Tunnel movable type high-pressure air curtain dust blocking, isolating and ventilating trolley and ventilating method thereof
By using a mobile high-pressure air curtain to block dust isolation ventilation trolleys during tunnel construction, the tunnel is divided into fresh air zones and waste air zones, and axial fan is used for ventilation, which solves the high cost of ventilation equipment and high energy consumption during tunnel construction. The problem of poor ventilation effect has achieved efficient ventilation effect and low-cost construction.
Patent Information
- Application Number
- CN202411099418.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-12-06
AI Technical Summary
The ventilation equipment during existing tunnel construction is high cost, energy consumption and limited ventilation effect. It is difficult to effectively discharge dust and wind during long tunnel construction, resulting in dirty air in the tunnel.
Design a mobile high-pressure air curtain dust-proof isolation ventilation trolley in tunnel. The high-pressure air curtain machine is used to separate the tunnel into fresh air zones and waste air zones, and axial fan is set up in each area for ventilation, through hydraulics and electricity The control system realizes the translation of the trolley, lifting and inflating the airbag, forming an efficient ventilation path.
The air supply and exhaust air distance and air resistance during tunnel construction are effectively reduced, cost is reduced, ventilation efficiency is improved, and dirty wind can be discharged more conveniently, solving the ventilation problem during long tunnel construction.
Smart Images

Figure CN119084058A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel construction equipment, and in particular to a tunnel movable high-pressure air curtain dust-proof isolation ventilation trolley and a ventilation method thereof. Background Art
[0002] Tunnel construction technology is improving day by day, and the length of new tunnels is getting longer and longer. With the widespread promotion of large-scale mechanized construction, the length of tunnel single-head excavation is increasing, and single-hole single-head excavation working faces of 3 to 4 km are everywhere. The effective ventilation length of the axial flow fan commonly used at present is basically around 1.5 to 2 km. Therefore, in the single-hole single-head excavation working face of 3 to 4 km, the traditional pressure-type ventilation cannot meet the ventilation needs at all, which brings huge pressure to tunnel ventilation, especially in plateau tunnel construction, where ventilation problems are more difficult to solve.
[0003] The commonly used ventilation method at present is to replace the fan with a higher power, but it is costly and consumes huge amounts of energy. It is also possible to use relay ventilation in the tunnel to improve the ventilation capacity of the tunnel, but because the polluted air has a long return distance, it is difficult to discharge it outside the tunnel, causing the air in the tunnel to remain polluted. In addition, some engineering practices use air channel ventilation to divide the tunnel cross section into two channels for fresh air intake and sewage exhaust, but this is very costly and difficult to construct.
[0004] Therefore, it is necessary to propose new measures to overcome the above-mentioned defects. Summary of the invention
[0005] The purpose of the present invention is to provide a tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley and a ventilation method thereof, so as to solve the problems of high cost, high energy consumption, limited ventilation effect and the like existing in the existing ventilation means.
[0006] In order to achieve the above object, the technical solution adopted by the present invention is:
[0007] A tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley, the ventilation trolley comprises a mobile stand, a high-pressure air curtain machine is arranged on the inner side of the longitudinal middle part of the mobile stand, and the air outlet of the high-pressure air curtain machine faces the center line of the tunnel;
[0008] A blocking plate is provided on the movable platform where the high-pressure air curtain machine is located. The blocking plate is arranged circumferentially on the movable platform to block all cross-sections of the movable platform and leave a middle operating area and an upper fan port.
[0009] Furthermore, an circumferentially arranged airbag is provided on the outer side of the movable platform, corresponding to the position of the blocking plate, and the airbag fills the gap between the blocking plate and the lining after being inflated.
[0010] Furthermore, the airbag is in a belt shape and is located in the same cross section as the high-pressure air curtain machine.
[0011] Furthermore, the airbag is connected to an air compressor, and the air compressor is arranged on the mobile platform.
