A combined construction method of deep well wall fracturing energy release and high-pressure grouting

Through the combined construction method of deep well wall fracturing energy release and high-pressure grouting, the strain energy release of the well wall surrounding rock is controlled, and the problems of rock explosion geological disasters and high-cost support in deep shaft construction are solved, and the wellbore stability and Dual optimization of cost.

CN114922628BActive Publication Date: 2024-11-19DEEP MINING LABORATORY BRANCH OF SHANDONG GOLD MINING TECHNOLOGY CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210598441.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-05-30
Publication Date
2024-11-19
Estimated Expiration
2042-05-30

AI Technical Summary

Technical Problem

During the construction of deep vertical shafts, the surrounding rocks on the well walls are prone to geological disasters, and the traditional strengthening of support technology is high, and the operation period is risky, and the maintenance is complicated.

Method used

The combined construction method of deep well wall fracturing and high-pressure grouting is adopted to determine the stress zone, hydraulic fracturing and high-pressure grouting through temporary support of anchor net, pressure relief holes and grouting holes of guide rail drilling machine, ultrasonic measurement, stress zone, hydraulic fracturing and high-pressure of rubber packer Grouting controls the release of surrounding rock strain energy, reduces construction costs and damage risks.

Benefits of technology

Effectively avoid rock burst geological disasters, reduce the chance of wellbore damage, reduce construction costs, and improve the stability of the surrounding rock on the well wall.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114922628B_ABST
    Figure CN114922628B_ABST
Patent Text Reader

Abstract

A method for combining fracturing and high-pressure grouting in a deep well wall, the method comprises the following steps: temporarily supporting the surrounding rock of the well wall with anchor nets; constructing pressure relief holes and grouting holes; cleaning the boreholes; ultrasonic measurement to determine the stress reduction area, stress increase area and original ground stress area; isolating the fracturing section in the pressure relief hole; pulsating hydraulic fracturing after constant pressure water injection; unblocking the fracturing section after the surrounding rock is fractured; completing hydraulic fracturing in the remaining pressure relief holes; ultrasonic measurement to determine that the stress has reached equilibrium again; grouting construction after cleaning the grouting holes; grouting construction after cleaning the pressure relief holes; completing the grouting construction of the remaining pressure relief holes and grouting holes; ultrasonic measurement to determine whether the surrounding rock of the well wall meets the design requirements; if the design requirements are not met, additional boreholes are drilled, and fracturing and high-pressure grouting are performed on the additional boreholes until the surrounding rock of the well wall meets the design requirements; and concrete lining is constructed on the inner side of the surrounding rock of the well wall. The invention can effectively release the high elastic strain energy of the surrounding rock of the well wall to control the fracture depth of the surrounding rock and reduce the construction cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of deep shaft engineering excavation and support, and in particular relates to a deep well wall fracturing energy release and high-pressure grouting combined construction method. Background Art

[0002] Deep vertical shafts are the throat of mining production. During the excavation of deep vertical shafts, due to the increase of ground stress, there is stress concentration in the surrounding rock of the shaft wall, and the energy release process often leads to stress-type geological disasters such as rock bursts and large-volume spalling, which seriously affect the excavation progress of deep vertical shafts and seriously threaten the lives of construction workers in the shaft.

[0003] Since the surrounding rock of the shaft wall is very prone to high-stress rock burst geological disasters during the construction of deep shafts, it is necessary to strengthen the support of the shaft wall of the deep shaft from the perspective of design and construction. However, the traditional strengthening support technology will significantly increase the construction cost, such as the use of anchor rods and ultra-thick high-strength concrete lining combined support method, and there is also the risk of damage to the shaft during the operation period, which not only poses a potential threat to the later mining production, but also makes the repair and maintenance process extremely complicated. Summary of the invention

[0004] In view of the problems existing in the prior art, the present invention provides a deep well wall fracturing energy release and high-pressure grouting combined construction method, which can effectively release the high elastic strain energy of the well wall surrounding rock and control the fracture depth of the surrounding rock; by reasonably arranging the operation cycle rhythm, stress-type geological disasters such as rock bursts that occur during the construction process can be effectively avoided; by reasonably designing support parameters, the construction cost can be effectively reduced, and at the same time, the probability of wellbore damage during shaft operation can be reduced.

