Control information prioritization techniques for multiple logical channels

By adjusting the resource distribution scheme, ensuring that the lower priority logical channels obtain resource allocation in the wireless communication system, the problems of window stagnation and logical channel release are solved, system efficiency is improved and delay and overhead are reduced.

CN119054366APending Publication Date: 2024-11-29QUALCOMM INC
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202280094725.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2022-04-30
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

In a wireless communication system with multi-logical channels, lower priority logical channels are prone to causing window stagnation and release of logical channel connections during resource allocation, increasing system delay and overhead.

Method used

By adjusting the resource distribution scheme, the priority bit rate of the lower priority logical channel is adjusted to the amount corresponding to the existence of high priority information, and the original value is restored after the high priority information is sent to ensure the lower priority logical channel Obtain resource allocation to prevent windows from stagnating.

Benefits of technology

It effectively avoids window stagnation, reduces the overhead of system delay and logical channel release, and reduces power consumption.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119054366A_ABST
    Figure CN119054366A_ABST
Patent Text Reader

Abstract

Methods, systems, and devices for wireless communication are described that provide techniques for resource distribution at a user equipment (UE) in which control data for lower priority logical channels may be transmitted to avoid window stagnation and connection release for such lower priority logical channels. A resource distribution scheme at the UE may be adjusted to change a prioritized bit rate (PBR) for one or more logical channels to an amount corresponding only to high priority information present for each logical channel. Then, after distributing resources to each logical channel for the high priority information, the PBRs for each logical channel are reset to original values, and the remaining uplink resources are distributed according to the logical channel priority and the associated PBRs.
Need to check novelty before this filing date? Find Prior Art

Description

Background Art

[0001] The following relates to wireless communications, including techniques for prioritizing control information for multiple logical channels.

[0002] Wireless communication systems are widely deployed to provide various types of communication content, such as voice, video, packet data, messaging, broadcast, etc. These systems may be able to support communication with multiple users by sharing available system resources (e.g., time, frequency, and power). Examples of such multiple access systems include fourth generation (4G) systems (such as long term evolution (LTE) systems, advanced LTE (LTE-A) systems, or LTE-A Pro systems) and fifth generation (5G) systems (which may be referred to as new radio (NR) systems). These systems may use techniques such as code division multiple access (CDMA), time division multiple access (TDMA), frequency division multiple access (FDMA), orthogonal FDMA (OFDMA), or discrete Fourier transform spread orthogonal frequency division multiplexing (DFT-S-OFDM). A wireless multiple access communication system may include one or more base stations or one or more network access nodes, each base station or network access node simultaneously supporting communication with multiple communication devices, which may be further referred to as user equipment (UE). Summary of the invention

[0003] A method for wireless communication at a user equipment (UE) is described. The method may include: receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for a distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein a distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold; adjusting the distribution scheme to provide an adjusted first amount of the resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and providing a second amount of the resource allocation to the second logical channel, the second amount of the resource allocation corresponding to a second amount of control information to be sent on the second logical channel; and sending one or more transport blocks, the one or more transport blocks including the first amount of control information for the first logical channel and the second amount of control information for the second logical channel.

[0004] An apparatus for wireless communication at a UE is described. The apparatus may include a processor, a memory coupled to the processor, and instructions stored in the memory. The instructions may be executed by the processor to cause the apparatus to: receive an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for a distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein a distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold; adjust the distribution scheme to provide an adjusted first amount of the resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and provide a second amount of the resource allocation to the second logical channel, the second amount of the resource allocation corresponding to a second amount of control information to be sent on the second logical channel; and send one or more transport blocks, the one or more transport blocks including the first amount of control information for the first logical channel and the second amount of control information for the second logical channel.

[0005] Another apparatus for wireless communication at a UE is described. The apparatus may include: means for receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for a distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein a distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold; means for adjusting the distribution scheme to provide an adjusted first amount of the resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and providing a second amount of the resource allocation to the second logical channel, the second amount of the resource allocation corresponding to a second amount of control information to be sent on the second logical channel; and means for sending one or more transport blocks, the one or more transport blocks including the first amount of control information for the first logical channel and the second amount of control information for the second logical channel.

[0006] A non-transitory computer-readable medium storing code for wireless communication at a UE is described. The code may include instructions executable by a processor to perform the following operations: receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for a distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein a distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold; adjusting the distribution scheme to provide an adjusted first amount of the resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and providing a second amount of the resource allocation to the second logical channel, the second amount of the resource allocation corresponding to a second amount of control information to be sent on the second logical channel; and sending one or more transport blocks, the one or more transport blocks including the first amount of control information for the first logical channel and the second amount of control information for the second logical channel.

[0007] Some examples of the methods, devices, and non-transitory computer-readable media described herein may also include operations, features, components, or instructions for performing the following operations: re-adjusting the distribution scheme to provide the first logical channel with the remaining portion of the first amount of the resource allocation, and wherein the one or more transport blocks include additional uplink data for at least the first logical channel based on the remaining portion of the first amount of the resource allocation. In some examples of the methods, devices, and non-transitory computer-readable media described herein, the adjustment may include operations, features, components, or instructions for updating to the following operations: updating the first prioritized bit rate (PBR) of the first logical channel to the first amount corresponding to the control information, and updating the second PBR of the second logical channel to the second amount corresponding to the control information. In some examples of the methods, devices, and non-transitory computer-readable media described herein, the first amount of control information and the second amount of control information occupy a first subset of the resource allocation, and the methods, devices, and non-transitory computer-readable media may include operations, features, components, or instructions for performing the following operations: distributing the second subset of the resource allocation between the at least two logical channels based on the original prioritized bit rate associated with each of the at least two logical channels.

[0008] In some examples of the methods, apparatuses, and non-transitory computer-readable media described herein, the adjustment may include operations, features, components, or instructions for performing the following operations: for each of the at least two logical channels, adjusting a prioritized bit rate (PBR) to a minimum of a current PBR or a corresponding amount of control information to be sent on the associated logical channel. In some examples of the methods, apparatuses, and non-transitory computer-readable media described herein, the first amount of control information corresponds to a first number of bytes in a first high priority service protocol data unit (PDU) of the first logical channel, and the second amount of control information corresponds to a second number of bytes in a second high priority service PDU of the second logical channel. In some examples of the methods, apparatuses, and non-transitory computer-readable media described herein, the highest priority logical channel of the two or more logical channels may be provided with any remaining resources of the resource allocation before any resources of the resource allocation are distributed to any lower priority logical channels.

[0009] Some examples of the methods, devices, and non-transitory computer-readable media described herein may also include operations, features, components, or instructions for performing the following operations: forming the one or more transmission blocks for transmission to the network entity according to the distribution scheme. In some examples of the methods, devices, and non-transitory computer-readable media described herein, the adjustment is performed at least in part based on whether the second logical channel has a radio link control (RLC) control protocol data unit (PDU) or high priority data in the associated transmission buffer. In some examples of the methods, devices, and non-transitory computer-readable media described herein, the adjustment is performed based on whether the first logical channel may have a prioritized bit rate (PBR) set to infinity. In some examples of the methods, devices, and non-transitory computer-readable media described herein, the adjustment to the distribution scheme prevents the release of the bearer of the second logical channel by providing resources for at least the second amount of control information for the second logical channel. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 and Figure 2 An example of a wireless communication system supporting control information prioritization techniques for multiple logical channels according to aspects of the present disclosure is illustrated.

[0011] Figure 3 An example of a flow chart illustrating a method of prioritizing control information for multiple logical channels in accordance with aspects of the present disclosure is illustrated.

[0012] Figure 4 An example of a process flow supporting control information prioritization techniques for multiple logical channels in accordance with aspects of the present disclosure is illustrated.

[0013] Figure 5 and Figure 6 A block diagram of an apparatus supporting control information prioritization techniques for multiple logical channels in accordance with aspects of the present disclosure is shown.

[0014] Figure 7 A block diagram of a communications manager supporting control information prioritization techniques for multiple logical channels in accordance with aspects of the present disclosure is shown.

[0015] Figure 8 A diagram of a system including devices supporting control information prioritization techniques for multiple logical channels is shown in accordance with aspects of the present disclosure.

[0016] Fig. 9 and Fig.10 A flow chart illustrating a method of supporting control information prioritization techniques for multiple logical channels in accordance with aspects of the present disclosure is shown. DETAILED DESCRIPTION

[0017] A wireless communication system may include communication devices that support wireless communication of data and control information, such as user equipment (UE) or a network entity (e.g., an eNodeB (eNB), a next-generation Node B, or a gigabit Node B (any of which may be referred to as a gNB), a transmitting and receiving point, or a base station). In some cases, communication between the UE and the network entity may use multiple logical channels, which may define data transfer services provided by a medium access control (MAC) layer. For example, data and signaling messages (e.g., control information messages) may be carried on a logical channel between a radio link control (RLC) layer and a MAC layer of a multi-layer protocol stack, and the logical channel may be divided into a control channel and a traffic channel.

[0018] In the case of multiple logical channels configured (e.g., UE has multiple logical channel identifiers (LCIDs)), the network entity can configure each LCID with a prioritized bit rate (PBR). The PBR may indicate the number of bits of data for the associated LCID to be distributed in the resource allocation before moving to the next LCID, wherein multiple LCIDs may be sorted based on the associated priority. If the resources from the uplink allocation are still remaining after the allocation for each LCID, the UE will repeat the process until the uplink resource allocation is completely consumed or no LCID has more data in its associated buffer. For example, a high priority LCID may have a relatively large amount of data in the buffer and may have a PBR set to infinity, which may cause a lower priority LCID to not obtain any resources from the uplink resource grant. In some cases, a logical channel may have an associated window, and if no transport block (TB) is sent on the logical channel during such an associated window, the logical channel may have a window stagnation that causes the network entity to release the logical channel connection. Therefore, in the case where a higher priority LCID consumes all resource allocations for multiple uplink grants, one or more lower priority LCIDs may be released and the UE will re-establish the channel in order to send any subsequent data. Such a situation may result in inefficiency and increase the overhead and latency associated with the release and re-establishment of logical channels.

