Gravity energy storage lifting system and operation method
By designing a multi-channel gravity energy storage lifting system, and using the transmission wheel and transmission rope to connect, the problems of medium and high construction costs and control complexity in the existing technology are solved, efficient power storage and release, and the mechanical loss of the system is reduced and Power discontinuity.
Patent Information
- Application Number
- CN202411051609.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-01
- Publication Date
- 2024-12-03
AI Technical Summary
The existing slope-type gravity energy storage system has problems such as high construction costs, mechanical transmission loss, high control complexity and discontinuous output power, and traditional systems require multiple sets of motors and multiple storage devices.
A gravity energy storage lifting system is designed, including upstream and downstream storage devices, conveying devices, lifting devices, drive devices and power devices. Through the linkage of the transmission wheel and the transmission rope, the transmission of heavy blocks and the storage and release of electric energy are realized. Multiple lifting channels and carriers are used for stacking and lifting to provide power supply.
It reduces the cost of system construction, improves efficiency, simplifies control complexity, solves the problem of no-load of heavy blocks, and realizes stable power output and efficient storage and release of electrical energy.
Smart Images

Figure CN119062531A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of compressed air energy storage, and in particular relates to a gravity energy storage lifting system and an operating method. Background Art
[0002] At present, all slope gravity energy storage systems are built on retired tracks or artificial structures. There are many problems with the system structure. First, a large-scale multi-channel system requires multiple sets of motor lifting mechanisms, and the system construction cost is relatively high. Second, the system has many mechanical transmission links, and the resulting losses will reduce the system efficiency. Third, the system track is long and the number of tracks is large, which increases the complexity of system control and easily leads to the problem of discontinuous output power. Fourth, traditional slope gravity energy storage systems are both an upstream storage device and a downstream storage device, which store the energy storage weights and the energy release weights respectively. Summary of the invention
[0003] In order to overcome the above problems existing in the prior art, the present invention provides a gravity energy storage lifting system and an operating method.
[0004] A gravity energy storage lifting system, the system comprising: an upstream storage device, a downstream storage device, a conveying device, a weight block, a lifting device, a driving device and an electric device, wherein:
[0005] The upstream storage device and the downstream storage device are used to store the weight blocks;
[0006] The conveying device is arranged on the lifting device and is used to transfer the heavy object block between the upstream storage device and the downstream storage device;
[0007] The driving device is used to drive the conveying device to move on the lifting device;
[0008] The power device is used to provide power supply.
[0009] According to the aspects described above and any possible implementation, an implementation is further provided, wherein the lifting device includes a first lifting channel with a certain slope, a second lifting channel and a top platform, and the top platform is arranged between the top ends of the first lifting channel and the second lifting channel.
[0010] According to the aspects described above and any possible implementation method, an implementation method is further provided, wherein the upstream storage device and the downstream storage device include at least two, wherein the first upstream storage device and the second upstream storage device are both arranged on the top platform; the first downstream storage device and the second downstream storage device are respectively arranged at the two bottom ends of the first lifting channel and the second lifting channel.
[0011] According to the above aspects and any possible implementation, an implementation is further provided, wherein the conveying device includes two carriers, a first carrier is disposed on the first lifting channel, and a second carrier is disposed on the first lifting channel.
[0012] According to the aspects described above and any possible implementation method, an implementation method is further provided, wherein the driving device includes at least three transmission wheels and a transmission rope, wherein both ends of the transmission rope are respectively connected to the first carrier vehicle and the second carrier vehicle, and the at least three transmission wheels are arranged on the top platform, wherein one driving wheel is connected to two driven wheels through the transmission rope.
[0013] According to the aspects described above and any possible implementation method, an implementation method is further provided, wherein the power device includes a motor, a rectifier, an inverter, a transformer and a power grid connected in sequence, and the motor is simultaneously connected to the driving wheel.
[0014] The present invention also provides an operation method of a gravity energy storage lifting system, which is implemented by using the system and includes an energy release stage and an energy storage stage.
[0015] According to the aspects and any possible implementations described above, an implementation is further provided, wherein the energy release stage includes: the energy release of the heavy blocks in the first carrier vehicle in the first lifting channel, the lifting process of the second carrier vehicle in the second lifting channel, and the lifting of the first carrier vehicle in the first lifting channel and the energy release process of the heavy blocks in the second carrier vehicle in the second lifting channel.
[0016] According to the aspects and any possible implementations described above, an implementation is further provided, wherein the energy storage stage includes an energy storage process of a first lifting channel and an energy storage process of a second lifting channel.
[0017] According to the aspects described above and any possible implementation method, an implementation method is further provided, wherein the energy release stage is carried out when the grid electricity price of the power device is low or the grid electricity is sufficient; and the energy storage stage is carried out when the grid electricity price of the power device is high or the grid electricity is insufficient.
