Model test device and test method for shield tunneling-induced melting and ice-containing mud cake formation
By designing a model test device for forming a shield excavation and ice-containing mud cake, the adhesion of frozen soil was measured, and the problem of the melting situation caused by shield excavation and the bonding of ice-containing mud cakes was solved in the prior art. The basis for preventing analysis of shield structure mud cakes in frozen soil strata improves construction efficiency and cost control.
Patent Information
- Application Number
- CN202210372123.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-03-31
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2042-03-31
AI Technical Summary
The prior art cannot effectively determine the melting situation caused by shield excavation and the law of the surface of the cutter plate to bond ice-containing mud cakes, and cannot solve the problem of shield structure mud cakes in frozen soil strata.
A model test device for forming a shield excavation and melting and ice-containing mud cake is designed, including a support frame, motor, rotating shaft, temperature control device, cutter plate, insulation box and frozen soil. By controlling temperature and excavation parameters, the shield is simulated. During the excavation process, the adhesion amount on the cutting board is measured and the relationship between the adhesion amount of soil is determined with the initial moisture content, freezing time and excavation parameters.
The adhesion amount of frozen soil was accurately measured, and the melting situation caused by the excavation of shield structures and the law of the surface of the knife plate bonding ice-containing mud cakes were obtained, which provided an analytical basis for the prevention of shield structures in frozen soil strata and improved the shield. Construction efficiency and cost control.
Smart Images

Figure CN114813431B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of shield tunnel construction, and particularly relates to a model test device and a test method for shield tunneling-induced melting and ice-containing mud cake formation in permafrost layers. Background Art
[0002] During the tunneling process, shield machines often encounter the phenomenon of soil adhering to or blocking the shield cutterhead. Adhesion is the attraction between soil and structure through the adsorption of water molecules. When the shield cutterhead cuts and squeezes the soil, it is very easy to form a high-strength mud cake at the center of the cutterhead, which gradually spreads to the surroundings, causing the cutterhead and tool to be wrapped and unable to effectively cut the soil layer, which reduces the efficiency of shield tunneling and greatly increases the construction period and construction cost. With the development of transportation infrastructure, more shield tunnel projects will pass through permafrost areas. The frozen soil will melt under the action of shield tunneling load, causing the ice-containing frozen soil to adhere to the cutterhead, making it necessary to study the melting caused by shield tunneling and the formation of ice-containing mud cake.
[0003] The search found that Xiao Yuhao used a self-made traction transmission adhesion test device in "Indoor test of reducing adhesion of clay by electroosmosis method" to measure the maximum adhesion of clay at different water contents; Liu Cheng used a self-designed adhesion pull test device in "Effect of soil moisture content and metal corrugated surface on interface adhesion" to achieve the corrugated convex effect of the measuring cone surface by winding metal wire, and analyzed the influence of different corrugated convexity and soil moisture content changes on the interface adhesion characteristics. The existing test device mainly measures the adhesion between the metal interface and the soil for soils with different moisture contents. Not only is there a lack of research on the adhesion characteristics of frozen soil, but related research cannot actually solve the problems of excavation-induced melting and ice-containing mud cake formation encountered during excavation in frozen strata.
[0004] Therefore, the existing technology cannot measure the melting situation caused by shield tunneling and the law of ice-containing mud cakes adhering to the cutter head surface, and cannot solve the problem of shield mud cakes in frozen soil layers. Summary of the invention
[0005] The purpose of the present invention is to solve the shortcomings and defects of the prior art, and to provide a model test device and test method for melting and ice-containing mud cake formation caused by shield tunneling. By calculating the viscosity of frozen soil under different factors, the relationship between the adhesion amount of soil and the initial moisture content of the soil, freezing time, control temperature and tunneling parameters is statistically analyzed, and the melting caused by shield tunneling and the law of ice-containing mud cake adhesion on the cutter head surface are summarized.