[0005] In order to achieve the above object, the present invention adopts the following technical scheme: a method for combining deep well wall fracturing energy release and high-pressure grouting, comprising the following steps:

[0006] Step 1: Temporary anchor net support for the surrounding rock of the well wall;

[0007] Step 2: Use a rail-type rock drill to construct pressure relief holes and grouting holes around the surrounding rock of the well wall;

[0008] Step 3: Use a pneumatic press to clean the constructed pressure relief holes and grouting holes;

[0009] Step 4: Use an ultrasonic measuring instrument to measure the pressure relief hole and determine the stress reduction area, stress increase area and original ground stress area of ​​the surrounding rock of the wellbore in the radial direction of the wellbore;

[0010] Step 5: Use the drill pipe to send two rubber packers to the stress-increasing area in the pressure relief hole. The two rubber packers are respectively located at the starting end and the end end of the wellbore radial direction in the stress-increasing area. Then use a hydraulic pump to pressurize the two rubber packers to expand them. The area in the hole between the two expanded rubber packers is sealed as a fracturing section.

[0011] Step 6: Use a hydraulic pump to inject water into the fracturing section at a constant pressure. After the constant pressure water injection is completed, replace the hydraulic pump with a pulsating water injector, use the pulsating water injector to apply pulsating pressure into the fracturing section, and perform pulsating hydraulic fracturing on the surrounding rock in the stress-increased area through the pulsating pressure;

[0012] Step 7: Compare the time of applying pulsating pressure each time. When the time difference between two consecutive times of applying pulsating pressure exceeds 1 times, or the pulsating pressure cannot be applied, it means that the surrounding rock in the stress-increased area in the pressure relief hole is fractured and the strain energy of the surrounding rock is released.

[0013] Step 8: Unloading the pressure in the fracturing section to atmospheric pressure, then depressurizing the two rubber packers, and then removing the depressurized rubber packers from the depressurization hole;

[0014] Step 9: Repeat steps 3 to 9 to complete the pulsating hydraulic fracturing of the surrounding rock in the pressure-increased area in the remaining pressure relief holes;

[0015] Step 10: Use an ultrasonic measuring instrument to measure the pressure relief holes where the pulsating hydraulic fracturing of the surrounding rock in the pressure-increased area has been completed, until it is determined that the stress of the surrounding rock on the well wall has reached a balance again;

[0016] Step 11: Use a high-pressure air pipe to clean the grouting hole, then install a grouting pipe in the grouting hole, then seal the grouting hole, and finally install a grouting stop valve on the grouting pipe;

[0017] Step 12: Inject high-water material into the grouting hole through the grouting pipe by high-pressure interval grouting. After the grouting is completed, the grouting pipe is blocked by the grouting stop valve;

[0018] Step 13: Use a high-pressure air duct to clean the pressure relief hole, then install a grouting pipe in the pressure relief hole, then seal the pressure relief hole, and finally install a grouting stop valve on the grouting pipe;

[0019] Step 14: Inject the cement and water glass mixed slurry into the pressure relief hole through the grouting pipe by high-pressure grouting. After the grouting is completed, the grouting pipe is blocked by the grouting stop valve;

[0020] Step 15: Repeat steps 11 to 14 to complete the grouting construction of the remaining pressure relief holes and grouting holes;

[0021] Step 16: Use an ultrasonic measuring instrument to measure the surrounding rock of the well wall after the grouting step. If it does not meet the design requirements, perform additional drilling, and then repeat steps 3 to 15 to perform fracturing and high-pressure grouting on the additional pressure relief holes and grouting holes until the surrounding rock of the well wall meets the design requirements after ultrasonic measurement;

[0022] Step 17: Support the formwork on the inner side of the surrounding rock of the well wall, and then pour concrete in the formwork. The concrete is prepared by the ground mixing station and lowered down by the bottom-discharging bucket. Then it enters the formwork through the ash separator and ash chute. The concrete in the formwork is vibrated layer by layer by a vibrating rod. After the vibration is completed, wait for the concrete to solidify. When the concrete reaches the designed strength, remove the formwork to finally form the concrete lining.

