BIM model data analysis method based on cloud

Through the cloud-based BIM model data analysis method, the Revit interface is used to perform logical processing and data conversion, the problem of large amount of BIM model data is solved, the online management and display of BIM model is realized, the user experience and application efficiency are improved, and the Popularization of BIM technology.

CN114510906BActive Publication Date: 2025-01-14NANJING RONGGUANG SOFTWARE TECH CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202210139832.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-02-16
Publication Date
2025-01-14
Estimated Expiration
2042-02-16

AI Technical Summary

Technical Problem

The existing BIM model has large data volume, complex management and inconvenient viewing problems, especially in the limited belt conditions, which are difficult to effectively transmit and utilize precise engineering data.

Method used

The cloud-based BIM model data analysis method is adopted to obtain model files through the secondary development application program interface provided by Revit, perform logical processing, calculation of the room where the device is located, and convert the data into gltf format to realize data refinement and online display.

Benefits of technology

It simplifies the management and use of BIM models, reduces the amount of data, improves user experience and application efficiency, and enables the popularization and promotion of BIM technology in the construction engineering and computer information technology industries to be quickly realized.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114510906B_ABST
    Figure CN114510906B_ABST
Patent Text Reader

Abstract

The present invention discloses a cloud-based BIM model data analysis method, which is simple to operate, has a small amount of data, and is easy to apply. The BIM model data analysis method of the present invention comprises the following steps: (10) model file acquisition: acquiring a BIM model file from the cloud and adding it to a data analysis queue; (20) model file logic processing: performing corresponding logic processing according to the model type corresponding to the BIM model file; the model type corresponding to the BIM model file includes a civil engineering model and an electromechanical model; (30) equipment room calculation: by using the secondary development application program interface provided by Revit, the BIM models of the civil engineering model and the electromechanical model of the same floor are loaded at the same time, and according to the space information and the equipment information, the room where the equipment is located is calculated and the data is stored.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of building information technology, and in particular to a cloud-based BIM model data parsing method. Background Art

[0002] BIM is widely used in the construction industry because of its rich real engineering data and accuracy, and BIM technology has been widely developed domestically and even internationally. The accuracy of construction engineering is one of the advantages of BIM technology, but because of this, this advantage is also its defect and bottleneck in the effective transmission and utilization of BIM. As we all know, under limited bandwidth conditions, the amount of data is proportional to the time consumption. Because of this, in order to reflect the actual appearance of the construction project, the more accurate the BIM model of the construction project, the more data it has, which brings about problems in the management of the BIM model, and it is highly dependent on the revit tool, making it very inconvenient to view and manage the data.

[0003] At present, the amount of data in the design phase of ordinary construction engineering BIM models can reach hundreds of megabytes or even gigabytes due to the business accuracy restrictions (similar to the LOD standard restrictions often mentioned in the industry). With the continuous development of hardware storage capacity, although the problem of storing gigabytes of data is no longer a difficult task, the problem of transmission and management of BIM models has always existed, as well as the problems of data extraction and real-time viewing.

[0004] In summary, the problems with the existing technology are: the process of parsing the BIM model to obtain valid data is very complicated, and the extracted data does not have a clear format, which is very unfriendly to users. Summary of the invention

[0005] The purpose of the present invention is to provide a cloud-based BIM model data analysis method, which is simple to operate, has a small amount of data, and is easy to apply.

[0006] The technical solution to achieve the purpose of the present invention is:

[0007] A cloud-based BIM model data parsing method comprises the following steps:

[0008] (10) Model file acquisition: Obtain BIM model files from the cloud and add them to the data analysis queue;

[0009] (20) Model file logic processing: performing corresponding logic processing according to the model type corresponding to the BIM model file;

[0010] The model types corresponding to the BIM model file include civil engineering model and electromechanical model;

[0011] (30) Calculation of the room where the equipment is located: By using the secondary development application interface provided by Revit, the BIM models of the civil engineering model and the electromechanical model of the same floor are loaded at the same time. Based on the space information and equipment information, the room where the equipment is located is calculated and the data is stored.

[0012] Compared with the prior art, the present invention has the following significant advantages:

[0013] 1. Simple operation: Through existing technologies, this automated process realizes the online management of BIM models, which can be used permanently after being uploaded once, thus improving the user experience, reducing the complex file transfer process, facilitating file management, and achieving the effect of online management of BIM models.

[0014] 2. Small amount of data: The analysis method mentioned in the present invention solves the problem of large amount of BIM model data. The model file is extracted through the public method provided by the revit software, and calculation and analysis are performed through a specific mathematical calculation method. The data is output and stored in a customized data format, and the huge amount of data is extracted and refined, and data useful for the actual production environment is analyzed, and useless information is removed, thereby improving the user's efficiency in using the BIM model, and effectively enhancing the user experience, which plays a significant role in the popularization and application of BIM technology.

[0015] 3. Convenient application: The present invention solves the technical limitations of the previous BIM model in terms of display. In the past, BIM models could only be loaded and displayed on supported software. Through the present invention, the BIM model is converted into a gltf format file that can be loaded by the browser. In this way, the BIM model can be loaded and viewed in the browser, thereby realizing the Web online display of the BIM model. From the perspective of the actual production environment, the application value of BIM technology is greatly improved, and BIM technology can be quickly popularized and promoted in multiple industries such as the construction engineering industry, engineering manufacturing industry, and computer information technology industry. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is the main flow chart of the cloud-based BIM model data parsing method of the present invention.

[0017] Figure 2 for Figure 1 Flowchart of the logical processing steps of the model file.

[0018] Figure 3 for Figure 2 Flowchart of the logical processing steps of the civil engineering model.