[0019] Various aspects of the present disclosure provide a technology for adjusting the resource distribution scheme at the UE so that control data of a lower priority LCID can be sent to avoid window stagnation and connection release of a logical channel. In some cases, the distribution scheme at the UE can be adjusted to change the PBR of each LCID to the amount corresponding only to the high priority information (e.g., control information) existing for each LCID. Then, after the resource is distributed to each LCID for the high priority information, these PBRs for each LCID are reset to the original value, and the remaining uplink resources are distributed according to the LCID priority and these associated PBRs. Such technology can provide for sending the higher priority data (e.g., RLC control protocol data unit (PDU) transmission or other high priority information) of each LCID in order to avoid window stagnation, because the network entity identifies that the RLC transmission window is moving and the connection associated with the LCID is therefore maintained.

[0020] The subject matter described in the present disclosure can be implemented so that wireless communication systems can achieve efficient communications, reduced power consumption, lower latency, etc. For example, configuring a communication device to support adjustments to resource distribution techniques to provide sufficient resources to lower priority logical channels to prevent window stagnation as described herein can result in reduced system latency and reduced overhead associated with less release of logical channels, as well as a corresponding reduction in power usage.

[0021] Various aspects of the present disclosure are first described in the context of a wireless communication system. Examples of processes and signaling exchanges that support control information prioritization are then described. Various aspects of the present disclosure are further illustrated and described by and with reference to apparatus diagrams, system diagrams, and flow diagrams related to control information prioritization techniques for multiple logical channels.

[0022] Figure 1 An example of a wireless communication system 100 supporting control information prioritization techniques for multiple logical channels according to various aspects of the present disclosure is illustrated. The wireless communication system 100 may include one or more base stations 105 (which may be examples of access network entities), one or more UEs 115, and a core network 130. In some examples, the wireless communication system 100 may be a long term evolution (LTE) network, an advanced LTE (LTE-A) network, an LTE-A Pro network, or a new radio (NR) network. In some examples, the wireless communication system 100 may support enhanced broadband communication, ultra-reliable communication, low latency communication, or communication with low-cost and low-complexity devices, or any combination thereof.

[0023] The base stations 105 may be dispersed throughout a geographic area to form the wireless communication system 100, and may be different forms of devices or devices with different capabilities. The base stations 105 and the UEs 115 may communicate wirelessly via one or more communication links 125. Each base station 105 may provide a coverage area 110 over which the UEs 115 and the base stations 105 may establish one or more communication links 125. The coverage area 110 may be an example of a geographic area over which the base stations 105 and the UEs 115 may support communication of signals according to one or more radio access technologies.

[0024] The UEs 115 may be dispersed throughout the coverage area 110 of the wireless communication system 100, and each UE 115 may be stationary or mobile or both stationary and mobile at different times. The UEs 115 may be devices in different forms or with different capabilities. Figure 1 Some example UEs 115 are illustrated in FIG. 1 . The UEs 115 described herein may be capable of communicating with various types of devices, such as other UEs 115, base stations 105, or network equipment (e.g., core network nodes, relay devices, IAB nodes, or other network equipment), such as Figure 1 shown.

[0025] The base stations 105 may communicate with the core network 130, or with each other, or both. For example, the base stations 105 may interface with the core network 130 via one or more backhaul links 120 (e.g., via S1, N2, N3, or other interfaces). The base stations 105 may communicate with each other via the backhaul links 120 (e.g., via X2, Xn, or other interfaces) directly (e.g., directly between the base stations 105) or indirectly (e.g., via the core network 130), or both. In some examples, the backhaul links 120 may be or include one or more wireless links. The UE 115 may communicate with the core network 130 via the communication link 155.

[0026] One or more of the base stations 105 described herein may include or may be referred to by a person of ordinary skill in the art as a transceiver base station, a radio base station, an access point, a network entity, a radio transceiver, a NodeB, an eNodeB (eNB), a next generation NodeB or a giga NodeB (any of which may be referred to as a gNB), a Home NodeB, a Home eNodeB, or other suitable terminology.

[0027] UE 115 may include or may be referred to as a mobile device, a wireless device, a remote device, a handheld device, or a subscriber device, or some other suitable term, where a "device" may also be referred to as a unit, a station, a terminal, or a client, etc. UE 115 may also include or may be referred to as a personal electronic device, such as a cellular phone, a personal digital assistant (PDA), a tablet computer, a laptop computer, or a personal computer. In some examples, UE 115 may include or may be referred to as a wireless local loop (WLL) station, an Internet of Things (IoT) device, an Internet of Everything (IoE) device, or a machine type communication (MTC) device, etc., which may be implemented in various objects such as appliances or vehicles, meters, etc.

[0028] like Figure 1 As shown, the UE 115 described herein may be able to communicate with various types of devices, such as other UEs 115, which may sometimes act as repeaters, as well as base stations 105 and network equipment, including macro eNBs or gNBs, small cell eNBs or gNBs, or relay base stations, etc.

[0029] The UE 115 and the base station 105 may communicate wirelessly with each other via one or more communication links 125 on one or more carriers. The term "carrier" may refer to a collection of radio frequency spectrum resources having a defined physical layer structure for supporting the communication link 125. For example, a carrier for the communication link 125 may include a portion of a radio frequency spectrum band (e.g., a bandwidth portion (BWP)) operating according to one or more physical layer channels of a given radio access technology (e.g., LTE, LTE-A, LTE-A Pro, NR). Each physical layer channel may carry acquisition signaling (e.g., synchronization signals, system information), control signaling for coordinating carrier operations, user data, or other signaling. The wireless communication system 100 may support communications with the UE 115 using carrier aggregation or multi-carrier operation. Depending on the carrier aggregation configuration, the UE 115 may be configured to have multiple downlink component carriers and one or more uplink component carriers. Carrier aggregation may be used for both frequency division duplex (FDD) and time division duplex (TDD) component carriers.

[0030] The signal waveform sent on the carrier may include multiple subcarriers (e.g., using multi-carrier modulation (MCM) techniques, such as orthogonal frequency division multiplexing (OFDM) or discrete Fourier transform spread OFDM (DFT-S-OFDM)). In a system using MCM technology, a resource element may include a symbol period (e.g., the duration of a modulation symbol) and a subcarrier, where the symbol period and the subcarrier spacing are inversely related. The number of bits carried by each resource element may depend on the modulation scheme (e.g., the order of the modulation scheme, the coding rate of the modulation scheme, or both). Therefore, the more resource elements received by UE 115 and the higher the order of the modulation scheme, the higher the data rate for UE 115 can be. Wireless communication resources may refer to a combination of radio frequency spectrum resources, time resources, and spatial resources (e.g., spatial layers or beams), and the use of multiple spatial layers can further improve the data rate or data integrity of communications with UE 115.

[0031] The time interval of the base station 105 or the UE 115 can be expressed as a multiple of a basic time unit, which can be, for example, a sampling period T s =1 / (Δf max ·N f ) seconds, where Δf max It can represent the maximum supported subcarrier spacing, and N f The maximum supported discrete Fourier transform (DFT) size may be indicated. Time intervals of the communication resources may be organized according to radio frames, each having a specified duration (e.g., 10 milliseconds (ms)). Each radio frame may be identified by a system frame number (SFN) (e.g., ranging from 0 to 1023).

[0032] Each frame may include multiple consecutively numbered subframes or time slots, and each subframe or time slot may have the same duration. In some examples, the frame may be divided into subframes (e.g., in the time domain), and each subframe may be further divided into a number of time slots. Alternatively, each frame may include a variable number of time slots, and the number of time slots may depend on the subcarrier spacing. Each time slot may include a number of symbol periods (e.g., depending on the length of the cyclic prefix appended in front of each symbol period). In some wireless communication systems 100, the time slot may be further divided into a plurality of mini-time slots containing one or more symbols. Excluding the cyclic prefix, each symbol period may contain one or more (e.g., N f The duration of a symbol period may depend on the subcarrier spacing or the operating band.

[0033] A subframe, a time slot, a mini-time slot, or a symbol may be the smallest scheduling unit (e.g., in the time domain) of the wireless communication system 100 and may be referred to as a transmission time interval (TTI). In some examples, the TTI duration (e.g., the number of symbol periods in a TTI) may be variable. Additionally or alternatively, the smallest scheduling unit of the wireless communication system 100 may be dynamically selected (e.g., in a burst of a short TTI (sTTI)).

[0034] Physical channels may be multiplexed on a carrier according to various techniques. For example, physical control channels and physical data channels may be multiplexed on a downlink carrier using one or more of a time division multiplexing (TDM) technique, a frequency division multiplexing (FDM) technique, or a hybrid TDM-FDM technique. A control region (e.g., a control resource set (CORESET)) of a physical control channel may be defined by a number of symbol periods and may extend across a system bandwidth or a subset of a system bandwidth of a carrier. One or more control regions (e.g., CORESETs) may be configured for a set of UEs 115. For example, one or more UEs in UE 115 may monitor or search a control region for control information according to one or more search space sets, and each search space set may include one or more control channel candidates in one or more aggregation levels arranged in a cascaded manner. The aggregation level of a control channel candidate may refer to the number of control channel resources (e.g., control channel elements (CCEs)) associated with coded information for a control information format having a given payload size. The search space sets may include a common search space set configured for transmitting control information to multiple UEs 115 , and a UE-specific search space set for transmitting control information to a specific UE 115 .

[0035] In some examples, base stations 105 may be mobile and, therefore, provide communication coverage for mobile geographic coverage areas 110. In some examples, different geographic coverage areas 110 associated with different technologies may overlap, but the different geographic coverage areas 110 may be supported by the same base station 105. In other examples, overlapping geographic coverage areas 110 associated with different technologies may be supported by different base stations 105. The wireless communication system 100 may include, for example, a heterogeneous network in which different types of base stations 105 provide coverage for various geographic coverage areas 110 using the same or different radio access technologies.

[0036] The wireless communication system 100 may be configured to support ultra-reliable communication or low-latency communication or various combinations thereof. For example, the wireless communication system 100 may be configured to support ultra-reliable low-latency communication (URLLC). The UE 115 may be designed to support ultra-reliable or low-latency or critical functions. Ultra-reliable communication may include private communication or group communication, and may be supported by one or more services (such as push-to-talk, video, or data). Support for ultra-reliable, low-latency functions may include prioritization of services, and such services may be used for public safety or general commercial applications. The terms ultra-reliable, low-latency, and ultra-reliable low-latency are used interchangeably herein.

