Power-on method, device, electronic equipment and storage medium for energy storage integrated cabinet
By introducing maintenance mode during power-on process of energy storage integrated cabinets, adjusting the self-test threshold and hardware self-test mode, the efficiency reduction caused by error detection during power-on process in the prior art is solved, and a more efficient power-on process is achieved.
Patent Information
- Application Number
- CN202411687957.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-25
- Publication Date
- 2025-02-25
- Estimated Expiration
- 2044-11-25
AI Technical Summary
In the prior art, if an error is detected during power-on, the power-on process will be stopped, resulting in a greatly reduced power-on efficiency when power-on is needed to deal with emergencies in an emergency.
By adding maintenance mode, the power-on process is promoted without affecting safety and improve power-on efficiency. The specific method includes responding to the power-on command, performing a first self-test processing on multiple indicators of the energy storage integrated cabinet, determining the operating mode based on the self-test results, and if it is a maintenance mode, adjusting the self-test threshold for the second self-test processing, and finally determining whether to perform power-on based on the self-test results of the hardware self-test mode.
By adding maintenance mode without affecting safety, the power-on efficiency of the energy storage integrated cabinet is improved and emergency situations can be dealt with more quickly.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of power-on control technology, and in particular to a power-on method, device, electronic equipment and storage medium for an energy storage integrated cabinet. Background Art
[0002] With the development of energy storage systems, the market demand is growing. The emergence of this system not only solves the problem of distribution network in limited land and power capacity resources, but also achieves basic balance between local energy production and energy load through energy storage and optimized configuration. The system can also participate in auxiliary services such as peak and frequency regulation of the power grid, peak shaving and valley filling, and even as a supporting facility for the energy Internet, it supports the integrated development of smart grid, smart charging, and smart information network. Therefore, it is necessary to ensure the rapid power-on of the system.
[0003] In the related art, if an error is detected during the power-on process, the power-on process will be stopped. When power-on is needed to deal with an emergency, the power-on efficiency is greatly affected. Summary of the invention
[0004] In view of this, the purpose of the present invention is to provide a power-on method, device, electronic device and storage medium for an energy storage integrated cabinet, which promotes the power-on process without affecting safety by adding a maintenance mode, thereby improving the power-on efficiency.
[0005] In a first aspect, an embodiment of the present invention provides a method for powering on an energy storage integrated cabinet, the method comprising: in response to a power-on instruction, performing a first self-check processing on multiple indicators of the energy storage integrated cabinet to obtain a first check result; determining an operation mode based on the first check result; if the operation mode is a maintenance mode, adjusting the self-check threshold of the target indicator to a target self-check threshold; performing a second self-check processing based on the target self-check threshold to obtain a second check result; determining the operation mode based on the second check result; if the operation mode is a hardware self-check mode, determining whether to power on the energy storage integrated cabinet based on the self-check result of the hardware self-check mode.
[0006] In a preferred embodiment of the present invention, the above-mentioned first self-inspection processing of multiple indicators of the energy storage integrated cabinet to obtain a first inspection result includes: based on a plurality of pre-set first self-inspection thresholds, self-inspection processing is performed on multiple first indicators of the energy storage integrated cabinet respectively to obtain a first sub-inspection result; the first self-inspection processing is executed by a battery management system; based on a plurality of pre-set second self-inspection thresholds, self-inspection processing is performed on multiple second indicators of the energy storage integrated cabinet respectively to obtain a second sub-inspection result; the second self-inspection processing is executed by an energy storage inverter; and the first inspection result is determined based on the first sub-inspection result and the second sub-inspection result.
[0007] In a preferred embodiment of the present invention, the above-mentioned target indicator is included in multiple first indicators, and the operation mode is determined based on the first inspection result, including: when the second sub-inspection result indicates that multiple second indicators all meet the corresponding second self-test threshold: if the first sub-inspection result indicates that the target indicator does not meet the corresponding first self-test threshold, and the indicators other than the target indicator among the multiple first indicators all meet the corresponding first self-test threshold, then the operation mode is determined to be the maintenance mode; if the first sub-detection result indicates that there are indicators among the multiple first indicators other than the target indicator that do not meet the corresponding first self-test threshold, then the operation mode is determined to be the mode to be checked; when the second sub-inspection result indicates that there are indicators among the multiple second indicators that do not meet the corresponding second self-test threshold: the operation mode is determined to be the mode to be checked.
[0008] In a preferred embodiment of the present invention, the second self-check processing based on the target self-check threshold to obtain the second inspection result includes: comparing the indicators in the target indicators that do not meet the first self-check threshold with the corresponding target self-check threshold to obtain the second inspection result.