[0006] A model test device for shield tunneling melting and ice-containing mud cake formation, the device comprises a support frame 1, bolts I 2, a motor 3, a rotating shaft 4, bolts II 5, a temperature control device 6, a cutter head 7, an insulation box 8, a metal box 9, frozen soil 10, a support platform 11, and a spring 12;
[0007] The motor 3 is connected to the support frame 1 through bolts 12;
[0008] The rotating shaft 4 at the lower part of the motor 3 is connected to the cutter disc 7 through the bolt II 5, and the cutter disc can be freely disassembled; after the motor 3 is started, the cutter disc 7 is driven to rotate through the rotating shaft 4;
[0009] The temperature control device 6 is placed on the heat preservation box 8; the temperature control device 6 is connected to the external air-conditioning outlet through the ventilation pipe 13 to achieve the purpose of controlling the external temperature of the frozen soil layer;
[0010] The insulation box 8 is placed on the support platform 11; the bottom of the support platform 11 is connected to the spring 12, and the compression of the spring 12 can push the insulation box 8 upward, allowing the cutter disc 7 to completely contact the frozen soil; the initial compression amount of the spring 12 determines the thrust of the cutter disc.
[0011] The test method of the shield tunneling melting and ice-containing mud cake formation model test device is connected with the above-mentioned shield tunneling melting and ice-containing mud cake formation model test device, and the specific steps are as follows:
[0012] ① Prepare different water contents w according to experimental requirements 0 The soil samples are evenly distributed, compacted in layers and packed into metal boxes;
[0013] ②Put the metal box containing the soil sample into a freezer, set a freezing temperature T between -5° and -20°, and obtain frozen soil 10 with a certain freezing degree after freezing for t time. By changing the freezing time t, frozen soil 10 with different freezing degrees can be obtained;
[0014] ③ Put the metal box 9 containing the frozen soil 10 into the heat preservation box 8, install the temperature control device 6 on the top, and set the temperature of the temperature control device 6 to T'. By setting different T', different external temperatures can be simulated;
[0015] ④Measure the original mass m of the cutter head 0 , and then installed on the lower end of the motor shaft by bolt II 5;
[0016] ⑤ The shield cutterhead 7 is driven forward, so that the cutterhead 7 touches and penetrates into the frozen soil layer, resulting in the destruction of the ice crystal structure inside the frozen soil, and then the frozen soil partially melts, and the ice-containing frozen soil produces a bonding effect, which is bonded to the bottom surface of the cutterhead 7; the driving parameter γ includes the top thrust and rotation speed of the cutterhead during driving, which affects the degree of damage to the ice crystal structure inside the frozen soil;
[0017] ⑥ Remove the cutter head 7 and measure the mass m of the cutter head 7 at this time and compare it with the original mass m 0 By comparison, the mass of clay attached to the cutter head 7 is: m 黏 , and the adhesion amount m on the blade 7 is calculated 黏 =mm 0 ;
[0018] ⑦ Adjust the initial moisture content w of the soil 0 , freezing time t, control temperature T' and excavation parameter γ, repeat steps ① to ⑥ to obtain the corresponding adhesion amount m 黏 .
[0019] Furthermore, by measuring the mass of frozen soil adhering to the cutterhead m 黏 The initial moisture content of the soil w 0 The relationship between the freezing time t, the control temperature T' and the excavation parameter γ is used to obtain the melting situation caused by shield excavation and the law of ice-containing mud cake adhesion on the cutterhead surface, thereby providing an analytical basis for the prevention of shield mud cake formation in frozen soil strata.
[0020] Beneficial Effects
[0021] The present invention provides a shield tunneling melting and ice-containing mud cake formation model test device and test method, the device comprises a support frame 1, bolts I 2, a motor 3, a rotating shaft 4, bolts II 5, a temperature control device 6, a cutter head 7, an insulation box 8, a metal box 9, frozen soil 10, a support platform 11, and a spring 12; a temperature control device is arranged on the upper part of the insulation box to provide a constant temperature environment; the motor is fixed on the rotating shaft; the motor drives the cutter head to stir the frozen soil block in the metal box to make it viscous; by measuring the mass of the ice-containing frozen soil adhered to the cutter head, the initial water content w of the frozen soil can be obtained. 0 The relationship between the adhesion of frozen soil and soil samples after different freezing times under the conditions of controlling temperature T' and excavation parameter γ.
