A construction engineering risk analysis and control method based on energy transfer model
Through the energy transfer model, the evolution process of risk events in construction projects is analyzed, the initial energy and change process are identified, the risk level is evaluated, and control measures are taken, which solves the problem of imperfect risk management in construction projects and effectively prevents the occurrence of construction safety accidents.
Patent Information
- Application Number
- CN202011245470.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-11-10
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2040-11-10
AI Technical Summary
The imperfect risk management in construction projects has led to frequent construction safety accidents, which has restricted the development of my country's construction industry.
The risk analysis and control method based on the energy transfer model is adopted. By identifying the initial energy of the engineering body, analyzing the energy change process and constraint failure factors, the critical value of energy constraint failure is calculated, and the engineering safety risk level is evaluated and corresponding energy control measures are taken. .
It effectively blocks the occurrence of major and serious safety accidents, fundamentally understands and controls the evolution process of construction project risks, and reduces the probability of safety accidents.
Smart Images

Figure CN112488454B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of safety accident management and control in major engineering construction, and in particular to a construction engineering risk analysis and control method based on an energy transfer model. Background Art
[0002] With the rapid development of social economy, my country's construction industry has made remarkable achievements. However, due to the characteristics of large-scale construction, wide distribution area, long construction period, complex working environment and labor-intensiveness, the difficulty of risk management of construction projects has gradually increased. Imperfect project risk management has led to frequent construction safety accidents, which has seriously restricted the development of my country's construction industry. In order to ensure the steady development of my country's construction industry and reduce the probability of safety accidents, the research on project management risks plays an important role in the development of the construction industry and is a scientific basis for the safety and quality management of engineering construction.
[0003] How to fundamentally understand the process of risk evolution in construction projects is the key to taking relevant and effective measures to control the occurrence of risk accidents. Summary of the invention
[0004] In view of the above problems, the present invention proposes a construction project risk analysis and control method based on energy transfer model.
[0005] To achieve the purpose of the present invention, a construction project risk analysis and control method based on an energy transfer model is provided, comprising the following steps:
[0006] s1. Analyze and identify potential risk events based on potential influencing factors of engineering risks;
[0007] s2. Based on potential risk events, identify the initial energy of the engineering entity, and identify the type, attached carrier and initial energy value of the initial energy of the engineering entity according to the physical state of the engineering entity;
[0008] s3. Analyze the change state of the engineering body according to the direction of change of the potential risk event and obtain the change direction and change process of the initial energy of the engineering body, and then determine whether there is external energy input according to whether there is an external physical medium added;
[0009] s4. Quantitatively analyze the energy that has qualitatively changed, calculate the energy value of the engineering body after the transfer change, and then analyze the properties of the changed energy according to the state change of the engineering body;
[0010] s5. Analyze the factors of energy constraint failure according to the potential risk events, and calculate the critical value of the energy constraint failure;
[0011] s6. After comparing the energy value of the transferred engineering body with the critical value of the energy constraint failure, the current engineering safety risk level is obtained and corresponding energy control measures are taken.
[0012] Furthermore, in step s2,
[0013] The specific process of identifying the initial energy of the engineering entity includes: identifying the initial energy of the engineering entity according to the natural environment, human behavior, the natural state of the object and the motion change state of the object;
[0014] The types of initial energy of the engineering entity include: chemical energy, gravitational potential energy and kinetic energy;
[0015] The carriers to which the initial energy of the project body is attached include: air temperature, concrete, scaffolding, formwork and construction personnel.
[0016] Furthermore, in the step s3, the changing state of the engineering body includes: from static to dynamic and from dynamic to static; the external physical medium includes: scaffolding and formwork.
[0017] Furthermore, in step s4,
[0018] The properties of the energy of the changed part include: hazardous energy and safe energy.
[0019] Furthermore, in step s6,
[0020] The corresponding energy control measures include: energy elimination, restriction, guidance, shielding, isolation, transfer, distance control, weakening and strengthening.
[0021] Compared with the prior art, the present invention has the following beneficial technical effects:
[0022] Based on the energy transfer model, the present invention analyzes the evolution process of construction engineering risk events from the perspective of energy transfer changes, and proposes an energy constraint control method for risk factors and event hazards to prevent energy constraint failure, thereby effectively blocking the occurrence of major safety accidents. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 is a flow chart of a construction engineering risk analysis and control method based on an energy transfer model in one embodiment;
[0024] Figure 2 is a system diagram of the energy transfer, change, constraint and control method framework of an embodiment; DETAILED DESCRIPTION
[0025] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0026] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0027] based on Figure 1 , Analysis of risk analysis and control of construction projects based on energy transfer models, Figure 2 The entire framework system of energy transfer, change, constraint and control in the energy transfer model is analyzed horizontally and vertically. The process of the energy transfer model can be seen vertically. First, risk events are analyzed, then the initial energy is defined and identified, and then the factors causing constraint failure are determined. The process of energy transfer change is analyzed, and finally beneficial management and control measures are proposed. Horizontally, specific events in each of the above processes are listed separately.