[0009] In a preferred embodiment of the present invention, the above-mentioned determination of the operating mode based on the second inspection result includes: if the second inspection result indicates that there is a target indicator that does not meet the target self-test threshold, then the operating mode is a to-be-checked mode; if the second inspection result indicates that all target indicators meet the target self-test threshold, then the operating mode is a hardware self-test mode.
[0010] In a preferred embodiment of the present invention, the above-mentioned hardware self-test mode includes: a first hardware self-test mode run by a battery management system and a second hardware self-test mode run by an energy storage converter; the self-test result includes: a first self-test result corresponding to the first hardware self-test mode and a second self-test result corresponding to the second hardware self-test mode; the self-test result is determined as follows: self-testing the state of the circuit breaker corresponding to the battery management system to determine whether the circuit breaker is closed; if the circuit breaker is closed, closing the main negative relay and the pre-charge relay; after closing the main negative relay and the pre-charge relay, if a preset percentage of pre-charge is reached within a preset time, disconnecting the pre-charge relay and closing the total positive relay to determine that the first self-test result is passed; performing self-test of the second hardware self-test mode by the energy storage converter to obtain a second self-test result; wherein the self-test of the second hardware self-test mode at least includes self-testing the state of the circuit breaker corresponding to the energy storage converter and self-testing the pre-charge; the second self-test result includes passed self-test and failed self-test.
[0011] In a preferred embodiment of the present invention, whether to power on the energy storage integrated cabinet is determined based on the self-test result of the hardware self-test mode, including: if the first self-test result and the second self-test result both pass the self-test, the energy storage integrated cabinet is powered on; otherwise, the operating mode is switched to the to-be-checked mode.
[0012] In a second aspect, an embodiment of the present invention further provides a power-on device for an energy storage integrated cabinet, comprising: a first self-check processing module, for responding to a power-on instruction, to perform a first self-check processing on multiple indicators of the energy storage integrated cabinet to obtain a first check result; a first operation mode determination module, for determining the operation mode based on the first check result; a self-check threshold adjustment module, for adjusting the self-check threshold of the target indicator to the target self-check threshold if the operation mode is a maintenance mode; a second self-check processing module, for performing a second self-check processing based on the target self-check threshold to obtain a second check result; a second operation mode determination module, for determining the operation mode based on the second check result; and a power-on judgment module, for determining whether to power on the energy storage integrated cabinet based on the self-check result of the hardware self-check mode if the operation mode is a hardware self-check mode.
[0013] In a third aspect, an embodiment of the present invention further provides an electronic device, including a processor and a memory, wherein the memory stores computer executable instructions that can be executed by the processor, and the processor executes the computer executable instructions to implement the power-on method of the energy storage integrated cabinet of the first aspect.
[0014] In a fourth aspect, an embodiment of the present invention further provides a computer-readable storage medium, which stores computer-executable instructions. When the computer-executable instructions are called and executed by a processor, the computer-executable instructions prompt the processor to implement the power-on method of the energy storage integrated cabinet of the first aspect mentioned above.
[0015] The embodiments of the present invention bring the following beneficial effects:
[0016] The embodiment of the present invention provides a power-on method, device, electronic device and storage medium for an energy storage integrated cabinet. In response to a power-on instruction, a first self-check process is performed on multiple indicators of the energy storage integrated cabinet to obtain a first check result, and an operation mode is determined based on the first check result. When the operation mode is a maintenance mode, the self-check threshold of the target indicator is adjusted to a target self-check threshold, and then a second self-check process is performed based on the target self-check threshold to obtain a second check result. The operation mode is determined based on the second check result. When the operation mode is a hardware self-check mode, whether to power on the energy storage integrated cabinet is determined based on the self-check result of the hardware self-check mode. In this method, the power-on process is promoted without affecting safety by adding a maintenance mode, thereby improving the power-on efficiency.
[0017] Other features and advantages of the present disclosure will be set forth in the following description, or some features and advantages may be inferred or unambiguously determined from the description, or may be learned by implementing the above-mentioned technology of the present disclosure.