[0037] In some examples, UE 115 may also be able to communicate directly with other UE 115 over a device-to-device (D2D) communication link 135 (e.g., using a peer-to-peer (P2P) or D2D protocol). One or more UEs 115 utilizing D2D communication may be located within a geographic coverage area 110 of a base station 105. Other UEs 115 in such a group may be outside the geographic coverage area 110 of the base station 105, or may be unable to receive transmissions from the base station 105 for other reasons. In some examples, a group of UEs 115 communicating via D2D communication may utilize a one-to-many (1:M) system, in which each UE 115 transmits to each other UE 115 in the group. In some examples, the base station 105 facilitates scheduling resources for D2D communication. In other cases, D2D communication is performed between these UEs 115 without the involvement of the base station 105.

[0038] The core network 130 may provide user authentication, access authorization, tracking, Internet Protocol (IP) connectivity, and other access, routing, or mobility functions. The core network 130 may be an evolved packet core (EPC) or a 5G core (5GC), which may include at least one control plane entity for managing access and mobility (e.g., a mobility management entity (MME), an access and mobility management function (AMF)) and at least one user plane entity for routing packets or interconnecting to an external network (e.g., a serving gateway (S-GW)), a packet data network (PDN) gateway (P-GW), or a user plane function (UPF)). The control plane entity may manage non-access stratum (NAS) functions, such as mobility, authentication, and bearer management for UE 115 served by a base station 105 associated with the core network 130. User IP packets may be transferred via a user plane entity, which may provide IP address allocation and other functions. The user plane entity may be connected to an IP service 150 for one or more network operators. IP services 150 may include access to the Internet, an intranet, an IP Multimedia Subsystem (IMS), or packet-switched streaming services.

[0039] Some network devices, such as base stations 105, may include subcomponents, such as access network entities 140, which may be examples of access node controllers (ANCs). Each access network entity 140 may communicate with UE 115 through one or more other access network transmission entities 145, which may be referred to as radio heads, smart radio heads, or transmit / receive points (TRPs). Each access network transmission entity 145 may include one or more antenna panels. In some configurations, the various functions of each access network entity 140 or base station 105 may be distributed across various network devices (e.g., radio heads and ANCs) or merged into a single network device (e.g., base station 105).

[0040] The wireless communication system 100 may operate using one or more frequency bands, for example, in the range of 300 megahertz (MHz) to 300 kilohertz (GHz). The region from 300 MHz to 3 GHz is often referred to as the ultra-high frequency (UHF) region or decimeter band because the wavelength range is about 1 decimeter to 1 meter. UHF waves may be blocked or redirected by buildings and environmental features, but these waves may be sufficient to penetrate structures so that macro cells provide services to UEs 115 located indoors. Transmission of UHF waves may be associated with smaller antennas and shorter ranges (e.g., less than 100 kilometers) compared to transmission using smaller frequencies and longer wavelengths in the high frequency (HF) or very high frequency (VHF) portions of the spectrum below 300 MHz.

[0041] The electromagnetic spectrum is typically subdivided into various categories, bands, channels, etc. based on frequency / wavelength. In 5GNR, two initial operating bands have been identified as frequency range designations FR1 (410 MHz-7.125 GHz) and FR2 (24.25 GHz-52.6 GHz). It should be understood that although a portion of FRI is greater than 6 GHz, in various documents and articles, FRI is often (interchangeably) referred to as the "below 6 GHz" band. A similar naming problem sometimes occurs with respect to FR2, which is often (interchangeably) referred to as the "millimeter wave" band in documents and articles, although it is different from the extremely high frequency (EHF) band (30 GHz-300 GHz) identified as the "millimeter wave" band by the International Telecommunication Union (ITU).

[0042] Frequencies between FR1 and FR2 are generally referred to as mid-band frequencies. Recent 5G NR research has identified the operating bands for these mid-band frequencies as frequency range designation FR3 (7.125GHz-24.25GHz). The bands falling within FR3 can inherit FR1 characteristics and / or FR2 characteristics, and therefore the features of FR1 and / or FR2 can be effectively extended to mid-band frequencies. In addition, higher frequency bands are currently being explored to extend 5G NR operations to more than 52.6GHz. For example, three higher operating bands have been identified as frequency range designations FR4a or FR4-1 (52.6GHz-71GHz), FR4 (52.6GHz-114.25GHz) and FR5 (114.25GHz-300GHz). Each of these higher frequency bands falls within the EHF band.

[0043] In view of the above aspects, unless otherwise specifically stated, it should be understood that if used in this article, the term "sub-6 GHz" and the like can be broadly referred to as frequencies that can be less than 6 GHz, can be within FR1, or can include mid-band frequencies. In addition, unless otherwise specifically stated, it should be understood that if the term "millimeter wave" and the like are used in this article, they can be broadly referred to as frequencies that can include mid-band frequencies, can be within FR2, FR4, FR4-a or FR4-1 and / or FR5, or can be within the EHF band.

[0044] The wireless communication system 100 may utilize both licensed and unlicensed radio frequency spectrum bands. For example, the wireless communication system 100 may employ licensed assisted access (LAA), LTE unlicensed (LTE-U) radio access technology, or NR technology in unlicensed bands such as the 5 GHz industrial, scientific, and medical (ISM) band. When operating in an unlicensed radio frequency spectrum band, devices (such as base stations 105 and UEs 115) may employ carrier sensing for conflict detection and conflict avoidance. In some examples, operations in unlicensed bands may be based on carrier aggregation configurations (e.g., LAA) in conjunction with component carriers operating in licensed bands. Operations in unlicensed spectrum may include downlink transmissions, uplink transmissions, P2P transmissions, or D2D transmissions, and the like.

[0045] The base station 105 or UE 115 may be equipped with multiple antennas, which can be used to employ technologies such as transmit diversity, receive diversity, multiple-input multiple-output (MIMO) communication, or beamforming. The antennas of the base station 105 or UE 115 may be located in one or more antenna arrays or antenna panels, which may support MIMO operations or transmit beamforming or receive beamforming. For example, one or more base station antennas or antenna arrays may be co-located at an antenna assembly such as an antenna tower. In some examples, the antennas or antenna arrays associated with the base station 105 may be located at different geographical locations. The base station 105 may have an antenna array with several rows and columns of antenna ports, which the base station 105 may use to support beamforming for communications with the UE 115. Similarly, the UE 115 may have one or more antenna arrays, which may support various MIMO or beamforming operations. Additionally or alternatively, the antenna panel may support radio frequency beamforming for signals sent via the antenna ports.

[0046] Beamforming (which may also be referred to as spatial filtering, directional transmission, or directional reception) is a signal processing technique that may be used at a transmitting device or a receiving device (e.g., a base station 105, a UE 115) to form or direct an antenna beam (e.g., a transmit beam, a receive beam) along a spatial path between the transmitting device and the receiving device. Beamforming may be achieved by combining signals conveyed via antenna elements of an antenna array so that some signals propagating at a particular orientation relative to the antenna array experience constructive interference, while other signals experience destructive interference. Adjustments to signals conveyed via antenna elements may include the transmitting device or the receiving device applying an amplitude offset, a phase offset, or both to signals carried via antenna elements associated with the device. Adjustments associated with each of these antenna elements may be defined by a set of beamforming weights associated with a particular orientation (e.g., relative to the antenna array of the transmitting device or the receiving device or relative to some other orientation).

[0047] UE 115 and base station 105 may support retransmission of data to increase the likelihood that the data is successfully received. Hybrid automatic repeat request (HARQ) feedback is a technique for increasing the likelihood of correctly receiving data through communication link 125. HARQ may include a combination of error detection (e.g., using cyclic redundancy check (CRC)), forward error correction (FEC), and retransmission (e.g., automatic repeat request (ARQ)). HARQ may improve the throughput at the medium access control (MAC) layer under poor radio conditions (e.g., low signal and noise conditions). In some examples, a device may support simultaneous slot HARQ feedback, wherein the device may provide HARQ feedback in a specific time slot for data received in a previous symbol in the time slot. In other cases, the device may provide HARQ feedback in a subsequent time slot or according to some other time interval.

[0048] In addition to or instead of being performed between the UE 115 and the base station 105, the techniques described herein may also be implemented via additional or alternative wireless devices (including IAB nodes 104, distributed units (DU) 165, centralized units (CU) 160, radio units (RU) 170, etc.). For example, in some specific implementations, the various aspects described herein may be implemented in the context of a decomposed radio access network (RAN) architecture (e.g., an open RAN architecture). In a decomposed architecture, the RAN may be split into three functional areas corresponding to the CU 160, DU 165, and RU 170. The functional split between the CU 160, DU 165, and RU 175 is flexible, and therefore many permutations of different functionality are generated depending on which functions (e.g., MAC functions, baseband functions, radio frequency functions, and any combination thereof) are performed at the CU 160, DU 165, and RU 175. For example, a functional split of the protocol stack may be employed between the DU 165 and the RU 170 such that the DU 165 may support one or more layers of the protocol stack and the RU 170 may support one or more different layers of the protocol stack.

[0049] Some wireless communication systems (e.g., wireless communication system 100), infrastructure for NR access, and spectrum resources may additionally support wireless backhaul link capabilities to supplement wired backhaul connections, thereby providing an IAB network architecture. One or more base stations 105 may include CU 160, DU 165, and RU 170, and may be referred to as donor base stations 105 or IAB donors. One or more DUs 165 (e.g., and / or RU 170) associated with the donor base station 105 may be controlled in part by the CU 160 associated with the donor base station 105. One or more donor base stations 105 (e.g., IAB donors) may communicate with one or more additional base stations 105 (e.g., IAB nodes 104) via supported access and backhaul links. The IAB node 104 may support mobile terminal (MT) functionality controlled and / or scheduled by the DU 165 of the coupled IAB donor. Additionally, the IAB node 104 may include a DU 165 that supports communication links with additional entities (e.g., IAB node 104, UE 115, etc.) within a relay chain or configuration (e.g., downstream) of the access network. In such cases, one or more components of the decomposed RAN architecture (e.g., one or more IAB nodes 104 or components of the IAB node 104) may be configured to operate in accordance with the techniques described herein.