[0028] The energy transfer change model will be specifically implemented and applied in combination with the collapse accident case of the construction platform of Fengcheng Power Plant in Jiangxi Province to understand and explain the evolution process of engineering risk events from the perspective of energy transfer change.
[0029] s1: Taking the investigation report of the construction platform collapse accident of Fengcheng Power Plant in Jiangxi as the main information source, collect and organize data to understand the construction situation and accident situation of the construction platform collapse accident of Fengcheng Power Plant in Jiangxi. According to the potential risk factors of the construction platform collapse accident of Fengcheng Power Plant in Jiangxi, analyze the possible risk events (D1~D7).
[0030] s2: According to possible risk events (D1-D7), analyze the actual energy situation during the risk event transfer process, such as energy attachment carrier, energy type, and gravitational potential energy formula E p =mgh, kinetic energy formula E k =1 / 2mv 2 , thermal energy formula Q=Δtmc, etc. to determine the initial energy value as shown in Table 1.
[0031] Table 1 Sources and types of hazardous energy in construction
[0032]
[0033] s3: Based on the basic energy characteristics and quantitative analysis of step s2, according to the direction in which the risk event may change, determine the direction of the initial energy change and the process of energy change, and determine whether there is external energy input. Risk events D5 to D7 all have input of gravitational potential energy, and the external input gravitational potential energy is converted into the kinetic energy of the body, causing the energy of the carrier to increase rapidly.
[0034] s4: Quantitatively analyze the qualitative energy, calculate the energy value of the project after the transfer change, and analyze the partial energy properties of the transfer change (hazardous energy, safety energy). Based on this model, it is determined that the gravitational potential energy is the hazardous energy that caused the accident.
[0035] s5: Analyze the factors of energy constraint failure according to engineering risk events and calculate the critical value E of energy constraint failure max The main factors that caused the failure of constraints in this accident include: sudden weather changes, compressed construction period, fatigue construction, etc.
[0036] s6: Compare whether the energy value E1 after the change exceeds the critical value E of energy constraint failure max , get the current engineering safety risk level, and take corresponding energy control measures, such as energy elimination, restriction, guidance, shielding, isolation, transfer, distance control, weakening and strengthening, etc. When external energy is input, methods such as elimination, guidance, and weakening can be used to limit the change of energy; when energy gathers in a certain direction, methods such as restriction, isolation, and evacuation can be used to control the transfer of energy; when positive energy deviates in the direction of risk events, timely measures should be taken to correct the direction of energy transfer changes.
[0037] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0038] It should be noted that the terms "first\second\third" involved in the embodiments of the present application are only used to distinguish similar objects, and do not represent a specific order for the objects. It is understandable that the specific order or sequence of "first\second\third" can be interchanged where permitted. It should be understood that the objects distinguished by "first\second\third" can be interchanged where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than those illustrated or described herein.
[0039] The terms "including" and "having" and any variations thereof in the embodiments of the present application are intended to cover non-exclusive inclusions. For example, a process, method, device, product, or equipment that includes a series of steps or modules is not limited to the listed steps or modules, but may optionally include steps or modules that are not listed, or may optionally include other steps or modules that are inherent to these processes, methods, products, or equipment.
[0040] The above-mentioned embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the invention patent. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent of the present application shall be subject to the attached claims.
Claims
1. A construction engineering risk analysis and control method based on energy transfer model, characterized in that: The following steps are involved: s1. Analyze and identify potential risk events based on potential influencing factors of engineering risks; s2. Based on potential risk events, identify the initial energy of the engineering entity, and identify the type, attached carrier and initial energy value of the initial energy of the engineering entity according to the physical state of the engineering entity; s3. Analyze the change state of the engineering body according to the direction of change of the potential risk event and obtain the change direction and change process of the initial energy of the engineering body, and then determine whether there is external energy input according to whether there is an external physical medium added; s4. Quantitatively analyze the energy that has qualitatively changed, calculate the energy value of the engineering body after the transfer change, and then analyze the properties of the changed energy according to the state change of the engineering body; s5. Analyze the factors of energy constraint failure according to the potential risk events, and calculate the critical value of the energy constraint failure; s6. After comparing the energy value of the transferred engineering body with the critical value of the energy constraint failure, the current engineering safety risk level is obtained and corresponding energy control measures are taken; In the step s2, the specific process of identifying the initial energy of the engineering body includes: identifying the initial energy of the engineering body according to the natural environment, human behavior, the natural state of the object and the motion change state of the object; The types of initial energy of the engineering entity include: chemical energy, gravitational potential energy and kinetic energy; The carriers to which the initial energy of the project is attached include: air temperature, concrete, scaffolding, formwork and construction personnel; In step s3, the changing state of the engineering body includes: changing from static to dynamic and changing from dynamic to static; the external physical medium includes: scaffolding and template; In the step s4, the properties of the changed part of energy include: hazardous energy and safe energy; In step s5, the main factors causing energy constraint failure are: sudden weather changes, compressed construction period, and fatigue construction; In step s6, the corresponding energy control measures include: energy elimination, restriction, guidance, shielding, isolation, transfer, distance control, weakening and strengthening.