vertical shaft is constructed. A post-construction maintenance is performed. The vertical shaft is constructed through a staged construction, which includes the following steps: S1, constructing from a vertical shaft surface to a contact air channel elevation; S2, constructing a contact air channel; S3, constructing from the contact air channel elevation to a vertical shaft bottom. Both constructing from the vertical shaft surface to the contact air channel elevation and from the contact air channel elevation to the vertical shaft bottom include constructing a lining structure from bottom to top.