[0050] In some examples, the wireless communication system 100 may include a core network 130 (e.g., a next generation core network (NGC)), one or more IAB donors, IAB nodes 104, and UEs 115, wherein the IAB nodes 104 may be controlled in part by each other and / or the IAB donor. The IAB donor node and the IAB node 104 may be examples of aspects of a base station 105. The IAB donor and the one or more IAB nodes 104 may be configured as a relay chain (e.g., or communicate according to a relay chain).

[0051] For example, an access network (AN) or RAN may refer to an access node (e.g., an IAB donor), communications between an IAB node 104, and one or more UEs 115. An IAB donor may facilitate a connection between a core network 130 and an AN (e.g., via a wired or wireless connection to the core network 130). That is, an IAB donor may refer to a RAN node having a wired or wireless connection to the core network 130. An IAB donor may include a CU 160 and at least one DU 165 (e.g., and RU 170), wherein the CU 160 may communicate with the core network 130 via an NG interface (e.g., some backhaul links). The CU 160 may be responsible for Layer 3 (L3) (e.g., RRC, Service Data Adaptation Protocol (SDAP), PDCP, etc.) functionality and signaling. At least one DU 165 and / or RU 170 may be responsible for lower layers, such as layer 1 (L1) and layer 2 (L2) (e.g., RLC, MAC, physical (PHY), etc.) functionality and signaling, and may each be controlled at least in part by CU 160. DU 165 may support one or more different cells. The IAB donor and IAB node 104 may communicate over the F1 interface according to a certain protocol (e.g., F1 AP protocol) that defines signaling messages. In addition, CU 160 may communicate with the core network over an NG interface (which may be an example of a portion of a backhaul link) and may communicate with other CUs 160 (e.g., CUs 160 associated with alternative IAB donors) over an Xn-C interface (which may be an example of a portion of a backhaul link).

[0052] An IAB node 104 may refer to a RAN node that provides IAB functionality (e.g., access for UE 115, wireless self-backhaul capabilities, etc.). An IAB node 104 may include a DU 165 and a MT. The DU 165 may act as a distributed scheduling node toward a child node associated with the IAB node 104, and the MT may act as a scheduled node toward a parent node associated with the IAB node 104. That is, an IAB donor may be referred to as a parent node that communicates with one or more child nodes (e.g., an IAB donor may relay transmissions for a UE through one or more other IAB nodes 104). In addition, depending on the relay chain or configuration of the AN, an IAB node 104 may also be referred to as a parent node or a child node of other IAB nodes 104. Thus, the MT entity (eg, MT) of IAB node 104 may provide a Uu interface for the child node to receive signaling from parent IAB node 104, and the DU interface (eg, DU 165) may provide a Uu interface for the parent node to signal to child IAB node 104 or UE 115.

[0053] For example, the IAB node 104 may be referred to as a parent node associated with the IAB node and a child node associated with the IAB donor. The IAB donor may include a CU 160 having a wired (e.g., optical fiber) or wireless connection to the core network, and may act as a parent node of the IAB node 104. For example, the DU 165 of the IAB donor may relay the transmission to the UE 115 through the IAB node 104, and may directly signal the UE 115 of the transmission. The CU 160 of the IAB donor may signal the IAB node 104 of the communication link establishment via the F1 interface, and the IAB node 104 may schedule the transmission (e.g., the transmission relayed from the IAB donor to the UE 115) through the DU 165. That is, data may be relayed to and from the IAB node 104 via signaling on the NR Uu interface of the MT to the IAB node 104. Communications with the IAB node 104 may be scheduled by the DU 165 of the IAB donor, and communications with the IAB node 104 may be scheduled by the DU 165 of the IAB node 104 .

[0054] Where the techniques described herein are applied in the context of a decomposed RAN architecture, one or more components of the decomposed RAN architecture (e.g., one or more network entities, such as one or more IAB nodes 104 or components of IAB nodes 104) may be configured to support the techniques for resource allocation distribution for multiple logical channels as described herein. For example, some operations described as being performed by UE 115 or base station 105 may additionally or alternatively be performed by components of the decomposed RAN architecture (e.g., IAB nodes, DUs, CUs, other network entities, etc.).

[0055] In the wireless communication system 100, the UE 115 and the base station 105 (e.g., an eNodeB (eNB), a next generation NodeB or a gigabit NodeB (any of which may be referred to as a gNB), or some other base station) may support wireless communication via one or more radio access technologies. Examples of radio access technologies include 4G systems (such as LTE systems) and 5G systems (which may be referred to as NR systems). The wireless communication system 100 may be configured to support the techniques for resource allocation distribution for multiple logical channels as described herein. For example, one or more devices may include a UE communication manager 101, a base station communication manager 102, or any combination thereof, which may be as described herein with reference to Figures 5 to 8An example of the communication manager described herein. UE 115 and base station 105 may perform resource allocation procedures and associated communications via the communication manager. For example, UE 115 may send a buffer status report (BSR) via the communication manager 101, which may indicate that there is an uplink data volume for uplink transmission at UE 115, and the uplink data volume may include data associated with multiple logical channels. Base station 105 may send an uplink grant to UE 115 via the communication manager 102, and the uplink grant indicates that UE 115 can be used for uplink communication. A set of uplink resources. Based on the configured LCID and the associated priority and the corresponding configured PBR, UE 115 can distribute uplink resources among multiple LCIDs according to the technology discussed herein.

[0056] Figure 2 An example of a wireless communication system 200 that supports control information prioritization techniques for multiple logical channels in accordance with various aspects of the present disclosure is illustrated. For example, the wireless communication system 200 may include a network entity 105-a and a UE 115-a, which may be examples of a base station 105 and a UE 115 as described herein. Additionally or alternatively, the UE 115-a and the network entity 105-a may be examples of an IAB node, a CPE, or other devices described herein. The UE 115-a may send an uplink communication 205 to the network entity 105-a, and the network entity 105-a may send a downlink communication 210 to the UE 115-a.

[0057] In some examples, the network entity 105-a may send control signaling 215 to the UE 115-a. In some cases, the control signaling 215 may indicate one or more LCIDs configured at the UE 115-a, wherein each LCID may have an associated priority and PBR, such as illustrated in table 230. According to various techniques discussed herein, the UE 115-a may adjust one or more PBRs in one or more LCIDs so as to provide sufficient transmission on each LCID to avoid window stagnation. In this example, the network entity 105-a may send an uplink grant 220 to the UE 115-a, which includes an uplink resource allocation for the UE 115-a. The UE 115-a may distribute the uplink resource allocation on the configured LCIDs and may send an uplink TB 225 to the network entity 105-a. In some cases, the UE 115-a may perform the adjustment of the PBR without any signaling or indication to the network entity 105-a. In other cases, the control signaling 215 may enable PBR adjustment to be performed at the UE 115 - a .

[0058] As discussed herein, in the case where multiple logical channels are configured, the network entity 105-a may configure each LCID using a PBR. The PBR may indicate the number of bits of data for the associated LCID to be distributed in the resource allocation before moving to the next LCID, which may be infinite (e.g., it indicates that all buffered data for the LCID may be allocated up to the amount of allocated uplink resources). Multiple LCIDs may be sorted based on associated priorities. If resources from the uplink allocation still remain after allocation for each LCID, the UE 115-a will repeat the process until the uplink resource allocation is completely consumed or no LCID has more data in its associated buffer.

[0059] For example, as illustrated in Table 230, UE 115-a may be configured with four LCIDs having corresponding LCID priorities 1 to 4. In this example, LCID1 has a 100-byte data buffer and has 10 bytes of high priority data (e.g., 10 bytes of RLC control PDU data). In addition, LCID2 has a 100-byte data buffer and a 20-byte high priority buffer, LCID3 has a 300-byte data buffer and a 30-byte high priority buffer, and LCID4 has a 400-byte data buffer and a 40-byte high priority buffer. If UE 115-a were to maintain a static PBR and the PBR for each LCID was set to infinity, an uplink grant allocating 660 bytes or less of resources would result in at least one of the LCIDs being unable to send any data. For example, if UE 115-a gets a grant of 200 bytes from network entity 105-a based on the configured PBR and currently pending data, LCID1 will get 110 bytes, LCID2 will get 90 bytes, and LCID3 and LCID4 will each get zero bytes. If this pattern continues for a certain period of time, network entity 105-a may detect it as a window stagnation for LCID3 and LCID4, and may release the associated connections based on a timer.

[0060] According to various techniques described herein, UE 115-a can adjust the distribution scheme of uplink resources to efficiently allocate grants and ensure that lower priority LCIDs get a certain portion of uplink grants (e.g., so that prioritized data such as RLC control PDUs or other priority data can be sent), and network entity 105-a will receive data (e.g., prioritized data) for lower priority LCIDs and will not release the associated connection. In some cases, if the lower priority LCD has RLC control PDUs or generally any higher priority data (e.g., data other than newly transmitted data indicated by a switched new data indicator (NDI)) to send, it will update the higher priority LCID PBR to accommodate the transmission of at least some of the data on the lower priority LCID. For example, for each higher priority LCID, the PBR can be adjusted according to the following formula:

[0061] New PBR = MIN (current PBR, current prioritized data pending buffer).

[0062] Continuing the example from table 230 above, the PBR of LCID1 may be adjusted to 10, the PBR of LCID2 may be adjusted to 20, the PBR of LCID3 may be adjusted to 30, and the PBR of LCID4 may be adjusted to 40. With the adjusted PBRs and the same 200 bytes of uplink resources, the distribution of grants to each LCID would be as follows:

[0063] 1.LCID 1: 110 bytes (10 for RLC control PDU + 100 for new TX);

[0064] 2.LCID 2: 20 bytes (20 for RLC control PDU);

[0065] 3.LCID 3: 30 bytes (30 for RLC control PDU);

[0066] 4.LCID 4: 40 bytes (40 is used for RLC control PDU).

