Problem

The manual rewiring and loose state of guide wires during the drilling process in horizontal directional drilling rigs lead to tangling, breakage, and high labor costs, especially under complex geological conditions, affecting drilling accuracy and efficiency.

Innovation Solution

A wire-guided automatic pay-off device installed on a horizontal directional drilling rig, comprising a conductive ring assembly, brush assembly, winding device, and guide device, which maintains the guide wire in a tight state and enables automatic pay-off, reducing manual intervention and joint impacts.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Productivity

If manual pay-off method is used, then device complexity is low, but productivity is low and reliability is low due to tangling and breakage

Engineering Contradiction:
Improvepay-off efficiencyVSAvoiddevice complexity
Core Design Contradiction:
ProductivityVSDevice complexity

Solution Approach 1:

The guide wire system performs self-tensioning automatically through the winding device and guide device mechanism, eliminating the need for manual intervention to maintain wire tension and prevent tangling during the drilling process

Inventive Principle:
Principle #25Self-service

Solution Approach 2:

The patent replaces manual mechanical pay-off operations with an automated mechanical system consisting of the winding device, guide device, and guide wire assembly that automatically manages wire tension and positioning

Inventive Principle:
Principle #28Mechanics substitution (Replace mechanical system)

2Reliability

If guide wire is kept loose during drilling, then ease of operation is high, but reliability is low due to breakage from mud impact

Engineering Contradiction:
Improveguide wire stabilityVSAvoidoperation complexity
Core Design Contradiction:
ReliabilityVSEase of operation

Solution Approach 1:

The system automatically maintains guide wire tension through the winding device and guide device mechanism, eliminating the need for manual tensioning operations while preventing wire breakage from mud impact

Inventive Principle:
Principle #25Self-service

Solution Approach 2:

The guide wire is pre-tensioned and positioned through the guide device before drilling begins, ensuring the wire remains in a tight state throughout the drilling process and is ready to handle mud impact without breaking

Inventive Principle:
Principle #10Preliminary action

3Productivity

If manual rewiring is performed at each drill pipe addition, then device complexity is low, but productivity is low and time is lost

Engineering Contradiction:
Improveconstruction efficiencyVSAvoidrewiring time
Core Design Contradiction:
ProductivityVSLoss of time

Solution Approach 1:

The guide wire system automatically repositions and re-tensions itself through the winding device and guide device mechanism when drill pipes are added, eliminating the need for manual rewiring operations and reducing construction time

Inventive Principle:
Principle #25Self-service

Solution Approach 2:

The guide wire maintains continuous tension and positioning through the automated winding and guide device system, ensuring uninterrupted signal transmission and drilling operation without time loss from manual rewiring between drill pipe additions

Inventive Principle:
Principle #20Continuity of useful action

Data Source

PatentUS12371948B2Wire-guided automatic pay-off device and method
Publication Date: 2025.07.29 XUZHOU XUGONG FOUNDATION CONSTRUCTION MACHINERY CO LTD
  • US12371948B2 patent drawing
  • US12371948B2 patent drawing
  • US12371948B2 patent drawing

AI summary

Disclosed are a wire-guided automatic pay-off device and method. The wire-guided automatic pay-off device is installed on a horizontal directional drilling rig and comprises a conductive ring assembly, a brush assembly, a winding device, a guide device and a guide wire. The conductive ring assembly fixed to a main shaft of a carriage assembly rotates together with the main shaft, the brush assembly fixed to a body of the carriage assembly does not rotate with the main shaft, and a conductive end of the brush assembly is in contact with the conductive ring assembly. The guide wire wound on the winding device has one end connected to the conductive ring assembly and the other end passing through the guide device, penetrating into a central hole in a drill pipe from a rear end of the drill pipe.