[0018] In order to make the above-mentioned objectives, features and advantages of the present disclosure more obvious and easy to understand, preferred embodiments are specifically cited below and described in detail with reference to the attached drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0020] Figure 1 A flowchart of a method for powering on an energy storage integrated cabinet provided in an embodiment of the present invention;
[0021] Figure 2 A flowchart of another method for powering on an energy storage integrated cabinet provided in an embodiment of the present invention;
[0022] Figure 3 A comparison chart of maintenance mode processing measures provided by an embodiment of the present invention;
[0023] Figure 4 A schematic diagram of a power-on strategy for an energy storage integrated cabinet provided in an embodiment of the present invention;
[0024] Figure 5 A schematic diagram of the structure of a power-on device for an energy storage integrated cabinet provided in an embodiment of the present invention;
[0025] Figure 6 A schematic diagram of the structure of an electronic device provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0027] In order to solve the problem in the related art that if an error is detected during the power-on process, the power-on process will be stopped, which greatly affects the power-on efficiency when power-on is needed to deal with emergencies in an emergency, the embodiment of the present invention provides a power-on method, device, electronic device and storage medium for an energy storage integrated cabinet. In response to a power-on instruction, a first self-check process is performed on multiple indicators of the energy storage integrated cabinet to obtain a first check result, and an operation mode is determined based on the first check result. When the operation mode is a maintenance mode, the self-check threshold of the target indicator is adjusted to the target self-check threshold, and then a second self-check process is performed based on the target self-check threshold to obtain a second check result. The operation mode is determined based on the second check result. When the operation mode is a hardware self-check mode, it is determined whether to power on the energy storage integrated cabinet based on the self-check result of the hardware self-check mode. In this method, the power-on process is promoted without affecting safety by adding a maintenance mode, thereby improving the power-on efficiency.
[0028] To facilitate understanding of this embodiment, a power-on method for an energy storage integrated cabinet disclosed in an embodiment of the present invention is first introduced in detail.
[0029] Example 1
[0030] The embodiment of the present invention provides a method for powering on an energy storage integrated cabinet. Figure 1 The following is a flow chart of a method for powering on an energy storage integrated cabinet provided by an embodiment of the present invention. Figure 1 As shown, the power-on method of the energy storage integrated cabinet may include the following steps:
[0031] Step S101, in response to a power-on instruction, a first self-check process is performed on a plurality of indicators of the energy storage integrated cabinet to obtain a first check result.
[0032] The first self-check process may include a self-check process executed by a battery management system and a self-check process executed by an energy storage converter.
[0033] Among them, the indicators of self-test run by the battery management system may include single cell information, total battery voltage information, current signal information, temperature information, relay adhesion information, insulation information, etc., and the indicators of self-test run by the energy storage inverter may include short circuit information, overvoltage information, overfrequency information, insulation information and hardware adhesion information.
[0034] The first inspection result represents the fault conditions of the respective multiple indicators. If a preset self-checking threshold is met, it is determined that there is no fault, and if the self-checking threshold is not met, it is determined that there is a fault.
[0035] Furthermore, before performing a first self-check process on multiple indicators of the energy storage integrated cabinet to obtain a first inspection result, the method may also include: judging the communication status, if a communication failure occurs, stopping power supply, if there is no communication failure, performing a first self-check process on multiple indicators of the energy storage integrated cabinet to obtain a first inspection result.
[0036] Among them, the battery management system and energy storage inverter have corresponding display screens. If a communication failure occurs, a prompt will be given through the display screen.
[0037] Step S102: determining the operation mode based on the first inspection result.
[0038] The operation mode may include a maintenance mode, a hardware self-check mode, and a troubleshooting mode.
[0039] Among them, the maintenance mode is a mode that can only be entered when a target indicator fails. It is used to relax the self-check threshold of the target indicator without affecting safety, so as not to affect the power-on process when power-on is urgently needed, thereby improving the power-on efficiency.
[0040] Among them, the hardware self-test mode is a mode that can be entered when the corresponding self-tests of the battery management system and the energy storage converter are passed, and is used to perform hardware self-test.
[0041] Among them, the pending troubleshooting mode is a mode that can be entered under the premise that a fault indicator appears and the fault indicator does not meet the requirements for entering the maintenance mode, and is used to prompt the staff to inspect the components corresponding to the indicator.
[0042] Step S103: If the operation mode is the maintenance mode, the self-check threshold of the target indicator is adjusted to the target self-check threshold.
[0043] The range of the self-test threshold is smaller than the range of the target self-test threshold. By relaxing the range of the self-test threshold, power-on is not affected when power-on is urgently needed, thereby improving power-on efficiency.
[0044] Step S104: performing a second self-check process based on the target self-check threshold to obtain a second check result.
[0045] Among them, the second self-check processing is aimed at the self-check of the battery management system operation, which is used to perform a secondary self-check on the target indicator. When the target indicator meets the target self-check threshold, the power-on process continues to improve the power-on efficiency.
[0046] Step S105, determining the operation mode based on the second inspection result.
[0047] Wherein, when the second inspection result is that the target indicator meets the target self-check threshold, the operation mode is determined to be the hardware self-check mode.