[0067] Therefore, in this example, LCID4 and LCID5 are used for higher priority data (e.g., for RLC control PDUs). Such techniques can help prioritize RLC control PDUs or other priority data so that data stagnation is reduced or eliminated, and the network entity 105-a sees the RLC send window move and thus maintains the associated connection. After the TB for higher priority data is formed, the UE 115-a can restore the PBR value to the configuration value received from the network entity 105-a, and any remaining uplink resources can be distributed accordingly. Such techniques can therefore also distribute resources to lower priority LCIDs to ensure that the RLC control PDU or any higher priority data is sent in a timely manner in the order of LCID priority, which can prevent the window stagnation of the lower priority LCID. In addition, the suboptimal PBR configuration performed by the network entity 105-a can be dynamically addressed according to the needs of the UE115-a.

[0068] Figure 3 An example of a flowchart 300 for supporting control information prioritization techniques for multiple logical channels according to various aspects of the present disclosure is illustrated. The operations of the flowchart 300 may be implemented by a UE or components thereof as described herein. For example, the operations may be implemented by a UE as described in reference to Figure 1 and Figure 2 The UE 115 may be used to perform the functions described. In some examples, the UE may execute an instruction set to control the functional elements of the UE to perform the functions described. Additionally or alternatively, the UE may use dedicated hardware to perform various aspects of the functions described.

[0069] In this example, operations may begin at 305. At 310, the UE may receive an uplink grant. In some cases, the uplink grant may be received from a network entity and may include an allocation of an uplink resource set. At 315, the UE may determine whether any lower priority LCID has a control PDU (or other higher priority data) to send, and whether any higher priority LCID has a PBR set to infinity.

[0070] If the determination at 315 is yes, then at 320, the UE may adjust one or more PBRs according to the techniques discussed herein. For example, for each LCID, the UE may rewrite the PBR to a new PBR = MIN (current PBR, current RLC control PDU / higher priority data buffer size). At 325, the UE may form TBs according to LCID priority based on the adjusted PBR. At 330, the UE may restore the PBR to the original value. At 335, after the operation at 330 or after the "no" determination at 315, the UE may perform TB formation according to LCID priority based on the original PBR. The operation may end at 340.

[0071] Figure 4 An example of a process flow 400 supporting a control information prioritization technique for multiple logical channels according to aspects of the present disclosure is illustrated. The process flow 400 may be implemented with reference to Figure 1 and Figure 2 Various aspects of the wireless communication system 100 and the wireless communication system 200 are described.

[0072] In the following description of process flow 400, operations between network entity 105-b and UE 115-b may be sent in an order different from the example order shown, or operations performed by network entity 105-b and UE 115-b may be performed in a different order or at a different time. Some operations may also be omitted from process flow 400, and other operations may be added to process flow 400. Network entity 105-b and UE 115-b may be as described with reference to FIG. Figure 1 and Figure 2 Examples of network entity 105 and UE 115 are described.

[0073] UE 115-b may establish a communication link with network entity 105-b according to a connection establishment technique (e.g., an RRC connection establishment technique). At 405, network entity 105-b may send control signaling to UE 115-b. The control signaling may include, for example, configuration information for multiple logical channels, which may include an associated priority and PBR for each LCID. In some examples, network entity 105-b may send control signaling in system information, radio resource control (RRC) signaling, MAC-CE, downlink control information, etc.

[0074] Optionally, at 410, UE 115-b may send a buffer status report (BSR). The BSR may indicate an amount of uplink data to be sent from UE 115-b on one or more logical channels. At 415, network entity 105-b may send an uplink grant to UE 115-b. For example, the uplink grant may include an uplink resource allocation for a set of uplink resources.

[0075] At 420, the UE 115-b may adjust the distribution scheme based on the buffer for each LCID and the priority associated with each LCID. The adjustment may include adjusting the PBR associated with one or more LCIDs according to the techniques discussed herein. At 425, the UE 115-b may distribute resources across the LCIDs based on the adjustment. Optionally, at 430, the UE 115-b may readjust the PBR and the distribution scheme, and at 435, the UE 115-b may distribute any remaining resources from the uplink resource set allocated in the uplink grant. At 440, the UE 115-b may send an uplink transmission to the network entity 105-b, including higher priority data for one or more lower priority LCIDs.

[0076] Figure 5 A block diagram 500 of a device 505 supporting control information prioritization techniques for multiple logical channels according to aspects of the present disclosure is shown. The device 505 may be an example of aspects of the UE 115 as described herein. The device 505 may include a receiver 510, a transmitter 515, and a communication manager 520. The device 505 may also include a processor. Each of these components may be in communication with each other (e.g., via one or more buses).

[0077] The receiver 510 may provide means for receiving information such as packets associated with various information channels (e.g., control channels, data channels, information channels related to control information prioritization techniques for multiple logical channels), user data, control information, or any combination thereof. The information may be communicated to other components of the device 505. The receiver 510 may utilize a single antenna or a collection of multiple antennas.

[0078] The transmitter 515 may provide means for transmitting signals generated by other components of the device 505. For example, the transmitter 515 may transmit information such as packets associated with various information channels (e.g., control channels, data channels, information channels related to control information prioritization techniques for multiple logical channels), user data, control information, or any combination thereof. In some examples, the transmitter 515 may be co-located with the receiver 510 in a transceiver module. The transmitter 515 may utilize a single antenna or a collection of multiple antennas.

[0079] The communication manager 520, the receiver 510, the transmitter 515, or various combinations thereof, or various components thereof may be examples of means for performing various aspects of the control information prioritization techniques for multiple logical channels as described herein. For example, the communication manager 520, the receiver 510, the transmitter 515, or various combinations or components thereof may support methods for performing one or more of the functions described herein.

[0080] In some examples, the communication manager 520, the receiver 510, the transmitter 515, or various combinations or components thereof may be implemented in hardware (e.g., in a communication management circuit). The hardware may include a processor, a digital signal processor (DSP), an application specific integrated circuit (ASIC), a field programmable gate array (FPGA) or other programmable logic device, discrete gate or transistor logic components, discrete hardware components, or any combination thereof that is configured to or otherwise supports means for performing the functions described in the present disclosure. In some examples, a processor and a memory coupled to the processor may be configured to perform one or more functions described herein (e.g., by executing instructions stored in the memory by the processor).

[0081] Additionally or alternatively, in some examples, the communication manager 520, the receiver 510, the transmitter 515, or various combinations or components thereof may be implemented in code executed by a processor (e.g., as communication management software or firmware). If implemented in code executed by a processor, the functionality of the communication manager 520, the receiver 510, the transmitter 515, or various combinations or components thereof may be performed by a general purpose processor (e.g., configured as or otherwise supporting means for performing the functionality described in the present disclosure), a DSP, a central processing unit (CPU), an ASIC, an FPGA, or any combination of these or other programmable logic devices.

[0082] In some examples, communication manager 520 can be configured to perform various operations (e.g., receive, monitor, transmit) using or otherwise cooperating with receiver 510, transmitter 515, or both. For example, communication manager 520 can receive information from receiver 510, transmit information to transmitter 515, or be integrated in conjunction with receiver 510, transmitter 515, or both to receive information, transmit information, or perform various other operations as described herein.

[0083] According to an example as disclosed herein, the communication manager 520 may support wireless communication at a UE. For example, the communication manager 520 may be configured to or otherwise support a means for receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for a distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein the distribution scheme provides a first amount of resource allocation to the first logical channel, and the first amount exceeds a threshold. The communication manager 520 may be configured to or otherwise support a means for adjusting the distribution scheme to provide an adjusted first amount of resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and to provide a second amount of resource allocation to the second logical channel, the second amount of resource allocation corresponding to a second amount of control information to be sent on the second logical channel. The communication manager 520 may be configured to or otherwise support a means for sending one or more transport blocks, the one or more transport blocks including a first amount of control information for the first logical channel and a second amount of control information for the second logical channel.

[0084] By including or configuring the communication manager 520 according to the examples described herein, the device 505 (e.g., a processor controlling or otherwise coupled to the receiver 510, the transmitter 515, the communication manager 520, or a combination thereof) can support adjustments to the resource distribution techniques to provide sufficient resources to lower priority logical channels to prevent window stagnation as described herein, which can result in reduced system latency, reduced overhead associated with less release of logical channels, and a corresponding reduction in power usage.

[0085] Figure 6 A block diagram 600 of a device 605 supporting control information prioritization techniques for multiple logical channels according to aspects of the present disclosure is shown. The device 605 may be an example of aspects of the device 505 or UE 115 as described herein. The device 605 may include a receiver 610, a transmitter 615, and a communication manager 620. The device 605 may also include a processor. Each of these components may be in communication with each other (e.g., via one or more buses).

[0086] The receiver 610 may provide means for receiving information such as packets associated with various information channels (e.g., control channels, data channels, information channels related to control information prioritization techniques for multiple logical channels), user data, control information, or any combination thereof. The information may be communicated to other components of the device 605. The receiver 610 may utilize a single antenna or a collection of multiple antennas.

[0087] The transmitter 615 may provide means for transmitting signals generated by other components of the device 605. For example, the transmitter 615 may transmit information such as packets associated with various information channels (e.g., control channels, data channels, information channels related to control information prioritization techniques for multiple logical channels), user data, control information, or any combination thereof. In some examples, the transmitter 615 may be co-located with the receiver 610 in a transceiver module. The transmitter 615 may utilize a single antenna or a collection of multiple antennas.

[0088] The device 605 or its various components may be examples of components for performing various aspects of the control information prioritization techniques for multiple logical channels as described herein. For example, the communication manager 620 may include a resource allocation manager 625, a distribution scheme manager 630, a transport block manager 635, or any combination thereof. The communication manager 620 may be an example of various aspects of the communication manager 520 as described herein. In some examples, the communication manager 620 or its various components may be configured to perform various operations (e.g., receive, monitor, send) using or otherwise cooperating with the receiver 610, the transmitter 615, or both. For example, the communication manager 620 may receive information from the receiver 610, transmit information to the transmitter 615, or be integrated with the receiver 610, the transmitter 615, or both to receive information, send information, or perform various other operations as described herein.

