Annular space particle migration simulation device and use method
By designing annular particle migration simulation device, simulating the wellbore and data acquisition system, the problem of unconsidered rock chip particle migration distribution in the blind tube-punching tube completion method is solved, and the accumulation and blockage of rock chip particle is achieved Effective analysis reduces drilling costs and increases oil well production.
Patent Information
- Application Number
- CN202210984857.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-17
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2042-08-17
AI Technical Summary
The existing annular particle migration simulation device fails to effectively consider the migration distribution of rock chip particles in the drilled pipe section in the blind tube-punching pipe completion method, resulting in the collapse and blockage of the well wall, affecting the oil well production.
A simulating device for the annular particle migration is designed, including a completion simulation system, an infusion system and a data acquisition system, which simulates the structure of the blind tube-punched tube by carrying sand fluid, and observes and analyzes rock chips. The accumulation and blockage of particles in the punched pipe section are used to evaluate the permeability index using pressure difference and flow data to understand the migration and distribution rules of annular particles.
Through the transparent observation window of the simulated wellbore, the data acquisition system can stably obtain pressure difference and flow data, analyze the blockage, reduce drilling operation costs, and increase the annular space under the blind tube-punching pipe completion mode Understanding the particle migration and distribution rules effectively solves the problems of well wall collapse and blockage.
Smart Images

Figure CN115508257B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of oil production, and in particular to an annular space particle migration simulation device and a use method thereof. Background Art
[0002] During the drilling process of the horizontal production layer, when a large number of sand and mudstone interlayers (with a high mud content) are encountered, the mudstone layer is hydrated and complex hydration occurs. The hydration changes the rock mechanical properties of the mudstone layer, reduces the rock strength, and easily causes the wellbore to shrink or collapse and fall off, making it difficult to lower the completion tail pipe, affecting the timeliness and safety of oil operations.
[0003] At present, oil fields adopt horizontal well completion and exploitation methods, mainly including blind pipe-screen pipe completion method and blind pipe-perforated pipe completion method. The former is mainly used in sandstone layers due to its shortcomings such as thin sand retaining layer, easy invasion of fine sand and blockage to reduce production, and short effective period, but not suitable for fine sandstone layers and mudstone layers. The latter can be applied to the above-mentioned mudstone production layers, but when the well wall collapses and blocks fall off, the collapsed mudstone layer particles will accumulate in the blind pipe section, and then migrate to the perforated pipe section under the impact of formation fluid (water-oil mixture), accumulate on the perforated pipe section, block the perforated pipe section, and cause the oil well production to decrease.
[0004] The current annulus particle migration simulation device only considers the migration and distribution of sand and gravel carried by formation fluid in the annulus formed by the screen section and the simulated wellbore, but does not consider the migration and distribution of rock cuttings particles accumulated in the blind pipe section in the blind pipe-perforated pipe completion method in the annulus formed by the perforated pipe section and the simulated wellbore. This has become a problem that needs to be solved urgently. Summary of the invention
[0005] An object of the present invention is to provide an annular space particle migration simulation device, which can simulate the migration and distribution of rock cutting particles in the annular space under the condition of a horizontal well completion method based on a blind pipe-perforated pipe.
[0006] To achieve this object, the present invention adopts the following technical solutions:
[0007] An annular particle migration simulation device includes a completion simulation system, a fluid infusion system and a data acquisition system, wherein the completion simulation system includes a simulated wellbore and a tail pipe, wherein the tail pipe is located in the simulated wellbore and includes a blind pipe section and a perforated pipe section, wherein the perforated pipe section is connected to the end face of the outlet end of the simulated wellbore, and the blind pipe section is closed at one end away from the perforated pipe section; the fluid infusion system is configured to transport sand-carrying fluid into the simulated wellbore; and the data acquisition system is configured to monitor the pressure difference between the two ends of the simulated wellbore and the flow rate of the sand-carrying fluid entering the simulated wellbore.
[0008] Optionally, the fluid infusion system includes a fluid storage tank and a diaphragm pump which are connected in sequence, and the outlet of the diaphragm pump is connected to the inlet of the simulated wellbore.
[0009] Optionally, the infusion system further includes a throttle valve and a throttle tube, the throttle valve is respectively connected to the outlet of the diaphragm pump, the inlet of the simulated wellbore and the inlet of the throttle tube through a three-way valve, and the outlet of the throttle tube is connected to the liquid storage tank.
[0010] Optionally, the data acquisition system includes a differential pressure sensor, a flow meter and a data collector, the two measuring points of the differential pressure sensor are respectively located at two ends of the simulated wellbore, the flow meter is located between the diaphragm pump and the simulated wellbore, and the data collector is connected to the differential pressure sensor and the flow meter, and can send the signals collected by the flow meter and the differential pressure sensor to a computer.
[0011] Optionally, the data acquisition system further includes a pressure sensor, and the pressure sensor is electrically connected to the data acquisition device.
[0012] Optionally, the simulated wellbore includes a barrel and a barrel cover, and a transparent observation window is provided at a position of the barrel corresponding to the perforated pipe section.
[0013] Optionally, the well completion simulation system further comprises a waste liquid tank, which is connected to the outlet of the simulated wellbore.
[0014] Another object of the present invention is to provide a method for using an annulus particle migration simulation device, which can simulate the migration and distribution of rock cuttings particles in the annulus during the production process in a horizontal well completion method based on a blind pipe-perforated pipe.
