A calender for producing ultra-wide glass
Through the symmetrical cooling structure and improved water separation chamber design, the problems of bending deformation and uneven cooling of the calender roll are solved, the temperature uniformity and yield of the glass plate are improved, and the pull-in volume and higher production are achieved. efficiency.
Patent Information
- Application Number
- CN202110781015.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-07-09
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2041-07-09
AI Technical Summary
In existing glass production equipment, the lengthening of the calender roll leads to severe bending deformation, making it impossible to produce lengthened glass plates that meet national standards, and uneven cooling leads to uneven glass thickness, affecting yield and production efficiency.
The symmetrical cooling structure is adopted, and water enters from both sides and then flows back. The water separation core design has no intermediate baffle. The water separation cavity structure is changed to two in four out, six out, ten out, and twelve out, increasing the number of water separation cavity. Using rolling bearings and universal shaft transmission, the motor reducer is independently driven, the water barrier on the side of the water distribution core is an integrated structure, the rotating water core can be detached and connected, and the outlet pipe regulating valve can be adjusted online.
The lateral uniformity of the temperature of the glass plate is achieved, the bending deformation is reduced, the width and yield of the glass original plate are improved, the edge cleaning loss rate is reduced, the pulling amount of a single branch line is increased, and the motor is stable, avoiding roller printing defects.
Smart Images

Figure HDA0005047637410000011 
Figure HDA0005047637410000021 
Figure HDA0005047637410000031
Abstract
Description
Technical Field
[0001] The invention relates to the field of glass production equipment, in particular to a calender for producing ultra-wide glass. Background Art
[0002] The calender used to produce photovoltaic glass has two calendering rollers, an upper calendering roller and a lower calendering roller. The high-temperature molten liquid glass (1120℃~1290℃) is directly squeezed and cooled by the upper calendering roller and the lower calendering roller into solid glass at a certain temperature.
[0003] At present, in order to prevent the calender roller from bending and deforming under high temperature, water is passed through the calender roller to cool it down, and the effective surface length of the calender roller is usually less than 3 meters. The width of the original glass produced by the calender is generally: 2 pieces of plate cut horizontally, the original plate width is between 2150mm and 2900mm, the effective plate width of cutting is between 1900mm and 2700mm, and the edge cleaning loss rate (edge loss rate) is between 4.1% and 6.2%. The pulling amount of photovoltaic glass produced can only be less than 190 tons / day.
[0004] The pulling amount refers to the weight of the original glass plate pulled per unit time in glass production, and is one of the important control parameters in glass production.
[0005] Pulling amount D = glass original plate width L * glass thickness T * pulling speed S * glass density ρ
[0006] It can be seen from the above formula that the original width of the glass directly determines the amount of pulling. Increasing the original width of the glass is the most direct way to increase the amount of pulling.
[0007] In order to increase the drawing amount, the effective length of the calendering roller needs to be increased. However, the cooling method in the prior art cannot better cool the lengthened calendering roller.
[0008] In the prior art, the cooling methods of the calender roller are one-in-four-out and two-in-eight-out structures. One-in-four-out means that water flows in from one side and flows out along the water diversion cavity in the calender roller. Figure 1 As shown, water enters from the water inlet of the rotary joint, flows along the inner wall of the calendering roller, and finally flows out from the outlet pipe, on which a valve can be set. Water flows from one side of the calendering roller to the other side. The temperature of the water is affected by heat transfer, and the temperature gradually increases from the low temperature on the inlet side to the outlet side. The temperature of the glass liquid at the overflow port is high in the middle and low on both sides. The temperature of the glass sheet squeezed out by the calendering roller is still high in the middle and low on both sides. Due to the surface tension of the glass, the thickness of the glass sheet is thin where the temperature is high in the middle, and thick on both sides. With this one-in-four-side structure, as the calendering roller is lengthened and the glass sheet becomes wider, the thickness difference will become larger.
[0009] In the existing patent CN105293872A, a calender for producing photovoltaic glass and a calender roller cooling device of the calender, the water-dividing core seals the inside of the calender roller into eight water-dividing chambers (four chambers on each side of the center of the calender roller), and the water output of each chamber can be adjusted individually by the water outlet valve, which also achieves the purpose of adjusting the roller bending by adjusting the water output online. However, the above structure has a most serious technical problem in actual production, such as Fig.10 The cross-sectional view of the calender roller and the overflow structure shows that the upper calender roller 2 is in a continuous rotation state. Water flows continuously in the four cavities E, F, H, and G inside the calender roller. The molten liquid glass 5 on the lip brick 15 is in direct contact with the calender roller. Since point A on the calender roller is the front end point of the front glass liquid, this point A forms a 90-degree angle with point B at the bottom of the calender roller. This part of the calender roller is in direct contact with the glass liquid or receives the maximum radiation heat conduction from the glass liquid. This area corresponds to exactly one quarter of the roller, and the corresponding inner cavity of the calender roller is exactly cavity G, where the temperature is instantly the highest and the thermal deformation is also the largest. In production, when there is a sudden speed adjustment, or the calender roller stops instantly, and the front glass liquid corresponds to a whole cavity, the calender roller is prone to a large bending deformation instantly. In particular, the longer the calender roller, the greater the bending deformation of the calender roller.