[0023] In step one, the length of the anchor rod in the anchor net temporary support is 3m, the diameter of the anchor rod is 20mm, the spacing between the anchor rod rows is 1.5m, the anchor rod model is HRB400, and the mesh diameter of the metal net is 6mm.

[0024] In step two, the number of pressure relief holes is 8, and the 8 pressure relief holes are evenly distributed along the circumferential direction of the wellbore. The hole depth of the pressure relief holes is 5m to 10m, and the hole diameter of the pressure relief holes is 40mm. The pressure relief holes are inclined downward and the inclination angle is 30°. The number of grouting holes is 8, and the 8 grouting holes are evenly distributed along the circumferential direction of the wellbore. The hole depth of the grouting holes is 3m to 5m, and the hole diameter of the grouting holes is 60mm; in the axial direction of the wellbore, the grouting holes are distributed on both sides of the pressure relief holes, and the vertical spacing between the grouting holes and the pressure relief holes in the axial direction of the wellbore is 400mm. In the circumferential direction of the wellbore, the grouting holes and the pressure relief holes are alternately distributed.

[0025] In step 3, the air volume of the air compressor is 3m 3 / min~6m 3 / min, the air pressure of the air compressor is 0.7MPa, the diameter of the water outlet pipe of the air compressor is 25mm, and the diameter of the air supply pipe of the air compressor is 10mm.

[0026] In step 4, the probe of the ultrasonic measuring instrument is first sent to the bottom of the pressure relief hole, and then the probe is moved toward the mouth of the pressure relief hole. The movement pattern of the probe is to alternately move 150 mm and 300 mm. The wave velocity is recorded once after each 150 mm movement, and the amplitude is recorded once after each 300 mm movement. The 150 mm and 300 mm movement distances are repeated 3 to 5 times until the mouth of the pressure relief hole is measured. Finally, the stress reduction area, stress increase area and original ground stress area of ​​the surrounding rock of the well wall are determined according to the measurement results of the wave velocity and the hole depth.

[0027] In step six, the constant pressure water injection flow rate is 5L / min~10L / min, the loading waveform of the pulsating water injector is a sine wave, the pulse frequency of the pulsating water injector is 0.1Hz~1Hz, the pulsating upper limit pressure is the surrounding rock crushing pressure, and the pulsating lower limit pressure is 50%~75% of the surrounding rock crushing pressure.

[0028] In step ten, the ultrasonic measurement is performed every 12 hours, and the period of the ultrasonic measurement is 3 to 5 days.

[0029] In step eleven, the grouting holes are sealed with anchoring agents, and the sealing length is 0.3m to 0.5m.

[0030] In step twelve, the grouting pressure is 3.5 MPa, the grouting maintenance time is 10 minutes, and the sealing time of the grouting pipe after grouting is 1 hour.

[0031] In step fourteen, the grouting pressure is 3.5 MPa, the grouting maintenance time is 10 minutes, and the grouting pipe is sealed for 1 hour after grouting.

[0032] Beneficial effects of the present invention:

[0033] The combined construction method of deep well wall fracturing energy release and high-pressure grouting of the present invention can effectively release the high elastic strain energy of the well wall surrounding rock and control the fracture depth of the surrounding rock; by reasonably arranging the operation cycle rhythm, stress-type geological disasters such as rock bursts that occur during the construction process can be effectively avoided; by reasonably designing support parameters, the construction cost can be effectively reduced, and the probability of shaft damage during shaft operation can be reduced. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 It is a cross-sectional view of the axial structure of a deep vertical shaft after the deep well wall fracturing energy release and high-pressure grouting combined construction method of the present invention is adopted;

[0035] Figure 2 It is a radial structural cross-sectional view (pressure relief hole cross-section) of a deep vertical shaft after the deep well wall fracturing energy release and high-pressure grouting combined construction method of the present invention is adopted;