[0089] According to examples as disclosed herein, the communication manager 620 may support wireless communication at a UE. For example, the resource allocation manager 625 may be configured to or otherwise support a means for receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for a distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein a distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold. The distribution scheme manager 630 may be configured to or otherwise support a means for adjusting the distribution scheme to provide an adjusted first amount of resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and to provide a second amount of resource allocation to the second logical channel, the second amount of resource allocation corresponding to a second amount of control information to be sent on the second logical channel. The transport block manager 635 may be configured to or otherwise support a means for sending one or more transport blocks, the one or more transport blocks including a first amount of control information for the first logical channel and a second amount of control information for the second logical channel.

[0090] Figure 7A block diagram 700 of a communication manager 720 supporting control information prioritization techniques for multiple logical channels in accordance with aspects of the present disclosure is shown. The communication manager 720 may be an example of the communication manager 520, the communication manager 620, or aspects of both as described herein. The communication manager 720 or its various components may be examples of means for performing various aspects of the control information prioritization techniques for multiple logical channels as described herein. For example, the communication manager 720 may include a resource allocation manager 725, a distribution scheme manager 730, a transport block manager 735, a PBR manager 740, or any combination thereof. Each of these components may communicate directly or indirectly with each other (e.g., via one or more buses).

[0091] According to examples as disclosed herein, the communication manager 720 may support wireless communication at a UE. For example, the resource allocation manager 725 may be configured to or otherwise support a means for receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for a distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein a distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold. The distribution scheme manager 730 may be configured to or otherwise support a means for adjusting the distribution scheme to provide an adjusted first amount of resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and to provide a second amount of resource allocation to the second logical channel, the second amount of resource allocation corresponding to a second amount of control information to be sent on the second logical channel. The transport block manager 735 may be configured to or otherwise support a means for sending one or more transport blocks, the one or more transport blocks including a first amount of control information for the first logical channel and a second amount of control information for the second logical channel.

[0092] In some examples, the distribution scheme manager 730 can be configured to or otherwise support means for readjusting the distribution scheme to provide the remaining portion of the first amount of resource allocation to the first logical channel. In some examples, the transport block manager 735 can be configured to or otherwise support means for including additional uplink data for at least the first logical channel in which one or more transport blocks include the remaining portion of the first amount of resource allocation.

[0093] In some examples, to support the adjustment, the PBR manager 740 may be configured or updated to otherwise support means for updating a first prioritized bit rate (PBR) of a first logical channel to a first amount corresponding to the control information. In some examples, to support the adjustment, the PBR manager 740 may be configured or updated to otherwise support means for updating a second PBR of a second logical channel to a second amount corresponding to the control information.

[0094] In some examples, the first amount of control information and the second amount of control information occupy a first subset of the resource allocation, and the distribution scheme manager 730 may be configured to or otherwise support components for distributing the second subset of the resource allocation among the at least two logical channels based on an original prioritized bit rate associated with each of the at least two logical channels.

[0095] In some examples, to support the adjustment, the PBR manager 740 may be configured or otherwise support means for adjusting the PBR for each of the at least two logical channels to correspond to a minimum of a current PBR or a corresponding amount of control information to be sent on the associated logical channel. In some examples, the first amount of control information corresponds to a first number of bytes in a first high priority service PDU of the first logical channel, and the second amount of control information corresponds to a second number of bytes in a second high priority service PDU of the second logical channel. In some examples, a highest priority logical channel of the two or more logical channels is provided any remaining resources of the resource allocation before any resources of the resource allocation are distributed to any lower priority logical channels.

[0096] In some examples, the distribution scheme manager 730 may be configured to or otherwise support means for forming one or more transport blocks for transmission to a network entity according to a distribution scheme. In some examples, the adjusting is performed based on whether the second logical channel has an RLC control PDU or high priority data in an associated transmit buffer. In some examples, the adjusting is performed based on whether the first logical channel has a PBR set to infinity.

[0097] In some examples, the adjustment to the distribution scheme prevents bearer release of the second logical channel by providing resources for at least a second amount of control information for the second logical channel.

[0098] Figure 8A diagram of a system 800 including a device 805 supporting control information prioritization techniques for multiple logical channels according to various aspects of the present disclosure is shown. The device 805 may be an example of a device 505, a device 605, or a UE 115 as described herein, or include components of these devices. The device 805 may communicate wirelessly with one or more base stations 105 (e.g., other network entities), UE 115, or any combination thereof. The device 805 may include components for two-way voice and data communications, including components for sending and receiving communications, such as a communication manager 820, an input / output (I / O) controller 810, a transceiver 815, an antenna 825, a memory 830, a code 835, and a processor 840. These components may be electronically communicated or otherwise coupled (e.g., operatively, communicatively, functionally, electronically, electrically) via one or more buses (e.g., a bus 845).

[0099] I / O controller 810 can manage input signals and output signals of device 805. I / O controller 810 can also manage peripheral devices that are not integrated into device 805. In some cases, I / O controller 810 can represent a physical connection or port to an external peripheral device. In some cases, I / O controller 810 can utilize an operating system such as or another known operating system. Additionally or alternatively, I / O controller 810 may represent or interact with a modem, keyboard, mouse, touch screen, or similar device. In some cases, I / O controller 810 may be implemented as part of a processor such as processor 840. In some cases, a user may interact with device 805 via I / O controller 810 or via hardware components controlled by I / O controller 810.

[0100] In some cases, the device 805 may include a single antenna 825. However, in some other cases, the device 805 may have more than one antenna 825, which may be able to send or receive multiple wireless transmissions concurrently. The transceiver 815 may communicate bidirectionally via one or more antennas 825, wired or wireless links as described herein. For example, the transceiver 815 may represent a wireless transceiver and may communicate bidirectionally with another wireless transceiver. The transceiver 815 may also include a modem for modulating packets, providing the modulated packets to one or more antennas 825 for transmission, and demodulating packets received from one or more antennas 825. The transceiver 815 or the transceiver 815 and one or more antennas 825 may be examples of transmitters 515, transmitters 615, receivers 510, receivers 610, or any combination thereof or components thereof as described herein.

[0101] The memory 830 may include random access memory (RAM) and read-only memory (ROM). The memory 830 may store computer-readable, computer-executable code 835 including instructions that, when executed by the processor 840, cause the device 805 to perform various functions described herein. The code 835 may be stored in a non-transitory computer-readable medium such as a system memory or another type of memory. In some cases, the code 835 may not be directly executable by the processor 840, but may (e.g., when compiled and executed) cause the computer to perform the functions described herein. In some cases, among other things, the memory 830 may contain a basic I / O system (BIOS) that may control basic hardware or software operations, such as interaction with peripheral components or devices.

[0102] The processor 840 may include an intelligent hardware device (e.g., a general-purpose processor, a DSP, a CPU, a microcontroller, an ASIC, an FPGA, a programmable logic device, a discrete gate or transistor logic component, a discrete hardware component, or any combination thereof). In some cases, the processor 840 may be configured to operate a memory array using a memory controller. In some other cases, the memory controller may be integrated into the processor 840. The processor 840 may be configured to execute computer-readable instructions stored in a memory (e.g., a memory 830) to cause the device 805 to perform various functions (e.g., functions or tasks that support control information prioritization techniques for multiple logical channels). For example, the device 805 or a component of the device 805 may include a processor 840 and a memory 830 coupled to the processor 840, and the processor 840 and the memory 830 are configured to perform the various functions described herein.

[0103] According to an example as disclosed herein, the communication manager 820 may support wireless communication at a UE. For example, the communication manager 820 may be configured to or otherwise support a means for receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for a distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein the distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold. The communication manager 820 may be configured to or otherwise support a means for adjusting the distribution scheme to provide an adjusted first amount of resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and to provide a second amount of resource allocation to the second logical channel, the second amount of resource allocation corresponding to a second amount of control information to be sent on the second logical channel. The communication manager 820 may be configured to or otherwise support a means for sending one or more transport blocks, the one or more transport blocks including a first amount of control information for the first logical channel and a second amount of control information for the second logical channel.

[0104] By including or configuring the communications manager 820 according to examples as described herein, the device 805 can support adjustments to resource distribution techniques to provide sufficient resources to lower priority logical channels to prevent window stagnation as described herein, which can result in reduced system latency, and reduced overhead associated with fewer releases of logical channels, and a corresponding reduction in power usage.

[0105] In some examples, the communication manager 820 may be configured to perform various operations (e.g., receive, monitor, transmit) using or otherwise cooperating with the transceiver 815, one or more antennas 825, or any combination thereof. Although the communication manager 820 is illustrated as a separate component, in some examples, one or more functions described with reference to the communication manager 820 may be supported or performed by the processor 840, the memory 830, the code 835, or any combination thereof. For example, the code 835 may include instructions executable by the processor 840 to cause the device 805 to perform various aspects of the control information prioritization techniques for multiple logical channels as described herein, or the processor 840 and the memory 830 may be otherwise configured to perform or support such operations.

[0106] Fig. 9 A flow chart illustrating a method 900 for supporting control information prioritization techniques for multiple logical channels according to various aspects of the present disclosure is shown. The operations of the method 900 may be implemented by a UE or a component thereof as described herein. For example, the operations of the method 900 may be implemented by a UE or a component thereof as described in reference to Figures 1 to 8The UE 115 may be used to perform the functions described. In some examples, the UE may execute an instruction set to control the functional elements of the UE to perform the functions described. Additionally or alternatively, the UE may use dedicated hardware to perform various aspects of the functions described.

[0107] At 905, the method may include receiving an uplink grant indicating a resource allocation for uplink communication from the UE to the network entity, the resource allocation being for a distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein the distribution scheme provides a first amount of resource allocation to the first logical channel, and the first amount exceeds a threshold. The operations of 905 may be performed according to examples as disclosed herein. In some examples, aspects of the operations of 905 may be performed as described in reference to Figure 7 The resource allocation manager 725 executes.

[0108] At 910, the method may include adjusting the distribution scheme to provide an adjusted first amount of resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and providing a second amount of resource allocation to the second logical channel, the second amount of resource allocation corresponding to the second amount of control information to be sent on the second logical channel. The operations of 910 may be performed according to examples as disclosed herein. In some examples, aspects of the operations of 910 may be performed as described in reference to Figure 7 The distribution solution manager 730 is used to execute.