[0018] Beneficial effects of the present invention
[0019] Compared with the prior art, the present invention has the following beneficial effects:
[0020] The gravity energy storage lifting system of the present invention comprises: an upstream storage device, a downstream storage device, a conveying device, a weight block, a lifting device, a driving device and an electric device, wherein the upstream storage device and the downstream storage device are used to store the weight block; the conveying device is arranged on the lifting device, and is used to transfer the weight block between the upstream storage device and the downstream storage device; the driving device is used to drive the conveying device to move on the lifting device; and the electric device is used to provide power supply. The present invention provides two upstream storage devices and two downstream storage devices, and while releasing energy on one side, the weight block on the other side is driven to rise, solving the problem of the weight block being empty. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the overall structure of the present invention. DETAILED DESCRIPTION
[0022] In order to better understand the technical solution of the present invention, the content of the present invention includes but is not limited to the specific implementation methods described below, and similar technologies and methods should be considered to be within the scope of protection of the present invention. In order to make the technical problems, technical solutions and advantages to be solved by the present invention clearer, the following will be described in detail with reference to the accompanying drawings and specific embodiments.
[0023] It should be clear that the embodiments described in the present invention are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0024] The terms used in the embodiments of the present invention are only for the purpose of describing specific embodiments, and are not intended to limit the present invention. The singular forms "a", "said" and "the" used in the embodiments of the present invention and the appended claims are also intended to include plural forms, unless the context clearly indicates other meanings.
[0025] The gravity energy storage lifting system of the present invention comprises: an upstream storage device, a downstream storage device, a conveying device, a weight block, a lifting device, a driving device and an electric device, wherein:
[0026] The upstream storage device and the downstream storage device are used to store the weight blocks;
[0027] The conveying device is arranged on the lifting device and is used to transfer the heavy object block between the upstream storage device and the downstream storage device;
[0028] The driving device is used to drive the conveying device to move on the lifting device;
[0029] The power device is used to provide power supply.
[0030] Preferably, the lifting device comprises a first lifting channel with a certain slope, a second lifting channel and a top platform, and the top platform is arranged between the top ends of the first lifting channel and the second lifting channel.
[0031] Preferably, the upstream storage device and the downstream storage device include at least two, wherein the first upstream storage device and the second upstream storage device are both arranged on the top platform; the first downstream storage device and the second downstream storage device are respectively arranged at the two bottom ends of the first lifting channel and the second lifting channel.
[0032] Preferably, the conveying device comprises two carriers, a first carrier is arranged on the first lifting channel, and a second carrier is arranged on the first lifting channel.
[0033] Preferably, the driving device includes at least three transmission wheels and transmission ropes, the two ends of the transmission ropes are respectively connected to the first carrier vehicle and the second carrier vehicle, the at least three transmission wheels are arranged on the top platform, and one of the driving wheels is connected to two driven wheels through the transmission rope.
[0034] Preferably, the electric power device comprises a motor, a rectifier, an inverter, a transformer and a power grid which are connected in sequence, and the motor is connected to the driving wheel at the same time.
[0035] like Figure 1As shown, the system includes two upstream storage devices, which are respectively called first upstream storage devices 11 and 12, two downstream storage devices, the first downstream storage device 21 and the second downstream storage device 22, the first carrier 211, the first carrier 212, transmission wheels 31, 32 and 33, transmission ropes, a lifting channel 5 including a first lifting channel 51, a second lifting channel 52 and a top platform between the two lifting channels for placing the first upstream storage devices 11 and 12; a weight block 6, a transmission shaft 7, a motor 8, a rectifier 9, an inverter 10, a transformer 111 and a power grid 112, and the transmission rope is realized by a steel wire rope 4. The carried weight blocks 6 are stacked in the first upstream storage devices 11 and 12, the first downstream storage device 21 and the second downstream storage device 22, and the number of stacks is more than one. Each of the first lifting channel 51 and the second lifting channel 52 is a slope channel, with an inclination angle of less than 90 degrees, preferably 50-70 degrees. At least three transmission wheels 31, 32 and 33 are loaded on the top platform. The two slope lifting channels are linked through the transmission wheels 31, 32 and 33 and the wire rope 4. The main transmission wheel 31 is connected to the transmission wheels 32 and 33 of each channel through the wire rope 4. The first channel transmission wheel 32 is connected to the first carrier 211 through the wire rope 4; the second channel transmission wheel 33 is connected to the second carrier 212 through the wire rope 4. The main transmission wheel 31 is connected to the motor 8 through its own transmission shaft. The other end of the motor 8 is connected to the rectifier 9 and the inverter 10 in turn, and the frequency and voltage of the motor 8 are modulated into the grid frequency and voltage, thereby realizing the production and transmission of electric energy and providing energy for the grid 112. The motor 8 can be used as a generator or a motor. Different forms can be used as needed in the following energy release or energy storage stage. The system of the present invention may include multiple lifting channels. A single power generation module is composed of two linked lifting channels. Multiple power generation modules will include multiple lifting channels. Figure 1 The case of a single power generation module is listed, in which the upstream and downstream storage devices are used to stack heavy blocks, and the number of stacks can be no less than one according to needs. The heavy blocks are placed in the carrier 211 or 212 and lifted together to achieve energy storage and energy release of the system. The heavy blocks drive the rotation of the transmission wheels 31, 32 and 33 as the vehicle rises and falls, thereby driving the motor 8 to generate electricity, and the grid is connected through the rectifier device and the inverter device. The rectifier device 9 is realized by a rectifier, and the inverter device 10 is realized by an inverter.