[0036] Figure 3 It is a radial structural cross-sectional view (grouting hole cross section) of a deep vertical shaft after the deep well wall fracturing energy release and high-pressure grouting combined construction method of the present invention is adopted;

[0037] In the figure, 1 is the pressure relief hole, 2 is the grouting hole, 3 is the stress reduction area, 4 is the stress increase area, 5 is the original ground stress area, and 6 is the concrete lining. DETAILED DESCRIPTION

[0038] The present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0039] In this embodiment, the bottom elevation of a deep vertical shaft is -1990m, the wellhead elevation of the deep vertical shaft is +15m, the shaft diameter of the deep vertical shaft is 10.5m, and the exploration depth is -1050.66m to -1056.44m. After lithology comparison, it is found that the rock in this area is a large type of granite, and the rock quality grade is V. The bedrock at this depth has a high initial stress and a strong impact tendency. The surrounding rock of the well wall is greatly deformed by the ground pressure. When the vertical shaft is constructed to this depth, corresponding unloading or reinforcement measures should be taken. Specifically, the deep well wall fracturing energy release and high-pressure grouting combined construction method of the present invention is adopted, which includes the following steps:

[0040] Step 1: Temporary anchor net support is performed on the surrounding rock of the well wall; specifically, the anchor rod length in the temporary anchor net support is 3m, the anchor rod diameter is 20mm, the anchor rod row spacing is 1.5m, the anchor rod model is HRB400, and the mesh diameter of the metal net is 6mm;

[0041] Step 2: Use a rail-type rock drill to construct pressure relief holes 1 and grouting holes 2 around the surrounding rock of the well wall; specifically, the number of pressure relief holes 1 is 8, and the 8 pressure relief holes 1 are evenly distributed along the circumferential direction of the wellbore, the hole depth of the pressure relief holes 1 is 5m-10m, the hole diameter of the pressure relief holes 1 is 40mm, the pressure relief holes 1 are inclined downward and the inclination angle is 30°, the number of grouting holes 2 is 8, and the 8 grouting holes 2 are evenly distributed along the circumferential direction of the wellbore, the hole depth of the grouting holes 2 is 3m-5m, and the hole diameter of the grouting holes 2 is 60mm; in the axial direction of the wellbore, the grouting holes 2 are distributed on both sides of the pressure relief holes 1, and the vertical spacing between the grouting holes 2 and the pressure relief holes in the axial direction of the wellbore is 400mm, and the grouting holes 2 and the pressure relief holes 1 are alternately distributed in the circumferential direction of the wellbore; the first energy release of the wellbore surrounding rock can be achieved through the construction of the pressure relief holes 1 and the grouting holes 2;

[0042] Step 3: Use the air compressor to clean the pressure relief hole 1 and grouting hole 2. Specifically, the air volume of the air compressor is 3m 3 / min~6m 3 / min, the air pressure of the air compressor is 0.7MPa, the diameter of the water outlet pipe of the air compressor is 25mm, and the diameter of the air supply pipe of the air compressor is 10mm;

[0043] Step 4: Use an ultrasonic measuring instrument to measure the pressure relief hole 1, and determine the stress reduction zone 3, stress increase zone 4 and original ground stress zone 5 of the surrounding rock of the wellbore in the radial direction of the wellbore; specifically, first send the probe of the ultrasonic measuring instrument to the bottom of the pressure relief hole 1, and then move the probe to the orifice side of the pressure relief hole 1, and the movement rule of the probe is to alternately move 150 mm and 300 mm, and record the wave velocity once after each 150 mm movement, and record the amplitude once after each 300 mm movement. The number of repeated measurements of the alternating 150 mm and 300 mm movement distances is 3 to 5 times, until the orifice of the pressure relief hole 1 is measured, and finally determine the stress reduction zone 3, stress increase zone 4 and original ground stress zone 5 of the surrounding rock of the wellbore according to the measurement results of the wave velocity and the hole depth;

[0044] Step 5: Use a drill pipe to deliver two rubber packers to the stress-increased area 4 in the pressure relief hole 1. The two rubber packers are respectively located at the starting end and the terminal end of the stress-increased area 4 in the radial direction of the wellbore. Then, use a hydraulic pump to pressurize the two rubber packers to expand them. The in-hole area between the two expanded rubber packers is sealed as a fracturing section.

