Boiler Tube Panel Alignment Inserts for Faster Installation

Resolve Bottlenecks,
Find Innovative Solutions
Generate Solutions

Solution Overview

Problem

The existing methods for replacing boiler tube panels in power plants are labor-intensive and time-consuming due to the need for precise alignment of large, welded tubes with minimal clearance, often requiring multiple personnel and extensive manual effort to correct for warpage and welding distortions.

Innovation Solution

An alignment device with a cylindrical and tapered design is used to facilitate the installation of boiler tube panels, featuring a cylindrical portion that fits within the tube and a tapered portion with a semi-spherical end, allowing for easier alignment and insertion into pipes with reduced rigging points, and a method involving the use of inserts to correct for distortions during installation.

Engineering Contradictions & Design Principles

VSEngineering Contradiction Analysis

1Manufacturing precision

If traditional alignment methods using multiple steel wedges and pulling devices are used, then alignment precision can be achieved, but the installation time and labor requirements increase significantly

Engineering Contradiction:
Improvealignment precisionVSAvoidinstallation time
Core Design Contradiction:
Manufacturing precisionVSLoss of time

Solution Approach 1:

The alignment device is segmented into multiple functional portions: a cylindrical first portion for fitting within the tube, a tapered second portion for alignment, and optionally a cylindrical third portion. This segmentation allows each portion to perform its specific function efficiently, reducing overall installation time while maintaining precision.

Inventive Principle:
Principle #1Segmentation

Solution Approach 2:

The alignment device acts as an intermediary tool between the tube panel and the pipes. By inserting this mediator device into the tubes before final installation, it facilitates precise alignment without requiring multiple personnel to manually position and adjust each tube individually.

Inventive Principle:
Principle #24Intermediary (Mediator)

2Manufacturing precision

If multiple personnel are used to manually align each tube individually, then alignment accuracy is maintained, but the complexity and cost of the installation process increase

Engineering Contradiction:
Improvealignment accuracyVSAvoidinstallation process complexity
Core Design Contradiction:
Manufacturing precisionVSDevice complexity

Solution Approach 1:

Multiple alignment functions are merged into a single integrated device. Instead of using separate wedges and pulling devices operated by multiple personnel, the combined alignment device performs all necessary alignment operations through its integrated structure, reducing both personnel requirements and process complexity.

Inventive Principle:
Principle #5Merging (Combining)

Solution Approach 2:

The alignment device is designed to perform alignment operations automatically once inserted into the tube. The tapered portion self-aligns with the pipe opening through geometric constraints, eliminating the need for manual adjustment by multiple workers and simplifying the installation process.

Inventive Principle:
Principle #25Self-service

3Manufacturing precision

If traditional alignment methods are used, then proper tube positioning can be achieved, but the number of personnel and equipment required increases

Engineering Contradiction:
Improvetube positioningVSAvoidnumber of personnel
Core Design Contradiction:
Manufacturing precisionVSQuantity of substance

Solution Approach 1:

The alignment device serves multiple functions simultaneously: it acts as a positioning tool, an alignment guide, and an insertion aid all in one device. This multi-functionality eliminates the need for multiple specialized tools and personnel, as a single worker can operate this universal device to achieve proper tube positioning.

Inventive Principle:
Principle #6Universality (Multi-functionality)

4Strength

If welding is performed between tubes to form panels, then structural strength is achieved, but welding distortions cause misalignment that requires additional correction time

Engineering Contradiction:
Improvestructural strengthVSAvoidcorrection time
Core Design Contradiction:
StrengthVSLoss of time

Solution Approach 1:

The alignment device is installed on the tube panel before the panel is welded into final position. This preliminary alignment ensures that even if welding causes subsequent distortions, the initial positioning is precise and can serve as a reference for making smaller correction adjustments after welding, rather than starting from scratch.

Inventive Principle:
Principle #10Preliminary action

Applied Scientific Principles

This section explains which scientific principles are used to turn an abstract innovation direction into a practical engineering solution.

Function Achieved in This Case

This solution significantly reduces the time and labor required for installing boiler tube panels, enabling faster and more efficient alignment and installation with fewer personnel, as the tapered inserts help correct for distortions and misalignments, thereby streamlining the replacement process.

Implementation Method 1

A tapered second portion is provided opposite the cylindrical first portion, the tapered second end having a first end diameter that is substantially the same size as the outer diameter

Methodology Applied
Scientific EffectTapered geometry: Wedge

Data Source

PatentUS11638974B2Boiler tube panel installation device and method of aligning
Publication Date: 2023.05.02 CONSOLIDATED EDISON CO OF NEW YORK INC
  • US11638974B2 patent drawing
  • US11638974B2 patent drawing

AI summary

An alignment device for aligning a tube panel with a plurality of pipes system and a method of performing the alignment is provided. The alignment device is used in a panel comprising a plurality of tubes having an inner diameter and an outer diameter. The alignment device includes a cylindrical first portion sized to fit within the tube inner diameter. A tapered second portion is provided opposite the cylindrical first portion, the tapered second end having a first end diameter that is substantially the same size as the outer diameter.