[0036] As an embodiment disclosed in the present invention, the present invention also provides an operation method of a gravity energy storage lifting system, which is implemented by the system, including an energy release stage and an energy storage stage. The energy release stage is carried out when the grid electricity price of the power device is low or the grid electricity is sufficient; the energy storage stage is carried out when the grid electricity price of the power device is high or the grid electricity is insufficient. The energy release stage includes: the energy release of the heavy blocks in the first carrier vehicle of the first lifting channel, the lifting process of the second carrier vehicle of the second lifting channel, and the lifting of the first carrier vehicle of the first lifting channel and the energy release process of the heavy blocks in the second carrier vehicle of the second lifting channel; the energy storage stage includes the energy storage process of the first lifting channel and the energy storage process of the second lifting channel.
[0037] Specifically, the energy storage and release process of the present invention is as follows:
[0038] The first channel transmission wheel 32 of the first lifting channel 51 and the second channel transmission wheel 33 of the second lifting channel 52 are connected to the main transmission wheel 31 through the wire rope 4, and are connected to the motor 8 to realize the energy storage and energy release of gravity energy storage.
[0039] The energy release process is as follows:
[0040] When the power price of the power grid is high or the power of the power grid is insufficient, the motor can be used to generate electricity, and the heavy objects can fall from the upstream storage device to the downstream storage device, and the gravitational potential energy can be converted into electrical energy. The specific process is as follows:
[0041] (1) Energy release of the weight block 6 in the first transport vehicle 211 of the first lifting channel 51 and lifting of the second transport vehicle 212 in the second lifting channel 52:
[0042] In the first lifting channel 51, the heavy object block 6 is transported from the first upstream storage device 11 to the first carrier 211 and transported to the first downstream storage device 21. The heavy object block 6 undergoes three motion processes of acceleration, uniform speed, and deceleration during transportation. Power generation requires relatively stable power, and the power cannot be high at one time and low at another. Only the uniform speed stage is stable during the above three motion processes. Therefore, the uniform speed stage is used for grid-connected power generation. At this time, the second empty carrier 212 of the second lifting channel 52 will be lifted from the second downstream storage device 22 to the upstream storage device 12. Since the two channels 51 and 52 are linked by the wire rope 4, the second empty carrier 212 also undergoes three motion processes of acceleration, uniform speed, and deceleration. In this stage, the heavy object block 6 is transported from the upstream storage device 11 to the first downstream storage device 21, driving the main drive wheel 31 to rotate and thereby driving the motor 8 to generate electricity, and the gravitational potential energy of the heavy object block in the second empty carrier 212 is converted into grid power.
[0043] (2) Lifting of the first carrier 211 in the first lifting channel 51 and release of the heavy object in the second carrier 212 in the second lifting channel 52:
[0044] Under this working condition, in the second lifting channel 52, the heavy object block is transported from the upstream storage device 12 to the second carrier 212 and transported to the second downstream storage device 22, and the heavy object block undergoes three motion processes of acceleration, uniform speed, and deceleration. At the same time, the first empty carrier 211 in the first lifting channel 51 is also lifted from the first downstream storage device 21 to the upstream storage device 11, and the first empty carrier 211 also undergoes three motion processes of acceleration, uniform speed, and deceleration. In this stage, the heavy object block is transported from the upstream storage device 12 to the second downstream storage device 22, driving the main drive wheel 31 to rotate and thereby driving the motor 8 to generate electricity, and the gravitational potential energy of the heavy object block is converted into grid electricity. During operation, the first empty carrier 211 in the first lifting channel 51 acts as a counterweight block for the second carrier 212 in the second lifting channel 52.