[0022] The advantages of the present invention are as follows:
[0023] 1) By controlling a stable low-temperature environment, the ice content is ensured not to change significantly before and after stirring, and the adhesion amount of frozen soil corresponding to the ice content can be accurately determined;
[0024] 2) By measuring frozen soils with different initial moisture contents and ice contents under different constant temperature conditions and cutterhead excavation parameters, the melting conditions caused by shield tunneling and the law of ice-containing mud cakes adhered to the cutterhead surface are obtained, thereby providing an analytical basis for the prevention of shield mud cake formation in frozen soil strata. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a schematic diagram of the structure of the device according to the present invention;
[0026] Explanation of reference numerals: support frame 1, bolt I 2, motor 3, rotating shaft 4, bolt II 5, temperature control device 6, cutter disc 7, insulation box 8, metal box 9, frozen soil 10, support platform 11, spring 12. DETAILED DESCRIPTION
[0027] The present invention will be further described below with reference to the accompanying drawings and embodiments.
[0028] like Figure 1 As shown, a model test device for shield tunneling melting and ice-containing mud cake formation includes a support frame 1, bolts I2, a motor 3, a rotating shaft 4, bolts II 5, a temperature control device 6, a cutter head 7, an insulation box 8, a metal box 9, frozen soil 10, a support platform 11, and a spring 12;
[0029] The motor 3 is connected to the support frame 1 through bolts 12;
[0030] The rotating shaft 4 at the lower part of the motor 3 is connected to the cutter disc 7 through the bolt II 5, and the cutter disc can be freely disassembled; after the motor 3 is started, the cutter disc 7 is driven to rotate through the rotating shaft 4;
[0031] The temperature control device 6 is placed on the heat preservation box 8; the temperature control device 6 is connected to the external air-conditioning outlet through the ventilation pipe 13 to achieve the purpose of controlling the external temperature of the frozen soil layer;
[0032] The insulation box 8 is placed on the support platform 11; the bottom of the support platform 11 is connected to the spring 12, and the compression of the spring 12 can push the insulation box 8 upward, allowing the cutter disc 7 to completely contact the frozen soil; the initial compression amount of the spring 12 determines the thrust of the cutter disc.
[0033] The test method of the shield tunneling melting and ice-containing mud cake formation model test device is connected with the above-mentioned shield tunneling melting and ice-containing mud cake formation model test device, and the specific steps are as follows:
[0034] ① Prepare different water contents w according to experimental requirements 0 The soil samples are evenly distributed, compacted in layers and packed into metal boxes;
[0035] ②Put the metal box containing the soil sample into a freezer, set a freezing temperature T between -5° and -20°, and obtain frozen soil 10 with a certain freezing degree after freezing for t time. By changing the freezing time t, frozen soil 10 with different freezing degrees can be obtained;
[0036] ③ Put the metal box 9 containing the frozen soil 10 into the heat preservation box 8, install the temperature control device 6 on the top, and set the temperature of the temperature control device 6 to T'. By setting different T', different external temperatures can be simulated;
[0037] ④Measure the original mass m of the cutter head0 , and then installed on the lower end of the motor shaft by bolt II 5;
[0038] ⑤ The shield cutterhead 7 is driven forward, so that the cutterhead 7 touches and penetrates into the frozen soil layer, resulting in the destruction of the ice crystal structure inside the frozen soil, and then the frozen soil partially melts, and the ice-containing frozen soil produces a bonding effect, which is bonded to the bottom surface of the cutterhead 7; the driving parameter γ includes the top thrust and rotation speed of the cutterhead during driving, which affects the degree of damage to the ice crystal structure inside the frozen soil;
[0039] ⑥ Remove the cutter head 7 and measure the mass m of the cutter head 7 at this time and compare it with the original mass m 0 By comparison, the mass of clay attached to the cutter head 7 is: m 黏 , and the adhesion amount m on the blade 7 is calculated 黏 =mm 0 ;
[0040] ⑦ Adjust the initial moisture content w of the soil 0 , freezing time t, control temperature T' and excavation parameter γ, repeat steps ① to ⑥ to obtain the corresponding adhesion amount m 黏 .