[0109] At 915, the method may include sending one or more transport blocks including a first amount of control information for a first logical channel and a second amount of control information for a second logical channel. The operations of 915 may be performed according to examples as disclosed herein. In some examples, aspects of the operations of 915 may be performed as described in reference to Figure 7 The transmission block manager 735 is used to execute.

[0110] Optionally, at 920, the method may include: re-adjusting the distribution scheme to provide the remaining portion of the first amount of resource allocation to the first logical channel. The operations of 920 may be performed according to examples as disclosed herein. In some examples, aspects of the operations of 920 may be performed as described in reference to Figure 7 The distribution scheme manager 730 is executed. In some cases, the one or more transport blocks include components for additional uplink data for at least the first logical channel based on a remaining portion of the first amount of resource allocation.

[0111] Fig.10A flow chart illustrating a method 1000 for supporting control information prioritization techniques for multiple logical channels according to aspects of the present disclosure is shown. The operations of the method 1000 may be implemented by a UE or a component thereof as described herein. For example, the operations of the method 1000 may be implemented by a UE or a component thereof as described in reference to Figures 1 to 8 The UE 115 may be used to perform the functions described. In some examples, the UE may execute an instruction set to control the functional elements of the UE to perform the functions described. Additionally or alternatively, the UE may use dedicated hardware to perform various aspects of the functions described.

[0112] At 1005, the method may include: receiving an uplink grant indicating a resource allocation for uplink communication from the UE to the network entity, the resource allocation being for a distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein the distribution scheme provides a first amount of resource allocation to the first logical channel, and the first amount exceeds a threshold. The operations of 1005 may be performed according to examples as disclosed herein. In some examples, aspects of the operations of 1005 may be performed as described in reference to Figure 7 The resource allocation manager 725 executes.

[0113] At 1010, the method may include updating a first prioritized bit rate (PBR) of a first logical channel to a first amount corresponding to the control information. The operations of 1010 may be performed according to examples as disclosed herein. In some examples, aspects of the operations of 1010 may be performed as described in reference Figure 7 The PBR manager 740 is used to execute.

[0114] At 1015, the method may include updating a second PBR of the second logical channel to a second amount corresponding to the control information. The operations of 1015 may be performed according to examples disclosed herein. In some examples, aspects of the operations of 1015 may be performed as described in reference to Figure 7 The PBR manager 740 is used to execute.

[0115] At 1020, the method may include distributing uplink resources based on the updated PBR, a first amount of control information to be sent on the first logical channel, and a second amount of control information to be sent on the second logical channel. The operations of 1020 may be performed according to examples as disclosed herein. In some examples, aspects of the operations of 1020 may be performed as described in reference to Figure 7 The distribution solution manager 730 is used to execute.

[0116] At 1025, the method may include sending one or more transport blocks including a first amount of control information for a first logical channel and a second amount of control information for a second logical channel. The operations of 1025 may be performed according to examples as disclosed herein. In some examples, aspects of the operations of 1025 may be performed as described in reference to Figure 7 The transmission block manager 735 is used to execute.

[0117] The following provides an overview of various aspects of the disclosure:

[0118] Aspect 1: A method for wireless communication at a UE, comprising: receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being distributed between at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein a distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold; adjusting the distribution scheme to provide an adjusted first amount of the resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and providing a second amount of the resource allocation to the second logical channel, the second amount of the resource allocation corresponding to a second amount of control information to be sent on the second logical channel; and sending one or more transport blocks, the one or more transport blocks including the first amount of control information for the first logical channel and the second amount of control information for the second logical channel.

[0119] Aspect 2: The method according to Aspect 1 also includes: readjusting the distribution scheme to provide the remaining portion of the resource allocation of the first amount to the first logical channel, and wherein the one or more transmission blocks include additional uplink data for at least the first logical channel based at least in part on the remaining portion of the resource allocation of the first amount.

[0120] Aspect 3: A method according to any one of Aspects 1 to 2, wherein the adjustment includes: updating the first prioritized bit rate (PBR) of the first logical channel to the first amount corresponding to the control information; and updating the second PBR of the second logical channel to the second amount corresponding to the control information.

[0121] Aspect 4: A method according to any one of Aspects 1 to 3, wherein the first amount of control information and the second amount of control information occupy a first subset of the resource allocation, and wherein the method further includes: distributing the second subset of the resource allocation among the at least two logical channels based at least in part on an original prioritized bit rate associated with each of the at least two logical channels.

[0122] Aspect 5: A method according to any one of Aspects 1 to 4, wherein the adjustment includes: for each of the at least two logical channels, adjusting the prioritized bit rate (PBR) to a minimum value corresponding to the current PBR or the corresponding amount of control information to be sent on the associated logical channel.

[0123] Aspect 6: A method according to any one of Aspects 1 to 5, wherein the first amount of control information corresponds to a first number of bytes in a first high priority service protocol data unit (PDU) of the first logical channel, and the second amount of control information corresponds to a second number of bytes in a second high priority service PDU of the second logical channel.

[0124] Aspect 7: A method according to any one of Aspects 1 to 6, wherein the highest priority logical channel among the two or more logical channels is provided with any remaining resources of the resource allocation before distributing any resources of the resource allocation to any lower priority logical channels.

[0125] Aspect 8: The method according to any one of aspects 1 to 7, further comprising: forming the one or more transport blocks for sending to the network entity according to the distribution scheme.

[0126] Aspect 9: A method according to any one of Aspects 1 to 8, wherein the adjustment is performed at least in part based on whether the second logical channel has an RLC control protocol data unit (PDU) or high priority data in an associated transmission buffer.

[0127] Aspect 10: The method according to any one of aspects 1 to 9, wherein the adjusting is performed at least in part based on whether the first logical channel has a prioritized bit rate (PBR) set to infinity.

[0128] Aspect 11: The method according to any one of aspects 1 to 10, wherein the adjustment of the distribution scheme prevents bearer release of the second logical channel by providing resources for at least the second amount of control information of the second logical channel.

[0129] Aspect 12: An apparatus for performing wireless communication at a UE, comprising: a processor; a memory coupled to the processor; and instructions stored in the memory and executable by the processor to cause the apparatus to perform a method according to any one of Aspects 1 to 11.

[0130] Aspect 13: An apparatus for performing wireless communication at a UE, comprising: at least one component for performing the method according to any one of aspects 1 to 11.

[0131] Aspect 14: A non-transitory computer-readable medium storing a code for wireless communication at a UE, the code comprising instructions executable by a processor to perform a method according to any one of aspects 1 to 11.

[0132] It should be noted that the methods described herein describe possible implementations, and that the operations and steps may be rearranged or otherwise modified and that other implementations are possible. Furthermore, aspects from two or more methods may be combined.

[0133] Although aspects of LTE, LTE-A, LTE-A Pro, or NR systems may be described for example purposes, and LTE, LTE-A, LTE-A Pro, or NR terminology may be used in much of the description, the techniques described herein may also be applicable to networks other than LTE, LTE-A, LTE-A Pro, or NR networks. For example, the techniques may be applicable to various other wireless communication systems, such as Ultra Mobile Broadband (UMB), Institute of Electrical and Electronics Engineers (IEEE) 802.11 (Wi-Fi), IEEE 802.16 (WiMAX), IEEE 802.20, Flash-OFDM, and other systems and radio technologies not explicitly mentioned herein.

[0134] The information and signals described herein may be represented using any of a variety of different techniques and methods. For example, data, instructions, commands, information, signals, bits, symbols, and chips mentioned throughout the specification may be represented by voltage, current, electromagnetic waves, magnetic fields or magnetic particles, light fields or optical particles, or any combination thereof.

[0135] The various illustrative blocks and components described in conjunction with the disclosure herein may be implemented or performed with a general purpose processor, DSP, ASIC, CPU, FPGA or other programmable logic device, discrete gate or transistor logic, discrete hardware components, or any combination thereof designed to perform the functions described herein. A general purpose processor may be a microprocessor, but in an alternative, the processor may be any processor, controller, microcontroller, or state machine. The processor may also be implemented as a combination of computing devices (e.g., a combination of a DSP and a microprocessor, a plurality of microprocessors, one or more microprocessors in conjunction with a DSP core, or any other such configuration).

[0136] The functions described herein may be implemented in hardware, software executed by a processor, firmware, or any combination thereof. When implemented in software executed by a processor, the functions may be stored as one or more instructions or codes on a computer-readable medium, or sent via a computer-readable medium. Other examples and specific implementations are within the scope of the present disclosure and the appended claims. For example, due to the nature of software, the functions described herein may be implemented using software executed by a processor, hardware, firmware, hard wiring, or any combination of these items. Features implementing the functions may also be physically located at different locations, including being distributed so that the various parts of the functions are implemented at different physical locations.

[0137] Computer-readable medium includes both non-transient computer storage medium and communication medium, and it includes any medium that facilitates computer program to transfer from one place to another place.Non-transient storage medium can be any available medium that can be accessed by general or special-purpose computer.By way of example and not limitation, non-transient computer-readable medium can include RAM, ROM, electrically erasable programmable ROM (EEPROM), flash memory, compact disc (CD) ROM or other optical disc storage device, disk storage or other magnetic storage device or can be used for carrying or storing desired program code member and any other non-transient medium that can be accessed by general or special-purpose computer or general or special-purpose processor in the form of instruction or data structure.Moreover, any connection is appropriately referred to as computer-readable medium.For example, if software is sent from website, server or other remote source using coaxial cable, optical fiber cable, twisted pair, digital subscriber line (DSL) or wireless technology such as infrared, radio and microwave, then coaxial cable, optical fiber cable, twisted pair, DSL or wireless technology such as infrared, radio and microwave are included in the definition of computer-readable medium. Disk and disc, as used herein, includes CD, laser disc, optical disc, digital versatile disc (DVD), floppy disk and Blu-ray disc, where disks usually reproduce data magnetically, while discs reproduce data optically with lasers. Combinations of the above are also included within the scope of computer-readable media.