[0010] Secondly, the water-dividing core water baffle of the above-mentioned technical patent adopts a two-layer structure, both of which are made of heat-resistant stainless steel. The lower layer is a groove structure, and the upper layer is inserted into the groove of the lower layer, and a spring is added between the upper and lower layers. In actual production, since the cooling water of the calendering roller contains a high content of alkaline ions and certain impurities, the spring is corroded by water for a long time and becomes less elastic, which causes the gap between the upper stainless steel plate and the inner wall of the calendering roller to be inconsistent. There is a phenomenon of water flow between the internal cavities of the calendering roller, which causes uneven cooling of the roller body of the calendering roller.
[0011] Thirdly, in production practice, since the water supply of the calender is circulating cooling water, water scaling often occurs. The water spray holes of the water inlet pipe of the water-dividing core of the above-mentioned existing patented technology often encounter blockage problems, and no water is sprayed onto the inner wall of the calender roller locally, resulting in the calender roller being poorly cooled locally and the thickness of the squeezed glass failing to meet the GB national standard.
[0012] Due to the above technical problems, as the calendering roller is further lengthened, the calendering roller bends severely and cannot produce lengthened glass plates. At present, the calendering of photovoltaic glass can usually only cut 2 plates, and the thickness of the glass plate squeezed out by the upper and lower main rollers cannot meet the national standards or industry standards. Now a new type of structural calender is needed to produce lengthened glass plates, thereby increasing the pulling capacity of the calender, which can greatly reduce the production cost. Summary of the invention
[0013] The object of the present invention is to provide a calender for producing ultra-wide glass, which increases the length of the calender rollers to increase the width of the produced glass plate, thereby increasing the pulling amount to reduce the production cost.
[0014] Technical solution of the present invention
[0015] A calendering machine for producing ultra-wide glass comprises a base, an upper calendering roller and a lower calendering roller, wherein the upper calendering roller and the lower calendering roller comprise a rotating water jacket, a rotating water core and a calendering roller body, wherein the calendering roller body comprises a calendering roller cylinder in the middle and calendering roller shaft heads at both ends, wherein the calendering roller shaft heads at both ends of the calendering roller body are detachably connected to the rotating water core, and the rotating water core is placed in the rotating water jacket; a water dividing core is arranged inside the calendering roller body, wherein the water dividing core comprises a water dividing core water inlet pipe and a water dividing core side water baffle, wherein the water dividing core side water baffle is fixed to the side wall of the water dividing core water inlet pipe, and the water dividing core side water baffle connects the calendering roller body to the calendering roller body. The inner cavity is divided into a plurality of water-dividing cavities, and a plurality of water-spraying holes are drilled on the water-dividing core water inlet pipe; the number of the side water-baffles of the water-dividing core is two, three, five or six; the two ends of the side water-baffles of the water-dividing core are fixedly connected to the two ends of the water-dividing core water inlet pipe, the two ends of the water-dividing core water inlet pipe are connected to the rotating water core water inlet pipe of the rotating water core, the rotating water core water inlet pipe is connected to the water inlet groove of the rotating water jacket, and the water inlet groove of the rotating water jacket is connected to the water inlet pipe; the two ends of the water-dividing cavity are connected to the water outlet cavity of the rotating water core, the water outlet cavity is connected to the water outlet groove on the rotating water jacket, the water outlet groove is connected to the water outlet pipe, and a water outlet regulating valve is installed on the water outlet pipe.
[0016] Beneficial effects of the present invention:
[0017] 1. Compared with the one-in-four-out structure of the existing calender, the present invention changes the water flow structure of the calender roller with water entering from one end and exiting from the other end. Water enters from both sides and then flows back to both sides, which is a symmetrical cooling structure. The high temperature of the glass liquid in the middle of the overflow port and the low temperature on both sides form a temperature compensation, so that the lateral temperature of the glass plate squeezed out by the upper calender roller and the lower calender roller is more uniform.
[0018] 2. The water inlet pipe of the water dividing core of the present application has no middle baffle, which has the following advantages: when the water inlet pressure or water flow on both sides is uneven, the water pressure in the water pipe can be balanced after the two streams of water converge in the pipe, and then the water is sprayed out along the water inlet pipe spray hole of the water dividing core, which will not cause uneven surface temperature of the calendering roller on both sides along the center line.
[0019] 3. The existing calender is sealed into eight water-dividing chambers (four chambers on each side of the center of the calender roller). The above structure has a serious problem in actual production, such as Fig.10The cross-sectional view of the calender roller and the overflow structure shows that the calender roller is in a continuous rotation state. Water flows out of the four cavities E, F, H, and G inside the calender roller. The molten liquid glass 5 on the lip brick directly contacts the calender roller. Since point A on the calender roller is the front end point (the front glass liquid contacts), this point A forms a 90-degree angle with point B at the bottom of the calender roller. This part of the calender roller directly contacts the glass liquid or receives the maximum radiation heat conduction from the glass liquid. This area corresponds to exactly one quarter of the roller, and the corresponding inner cavity of the calender roller is exactly cavity G, where the temperature is instantly the highest and the thermal deformation is also the largest. In production, when there is a sudden speed adjustment or the roller stops instantly, which corresponds to a whole cavity, the roller is prone to a large bending deformation instantly. In particular, the longer the roller, the greater the bending deformation of the roller.