[0048] Step S106: If the operation mode is the hardware self-test mode, determine whether to power on the energy storage integrated cabinet based on the self-test result of the hardware self-test mode.
[0049] Among them, the battery management system and the energy storage converter correspond to different hardware self-test modes respectively. The battery management system includes self-test corresponding to the circuit breaker status and self-test of the pre-charge condition, and the energy storage converter at least includes self-test corresponding to the circuit breaker status and self-test of the pre-charge condition.
[0050] The power-on method of the energy storage integrated cabinet provided in the embodiment of the present invention can perform a first self-check process on multiple indicators of the energy storage integrated cabinet in response to a power-on instruction to obtain a first check result, determine the operation mode based on the first check result, and when the operation mode is the maintenance mode, adjust the self-check threshold of the target indicator to the target self-check threshold, and then perform a second self-check process based on the target self-check threshold to obtain a second check result, determine the operation mode based on the second check result, and when the operation mode is the hardware self-check mode, determine whether to power on the energy storage integrated cabinet based on the self-check result of the hardware self-check mode. In this method, the power-on process is promoted without affecting safety by adding a maintenance mode, thereby improving the power-on efficiency.
[0051] Example 2
[0052] The embodiment of the present invention also provides another method for powering on an integrated energy storage cabinet; this method is implemented on the basis of the method in the above embodiment.
[0053] Figure 2 A flowchart of another method for powering on an energy storage integrated cabinet provided in an embodiment of the present invention, such as Figure 2 As shown, the power-on method of the energy storage integrated cabinet may include the following steps:
[0054] Step S201, in response to a power-on instruction, a first self-check process is performed on a plurality of indicators of the energy storage integrated cabinet to obtain a first check result.
[0055] Specifically, a first self-inspection process is performed on multiple indicators of the energy storage integrated cabinet to obtain a first inspection result, including: based on a plurality of pre-set first self-inspection thresholds, a plurality of first indicators of the energy storage integrated cabinet are respectively self-inspected to obtain a first sub-inspection result; the first self-inspection process is executed by a battery management system; based on a plurality of pre-set second self-inspection thresholds, a plurality of second indicators of the energy storage integrated cabinet are respectively self-inspected to obtain a second sub-inspection result; the second self-inspection process is executed by an energy storage inverter; and the first inspection result is determined based on the first sub-inspection result and the second sub-inspection result.
[0056] Among them, the first indicator may include single cell information, total battery voltage information, current signal information, temperature information, relay adhesion information, insulation information, etc., and the second indicator may include short circuit information, overvoltage information, overfrequency information, insulation information and hardware adhesion information.
[0057] Each of the above information has a corresponding self-check threshold, and whether a fault occurs is determined by comparing it with the self-check threshold, thereby determining the first inspection result.
[0058] Specifically, Table 1 is a comparison table of indicators and self-test thresholds under normal charging and discharging conditions:
[0059] Table 1:
[0060]
[0061] Step S202: determining the operation mode based on the first inspection result.
[0062] Specifically, when the second sub-inspection result indicates that multiple second indicators all meet the corresponding second self-inspection threshold: if the first sub-inspection result indicates that the target indicator does not meet the corresponding first self-inspection threshold, and the indicators other than the target indicator among the multiple first indicators all meet the corresponding first self-inspection threshold, then the operation mode is determined to be the maintenance mode; if the first sub-inspection result indicates that there are indicators other than the target indicator among the multiple first indicators that do not meet the corresponding first self-inspection threshold, then the operation mode is determined to be the troubleshooting mode.
[0063] When the second sub-inspection result indicates that there is an indicator among the plurality of second indicators that does not meet the corresponding second self-inspection threshold value: determining the operation mode to be checked mode.
[0064] Step S203: If the operation mode is the maintenance mode, the self-check threshold of the target indicator is adjusted to the target self-check threshold.
[0065] Among them, when it is determined that the target indicator has a fault, the battery management system will feedback to the EMS whether to execute the maintenance mode. If feedback to execute the maintenance mode is received within the preset waiting time, the maintenance mode will be executed, otherwise it will enter the troubleshooting mode.
[0066] The preset waiting time may be 30 minutes.
[0067] Among them, the target indicators may include: single cell voltage, cluster total voltage, pack total voltage, temperature, temperature difference, pressure difference and state of charge; the specific fault causes may be single cell voltage too low, cluster total voltage too low, pack total voltage too low, temperature too low, temperature difference too large, pressure difference too large and state of charge too low.