[0041] The above is only a preferred implementation of the technology of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.
Claims
1. Model test device for shield tunneling-induced melting and ice-containing mud cake formation, It is characterized in that It comprises a support frame (1), bolts I (2), a motor (3), a rotating shaft (4), bolts II (5), a temperature control device (6), a cutter head (7), a heat preservation box (8), a metal box (9), frozen soil (10), a support platform (11), and a spring (12); The motor (3) is connected to the support frame (1) via bolts 1 (2); The rotating shaft (4) at the bottom of the motor (3) is connected to the cutter disc (7) via a bolt II (5), and the cutter disc can be freely disassembled; after the motor (3) is started, the cutter disc (7) is driven to rotate via the rotating shaft (4); The temperature control device (6) is placed on the heat preservation box (8); the temperature control device (6) is connected to the external air-conditioning outlet through the ventilation pipe (13), so as to achieve the purpose of controlling the external temperature of the frozen soil layer; The heat preservation box (8) is placed on the support platform (11); the bottom of the support platform (11) is connected to the spring (12); the compression of the spring (12) can push the heat preservation box (8) upward, so that the cutter disc (7) can be completely in contact with the frozen soil; the initial compression amount of the spring (12) determines the thrust of the cutter disc.
2. Test method of shield tunneling induced melting and ice-containing mud cake formation model test device, It is characterized in that The shield tunneling melting and ice-containing mud cake formation model test device described in claim 1 is connected, and the specific steps are as follows: ① Prepare soil samples with different moisture contents w0 according to experimental requirements, evenly distribute them, compact them in layers and pack them into metal boxes; ② Place the metal box containing the soil sample in a freezer, set a freezing temperature T between -5° and -20°, and freeze for t time to obtain frozen soil with a certain freezing degree (10). By changing the freezing time t, frozen soil with different freezing degrees (10) can be obtained; ③ The metal box (9) containing the frozen soil (10) is placed in the heat preservation box (8), and a temperature control device (6) is installed on the top. The temperature of the temperature control device (6) is set to T', and different external temperatures are simulated by setting different T'; ④Measure the original mass m of the cutter head 0 , and then mounted on the lower end of the motor shaft by bolt II (5); ⑤ Excavating the shield cutterhead (7), so that the cutterhead (7) touches and penetrates into the frozen soil layer, resulting in the destruction of the ice crystal structure inside the frozen soil, and then the frozen soil partially melts, and the ice-containing frozen soil produces a bonding effect and adheres to the bottom surface of the cutterhead (7); the excavation parameter γ includes the top thrust and rotation speed of the cutterhead during excavation, which affects the degree of destruction of the ice crystal structure inside the frozen soil; ⑥ Remove the cutter head (7) and measure the mass m of the cutter head (7) at this time and compare it with the original mass m 0 By comparison, the mass of clay attached to the cutterhead (7) is: m 黏 , and the adhesion amount m on the cutter head (7) is calculated from this 黏 =mm 0 ; ⑦ Adjust the initial moisture content w of the soil 0 , freezing time t, control temperature T' and excavation parameter γ, repeat steps ① to ⑥ to obtain the corresponding adhesion amount m 黏 .
3. The method according to claim 2, It is characterized in that According to the adhesion of soil m 黏 The initial moisture content of the soil w 0 The relationship between the freezing time t, the control temperature T' and the excavation parameter γ is used to obtain the melting situation caused by shield excavation and the law of ice-containing mud cake adhesion on the cutterhead surface, thereby providing an analytical basis for the prevention of shield mud cake formation in frozen soil strata.
Citation Information
Patent Citations
Testing device and method for testing wear characteristics of shield cutterhead and cutter
CN109443969A
Testing device for testing shield cutter head-soil body intermediate lateral adhesion force
CN109682752A
Constant-temperature heating interface-soil body adhesive force testing device and testing method thereof
CN111650121A
Can eliminate anchoring strength test device of vacuum suction influence
CN205808897U
Connecting method of shield tunnel and shielding machine
JP1991087497A