[0020] Compared with the existing calendering machine's two-inlet and eight-outlet structure, the two-inlet and four-outlet, six-outlet, ten-outlet, and twelve-outlet structures of the present invention are more scientific and reasonable, avoiding the phenomenon that the water outlet cavity occupies a quarter of the calender roller in the two-inlet and eight-outlet structure in the prior art. Fig. 9 In the two-inlet and six-outlet structure of the present application, the glass liquid occupies a part of the G water outlet cavity. Although the temperature from point A to point B is high and the deformation is large, there is still water flowing in the cavity G corresponding to the area from point A to point C, which changes the temperature change in the entire cavity. Therefore, the roller surface in this area will not produce excessive temperature changes. If it is a two-inlet and four-outlet, ten-outlet, or twelve-outlet structure, the glass liquid is not facing an entire cavity, so the calender roller surface will not produce excessive temperature changes.
[0021] 4. The water diversion chamber in the calendering roller of the present application is connected to the water diversion chamber at the shaft head of the calendering roller, which solves the water blocking problem caused by using a water outlet pipe at the shaft head of the calendering roller in the prior art and makes the water flow smoother.
[0022] 5. Due to the increase in the length of the calendering roller, the width of the original glass plate produced by the calendering machine of the present application is more than 1.15 times the original width, the edge cleaning loss rate (edge loss rate) can be further reduced by more than 0.5%, and the yield rate is directly increased by more than 0.5%, thereby reducing the production cost. The pulling capacity of a single branch line is more than 251 tons / day.
[0023] 6. The cooling structures of two-in-four-out, two-in-six-out, two-in-ten-out, and two-in-twelve-out of the present application are more scientific and reasonable. The water will not gather at the calender roller shaft head to form the "water holding" phenomenon, and the water can flow out along each water diversion cavity separately. At the same time, when the calender roller bends at high temperature, each regulating valve on the rotating water jacket of the calender roller can be adjusted separately, and the bending deformation of the calender roller can be adjusted by adjusting the water temperature of a certain area, so as to control the thickness of the glass liquid squeezed between the upper roller and the lower roller within the standard range.
[0024] 7. The water baffle plate of the water-dividing core of the present application is an integrated structure. A plurality of water baffle plate fixing ribs are installed at regular intervals in the longitudinal direction of the side water baffle plate. The water baffle plate of the water-dividing core and the water baffle plate fixing ribs are welded together and connected to the inner wall of the calendering roller. The fixing ribs are spot welded or bolted to the outer inner wall of the calendering roller. The existing technology overcomes the problem that the spring elasticity is poor after the spring is corroded, resulting in a large gap between the local stainless steel plate of the upper layer and the inner wall of the calendering roller, resulting in poor sealing between the water-dividing chambers and water flow between the chambers.
[0025] The water inlet pipe of the water-dividing core of the present application can be pulled out from the calendering roller, which is convenient for replacing the water inlet pipe of the water-dividing core. If the water spray hole of the water-dividing core water inlet pipe is in the wrong position, it can be pulled out and replaced or re-welded and drilled to rearrange the size and position of the water hole. At the same time, when the water spray hole of the water-dividing core water inlet pipe is blocked, the water inlet pipe of the water-dividing core can be pulled out from the calendering roller to clean and unclog the water spray hole.
[0026] 8. The universal shaft transmission method is adopted to overcome the phenomenon of tensile deformation that is easy to occur in the previous chain transmission or joint transmission, thereby avoiding the defects of the glass plate surface caused by poor tooth engagement after tensile deformation.
[0027] 9. The upper calendering roller and the lower calendering roller of the present application are driven separately by a frequency converter and a motor reducer with a power greater than or equal to 5.5KW, which has greater power and avoids the phenomenon of unexpected motor stalling caused by the increase in motor current after the increase in pulling amount.
[0028] 10. The shaft heads on both sides of the upper and lower calendering rollers adopt rolling bearing structures. This replaces the widely used bearing structure, which is conducive to reducing the roller mark defects on the glass plate surface. The reason why the bearing structure can cause roller mark defects on the glass is that there is a gap between the bearing and the shaft head of the calendering roller. In normal production, the calendering roller rolls, while the bearing is fixed. Because of the gap, the calendering roller will jump during the rolling process. The glass pressed by the calendering roller will have horizontal stripes, which is called roller mark. However, rolling bearings can completely solve the jumping phenomenon between the shaft head of the calendering roller and the rolling bearing. Thus, the roller mark defect problem is fundamentally solved.
[0029] 11. The rotating water core is provided with a hexagonal bolt at the outer end of the long groove on the side of the calender not connected to the motor reducer (non-transmission side) for blocking the long groove. When the water spray hole on the water inlet pipe wall of the water dividing core is blocked, the bolt can be unscrewed and a steel pipe can be inserted into the rotating water core water inlet groove and the water dividing core water inlet pipe along the bolt hole for online cleaning to clear the blocked water spray hole. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 A front view schematic diagram of a calender with two-inlet and four-outlet structures according to the present invention.
[0031] Figure 2a It is an overall schematic diagram of the calendering roller with two-inlet and four-outlet structure of the present invention.
[0032] Figure 2b This is a cross-sectional view of the calendering roller body with a two-inlet and four-outlet structure of the present invention.
[0033] Figure 2c It is a schematic diagram of the water-dividing core structure of the calendering roller with two-inlet and four-outlet structures of the present invention.