[0019] Figure 4 for Figure 2 Flowchart of the logical processing steps of the electromechanical model. DETAILED DESCRIPTION

[0020] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0021] Examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.

[0022] In the description of the present invention, it is necessary to understand that the terms “resume transmission”, “model conversion”, “data parsing”, etc. are specific technical means in the model parsing process, which are only used to facilitate the description of the specific processes and steps of the present invention, and therefore cannot be understood as limitations on the present invention.

[0023] like Figure 1 As shown, the cloud-based BIM model data parsing method of the present invention includes the following steps:

[0024] (10) Model file acquisition: Obtain BIM model files from the cloud and add them to the data analysis queue;

[0025] The data parsing queue is processed in the first-in-first-out principle and is processed in the order of submission time.

[0026] (20) Model file logic processing: performing corresponding logic processing according to the model type corresponding to the BIM model file;

[0027] The model types corresponding to the BIM model file include civil engineering model and electromechanical model.

[0028] like Figure 2 As shown, the (20) model file logic processing steps include:

[0029] (21) Civil engineering model logic processing: When the model type corresponding to the BIM model is a civil engineering model, extract room information, generate room files, convert file formats, and upload them to the server;

[0030] like Figure 3 As shown, the (21) civil engineering model logic processing steps include: (211) room information extraction: by using the secondary development application program interface provided by Revit, the room information is extracted and synchronized to the basic database table, and the parsing status and parsing time are synchronized at the same time;

[0031] (212) Room file generation: Generate a custom format file that can directly load room information based on the BIM model, upload it to the server, and synchronize the generation status and generation time;

[0032] (213) File format conversion: Convert the BIM model into a gltf format file, upload it to the server, and synchronize the conversion status and generation time.

[0033] (22) Mechanical and electrical model logic processing: When the model type corresponding to the BIM model is a mechanical and electrical model, extract the equipment information, generate equipment files, parse the model filter data, convert the file format, and upload it to the server;

[0034] like Figure 4 As shown, the (22) electromechanical model logic processing step includes:

[0035] (221) Equipment information extraction: By using the secondary development application program interface provided by Revit, component and equipment information, as well as the properties of each component, are extracted and synchronized to the basic database table, while also synchronizing the parsing status and parsing time;

[0036] (222) Equipment file generation: Generate a custom format file containing equipment information based on the BIM model, upload it to the server, and synchronize the generation status and generation time;

[0037] (223) Model filter data parsing: according to the BIM model, the filter data contained in the parsed model is synchronized to the basic database table, and the parsing status and parsing time are synchronized at the same time;

[0038] (224) File format conversion: Convert the BIM model into a gltf format file, upload it to the server, and synchronize the conversion status and generation time.

[0039] (30) Calculation of the room where the equipment is located: By using the secondary development application interface provided by Revit, the BIM models of the civil engineering model and the electromechanical model of the same floor are loaded at the same time. Based on the space information and equipment information, the room where the equipment is located is calculated and the data is stored.

[0040] The entire automated process will perform each of the above steps, but specific business needs may require only one step to be processed separately. The present invention supports single-step processing operations and performs separate analysis and processing operations (failure retry, or data update, etc.) according to needs.

[0041] In the description of this specification, the description of reference terms such as "breakpoint resume", "online parsing", "format conversion", "data synchronization", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0042] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A cloud-based BIM model data parsing method, comprising the following steps: (10) Model file acquisition: Obtain BIM model files from the cloud and add them to the data analysis queue; (20) Logical processing of model files: performing corresponding logical processing according to the model type corresponding to the BIM model file; The model types corresponding to the BIM model file include civil engineering model and electromechanical model; (30) Calculation of the room where the equipment is located: By using the secondary development application program interface provided by Revit, the BIM models of the civil engineering model and the electromechanical model of the same floor are loaded at the same time. Based on the space information and equipment information, the room where the equipment is located is calculated and stored; The (20) model file logic processing step includes: (21) Civil engineering model logic processing: When the model type corresponding to the BIM model is a civil engineering model, extract the room information, generate the room file, convert the file format, and upload it to the server; (22) Mechanical and electrical model logic processing: When the model type corresponding to the BIM model is a mechanical and electrical model, extract the equipment information, generate equipment files, parse the model filter data, convert the file format, and upload it to the server; The (21) civil engineering model logic processing steps include: (211) Room information extraction: By using the secondary development application program interface provided by Revit, the room information is extracted and synchronized to the basic database table, while synchronizing the analysis status and analysis time; (212) Room file generation: generating a custom format file that can directly load room information based on the BIM model, uploading it to the server, and synchronizing the generation status and generation time; (213) File format conversion: convert the BIM model into a gltf format file, upload it to the server, and synchronize the conversion status and generation time; The (22) electromechanical model logic processing step includes: (221) Equipment information extraction: By using the secondary development application program interface provided by Revit, component and equipment information, as well as the properties of each component, are extracted and synchronized to the basic database table, while also synchronizing the parsing status and parsing time; (222) Equipment file generation: generating a custom format file containing equipment information based on the BIM model, uploading it to the server, and synchronizing the generation status and generation time; (223) Model filter data parsing: parsing the filter data contained in the model according to the BIM model, synchronizing the data to the basic database table, and synchronizing the parsing status and parsing time; (224) File format conversion: Convert the BIM model into a gltf format file, upload it to the server, and synchronize the conversion status and generation time.

Citation Information

Patent Citations

  • Method for lightening of BIM

    CN107247822A

  • Device and method based on BIM (Building Information Modeling) and operation and maintenance information interaction in intelligent building management

    CN108615143A