[0068] Specifically, Figure 3 A comparison diagram of maintenance mode processing measures provided by an embodiment of the present invention, such as Figure 3 As shown in the figure, the abnormal conditions of the target indicators in the maintenance mode, condition thresholds (target self-test thresholds), trigger time, recovery time, charge and discharge modes, processing measures, alarm level reporting, and manual processing measures are described in detail.
[0069] Step S204: compare the target indicators that do not meet the first self-check threshold with the corresponding target self-check threshold to obtain a second check result.
[0070] Step S205: If the second inspection result indicates that there is a target indicator that does not meet the target self-inspection threshold, the operation mode is a waiting-for-inspection mode.
[0071] Step S206: If the second inspection result indicates that the target indicators all meet the target self-check threshold, the operation mode is the hardware self-check mode.
[0072] The hardware self-test mode includes: a first hardware self-test mode run by the battery management system and a second hardware self-test mode run by the energy storage converter; the self-test result includes: a first self-test result corresponding to the first hardware self-test mode and a second self-test result corresponding to the second hardware self-test mode;
[0073] Step S207: If the operation mode is the hardware self-test mode, determine whether to power on the energy storage integrated cabinet based on the self-test result of the hardware self-test mode.
[0074] Specifically, the self-test result is determined as follows: self-test the state of the circuit breaker corresponding to the battery management system to determine whether the circuit breaker is closed; if the circuit breaker is closed, close the main negative relay and the pre-charge relay; after closing the main negative relay and the pre-charge relay, if a preset percentage of pre-charge is reached within a preset time, disconnect the pre-charge relay and close the total positive relay to determine that the first self-test result is passed; perform a self-test of the second hardware self-test mode on the energy storage inverter to obtain a second self-test result; wherein the self-test of the second hardware self-test mode includes at least a self-test of the state of the circuit breaker corresponding to the energy storage inverter and a self-test of the pre-charge; the second self-test result includes a passed self-test and a failed self-test.
[0075] Among them, the preset time can be 3 seconds, the preset percentage can be 90%, and the pre-charging resistor burning out, the pre-charging resistor being too large, the load short circuit, the high-voltage component short circuit, etc. may all cause the pre-charging to fail to meet the preset percentage.
[0076] Among them, the circuit breaker will open and close during self-inspection, and the circuit breaker will send the current working status to the battery management system. This action is considered to be feedback from the circuit breaker, so it can be determined whether the circuit breaker is closed. Otherwise, it is considered that the circuit breaker has no feedback and a fault has occurred.
[0077] If both the first self-test result and the second self-test result are through, the energy storage integrated cabinet is powered on; otherwise, the operation mode is switched to the to-be-checked mode.
[0078] For ease of understanding, Figure 4 A schematic diagram of a power-on strategy for an energy storage integrated cabinet provided in an embodiment of the present invention, such as Figure 4 As shown, after receiving the power-on command, the communication status can be judged first. When there is no fault in the communication status, the self-test of the battery management system and the self-test of the energy storage converter can be performed at the same time. Each self-test has a corresponding self-test indicator. When there is no fault in each indicator, or when only the target indicator has a fault but there is no fault after passing the maintenance mode, it can be considered that the self-test has passed, and the hardware self-test mode is entered. After the self-test result of the hardware self-test mode indicates that there is no fault, the self-test is completed, the high voltage is powered on, and the EMS instruction is waited.
[0079] It should be noted that the maintenance mode is only performed once for each self-test.
[0080] It should be noted that after the hardware self-test mode corresponding to the battery management system ends, it is necessary to exit the insulation test; after receiving the power-on command, it is also necessary to make a communication judgment on the EMS. If a communication failure occurs, the corresponding display screen of the EMS will also display it.
[0081] The power-on method for the energy storage integrated cabinet provided in the embodiment of the present invention can be performed by the battery management system and the energy storage converter to run self-tests in parallel, which saves the time for self-tests, and the power-on is performed after both have passed the self-tests, which improves the power-on safety, and when the battery management system runs the self-test, if the target indicator does not meet the first self-test threshold, the self-test threshold of the target indicator is amplified within a safe range, so as to realize power-on in the scenario where power-on is urgently needed, thereby improving the power-on efficiency.
[0082] Example 3
[0083] Corresponding to the above method embodiment, the embodiment of the present invention provides a power-on device for an energy storage integrated cabinet, Figure 5 A schematic diagram of a power-on device for an energy storage integrated cabinet provided in an embodiment of the present invention is shown in FIG. Figure 5 As shown, the power-on device of the energy storage integrated cabinet may include:
[0084] The first self-check processing module 301 is used to respond to a power-on instruction and perform a first self-check processing on multiple indicators of the energy storage integrated cabinet to obtain a first check result.