[0034] Figure 2d This is a cross-sectional view of the water-dividing core of the calendering roller with a two-inlet and four-outlet structure of the present invention.
[0035] Figure 2e This is a schematic diagram of the structure of the rotating water jacket of the calender roller with two-inlet and four-outlet structures of the present invention.
[0036] Figure 2f It is a schematic diagram of the cross-sectional structure of the rotating water jacket and the rotating water core of the calender roller with two-inlet and four-outlet structures of the present invention.
[0037] Figure 2g This is a schematic diagram of the rotating water core structure of the calender roller with two-inlet and four-outlet structures of the present invention.
[0038] Figure 3 A front view schematic diagram of a calender with two-inlet and six-outlet structures according to the present invention.
[0039] Figure 4a It is an overall schematic diagram of the calendering roller with two-inlet and six-outlet structures of the present invention.
[0040] Figure 4b This is a cross-sectional view of the calendering roller body of the calendering roller with two-inlet and six-outlet structure of the present invention.
[0041] Figure 4c It is a schematic diagram of the water-dividing core structure of the calendering roller with two-inlet and six-outlet structures of the present invention.
[0042] Figure 4d This is a cross-sectional view of the water-dividing core of the calendering roller with two-inlet and six-outlet structures according to the present invention.
[0043] Figure 4e This is a schematic diagram of the structure of the rotating water jacket of the calender roller with two-inlet and six-outlet structures of the present invention.
[0044] Figure 4f It is a schematic diagram of the cross-sectional structure of the rotating water jacket and the rotating water core of the calender roller with two-inlet and six-outlet structures of the present invention.
[0045] Figure 4g This is a schematic diagram of the rotating water core structure of the calender roller with two-inlet and six-outlet structures of the present invention.
[0046] Figure 5 A front view schematic diagram of a calender with a two-inlet and ten-outlet structure according to the present invention.
[0047] Figure 6aIt is an overall schematic diagram of the calendering roller with a two-in-ten-out structure of the present invention.
[0048] Figure 6b This is a cross-sectional view of the calendering roller body of the two-in-ten-out structure calendering roller of the present invention.
[0049] Figure 6c This is a schematic diagram of the water-dividing core structure of the calender roller with a two-in-ten-out structure of the present invention.
[0050] Figure 6d This is a cross-sectional view of the water-dividing core of the calendering roller with a two-in-ten-out structure of the present invention.
[0051] Figure 6e This is a schematic diagram of the structure of the rotating water jacket of the calender roller with a two-inlet and ten-outlet structure of the present invention.
[0052] Figure 6f It is a schematic diagram of the cross-sectional structure of the rotating water jacket and the rotating water core of the calender roller with a two-inlet and ten-outlet structure of the present invention.
[0053] Figure 6g This is a schematic diagram of the rotating water core structure of the calender roller with two-inlet and ten-outlet structures of the present invention.
[0054] Figure 7 A front view schematic diagram of a calender with two-inlet and twelve-outlet structures according to the present invention.
[0055] Figure 8a It is an overall schematic diagram of the calendering roller with two-inlet and twelve-outlet structure of the present invention.
[0056] Figure 8b This is a cross-sectional view of the calendering roller body of the calendering roller with two-inlet and twelve-outlet structure of the present invention.
[0057] Figure 8c It is a schematic diagram of the water-dividing core structure with two inlets and twelve outlets according to the present invention.
[0058] Figure 8d This is a cross-sectional view of the water-dividing core of the calendering roller with a two-inlet and twelve-outlet structure of the present invention.
[0059] Figure 8e This is a schematic diagram of the structure of the rotating water jacket of the calender roller with two-inlet and twelve-outlet structures of the present invention.
[0060] Figure 8f It is a schematic diagram of the cross-sectional structure of the rotating water jacket and the rotating water core of the calender roller with two-inlet and twelve-outlet structures of the present invention.
[0061] Figure 8g This is a schematic diagram of the rotating water core structure of the calender roller with two-inlet and twelve-outlet structures of the present invention.
[0062] Fig. 9 This is a partial cross-sectional view of the calendering roller and overflow port of the two-inlet and six-outlet structure of the present application.
[0063] Fig.10It is a cross-sectional view of the calender roller and overflow port structure of an existing calender.
[0064] Fig.11 This is a schematic diagram of the side structure of the calender in this application.
[0065] Fig.12 It is a schematic diagram of the rotating water core structure (the long groove is a through groove). DETAILED DESCRIPTION
[0066] In order to increase the effective length of the calendering roller and thus increase the drawing amount, the inventor adjusted the cooling method of the calendering roller. The specific scheme is as follows:
[0067] A calendering machine for producing ultra-wide glass comprises a base 1, a lower calendering roller 3 and an auxiliary roller support seat 14 are installed on the base 1, an upper calendering roller column 15 is fixed on the upper part of the support seat by bolts, a rocker arm 16 is installed on the upper calendering roller column 15 by a fixing pin, and an upper calendering roller 2 is installed at the front end of the rocker arm 16. The upper calendering roller 2 and the lower calendering roller 3 are driven to rotate by separate motors. The molten glass flows between the upper calendering roller 2 and the lower calendering roller 3, and after passing through the auxiliary roller 10, forms glass plates of different thicknesses.