[0012] Furthermore, the upper portion of the movable platform is a fan rack, and the fan rack is located above the middle working area. Two axial flow fans are arranged in the fan rack in a left-right symmetrical arrangement.
[0013] Furthermore, both sides of the bottom of the movable stand are provided with running wheels.
[0014] On the other hand, a ventilation method for a tunnel movable high-pressure air curtain dust-proof isolation ventilation trolley as described above is provided, the method comprising:
[0015] When the tunnel excavation length is less than 1500m, ordinary forced-in ventilation is adopted. The axial flow fan is set outside the tunnel. The fresh air is sent to the tunnel face through the wind tube, and the polluted air is pressed out of the tunnel.
[0016] When the tunnel excavation length is greater than 1500m, the ventilation trolley is driven into the tunnel;
[0017] After the ventilation trolley is in place, the hydraulic control system is used to translate and lift the mobile trolley to center it; the airbag and high-pressure air curtain are turned on to form a high-pressure air curtain at the section where the high-pressure air curtain is located, so that the area from the high-pressure air curtain to the outside of the tunnel forms a fresh air zone, and the area from the high-pressure air curtain to the face forms a polluted air zone;
[0018] Turn on the axial flow fan, use the first axial flow fan and the wind duct located in the dirty air zone and connected to the front air outlet of the first axial flow fan to deliver the fresh air in the fresh air zone to the heading face, and use the second axial flow fan and the wind duct located in the fresh air zone and connected to the rear air outlet of the second axial flow fan to discharge the dirty air in the dirty air zone out of the tunnel.
[0019] Furthermore, after the ventilation trolley travels into the tunnel, it stops at a position halfway along the excavation length.
[0020] Furthermore, an electric control system is deployed on the mobile test bench, and the driving device of the travel wheel, the air compressor, the high-pressure air curtain machine and the axial flow fan are all controlled by the electric control system.
[0021] Furthermore, a hydraulic control system is deployed on the mobile platform, and the operation of the hydraulic rod body in the mobile platform is controlled by the hydraulic control system.
[0022] Compared with the prior art, the present invention has the following beneficial effects:
[0023] The present invention provides a tunnel mobile high-pressure wind curtain dust-proof isolation ventilation trolley and a ventilation method thereof. The tunnel is isolated into a fresh air area and a polluted air area by using a high-pressure wind curtain, and an axial flow fan is arranged in each area for ventilation. The air supply and exhaust distances of long and large tunnel construction ventilation can be halved, and the wind resistance is halved. Fresh air can be more effectively delivered to the heading face, and polluted air can be exhausted out of the tunnel. The cost is low and the construction is convenient. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, drawings of other embodiments can be obtained based on these drawings without paying creative work.
[0025] Figure 1 It is a cross-sectional view of the trolley of the present invention.
[0026] Figure 2 It is a longitudinal sectional view of the trolley of the present invention.
[0027] Figure 3 yes Figure 2 AA section view in.
[0028] Figure 4 Schematic diagram of ventilation in the first stage of the method of the present invention.
[0029] Figure 5 Schematic diagram of ventilation in the first stage of the method of the present invention.
[0030] The symbols in the figure are:
[0031] 1-lining, 2-airbag, 3-mobile test bench, 4-power control system, 5-hydraulic control system, 6-air compressor, 7-high-pressure air curtain, 8-traveling wheel, 9-first axial flow fan, 10-second axial flow fan, 11-blocking plate. DETAILED DESCRIPTION
[0032] In order to facilitate the understanding of the present invention, the present invention will be described more fully below with reference to the relevant drawings. The preferred embodiments of the present invention are given in the drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thoroughly understood.
[0033] In the description of the present invention, it is necessary to understand that the terms "center line", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "longitudinal", "lateral" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0034] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "connection", "setting", etc. should be understood in a broad sense, for example, it can be fixed connection, setting, or detachable connection, setting, or integral connection, setting. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0035] Meanwhile, in the description of the present invention, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance. Of course, such objects can be interchanged where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than that illustrated or described herein.