[0138] As used herein (including in the claims), "or" used in a list of items (e.g., a list of items followed by a phrase such as "at least one of" or "one or more of") indicates an inclusive list, so that, for example, a list of at least one of A, B, or C means A or B or C or AB or AC or BC or ABC (i.e., A and B and C). In addition, as used herein, the phrase "based on" should not be interpreted as a reference to a closed set of conditions. For example, an example step described as "based on condition A" may be based on condition A and condition B without departing from the scope of the present disclosure. In other words, as used herein, the phrase "based on" should be interpreted in the same manner as the phrase "based at least in part on."

[0139] The terms "determine" or "determine" encompass a wide variety of actions, and thus, "determine" may include calculating, computing, processing, deriving, investigating, looking up (such as via looking up in a table, database or other data structure), ascertaining, and similar actions. Additionally, "determine" may include receiving (such as receiving information), accessing (such as accessing data in a memory), and similar actions. Additionally, "determine" may include resolving, selecting, choosing, establishing, and other such similar actions.

[0140] In the drawings, similar components or features may have the same reference label. In addition, various components of the same type may be distinguished by following the reference label with a dash and a second label to distinguish between similar components. If only the first reference label is used in the specification, the description may apply to any of the similar components having the same first reference label regardless of the second reference label, or other subsequent reference labels.

[0141] The descriptions set forth herein in conjunction with the accompanying drawings describe example configurations and do not represent all examples that may be implemented or within the scope of the claims. The term "example" as used herein means "used as an example, instance, or illustration," rather than "preferred" or "advantageous over other examples." The detailed description includes specific details for providing an understanding of the technology. However, the technologies may be practiced without these specific details. In some instances, known structures and devices are shown in block diagram form to suppress the concept of obscuring the examples.

[0142] The description herein is provided to enable one of ordinary skill in the art to implement or use the present disclosure. Various modifications to the present disclosure will be apparent to one of ordinary skill in the art, and the general principles defined herein may be applied to other variations without departing from the scope of the present disclosure. Thus, the present disclosure is not limited to the examples and designs described herein, but should be granted the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A method for wireless communication at a user equipment (UE), comprising: receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein a distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold; adjusting the distribution scheme to provide an adjusted first amount of the resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and providing a second amount of the resource allocation to the second logical channel, the second amount of the resource allocation corresponding to a second amount of control information to be sent on the second logical channel; as well as One or more transport blocks are sent, the one or more transport blocks comprising the first amount of control information for the first logical channel and the second amount of control information for the second logical channel.

2. The method according to claim 1, further comprising: re-adjusting the distribution scheme to provide a remainder of the first amount of the resource allocation to the first logical channel, and wherein the one or more transport blocks include additional uplink data for at least the first logical channel based at least in part on the remaining portion of the resource allocation of the first amount.

3. The method according to claim 1, wherein the adjusting comprises: updating a first prioritized bit rate (PBR) of the first logical channel to the first amount corresponding to the control information; as well as A second PBR of the second logical channel is updated to the second amount corresponding to the control information.

4. The method of claim 1 , wherein the first amount of control information and the second amount of control information occupy a first subset of the resource allocation, and wherein the method further comprises: A second subset of the resource allocations is distributed among the at least two logical channels based at least in part on an original prioritized bit rate associated with each of the at least two logical channels.

5. The method according to claim 1, wherein the adjusting comprises: For each of the at least two logical channels, a prioritized bit rate (PBR) is adjusted to correspond to a minimum of a current PBR or a corresponding amount of control information to be sent on the associated logical channel.

6. A method according to claim 1, wherein the first amount of control information corresponds to a first number of bytes in a first high priority service protocol data unit (PDU) of the first logical channel, and the second amount of control information corresponds to a second number of bytes in a second high priority service PDU of the second logical channel.

7. The method of claim 1, wherein a highest priority logical channel among the two or more logical channels is provided any remaining resources of the resource allocation before distributing any resources of the resource allocation to any lower priority logical channels.

8. The method according to claim 1, further comprising: The one or more transport blocks are formed according to the distribution scheme for sending to the network entity.

9. The method of claim 1, wherein the adjusting is performed based at least in part on whether the second logical channel has a radio link control (RLC) control protocol data unit (PDU) or high priority data in an associated transmit buffer.

10. The method of claim 1, wherein the adjusting is performed based at least in part on whether the first logical channel has a prioritized bit rate (PBR) set to infinity.

11. The method of claim 1, wherein the adjustment to the distribution scheme prevents bearer release of the second logical channel by providing resources for at least the second amount of control information of the second logical channel.

12. An apparatus for wireless communication at a user equipment (UE), comprising: processor; and a memory, the memory being coupled to the processor, the processor and the memory being configured to: receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein a distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold; adjusting the distribution scheme to provide an adjusted first amount of the resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and providing a second amount of the resource allocation to the second logical channel, the second amount of the resource allocation corresponding to a second amount of control information to be sent on the second logical channel; as well as One or more transport blocks are sent, the one or more transport blocks comprising the first amount of control information for the first logical channel and the second amount of control information for the second logical channel.

13. The apparatus of claim 12, wherein the processor and the memory are further configured to: re-adjusting the distribution scheme to provide a remainder of the first amount of the resource allocation to the first logical channel, and wherein the one or more transport blocks include additional uplink data for at least the first logical channel based at least in part on the remaining portion of the resource allocation of the first amount.

14. The apparatus of claim 12, wherein to adjust the distribution scheme, the processor and the memory are configured to: updating a first prioritized bit rate (PBR) of the first logical channel to the first amount corresponding to the control information; and A second PBR of the second logical channel is updated to the second amount corresponding to the control information.

15. The apparatus of claim 12, wherein the first amount of control information and the second amount of control information occupy a first subset of the resource allocation, and the processor and the memory are further configured to: A second subset of the resource allocations is distributed among the at least two logical channels based at least in part on an original prioritized bit rate associated with each of the at least two logical channels.

16. The apparatus of claim 12, wherein to adjust the distribution scheme, the processor and the memory are configured to: For each of the at least two logical channels, a prioritized bit rate (PBR) is adjusted to correspond to a minimum of a current PBR or a corresponding amount of control information to be sent on the associated logical channel.

17. The apparatus of claim 12, wherein the first amount of control information corresponds to a first number of bytes in a first high priority service protocol data unit (PDU) of the first logical channel, and the second amount of control information corresponds to a second number of bytes in a second high priority service PDU of the second logical channel.

18. The apparatus of claim 12, wherein a highest priority logical channel among the two or more logical channels is provided any remaining resources of the resource allocation before distributing any resources of the resource allocation to any lower priority logical channels.

19. The apparatus of claim 12, wherein the processor and the memory are further configured to: The one or more transport blocks are formed according to the distribution scheme for sending to the network entity.

20. The apparatus of claim 12, wherein the adjustment of the distribution scheme is performed based at least in part on whether the second logical channel has a radio link control (RLC) control protocol data unit (PDU) or high priority data in an associated transmit buffer.

21. The apparatus of claim 12, wherein the adjustment of the distribution scheme is performed based at least in part on whether the first logical channel has a prioritized bit rate (PBR) set to infinity.

22. The apparatus of claim 12, wherein the adjustment to the distribution scheme prevents bearer release of the second logical channel by providing resources for at least the second amount of control information of the second logical channel.

23. An apparatus for wireless communication at a user equipment (UE), comprising: means for receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein a distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold; means for adjusting the distribution scheme to provide an adjusted first amount of the resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and providing a second amount of the resource allocation to the second logical channel, the second amount of the resource allocation corresponding to a second amount of control information to be sent on the second logical channel; and Means for sending one or more transport blocks, the one or more transport blocks comprising the first amount of control information for the first logical channel and the second amount of control information for the second logical channel.

24. The apparatus according to claim 23, further comprising: means for re-adjusting the distribution scheme to provide a remainder of the first amount of the resource allocation to the first logical channel, and Means for wherein the one or more transport blocks include additional uplink data for at least the first logical channel based at least in part on the remaining portion of the resource allocation of the first amount.

25. The apparatus of claim 23, wherein the means for adjusting comprises: means for updating a first prioritized bit rate (PBR) of the first logical channel to the first amount corresponding to the control information; and means for updating a second PBR of the second logical channel to correspond to the second amount of control information.

26. The apparatus of claim 23, wherein the first amount of control information and the second amount of control information occupy a first subset of the resource allocation, the apparatus further comprising: Means for distributing a second subset of the resource allocations among the at least two logical channels based at least in part on an original prioritized bit rate associated with each of the at least two logical channels.

27. A non-transitory computer-readable medium storing code for wireless communication at a user equipment (UE), the code comprising instructions executable by a processor to: receiving an uplink grant indicating a resource allocation for uplink communication from the UE to a network entity, the resource allocation being for distribution among at least two logical channels including a first logical channel having a higher priority than a second logical channel, wherein a distribution scheme provides a first amount of the resource allocation to the first logical channel, and the first amount exceeds a threshold; adjusting the distribution scheme to provide an adjusted first amount of the resource allocation corresponding to a first amount of control information to be sent on the first logical channel, and providing a second amount of the resource allocation to the second logical channel, the second amount of the resource allocation corresponding to a second amount of control information to be sent on the second logical channel; as well as One or more transport blocks are sent, the one or more transport blocks comprising the first amount of control information for the first logical channel and the second amount of control information for the second logical channel.

28. The non-transitory computer readable medium of claim 27, wherein the instructions are further executable by the processor to: re-adjusting the distribution scheme to provide a remainder of the first amount of the resource allocation to the first logical channel, and wherein the one or more transport blocks include additional uplink data for at least the first logical channel based at least in part on the remaining portion of the resource allocation of the first amount.

29. The non-transitory computer readable medium of claim 27, wherein the instructions for adjusting are executable by the processor to: updating a first prioritized bit rate (PBR) of the first logical channel to the first amount corresponding to the control information; and A second PBR of the second logical channel is updated to the second amount corresponding to the control information.

30. The non-transitory computer readable medium of claim 27, wherein the instructions for adjusting are executable by the processor to: For each of the at least two logical channels, a prioritized bit rate (PBR) is adjusted to correspond to a minimum of a current PBR or a corresponding amount of control information to be sent on the associated logical channel.