[0068] The upper calendering roller 2 and the lower calendering roller 3 include two rotating water jackets 4, two rotating water cores 5 and a calendering roller body 6 in the middle. The calendering roller body 6 includes a calendering roller cylinder 61 in the middle and calendering roller shaft heads 62 at both ends. The calendering roller shaft heads 62 and the calendering roller cylinder 61 are bolted or manufactured into an integrated structure. The rotating water core 5 is placed in the rotating water jacket 4, and the rotating water core 5 is bolted to the calendering roller shaft head 62. A water dividing core 7 is arranged inside the calendering roller body 6. The water dividing core 7 includes a water dividing core water inlet pipe 71 and a water dividing core side water baffle 72. The outer end of the water dividing core side water baffle is fixedly connected to the inner wall of the calendering roller, and the inner end extends to the water dividing core water inlet pipe and abuts against the water dividing core water inlet pipe wall. The water dividing core side water baffle 72 divides the inner cavity of the calendering roller body into multiple water dividing cavities. The water dividing core water inlet pipe 71 is drilled with a plurality of water spray holes 74. The water-dividing core side water baffles 72 are two, three, five or six, dividing the interior of the calendering roller into two, three, five or six chambers. The two ends of the water-dividing core water inlet pipe 71 are connected to the rotating water core water inlet pipe 52 of the rotating water core, the rotating water core water inlet pipe 52 is connected to the water inlet groove 43 of the rotating water jacket, and the water inlet groove 43 of the rotating water jacket is connected to the water inlet pipe 8. The two ends of the water-dividing chamber 73 are connected to the water outlet chamber 54 of the rotating water core, the water outlet chamber 54 is connected to the water outlet groove 42 on the rotating water jacket, the water outlet groove 42 is connected to the water outlet pipe 9, and the water outlet regulating valve 91 is installed on the water outlet pipe. The length of the calendering roller is greater than or equal to 4200mm.
[0069] The rotating water jacket 4 comprises a cylindrical rotating water jacket body 41, the inner wall of which is provided with two, three, five or six annular water outlet grooves 42 and an annular water inlet groove 43, and rolling bearings 44 are installed at both ends of the inner wall of the rotating water jacket body 41; the water inlet groove 43 is connected to the water inlet pipe 8, the water outlet groove 42 is connected to the water outlet pipe 9, a water outlet regulating valve 91 is installed on the water outlet pipe 9, and an oil filling hole is opened on the side wall of the rotating water jacket 4 body corresponding to the position of the rolling bearing 44, and an oil filling nozzle 45 is installed on the oil filling hole.
[0070] The rotating water core 5 includes a rotating water core body 51, in which a rotating water core water inlet pipe 52, a rotating water core water inlet channel 53, a spring 56, a water outlet chamber 54, a clamping edge 55 and a spring ring 57 are arranged. The diameters at both ends of the rotating water core water inlet pipe 52 are different, and the large diameter part and the small diameter part are connected by an oblique shoulder structure. Both ends of the water-dividing core water inlet pipe 71 are inserted into the large diameter end of the rotating water core water inlet pipe, and the front end is against the oblique shoulder. A long groove is opened at the longitudinal center line of the rotating water core body, and the small diameter end of the rotating water core water inlet pipe is inserted into the long groove. A spring 56 is installed between the small diameter end of the rotating water core water inlet pipe 52 and the rotating water core body, and the small diameter end of the rotating water core water inlet pipe 52 is connected to the rotating water core water inlet channel opened on the side wall of the rotating water core.
[0071] 53 is connected, the rotating water core water inlet 53 is connected with the water inlet groove 43 of the rotating water jacket, two, three, five or six longitudinal water outlet chambers 54 are opened in the rotating water core body outside the rotating water core water inlet pipe 52, and the water outlet chambers 54 are connected with the water outlet groove 42 in the rotating water jacket, and the rotating water core body is provided with a clamping edge 55 at one end of the outer circumference, and a spring ring 57 at the other end, and the clamping edge 55 is detachably connected with the calender roller shaft head. A bolt hole 58 is opened on the outer end surface of the rotating water core, and the rotating water core is connected to the universal shaft 201 by bolts in the bolt hole 58.
[0072] The upper and lower calendering rollers are not close to the rotating water core at one end of the motor reducer, such as Fig.12 As shown in FIG. 1 , the long groove in the rotating water core is a through groove, and the outer end of the long groove has an internal thread and is installed with a hexagonal bolt 59. During normal operation, the hexagonal bolt blocks the long groove to prevent water from flowing out. When the water outlet hole on the water diversion core in the calendering roller is blocked, the hexagonal bolt 59 can be unscrewed, and a steel pipe can be inserted into the rotating water core and the calendering roller water diversion core to flush out the foreign matter blocking the water diversion hole with water, thereby achieving the purpose of cleaning.
[0073] A plurality of fixed ribs 75 are installed equidistantly in the longitudinal direction of the water inlet pipe of the water dividing core. The fixed ribs 75 are composed of two arc-shaped water inlet pipe ribs 751 in the middle and two long strip side water baffle ribs 752 on both sides. The side water baffle ribs are fixedly connected to the inner walls of both ends of the calendering roller with bolts or directly welded. The two ends of the upper and lower arc-shaped water inlet pipe ribs are connected to the long strip side water baffles and ribs to form a closed structure, which surrounds the water inlet pipe and the side water baffles of the water dividing core.