[0036] It should also be noted that although the order of steps is mentioned in the method description, in some cases, they may be performed in an order different from that shown here, and it should not be understood as a limitation on the order of steps.
[0037] In a specific implementation manner, the tunnel length direction is defined as the longitudinal direction, the direction perpendicular to the tunnel length direction is defined as the transverse direction, the direction toward the tunnel face is defined as the front direction, and the direction toward the outside of the tunnel opening is defined as the rear direction.
[0038] The present invention provides a tunnel mobile high-pressure wind curtain dust-proof isolation ventilation trolley, which is used for effectively ventilating a single-hole dead-end tunnel with a long excavation length, supplying fresh air, exhausting polluted air, and ensuring the air working environment in the tunnel.
[0039] like Figure 1-3 The ventilation trolley includes a mobile gantry 3, and the frame of the mobile gantry 3 includes a hydraulic rod body, which can control the translation and lifting of the mobile gantry 3 and adjust the position of the mobile gantry 3 to make it centered. The entire mobile gantry 3 is in the shape of a door, and the middle working area is below the door-shaped frame. The bottom of the mobile gantry 3 has walking wheels 8 on both sides, and is equipped with a driving device, so that the mobile gantry 3 can move longitudinally in the tunnel.
[0040] A high-pressure air curtain machine 7 is arranged inside the longitudinal middle of the mobile platform 3, and the air outlet of the high-pressure air curtain machine 7 faces the center line of the tunnel. The high-pressure air curtain machine 7 is located on one side of the mobile platform 3 and is arranged in the height range of the middle working area. After starting, a high-pressure air curtain can be formed at the section where it is located to separate the air environment on both sides of the longitudinal direction. The high-pressure air curtain machine 7 can be FM-6020A type, and multiple units can be arranged adjacent to each other longitudinally if necessary.
[0041] A blocking plate 11 is provided on the mobile stand 3 where the high-pressure air curtain machine 7 is located. The blocking plate 11 is arranged circumferentially on the mobile stand 3 to block the entire cross-section of the mobile stand 3 and leave a middle operating area and an upper fan port.
[0042] The outer side of the mobile platform 3 and the position corresponding to the blocking plate 11 are provided with an annularly arranged airbag 2. The airbag 2 is in the shape of a belt and is located in the same cross section as the high-pressure air curtain machine 7. After the airbag 2 is inflated, it fills the gap between the blocking plate 11 and the lining. The airbag 2 is connected to the air compressor 6, and the air compressor 6 can be used to inflate and deflate the airbag 2. The air compressor 6 can be set on the mobile platform 3. When the ventilation trolley moves, the gas in the airbag 2 is released to create a certain gap between it and the lining for easy walking; after the ventilation trolley is in place, the air compressor 6 is used to inflate the airbag 2 to block the gap between the ventilation trolley and the lining.
[0043] After the airbag 2 is inflated, the high-pressure air curtain machine 7 is turned on to form a high-pressure air curtain. The high-pressure air curtain, the blocking plate 11 and the airbag 2 can fully block the section where they are located, and isolate the air environment inside the tunnel longitudinally from front to back.
[0044] The upper part of the mobile platform 3 is a fan rack, which is located above the middle working area. Two axial flow fans are arranged in the fan rack, which are symmetrically arranged on the left and right, namely the first axial flow fan 9 and the second axial flow fan 10, which pass through the upper fan port of the blocking plate 11. The first axial flow fan 9 can be used to supply fresh air to the face, and the second axial flow fan 10 can be used to exhaust the dirty air out of the hole.