[0085] The first operation mode determination module 302 is configured to determine an operation mode based on a first inspection result.
[0086] The self-check threshold adjustment module 303 is used to adjust the self-check threshold of the target indicator to the target self-check threshold if the operation mode is the maintenance mode.
[0087] The second self-check processing module 304 is used to perform a second self-check processing based on the target self-check threshold to obtain a second check result.
[0088] The second operation mode determination module 305 is used to determine the operation mode based on the second inspection result.
[0089] The power-on determination module 306 is used to determine whether to power on the energy storage integrated cabinet based on the self-test result of the hardware self-test mode if the operation mode is the hardware self-test mode.
[0090] The power-on device of the energy storage integrated cabinet provided in the embodiment of the present invention can perform a first self-check process on multiple indicators of the energy storage integrated cabinet in response to a power-on instruction to obtain a first check result, determine the operation mode based on the first check result, and when the operation mode is the maintenance mode, adjust the self-check threshold of the target indicator to the target self-check threshold, and then perform a second self-check process based on the target self-check threshold to obtain a second check result, determine the operation mode based on the second check result, and when the operation mode is the hardware self-check mode, determine whether to power on the energy storage integrated cabinet based on the self-check result of the hardware self-check mode. In this method, the power-on process is promoted without affecting safety by adding a maintenance mode, thereby improving the power-on efficiency.
[0091] In some embodiments, the first self-test processing module is also used to perform self-test processing on multiple first indicators of the energy storage integrated cabinet based on multiple pre-set first self-test thresholds to obtain a first sub-inspection result; the first self-test processing is executed by the battery management system; based on multiple pre-set second self-test thresholds, multiple second indicators of the energy storage integrated cabinet are self-tested to obtain a second sub-inspection result; the second self-test processing is executed by the energy storage inverter; and the first inspection result is determined based on the first sub-inspection result and the second sub-inspection result.
[0092] In some embodiments, the first operating mode determination module is also used to, when the second sub-inspection result indicates that multiple second indicators all meet the corresponding second self-test threshold: if the first sub-inspection result indicates that the target indicator does not meet the corresponding first self-test threshold, and the indicators among the multiple first indicators except the target indicator all meet the corresponding first self-test threshold, then determine that the operating mode is the maintenance mode; if the first sub-detection result indicates that there are indicators among the multiple first indicators except the target indicator that do not meet the corresponding first self-test threshold, then determine that the operating mode is the to-be-checked mode; when the second sub-inspection result indicates that there are indicators among the multiple second indicators that do not meet the corresponding second self-test threshold: determine that the operating mode is the to-be-checked mode.
[0093] In some embodiments, the second self-check processing module is further used to compare the target indicator that does not meet the first self-check threshold with the corresponding target self-check threshold to obtain a second check result.
[0094] In some embodiments, the second operating mode determination module is also used to determine that if the second inspection result indicates that there is a target indicator that does not meet the target self-test threshold, the operating mode is a to-be-checked mode; if the second inspection result indicates that all target indicators meet the target self-test threshold, the operating mode is a hardware self-test mode.
[0095] In some embodiments, the hardware self-test mode includes: a first hardware self-test mode run by a battery management system and a second hardware self-test mode run by an energy storage inverter; the self-test results include: a first self-test result corresponding to the first hardware self-test mode and a second self-test result corresponding to the second hardware self-test mode; the power-on judgment module is also used to self-test the state of the circuit breaker corresponding to the battery management system to determine whether the circuit breaker is closed; if the circuit breaker is closed, the main negative relay and the pre-charge relay are closed; after closing the main negative relay and the pre-charge relay, if a preset percentage of pre-charge is reached within a preset time, the pre-charge relay is disconnected and the total positive relay is closed to determine that the first self-test result is passed; the energy storage inverter performs a self-test in the second hardware self-test mode to obtain a second self-test result; wherein the self-test in the second hardware self-test mode at least includes a self-test of the state of the circuit breaker corresponding to the energy storage inverter and a self-test of the pre-charge; the second self-test result includes a passed self-test and a failed self-test.
[0096] In some embodiments, the power-on judgment module is further used to power on the energy storage integrated cabinet if both the first self-test result and the second self-test result pass the self-test; otherwise, the operation mode is switched to a to-be-checked mode.
[0097] The device provided in the embodiment of the present invention has the same implementation principle and technical effects as those of the aforementioned method embodiment. For the sake of brief description, for matters not mentioned in the device embodiment, reference may be made to the corresponding contents in the aforementioned method embodiment.