[0074] Rolling bearings are installed at the calendering roller shaft heads on both sides of the upper calendering roller 2 and the lower calendering roller 3. The rolling bearings are respectively fixed in the bearing shell covers of the upper calendering roller and the lower calendering roller. The bearing shell covers 17 are fixed on the base.
[0075] The upper calendering roller 2 and the lower calendering roller 3 are driven separately by a motor reducer 20. The output shaft of the motor reducer 20 is connected to the upper calendering roller or the lower calendering roller through a universal shaft 201. The other end of the universal shaft 201 is connected to the bolt hole at the end of the rotating water core through a bolt.
[0076] In order to prevent water leakage and water seepage at the contact position, a first sealing ring 131 is provided between the long groove in the rotating water core and the water inlet pipe of the rotating water core. A second sealing ring 132 is provided between the water inlet pipe of the rotating water core and the water inlet pipe of the water distribution core. A third sealing ring 133 is provided between the outer periphery of the rotating water core and the calender roller shaft head. A fourth sealing ring 134 is provided on both sides of the water inlet and outlet grooves of the rotating water jacket.
[0077] Example 1: Figure 1-2g As shown, the water-dividing core has a two-inlet and four-outlet structure.
[0078] The upper calendering roller 2 and the lower calendering roller 3 include two rotating water jackets 4, two rotating water cores 5 and a calendering roller body 6. The rotating water cores are connected to the two ends of the calendering roller body, and the rotating water cores are placed in the rotating water jackets. The rotating water cores and the calendering roller body rotate, and the rotating water jackets are relatively stationary. The calendering roller body 6 includes a calendering roller cylinder 64 in the middle and calendering roller shaft heads 62 at both ends, and the calendering roller shaft heads and the calendering roller cylinders are bolted. The calendering roller cylinder lengths of the upper calendering roller and the lower calendering roller are greater than or equal to 4200 mm.
[0079] The calendering roller body 6 is provided with a water-dividing core 7 inside, and the water-dividing core 7 includes a water-dividing core water inlet pipe 71, a water-dividing core side water baffle plate 72, and a fixed rib plate 75. There are two water-dividing core side water baffle plates, and the water-dividing core side water baffle plates divide the inner cavity of the calendering roller body into two water-dividing cavities. The water-dividing core water inlet pipe is drilled with water spray holes of equal or unequal diameters at regular intervals, and the water spray holes are arranged in two rows along the longitudinal length of the water-dividing core to spray water into the water-dividing cavity.
[0080] The rotating water jacket 4 comprises a cylindrical rotating water jacket body 41, on the inner wall of which are two annular water outlet grooves 42 and an annular water inlet groove 43. Two rolling bearings 44 are mounted on the inner wall of the rotating water jacket body. The water inlet groove is connected to the water inlet pipe 8, the water outlet groove is connected to the water outlet pipe 9, and a water outlet regulating valve 91 is mounted on the water outlet pipe. An oil filling hole is opened on the side wall of the rotating water jacket body corresponding to the position of the rolling bearing, and an oil filling nozzle 45 is mounted on the oil filling hole.
[0081] The rotating water core 5 comprises a rotating water core body 51, in which a rotating water core water inlet pipe 52, a rotating water core water inlet channel 53, a spring 56, a water outlet cavity 54, a clamping edge 55 and a spring ring 57 are arranged. A clamping edge 55 is arranged on the outer periphery of the rotating water core body. The rotating water core water inlet pipe is arranged in a long groove on the longitudinal center line of the rotating water core body, and two longitudinal water outlet cavities are opened on the outer periphery of the rotating water core water inlet pipe. A spring is arranged between the small diameter end of the rotating water core water inlet pipe and the rotating water core body, the small diameter end of the rotating water core water inlet pipe is connected to the rotating water core water inlet channel, the rotating water core water inlet channel is connected to the water inlet pipe, the water outlet cavity is connected to the water outlet groove in the rotating water jacket, and the clamping edge is bolted to the calender roller shaft head. There is no rotating water core water inlet pipe inside the rotating water core, and a spring ring is installed on one end, which is clamped on the outside of the rotating water jacket to prevent the rotating water jacket from separating from the rotating water core during rotation. The two ends of the water inlet pipe of the water dividing core pass through the water inlet pipe of the rotating water core to communicate with the water inlet groove of the rotating water jacket, and the water inlet groove is connected to the water inlet pipe. The two ends of the water dividing cavity are connected to the water outlet groove on the rotating water jacket through the water outlet cavity in the rotating water core, and the water outlet groove is connected to the water outlet pipe.
[0082] Rolling bearings are installed at the calendering roller shaft heads on both sides of the upper calendering roller or the lower calendering roller, and the rolling bearings are fixed in the bearing shell covers on both sides of the upper main roller and the lower main roller. The upper calendering roller and the lower calendering roller of the calendering machine of the present application are driven separately by a frequency converter greater than or equal to 5.5KW and a motor reducer. The calendering roller is connected to the motor shaft end through a universal shaft. One end of the universal shaft is connected to the motor shaft end, and the other end is connected to the rotating water core.