[0045] The ventilation method implemented by using the above-mentioned tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley specifically includes the following steps:
[0046] S1: When the tunnel excavation length is less than 1500m, ordinary pressure ventilation is adopted. The axial flow fan is set outside the tunnel. The fresh air is delivered to the heading through the wind pipe, and the polluted air is pressed out of the tunnel.
[0047] S2: When the tunnel excavation length is greater than 1500m, the ventilation trolley will be driven into the tunnel.
[0048] Specifically, after the ventilation trolley travels into the tunnel, it stops at a position halfway along the excavation length.
[0049] S3: After the ventilation trolley is in place, the hydraulic control system 5 is used to translate and lift the mobile gantry 3 to make it centered. The airbag 2 and the high-pressure air curtain machine 7 are turned on to form a high-pressure air curtain at the section where the high-pressure air curtain machine 7 is located, so that the area from the high-pressure air curtain machine 7 to the outside of the tunnel forms a fresh air area, and the area from the high-pressure air curtain machine 7 to the face of the tunnel forms a polluted air area;
[0050] S4: Turn on the axial flow fan, use the first axial flow fan 9 and the wind tube located in the dirty air zone and connected to the front air outlet of the first axial flow fan 9 to deliver the fresh air in the fresh air zone to the face, and use the second axial flow fan 10 and the wind tube located in the fresh air zone and connected to the rear air outlet of the second axial flow fan 10 to discharge the dirty air in the dirty air zone out of the tunnel.
[0051] The first axial flow fan 9 and the second axial flow fan 10 are arranged in opposite directions to form airflows in different directions, thereby achieving long-distance polluted air discharge and fresh air transmission.
[0052] The present invention deploys an electric control system 4 on the mobile platform 3, and the driving device of the travel wheel 8, the air compressor 6, the high-pressure air curtain machine 7 and the axial flow fan are all controlled by the electric control system 4. In addition, a hydraulic control system 5 is deployed on the mobile platform 3, and the operation of the hydraulic rod body in the mobile platform 3 is controlled by the hydraulic control system 5.
[0053] The above ventilation process includes two ventilation stages:
[0054] First stage ventilation:
[0055] like Figure 4 The tunnel excavation length is <1500m, and ordinary pressure-type ventilation is adopted. The axial flow fan is installed outside the tunnel. The fresh air is delivered to the heading face through the wind pipe, and the polluted air is pressed out of the tunnel.
[0056] Second stage ventilation:
[0057] like Figure 5 , when the tunnel excavation length L1>1500m, a high-pressure air curtain is used for dust-proof isolation ventilation, and the ventilation trolley drives to L1 / 2 in the tunnel. The high-pressure air curtain machine 7 is turned on, and together with the airbag 2 and the blocking plate 11, the tunnel is isolated into a fresh air zone and a polluted air zone. The fresh air zone of the tunnel is the area from the high-pressure air curtain to the outside of the tunnel, and the polluted air zone is the area from the high-pressure air curtain to the face. The source of polluted air is mainly dust generated by blasting, slag discharge, grouting and electric welding operations.
[0058] Two axial flow fans are turned on, the first axial flow fan 9 delivers fresh air into the face through the wind tube, and the first axial flow fan 10 draws the dirty air out of the hole through the wind tube.
[0059] As the tunnel excavation length increases and the ventilation difficulty increases, the ventilation trolley is moved forward and the above-mentioned second stage ventilation steps are repeated.
[0060] The present invention separates the tunnel into a fresh air zone and a polluted air zone, and ventilates each zone through an axial flow fan. This method reduces the air supply and exhaust distances of long tunnel construction ventilation by half, reduces the wind resistance by half, and more effectively delivers fresh air to the face and exhausts polluted air out of the tunnel, solving the problem of long polluted air return distance and difficulty in exhausting polluted air out of the tunnel in traditional relay ventilation of a single-tunnel single-headed excavation face of 3 to 4 km, causing the tunnel to remain polluted. Compared with high-power axial flow fans, it has lower costs. Compared with air channel ventilation, it is more convenient to construct.