[0098] Example 4
[0099] The embodiment of the present invention also provides an electronic device for running the power-on method of the above energy storage integrated cabinet; see Figure 6 A structural schematic diagram of an electronic device is shown, which includes a memory 400 and a processor 401, wherein the memory 400 is used to store one or more computer instructions, and the one or more computer instructions are executed by the processor 401 to implement the power-on method of the above-mentioned energy storage integrated cabinet.
[0100] Further, Figure 6The electronic device shown further includes a bus 402 and a communication interface 403 , and the processor 401 , the communication interface 403 and the memory 400 are connected via the bus 402 .
[0101] The memory 400 may include a high-speed random access memory (RAM), and may also include a non-volatile memory, such as at least one disk storage. The communication connection between the system network element and at least one other network element is realized through at least one communication interface 403 (which may be wired or wireless), and the Internet, wide area network, local area network, metropolitan area network, etc. may be used. The bus 402 may be an ISA bus, a PCI bus, or an EISA bus, etc. The bus can be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 6 Only one bidirectional arrow is used in the diagram, but this does not mean that there is only one bus or only one type of bus.
[0102] The processor 401 may be an integrated circuit chip with signal processing capabilities. In the implementation process, each step of the above method can be completed by the hardware integrated logic circuit or software instructions in the processor 401. The above processor 401 can be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it can also be a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field-programmable gate array (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components. The methods, steps and logic block diagrams disclosed in the embodiments of the present invention can be implemented or executed. The general processor can be a microprocessor or the processor can also be any conventional processor, etc. The steps of the method disclosed in the embodiment of the present invention can be directly embodied as a hardware decoding processor for execution, or a combination of hardware and software modules in the decoding processor for execution. The software module may be located in a storage medium mature in the art, such as a random access memory, a flash memory, a read-only memory, a programmable read-only memory, or an electrically erasable programmable memory, a register, etc. The storage medium is located in the memory 400, and the processor 401 reads the information in the memory 400 and completes the steps of the method of the above embodiment in combination with its hardware.
[0103] An embodiment of the present invention further provides a computer-readable storage medium, which stores computer-executable instructions. When the computer-executable instructions are called and executed by a processor, the computer-executable instructions prompt the processor to implement the power-on method of the above-mentioned energy storage integrated cabinet. The specific implementation can be found in the method embodiment, which will not be repeated here.
[0104] The computer program product for the method of powering on an energy storage integrated cabinet provided in an embodiment of the present invention includes a computer-readable storage medium storing a non-volatile program code executable by a processor. The instructions included in the program code can be used to execute the method described in the previous method embodiment. The specific implementation can be referred to the method embodiment, which will not be repeated here.
[0105] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.
[0106] In the several embodiments provided by the present invention, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. The device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some communication interfaces, and the indirect coupling or communication connection of devices or units can be electrical, mechanical or other forms.
[0107] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0108] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.
[0109] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a non-volatile computer-readable storage medium that can be executed by a processor. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art, or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions for enabling a computer device (which can be a personal computer, server, or network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk, etc., various media that can store program codes.
[0110] Finally, it should be noted that the above-described embodiments are only specific implementations of the present invention, which are used to illustrate the technical solutions of the present invention, rather than to limit them. The protection scope of the present invention is not limited thereto. Although the present invention is described in detail with reference to the above-mentioned embodiments, ordinary technicians in the field should understand that any technician familiar with the technical field can still modify the technical solutions recorded in the above-mentioned embodiments within the technical scope disclosed by the present invention, or can easily think of changes, or make equivalent replacements for some of the technical features therein; and these modifications, changes or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present invention, and should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention shall be based on the protection scope of the claims.