[0083] Specifically, the calender roller cooling method adopts a two-in-four-out structure. The upper calender roller inverter controls the upper calender roller motor reducer, which is bolted to the rotating water core bolt hole on one side of the upper calender roller through a universal shaft. The lower calender roller inverter controls the lower calender roller motor reducer, which is bolted to the rotating water core bolt hole on one side of the lower calender roller through a universal shaft. The upper calender roller and the lower calender roller are in a continuous rotation state in the rolling bearings on both sides. During normal production, a certain gap size is maintained between the upper calender roller and the lower calender roller, so that the glass in a high temperature state is quickly cooled through the upper and lower calender rollers and extruded into a glass plate of a certain thickness. The effective surface length of the roller body of the calender roller is usually greater than or equal to 4200MM. The water flows from the water collecting pipe 11 at the lower part of the calender, through each water distribution pipe, and then through the stainless steel metal hose 12, through the water inlet pipe 8 on the rotating water jacket on both sides of the upper calender roller, and then enters the rotating water jacket 4, and then flows through the rotating water core 5 into the rotating water core water inlet pipe 52, and then enters the calender roller water distribution core 7, and then flows out through the water spray hole 74 on the water distribution core 7 in the calender roller. The water flows back to the water outlet chamber 54 of the rotating water core along the water distribution chamber in the calender roller, and then flows out along the water outlet trough of the rotating water jacket, and then flows out through the water outlet pipe 9. The water outlet valve 91 can be set on the water outlet pipe 9 to adjust the water output. The water that finally flows out can be collected by the return water tank and recycled.
[0084] During normal production, the rotating water jacket is usually fixed, and the water outlet groove on the rotating water jacket is connected to the water outlet cavity of the rotating water core through a rotating combined sealing ring. The rotating water core is provided with a retaining ring, which is stuck on the outside of the rotating water jacket shell to prevent the rotating water jacket and the rotating water core from separating during rotation. A rolling bearing is arranged in the rotating water jacket, and the rotating water core rotates in the rolling bearing, and the rotating water jacket is fixed. In order to prevent the rolling bearing from rusting due to contact with water, an oil filling hole is arranged in the rotating water jacket, and an oil filling nozzle is installed on the outside of the oil filling hole, so that the bearing in the rotating water jacket can be well lubricated by regularly injecting lubricating oil or grease. The two ends of the water inlet pipe of the water-dividing core in the calendering roller are directly inserted into the water inlet pipes of the rotating water core on both sides. In order to prevent water leakage due to poor sealing effect, an O-ring is installed on the inside of the water inlet pipe of the rotating water core. At the same time, in order to prevent the water inlet pipe of the calender roller water core from contacting poorly with the water inlet pipe of the rotating water core, a compression spring is installed inside the water inlet pipe of the rotating water core, so that there is a certain degree of buffering when the rotating water core outlet pipe and the calender roller water core are installed. In actual use, when the upper calender roller or the lower calender roller is bent, the glass liquid squeezed out between the two main rollers will have uneven thickness. The uneven thickness detection method can be measured by a digital micrometer; it can also be monitored by the curve formed by the infrared instrument installed behind the main calender roller. When the curve formed by the infrared instrument fluctuates greatly (≥10°), it means that the roller is seriously bent. In this case, the water outlet valve on the rotating water jacket can be adjusted to reduce the water outlet of the corresponding water outlet cavity. When the water outlet valve is closed, the water temperature in the water outlet cavity rises. Due to the principle of thermal expansion and contraction, the originally bent calender roller gradually straightens, making the thickness of the glass liquid squeezed out by the upper calender roller and the lower calender roller uniform. The curve formed by the infrared instrument is used for timely monitoring and adjustment. When the water outlet valves on both sides of a cavity are closed at the same time, the curve fluctuation becomes smaller, which means that the valve corresponding to this cavity is adjusted correctly. On the contrary, when the valves corresponding to both sides of this cavity are adjusted, the curve fluctuation does not change or becomes larger, which means that the adjusted valve is incorrect and the valve corresponding to another cavity needs to be adjusted until the curve becomes smaller and smaller.
[0085] The present application has a two-inlet and four-outlet structure, with two water outlet cavities at each end of the calendering roller. Therefore, the area where the front glass liquid is in direct contact with the calendering roller only occupies half of the water outlet cavity below the upper calendering roller, and water also flows in the other half of the water outlet cavity. This can prevent the calendering roller from bending due to the glass liquid when the calendering roller is suddenly adjusted in speed or stopped, thereby preventing the pressed glass from having uneven thickness.
[0086] Example 2: Figure 3-4g As shown, the water-dividing core has a two-inlet and six-outlet structure.
[0087] The structure of the calender is the same as the two-inlet and four-outlet structure. There are three water outlet grooves on the rotating water jacket, and three water outlet chambers on the rotating water core. There are three side water baffles on the water inlet pipe of the water distribution core, and three water distribution chambers in the water distribution core. The corresponding water spray holes are in three rows.
[0088] The calendering roller lengths of the upper calendering roller and the lower calendering roller are greater than or equal to 4200 mm.
[0089] Example 3: Figure 5-6g As shown, the water-dividing core has a two-inlet and ten-outlet structure.
[0090] The structure of the calender is the same as the two-inlet and four-outlet structure. There are five water outlet grooves on the rotating water jacket, and five water outlet chambers on the rotating water core. There are five side water baffles on the water inlet pipe of the water distribution core, and five water distribution chambers in the water distribution core. There are five rows of corresponding water spray holes.
[0091] The calendering roller lengths of the upper calendering roller and the lower calendering roller are greater than or equal to 4200 mm.