[0045] The energy storage process is as follows:
[0046] It is the reverse process of the energy release process. When the power price of the power grid is low or the power of the power grid is sufficient, the heavy objects can be lifted from the downstream storage device to the upstream storage device by the motor, and the electrical energy is converted into gravitational potential energy. The specific process is as follows:
[0047] (1) Energy storage process of the first lifting channel 51
[0048] In this process, the weight block 6 of the first downstream storage device 21 is transported to the first carrier 211 of the first lifting channel 51 through the horizontal transfer mechanism provided in the device, and the power grid 112 provides electric energy to the motor 8, driving the first channel transmission wheel 32 and the second channel transmission wheel 33 to lift the first carrier 211 and the weight block 6 to the upstream storage device 11 and unload, thereby realizing the conversion of electric energy into gravitational potential energy; at this time, the second empty carrier 212 of the second lifting channel 52 simultaneously falls from the upstream storage device 12 to the second downstream storage device 22 and is loaded, preparing for the energy storage process of the second lifting channel 52. During operation, the second carrier 212 in the second lifting channel 52 acts as a counterweight block for the first carrier 211 in the first lifting channel 51, so that there is no need to provide energy for lifting the first carrier 211.
[0049] (2) Energy storage process of the second lifting channel 52
[0050] The heavy blocks of the second downstream storage device 22 are transported to the second carrier 212 of the second lifting channel 52 through the horizontal transfer mechanism provided therein, and the first carrier 211 of the first lifting channel 51 unloads the heavy blocks at the same time. The power grid 112 provides electric energy to the motor 8, driving the first channel transmission wheel 32 and the second channel transmission wheel 33 to lift the second carrier 212 and the heavy blocks therein to the upstream storage device 12, thereby realizing the conversion of electric energy into gravitational potential energy. During operation, the first carrier 211 of the first lifting channel 51 acts as a counterweight block for the second carrier 212 of the second lifting channel 52, so that no energy needs to be provided for lifting the second carrier 212.
[0051] The horizontal transfer mechanisms in the first downstream storage device 21 and the second downstream storage device 22 are arranged using existing transport structures.
[0052] The above description shows and describes several preferred embodiments of the present invention, but as mentioned above, it should be understood that the present invention is not limited to the form disclosed herein, and should not be regarded as excluding other embodiments, but can be used in various other combinations, modifications and environments, and can be modified within the scope of the application concept described herein through the above teachings or the technology or knowledge of the relevant field. The changes and modifications made by those skilled in the art shall not depart from the spirit and scope of the present invention, and shall be within the scope of protection of the claims attached to the present invention.
Claims
1. A gravity energy storage lifting system, characterized in that: The system comprises: an upstream storage device, a downstream storage device, a conveying device, a weight block, a lifting device, a driving device and an electric device, wherein: The upstream storage device and the downstream storage device are used to store the weight blocks; The conveying device is arranged on the lifting device and is used to transfer the heavy object block between the upstream storage device and the downstream storage device; The driving device is used to drive the conveying device to move on the lifting device; The power device is used to provide power supply.
2. The gravity energy storage lifting system according to claim 1, characterized in that: The lifting device comprises a first lifting channel with a certain slope, a second lifting channel and a top platform, and the top platform is arranged between the top ends of the first lifting channel and the second lifting channel.
3. The gravity energy storage lifting system according to claim 2, characterized in that: The upstream storage device and the downstream storage device include at least two, wherein the first upstream storage device and the second upstream storage device are both arranged on the top platform; the first downstream storage device and the second downstream storage device are respectively arranged at the two bottom ends of the first lifting channel and the second lifting channel.
4. The gravity energy storage lifting system according to claim 3, characterized in that: The conveying device includes two carriers, a first carrier is arranged on the first lifting channel, and a second carrier is arranged on the first lifting channel.
5. The gravity energy storage lifting system according to claim 4, characterized in that: The driving device includes at least three transmission wheels and transmission ropes, the two ends of the transmission ropes are respectively connected to the first carrier vehicle and the second carrier vehicle, the at least three transmission wheels are arranged on the top platform, and one driving wheel is connected to two driven wheels through the transmission rope.
6. The gravity energy storage lifting system according to claim 5, characterized in that: The electric power device comprises a motor, a rectifier, an inverter, a transformer and a power grid which are connected in sequence, and the motor is connected to the driving wheel at the same time.
7. A method for operating a gravity energy storage lifting system, characterized in that: The method is implemented by using the system described in any one of claims 1 to 6, and includes an energy release phase and an energy storage phase.
8. The operating method according to claim 7, characterized in that: The energy release stage includes: energy release of the heavy object in the first carrier of the first lifting channel, lifting process of the second carrier in the second lifting channel, lifting of the first carrier in the first lifting channel and energy release process of the heavy object in the second carrier in the second lifting channel.
9. The operating method according to claim 7, characterized in that: The energy storage stage includes an energy storage process of a first lifting channel and an energy storage process of a second lifting channel.
10. The operating method according to claim 7, characterized in that: The energy release phase is carried out when the grid electricity price of the power device is low or the grid electricity is sufficient; the energy storage phase is carried out when the grid electricity price of the power device is high or the grid electricity is insufficient.