Claims
1. A method for powering on an energy storage integrated cabinet, characterized in that: The method comprises: In response to the power-on instruction, a first self-check process is performed on multiple indicators of the energy storage integrated cabinet to obtain a first check result; determining an operating mode based on the first inspection result; If the operation mode is the maintenance mode, adjusting the self-check threshold of the target indicator to the target self-check threshold; Performing a second self-check process based on the target self-check threshold to obtain a second check result; determining the operating mode based on the second inspection result; If the operation mode is a hardware self-test mode, determining whether to power on the energy storage integrated cabinet based on a self-test result of the hardware self-test mode; The first self-checking process is performed on multiple indicators of the energy storage integrated cabinet to obtain a first check result, including: Based on a plurality of preset first self-check thresholds, a first sub-self-check process is performed on a plurality of first indicators of the energy storage integrated cabinet to obtain a first sub-check result; the first sub-self-check process is executed by a battery management system; Based on multiple preset second self-check thresholds, second sub-self-check processing is performed on multiple second indicators of the energy storage integrated cabinet to obtain second sub-check results; the second sub-self-check processing is performed by the energy storage converter; determining the first inspection result based on the first sub-inspection result and the second sub-inspection result; The target indicator is included in the plurality of the first indicators, and the determining of the operation mode based on the first inspection result includes: When the second sub-inspection result indicates that the plurality of second indicators all meet the corresponding second self-inspection thresholds: If the first sub-inspection result indicates that the target indicator does not meet the corresponding first self-inspection threshold, and the indicators other than the target indicator among the plurality of the first indicators meet the corresponding first self-inspection threshold, determining that the operation mode is a maintenance mode; If the first sub-detection result indicates that among the first indicators, except for the target indicator, there is an indicator that does not meet the corresponding first self-check threshold, determining that the operation mode is a to-be-checked mode; When the second sub-inspection result indicates that there is an indicator among the plurality of second indicators that does not meet the corresponding second self-inspection threshold: Determining that the operating mode is a to-be-checked mode; The maintenance mode is a mode entered only when the target indicator fails, and is used to relax the self-check threshold of the target indicator without affecting safety, so as not to affect power-on in an urgent need of power-on, thereby improving power-on efficiency.
2. The method according to claim 1, characterized in that: The performing a second self-check process based on the target self-check threshold to obtain a second check result includes: The target indicators that do not meet the first self-check threshold are compared with the corresponding target self-check threshold to obtain a second check result.
3. The method according to claim 1, characterized in that The determining the operation mode based on the second inspection result includes: If the second inspection result indicates that the target indicator does not meet the target self-inspection threshold, the operation mode is a waiting-for-inspection mode; If the second inspection result indicates that the target indicators all meet the target self-check threshold, then the operation mode is the hardware self-check mode.
4. The method according to claim 1, characterized in that: The hardware self-test mode includes: a first hardware self-test mode run by the battery management system and a second hardware self-test mode run by the energy storage converter; the self-test result includes: a first self-test result corresponding to the first hardware self-test mode and a second self-test result corresponding to the second hardware self-test mode; The self-test result is determined in the following manner: Performing a self-check on the state of the circuit breaker corresponding to the battery management system to determine whether the circuit breaker is closed; If the circuit breaker is closed, the main negative relay and the pre-charge relay are closed; After closing the main negative relay and the pre-charge relay, if a preset percentage of pre-charge is reached within a preset time, disconnecting the pre-charge relay and closing the main positive relay, and determining that the first self-test result is passed; Performing a self-test in a second hardware self-test mode on the energy storage converter to obtain a second self-test result; The self-test of the second hardware self-test mode at least includes a self-test of the state of the circuit breaker corresponding to the energy storage converter and a self-test of the pre-charge; and the second self-test result includes a self-test pass and a self-test fail.
5. The method according to claim 4, characterized in that The determining whether to power on the energy storage integrated cabinet based on the self-test result of the hardware self-test mode includes: If both the first self-test result and the second self-test result are passed, powering on the energy storage integrated cabinet; Otherwise, the operation mode is switched to a to-be-checked mode.
6. A power-on device for an energy storage integrated cabinet, characterized in that: A method for powering on an energy storage integrated cabinet according to any one of claims 1 to 5, the device comprising: A first self-check processing module, configured to perform a first self-check processing on a plurality of indicators of the energy storage integrated cabinet in response to a power-on instruction to obtain a first check result; A first operation mode determination module, configured to determine an operation mode based on the first inspection result; A self-check threshold adjustment module, used for adjusting the self-check threshold of the target indicator to a target self-check threshold if the operation mode is a maintenance mode; A second self-check processing module, configured to perform a second self-check processing based on the target self-check threshold to obtain a second check result; A second operation mode determination module, configured to determine the operation mode based on the second inspection result; The power-on judgment module is used to determine whether to power on the energy storage integrated cabinet based on the self-test result of the hardware self-test mode if the operating mode is the hardware self-test mode.
7. An electronic device, characterized in that: It includes a processor and a memory, the memory stores computer executable instructions that can be executed by the processor, and the processor executes the computer executable instructions to implement the power-on method of the energy storage integrated cabinet according to any one of claims 1 to 5.
8. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer-executable instructions. When the computer-executable instructions are called and executed by the processor, the computer-executable instructions prompt the processor to implement the power-on method of the energy storage integrated cabinet according to any one of claims 1 to 5.
Citation Information
Patent Citations
Plug-and-play operation control method of grid-connected distributed energy storage system
CN110212557A
Fault detection method and device for energy storage charging pile, and computer readable storage medium
CN113468806A