[0092] Example 4: Figure 7-8g As shown, the water-dividing core has a two-inlet and twelve-outlet structure.
[0093] The structure of the calender is the same as the two-inlet and four-outlet structure. There are six water outlet grooves on the rotating water jacket, and six water outlet chambers on the rotating water core. There are six side water baffles on the water inlet pipe of the water distribution core, and six water distribution chambers in the water distribution core. The corresponding water spray holes are six rows.
[0094] The above descriptions are only five preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A calender for producing ultra-wide glass, comprising a base, an upper calendering roller and a lower calendering roller, characterized in that: The upper calendering roller and the lower calendering roller include a rotating water jacket, a rotating water core and a calendering roller body. The calendering roller body includes a calendering roller cylinder in the middle and calendering roller shaft heads at both ends. The calendering roller shaft heads at both ends of the calendering roller body are detachably connected to the rotating water core, and the rotating water core is placed in the rotating water jacket; a water dividing core is arranged inside the calendering roller body, and the water dividing core includes a water dividing core water inlet pipe and a water dividing core side water baffle plate. The inner cavity of the calendering roller is fixed with a water dividing core side water baffle plate, and the inner end of the water dividing core side water baffle plate extends toward the water dividing core water inlet pipe. The water dividing core side water baffle plate divides the calendering roller into a plurality of calendering rollers. The inner cavity of the rolling roller is divided into multiple water-dividing cavities, and a plurality of water spray holes are drilled on the water-dividing core water inlet pipe; the number of side water baffles of the water-dividing core is two, three, five or six; the two ends of the water-dividing core water inlet pipe are connected with the rotating water core water inlet pipe of the rotating water core, the rotating water core water inlet pipe is connected with the water inlet groove of the rotating water jacket, and the water inlet groove of the rotating water jacket is connected with the water inlet pipe; the two ends of the water-dividing cavity are connected with the water outlet cavity of the rotating water core, the water outlet cavity is connected with the water outlet groove on the rotating water jacket, the water outlet groove is connected with the water outlet pipe, and a water outlet regulating valve is installed on the water outlet pipe.
2. A calender for producing ultra-wide glass according to claim 1, characterized in that: The rotating water jacket comprises a cylindrical rotating water jacket body, the inner wall of which is provided with two, three, five or six annular water outlet grooves and one annular water inlet groove, and a rolling bearing is installed on the inner wall of the rotating water jacket body; the water inlet groove is connected to a water inlet pipe, and the water outlet groove is connected to a water outlet pipe, and an oil filling hole is opened on the outer wall of the rotating water jacket body at a position corresponding to the rolling bearing, and an oil filling nozzle is installed on the oil filling hole.
3. The calender for producing ultra-wide glass according to claim 1, characterized in that: The rotating water core comprises a rotating water core body, in which a rotating water core water inlet pipe, a rotating water core water inlet channel, a spring, a water outlet cavity, a clamping edge and a clamping spring ring are arranged; the diameters of the two ends of the rotating water core water inlet pipe are different, and the large diameter part and the small diameter part are connected by an oblique shoulder structure, and the two ends of the water inlet pipe of the water-dividing core are inserted into the large diameter end of the rotating water core water inlet pipe; a long groove is opened at the longitudinal center line of the rotating water core body, and the small diameter end of the rotating water core water inlet pipe is inserted into the long groove, and the rotating water core water inlet pipe is small. A spring is installed between the diameter end and the rotating water core body, the small diameter end of the rotating water core water inlet pipe is connected to the rotating water core water inlet channel opened on the side wall of the rotating water core, the rotating water core water inlet channel is connected to the water inlet groove of the rotating water jacket, and two, three, five or six longitudinal water outlet cavities are opened in the rotating water core body outside the rotating water inlet pipe, the water outlet cavities are connected to the water outlet groove in the rotating water jacket, a clamping edge is provided at one end of the outer circumference of the rotating water core body, and a retaining spring ring is provided at the other end, and the clamping edge is detachably connected to the calendering roller shaft head.
4. The calender for producing ultra-wide glass according to claim 1, characterized in that: The length of the calendering roller is greater than or equal to 4200 mm.
5. The calender for producing ultra-wide glass according to claim 1, characterized in that: A plurality of fixed ribs are installed in the longitudinal direction of the water inlet pipe of the water dividing core. The fixed ribs are composed of the middle upper and lower arc-shaped water inlet pipe ribs and the outer long strip side water retaining plate ribs. The fixed ribs are fixedly connected to the side water retaining plate of the water dividing core and the inner wall of the calendering roller.
6. The calender for producing ultra-wide glass according to claim 1, characterized in that: The long grooves opened in the rotating water core on the side of the upper calendering roller and the lower calendering roller away from the motor reducer are through grooves, and the outer ends of the through grooves are blocked with hexagonal bolts.
7. The calender for producing ultra-wide glass according to claim 1, characterized in that: Rolling bearings are installed at the calendering roller shaft heads on both sides of the upper calendering roller and the lower calendering roller, and the rolling bearings are fixed on the bearing shell covers on the calender base.
8. The calender for producing ultra-wide glass according to claim 1, characterized in that: The upper calendering roller and the lower calendering roller are driven separately by motor reducers, the output shaft of the motor reducer is connected to one end of the universal shaft, and the other end of the universal shaft is bolted to the bolt hole at the end of the rotating water core.