Problem

Existing wind turbine tower pre-tensioning methods require complex and space-intensive tensioning systems, with tensioning elements needing to be directly anchored to the foundation or head piece, making assembly and replacement cumbersome and requiring large foundation reinforcement.

Innovation Solution

A pre-tensioned wind turbine tower structure where tensioning elements are indirectly anchored via a short anchor rod, with the anchor rod's first end fixed in a tendon anchor and the second end anchored to the foundation or head piece, allowing for flexible assembly and reduced space requirements, using a thread or adaptor piece for easy connection and alignment.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Reliability

If tensioning elements are directly anchored to the foundation or head piece, then the pre-tensioning structure is stable and reliable, but the assembly becomes cumbersome and requires large foundation reinforcement

Engineering Contradiction:
Improvepre-tensioning structure stabilityVSAvoidassembly ease
Core Design Contradiction:
ReliabilityVSEase of operation

Solution Approach 1:

The anchoring system is segmented into two distinct parts: a stationary anchor rod embedded in the foundation/head piece, and a replaceable tensioning element with tendon anchor. This segmentation allows the tensioning element to be independently installed, adjusted, and replaced without affecting the foundation anchoring, thereby improving assembly ease while maintaining structural reliability

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The anchor rod serves as an intermediary component between the foundation/head piece and the tensioning element. It provides a stable embedded anchoring point while enabling flexible connection and replacement of the tensioning element through the accommodation interface, resolving the contradiction between reliability and ease of operation

Inventive Principle:
Principle #24Intermediary (Mediator)

2Device complexity

If tensioning elements are anchored directly to the foundation, then the structure is simple, but the foundation must be comparatively large and provided with strong reinforcement

Engineering Contradiction:
Improveanchoring system simplicityVSAvoidfoundation size
Core Design Contradiction:
Device complexityVSArea of stationary object

Solution Approach 1:

The anchoring function is segmented between the anchor rod (embedded in foundation) and the tendon anchor (on tensioning element). This allows the foundation to accommodate only the compact anchor rod rather than requiring large-scale reinforcement for direct tensioning element anchoring, reducing foundation area while maintaining anchoring simplicity

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The anchor rod acts as an intermediary that transfers the anchoring function from the large foundation structure to a compact embedded element. The tendon anchor then connects to this intermediary, enabling the tensioning system to be anchored in a space-efficient manner while keeping the overall system conceptually simple

Inventive Principle:
Principle #24Intermediary (Mediator)

3Reliability

If tensioning elements are threaded through openings in connecting elements, then the structure is stable, but the threading process is time-consuming

Engineering Contradiction:
Improveconnection stabilityVSAvoidassembly time
Core Design Contradiction:
ReliabilityVSLoss of time

Solution Approach 1:

The accommodation in the tendon anchor serves as an intermediary connection interface that replaces the threading process. The anchor rod is inserted into this accommodation and secured via threading or adaptor pieces, providing stable connection without requiring time-consuming threading of the entire tensioning element through openings

Inventive Principle:
Principle #24Intermediary (Mediator)

Solution Approach 2:

The accommodation is preliminarily prepared in the tendon anchor with the appropriate threading or adaptor piece configuration. This preliminary preparation enables quick connection of the anchor rod without time-consuming threading operations during assembly, while still ensuring connection stability

Inventive Principle:
Principle #10Preliminary action

Data Source

PatentUS12134895B2Structure pretensioned by at least one tensioning element, and method for producing a structure pretensioned by at least one tensioning element
Publication Date: 2024.11.05 MAX BOEGL WIND
  • US12134895B2 patent drawing
  • US12134895B2 patent drawing
  • US12134895B2 patent drawing

AI summary

A structure, in particular, a wind turbine tower (1), which is pre-tensioned with at least one tensioning element (3), has a foundation (2), a concrete tower section (4), in particular, consisting of a plurality of precast concrete elements (5), as well as a head piece (6), wherein the tensioning element (3) at least at one of its ends has a tendon anchor (7, 7a, 7b). The tendon anchor (7, 7a, 7b) has an accommodation (8) in which a first end (10a) of an anchor rod (9) is fastened, in particular screwed in. A second end (10b) of the anchor rod (9) is anchored to the foundation (2) or to the head piece (6). In a corresponding method for manufacturing a structure, a first end (10a) of an anchor rod (9) is fastened, in particular screwed in an accommodation (8) of a tendon anchor (7, 7a, 7b), and a second end (10b) of the anchor rod (9) is anchored to the foundation (2) or to the head piece (6).