[0045] Step six: use a hydraulic pump to inject water into the fracturing section at a constant pressure. After the constant pressure water injection is completed, replace the hydraulic pump with a pulsating water injector, use the pulsating water injector to apply pulsating pressure to the fracturing section, and perform pulsating hydraulic fracturing on the surrounding rock in the stress-increased zone 4 through the pulsating pressure; specifically, the constant pressure water injection flow rate is 5L / min~10L / min, the loading waveform of the pulsating water injector is a sine wave, the pulse frequency of the pulsating water injector is 0.1Hz~1Hz, the pulsating upper limit pressure is the surrounding rock crushing pressure, and the pulsating lower limit pressure is 50%~75% of the surrounding rock crushing pressure; through the pulsating hydraulic fracturing of the surrounding rock in the stress-increased zone 4, the second energy release of the well wall surrounding rock is achieved;

[0046] Step 7: Compare the time of applying the pulsating pressure each time. When the time difference between two consecutive times of applying the pulsating pressure exceeds 1 times, or the pulsating pressure cannot be applied, it indicates that the surrounding rock in the stress-increased zone 4 in the pressure relief hole 1 is fractured, and the strain energy of the surrounding rock is completely released;

[0047] Step 8: Unloading the pressure in the fracturing section to atmospheric pressure, then depressurizing the two rubber packers, and then removing the depressurized rubber packers from the depressurization hole 1;

[0048] Step 9: Repeat steps 3 to 9 to complete the pulsating hydraulic fracturing of the surrounding rock in the pressure-increased area 4 in the remaining pressure relief holes 1;

[0049] Step 10: Use an ultrasonic measuring instrument to measure the pressure relief hole 1 that has completed the pulsating hydraulic fracturing of the surrounding rock in the pressure-increased zone 4 until it is determined that the stress of the surrounding rock of the well wall has reached a balance again; specifically, the ultrasonic measurement is performed once every 12 hours, and the cycle of the ultrasonic measurement is 3 to 5 days;

[0050] Step 11: Use a high-pressure air pipe to clean the grouting hole 2, then install a grouting pipe in the grouting hole 2, then seal the grouting hole 2, and finally install a grouting stop valve on the grouting pipe; specifically, the grouting hole 2 uses an anchoring agent as a sealing material, and the sealing length is 0.3m to 0.5m;

[0051] Step 12: inject high-water material into the grouting hole 2 through the grouting pipe in a high-pressure interval grouting manner, and seal the grouting pipe through the grouting stop valve after the grouting is completed; specifically, the grouting pressure is 3.5MPa, the grouting maintenance time is 10 minutes, and the grouting pipe is sealed for 1 hour after grouting;

[0052] Step 13: Use a high-pressure air pipe to clean the pressure relief hole 1, then install a grouting pipe in the pressure relief hole 1, then seal the pressure relief hole 1, and finally install a grouting stop valve on the grouting pipe;

[0053] Step 14: inject cement and water glass mixed slurry into the pressure relief hole 1 through the grouting pipe by high-pressure grouting, and seal the grouting pipe through the grouting stop valve after the grouting is completed; specifically, the grouting pressure is 3.5MPa, the grouting maintenance time is 10 minutes, and the grouting pipe is sealed for 1 hour after grouting;

[0054] Step 15: Repeat steps 11 to 14 to complete the grouting construction of the remaining pressure relief holes 1 and grouting holes 2;

[0055] Step 16: Use an ultrasonic measuring instrument to measure the surrounding rock of the well wall after the grouting step is completed. If it does not meet the design requirements, additional drilling is performed, and then steps 3 to 15 are repeated to perform fracturing energy release and high-pressure grouting on the additionally constructed pressure relief hole 1 and grouting hole 2 until the surrounding rock of the well wall meets the design requirements after ultrasonic measurement;

[0056] Step 17: Support the formwork on the inner side of the surrounding rock of the shaft wall, and then pour concrete in the formwork. The concrete is prepared by the ground mixing station and lowered down by the bottom-unloading bucket. Then it enters the formwork through the ash distributor and ash chute. The concrete in the formwork is vibrated layer by layer by the vibrating rod. After the vibration is completed, wait for the concrete to solidify. When the concrete reaches the designed strength, remove the formwork and finally form the concrete lining 6. The deep shaft after construction is as follows Figures 1 to 3 shown.

