Real-time communication and data interaction method for coordinated operation of energy storage power station and power grid dispatching

By optimizing communication rates through multi-dimensional load monitoring and dynamic adjustment algorithms, distinguishing between priority and secondary data, and performing binary conversion and encryption, the problem of insufficient transmission rate control is solved, and efficient collaborative operation between energy storage power stations and grid dispatch is achieved.

CN120434196BActive Publication Date: 2026-06-02NANJING ZHONGHUI ELECTRIC TECH CO LTD
3 Cites 0 Cited by

Patent Information

Application Number
CN202510611698.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-05-13
Publication Date
2026-06-02
Estimated Expiration
2045-05-13

AI Technical Summary

Technical Problem

In the collaborative operation of energy storage power stations and power grid dispatch, existing technologies rely on simple indicators for transmission rate control, which cannot adapt to the dynamic changes in network load, resulting in data redundancy and low transmission efficiency, and failing to meet the requirements of efficient collaborative operation.

Method used

By performing multi-dimensional load monitoring and dynamic adjustment of communication data, combined with genetic algorithm to optimize load threshold, adopting linear adjustment algorithm and improved rate control, distinguishing between priority and secondary communication data, and formulating refined interaction strategies, binary conversion, segmentation and encryption processing are performed to ensure data security and efficient transmission.

Benefits of technology

It ensures priority protection of critical data, improves response speed and accuracy, avoids network congestion, enhances data transmission efficiency and reliability, and meets the collaborative operation requirements of energy storage power stations and grid dispatch.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The application discloses a real-time communication and data interaction method for coordinated operation of energy storage power stations and power grid dispatching, and relates to the technical field of data processing.The application solves the technical problems that transmission rate control is only dependent on simple indexes and fixed adjustment mode, cannot adapt to dynamic changes of network load, and has data redundancy and low transmission efficiency in the transmission process.The application can more flexibly and accurately adjust the data transmission rate according to the real-time changes of the network load, improve the data transmission efficiency and network utilization, and guarantee the stability and smoothness of data transmission by constructing a multi-dimensional load monitoring system, comprehensively considering indexes such as CPU usage, memory usage, network bandwidth utilization and packet loss rate, and processing the data through binary conversion, segmentation, recombination and encryption, classifying and recombining the data according to the total sum of binary numbers, combining parity encryption, and enhancing data security; and adding meta information header to integrate data and optimize the transmission structure.
Need to check novelty before this filing date? Find Prior Art