[0061] The above specific examples are used to illustrate the present invention, which is only used to help understand the present invention and is not intended to limit the present invention. For those skilled in the art, according to the concept of the present invention, some simple deductions, modifications or substitutions can be made.
Claims
1. Tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley, characterized by: The ventilation trolley comprises a movable stand (3), a high-pressure air curtain machine (7) is arranged on the inner side of the longitudinal middle portion of the movable stand (3), and the air outlet of the high-pressure air curtain machine (7) faces the center line of the tunnel; A blocking plate (11) is provided on the movable platform (3) where the high-pressure air curtain machine (7) is located. The blocking plate (11) is arranged in a circumferential direction on the movable platform (3) to block the entire cross-section of the movable platform (3) and leave a middle operating area and an upper fan port.
2. The tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley according to claim 1 is characterized by: An air bag (2) arranged in a circular direction is provided on the outer side of the movable platform (3) at a position corresponding to the blocking plate (11); the air bag (2) fills the gap between the blocking plate (11) and the lining after being inflated.
3. The tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley according to claim 2 is characterized by: The air bag (2) is in a belt shape and is located in the same cross section as the high-pressure air curtain machine (7).
4. The tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley according to claim 3 is characterized by: The air bag (2) is connected to an air compressor (6), and the air compressor (6) is arranged on the mobile platform (3).
5. The tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley according to claim 4 is characterized by: The upper part of the mobile platform (3) is a fan frame, and the fan frame is located above the middle working area. Two axial flow fans are arranged in the fan frame in a left-right symmetrical manner.
6. The tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley according to claim 5 is characterized by: The movable stand (3) has running wheels (8) on both sides of its bottom.
7. The ventilation method of the tunnel movable high-pressure air curtain dust-proof isolation ventilation trolley according to claim 6, characterized in that: The method comprises: When the tunnel excavation length is less than 1500m, ordinary forced-in ventilation is adopted. The axial flow fan is set outside the tunnel. The fresh air is sent to the tunnel face through the wind tube, and the polluted air is pressed out of the tunnel. When the tunnel excavation length is greater than 1500m, the ventilation trolley is driven into the tunnel; After the ventilation trolley is in place, the hydraulic control system (5) is used to translate and lift the movable trolley (3) to center it; the air bag (2) and the high-pressure air curtain machine (7) are opened to form a high-pressure air curtain at the section where the high-pressure air curtain machine (7) is located, so that the area from the high-pressure air curtain machine (7) to the outside of the tunnel forms a fresh air area, and the area from the high-pressure air curtain machine (7) to the face of the tunnel forms a polluted air area; The axial flow fan is turned on, and fresh air from the fresh air zone is delivered to the tunnel face using the first axial flow fan (9) and a wind tube located in the dirty air zone and connected to the front air outlet of the first axial flow fan (9), and the dirty air from the dirty air zone is discharged out of the tunnel using the second axial flow fan (10) and a wind tube located in the fresh air zone and connected to the rear air outlet of the second axial flow fan (10).
8. The ventilation method of the tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley according to claim 7 is characterized by: After the ventilation trolley drives into the tunnel, it stops at a position halfway along the excavation length.
9. The ventilation method of the tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley according to claim 8, characterized in that: An electric control system (4) is deployed on the mobile platform (3), and the driving device of the walking wheel (8), the air compressor (6), the high-pressure air curtain machine (7) and the axial flow fan are all controlled by the electric control system (4).
10. The ventilation method of the tunnel mobile high-pressure air curtain dust-proof isolation ventilation trolley according to claim 9, characterized in that: A hydraulic control system (5) is deployed on the mobile platform (3), and the operation of the hydraulic rod body in the mobile platform (3) is controlled by the hydraulic control system (5).
Citation Information
Cited By
Local ventilation system and method for high-pollution area in tunnel construction period
CN121088449A