[0057] The solutions in the embodiments are not intended to limit the patent protection scope of the present invention. All equivalent implementations or changes that do not deviate from the present invention are included in the patent scope of this case.

Claims

1. A method for combining deep well wall fracturing energy release and high-pressure grouting, characterized in that The steps include: Step 1: Temporary anchor net support for the surrounding rock of the well wall; Step 2: Use a rail-type rock drill to construct pressure relief holes and grouting holes around the surrounding rock of the well wall; Step 3: Use a pneumatic press to clean the constructed pressure relief holes and grouting holes; Step 4: Use an ultrasonic measuring instrument to measure the pressure relief hole and determine the stress reduction area, stress increase area and original ground stress area of ​​the surrounding rock of the wellbore in the radial direction of the wellbore; Step 5: Use the drill pipe to send two rubber packers to the stress-increasing area in the pressure relief hole. The two rubber packers are respectively located at the starting end and the end end of the wellbore radial direction in the stress-increasing area. Then use a hydraulic pump to pressurize the two rubber packers to expand them. The area in the hole between the two expanded rubber packers is sealed as a fracturing section. Step 6: Use a hydraulic pump to inject water into the fracturing section at a constant pressure. After the constant pressure water injection is completed, replace the hydraulic pump with a pulsating water injector, use the pulsating water injector to apply pulsating pressure into the fracturing section, and perform pulsating hydraulic fracturing on the surrounding rock in the stress-increased area through the pulsating pressure; Step 7: Compare the time of applying pulsating pressure each time. When the time difference between two consecutive times of applying pulsating pressure exceeds 1 times, or the pulsating pressure cannot be applied, it means that the surrounding rock in the stress-increased area in the pressure relief hole is fractured and the strain energy of the surrounding rock is released. Step 8: Unloading the pressure in the fracturing section to atmospheric pressure, then depressurizing the two rubber packers, and then removing the depressurized rubber packers from the depressurization hole; Step 9: Repeat steps 3 to 9 to complete the pulsating hydraulic fracturing of the surrounding rock in the pressure-increased area in the remaining pressure relief holes; Step 10: Use an ultrasonic measuring instrument to measure the pressure relief holes where the pulsating hydraulic fracturing of the surrounding rock in the pressure-increased area has been completed, until it is determined that the stress of the surrounding rock on the well wall has reached a balance again; Step 11: Use a high-pressure air pipe to clean the grouting hole, then install a grouting pipe in the grouting hole, then seal the grouting hole, and finally install a grouting stop valve on the grouting pipe; Step 12: Inject high-water material into the grouting hole through the grouting pipe by high-pressure interval grouting. After the grouting is completed, the grouting pipe is blocked by the grouting stop valve; Step 13: Use a high-pressure air duct to clean the pressure relief hole, then install a grouting pipe in the pressure relief hole, then seal the pressure relief hole, and finally install a grouting stop valve on the grouting pipe; Step 14: Inject the cement and water glass mixed slurry into the pressure relief hole through the grouting pipe by high-pressure grouting. After the grouting is completed, the grouting pipe is blocked by the grouting stop valve; Step 15: Repeat steps 11 to 14 to complete the grouting construction of the remaining pressure relief holes and grouting holes; Step 16: Use an ultrasonic measuring instrument to measure the surrounding rock of the well wall after the grouting step. If it does not meet the design requirements, perform additional drilling, and then repeat steps 3 to 15 to perform fracturing and high-pressure grouting on the additional pressure relief holes and grouting holes until the surrounding rock of the well wall meets the design requirements after ultrasonic measurement; Step 17: Support the formwork on the inner side of the surrounding rock of the well wall, and then pour concrete in the formwork. The concrete is prepared by the ground mixing station and lowered down by the bottom-discharging bucket. Then it enters the formwork through the ash separator and ash chute. The concrete in the formwork is vibrated layer by layer by a vibrating rod. After the vibration is completed, wait for the concrete to solidify. When the concrete reaches the designed strength, remove the formwork to finally form the concrete lining.

2. A deep well wall fracturing energy release and high pressure grouting combined construction method according to claim 1, characterized in that: In step one, the length of the anchor rod in the anchor net temporary support is 3m, the diameter of the anchor rod is 20mm, the spacing between the anchor rod rows is 1.5m, the anchor rod model is HRB400, and the mesh diameter of the metal net is 6mm.

3. A deep well wall fracturing energy release and high pressure grouting combined construction method according to claim 1, characterized in that: In step two, the number of pressure relief holes is 8, and the 8 pressure relief holes are evenly distributed along the circumferential direction of the wellbore. The hole depth of the pressure relief holes is 5m to 10m, and the hole diameter of the pressure relief holes is 40mm. The pressure relief holes are inclined downward and the inclination angle is 30°. The number of grouting holes is 8, and the 8 grouting holes are evenly distributed along the circumferential direction of the wellbore. The hole depth of the grouting holes is 3m to 5m, and the hole diameter of the grouting holes is 60mm; in the axial direction of the wellbore, the grouting holes are distributed on both sides of the pressure relief holes, and the vertical spacing between the grouting holes and the pressure relief holes in the axial direction of the wellbore is 400mm. In the circumferential direction of the wellbore, the grouting holes and the pressure relief holes are alternately distributed.

4. A deep well wall fracturing energy release and high pressure grouting combined construction method according to claim 1, characterized in that: In step 3, the air volume of the air compressor is 3m 3 / min~6m 3 / min, the air pressure of the air compressor is 0.7MPa, the diameter of the water outlet pipe of the air compressor is 25mm, and the diameter of the air supply pipe of the air compressor is 10mm.

5. A deep well wall fracturing energy release and high pressure grouting combined construction method according to claim 1, characterized in that: In step 4, the probe of the ultrasonic measuring instrument is first sent to the bottom of the pressure relief hole, and then the probe is moved toward the mouth of the pressure relief hole. The movement pattern of the probe is to alternately move 150 mm and 300 mm. The wave velocity is recorded once after each 150 mm movement, and the amplitude is recorded once after each 300 mm movement. The 150 mm and 300 mm movement distances are repeated 3 to 5 times until the mouth of the pressure relief hole is measured. Finally, the stress reduction area, stress increase area and original ground stress area of ​​the surrounding rock of the well wall are determined according to the measurement results of the wave velocity and the hole depth.

6. A deep well wall fracturing energy release and high pressure grouting combined construction method according to claim 1, characterized in that: In step six, the constant pressure water injection flow rate is 5L / min~10L / min, the loading waveform of the pulsating water injector is a sine wave, the pulse frequency of the pulsating water injector is 0.1Hz~1Hz, the pulsating upper limit pressure is the surrounding rock crushing pressure, and the pulsating lower limit pressure is 50%~75% of the surrounding rock crushing pressure.

7. A deep well wall fracturing energy release and high pressure grouting combined construction method according to claim 1, characterized in that: In step ten, the ultrasonic measurement is performed every 12 hours, and the period of the ultrasonic measurement is 3 to 5 days.

8. A deep well wall fracturing energy release and high pressure grouting combined construction method according to claim 1, characterized in that: In step eleven, the grouting holes are sealed with anchoring agents, and the sealing length is 0.3m to 0.5m.

9. A deep well wall fracturing energy release and high pressure grouting combined construction method according to claim 1, characterized in that: In step twelve, the grouting pressure is 3.5 MPa, the grouting maintenance time is 10 minutes, and the sealing time of the grouting pipe after grouting is 1 hour.

10. A deep well wall fracturing energy release and high pressure grouting combined construction method according to claim 1, characterized in that: In step fourteen, the grouting pressure is 3.5 MPa, the grouting maintenance time is 10 minutes, and the grouting pipe is sealed for 1 hour after grouting.