[0015] To achieve this object, the present invention adopts the following technical solutions:
[0016] The method for using the annular space particle migration simulation device is implemented using the annular space particle migration simulation device, and comprises the following steps:
[0017] configuring the sand-carrying fluid;
[0018] configuring rock cuttings particles and loading them into the simulated wellbore;
[0019] The sand-carrying fluid is allowed to enter the simulated wellbore to impact the rock cuttings particles, and the accumulation and blockage of the rock cuttings particles in the perforated pipe section are observed.
[0020] Another object of the present invention is to provide a method for using an annulus particle migration simulation device, which can simulate the migration and distribution of rock cuttings particles in the annulus during the completion process in a horizontal well completion method based on a blind pipe-perforated pipe.
[0021] To achieve this purpose, the present invention adopts the following technical scheme: configuring the sand-carrying fluid;
[0022] configuring the rock cuttings particles;
[0023] After mixing the configured rock cuttings particles with the configured sand-carrying fluid, the fluid infusion system is controlled to input them into the simulated wellbore together, and the accumulation and blockage of the rock cuttings particles in the perforated pipe section are observed. Optionally, in the above-mentioned method of use, the blockage of the rock cuttings particles in the perforated pipe section is evaluated by the permeability index r, assuming that the initial permeability is k o , the permeability at the end is k5, then the formula for the permeability index is:
[0024]
[0025] The beneficial effects of the present invention are:
[0026] The annular particle migration simulation device proposed in the present invention simulates an actual horizontal well with a simulated wellbore, simulates an actual pumping pipe under a blind-pipe-perforated pipe completion mode with a tail pipe in the form of a blind-pipe-perforated pipe, simulates formation fluid with a sand-carrying fluid, and transports the sand-carrying fluid into the simulated wellbore through a fluid infusion system. Under the action of the sand-carrying fluid, rock cuttings particles are driven to move in the simulated wellbore. Since the position of the simulated wellbore corresponding to the perforated pipe section is transparent, it is convenient to observe the accumulation of rock cuttings particles in the perforated pipe section. At the same time, after the pressure difference and flow rate obtained by the data acquisition system are stable, the blockage of the perforated pipe section by rock cuttings particles can be analyzed, so as to conveniently summarize the annular particle migration distribution law under the blind-pipe-perforated pipe completion mode, so as to reduce the drilling operation cost.
[0027] The method for using the annular space particle migration simulation device proposed in the present invention fully considers the complexity of the formation, simulates the annular space migration distribution of the rock cuttings particles accumulated in the blind pipe section during the production process, and makes the sand-carrying fluid impact the rock cuttings particles accumulated in the blind pipe section. After the pressure difference and flow rate obtained by the data acquisition system are stable, the accumulation of the rock cuttings particles in the perforated pipe section is observed from outside the simulated wellbore. At the same time, the blockage of the rock cuttings particles in the perforated pipe section can be analyzed according to the pressure difference and flow rate changes, so as to obtain the annular space particle migration distribution law during the production process.
[0028] Another method for using an annular space particle migration simulation device proposed in the present invention simulates the annular space migration distribution of rock cuttings particles during the completion process, so that the rock cuttings particles are mixed with the sand-carrying fluid and then enter the annulus together. After the pressure difference and flow rate obtained by the data acquisition system are stable, the accumulation of rock cuttings particles in the perforated pipe section is observed from outside the simulated wellbore. At the same time, the blockage of rock cuttings particles in the perforated pipe section is analyzed according to the pressure difference and flow rate changes, thereby obtaining the annular space particle migration distribution law during the completion process. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a structural schematic diagram of the annular space particle migration simulation device provided by the present invention;
[0030] In the figure: 10, completion simulation system; 11, simulated wellbore; 12, tail pipe; 121, blind pipe section; 122, perforated pipe section; 13, waste liquid tank; 20, infusion system; 21, liquid storage tank; 22, diaphragm pump; 23, throttle valve; 24, throttle tube; 30, data acquisition system; 31, flow meter; 32, differential pressure sensor; 33, pressure sensor; 34, data acquisition device; 4, computer. DETAILED DESCRIPTION
[0031] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only parts related to the present invention, rather than all structures, are shown in the accompanying drawings.
[0032] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0033] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0034] In the description of this embodiment, the terms "upper", "lower", "right", etc., directions or positional relationships are based on the directions or positional relationships shown in the drawings, and are only for the convenience of description and simplification of operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.
[0035] Embodiment 1:
[0036] The present embodiment provides an annulus particle migration simulation device, including a completion simulation system for simulating a horizontal well completion method of a blind pipe-perforated pipe and a fluid infusion system for conveying sand-carrying fluid (the sand-carrying fluid simulates formation fluid) into the completion simulation system. By observing the migration and distribution of cuttings particles in the annulus in the completion simulation system, it is convenient to summarize the annulus particle migration distribution law under the blind pipe-perforated pipe completion method, and then apply it to the actual production process.
[0037] refer to Figure 1 As shown, the annular particle migration simulation device of the present invention includes a fluid infusion system 20 , a well completion simulation system 10 and a data acquisition system 30 .
[0038] The fluid infusion system 20 is used to provide sand-carrying fluid to the completion simulation system 10, and includes a fluid storage tank 21 and a diaphragm pump 22 that are connected in sequence. The fluid storage tank 21 is used to store the sand-carrying fluid configured with reference to the viscosity or density of the formation fluid in actual working conditions. The diaphragm pump 22 is used to pump the sand-carrying fluid into the completion simulation system 10, and its pump pressure and displacement are adjustable.
[0039] The completion simulation system 10 includes a simulated wellbore 11, a tail pipe 12 and a waste liquid tank 13. The simulated wellbore 11 is a hollow column, and its two ends are respectively connected to the outlet of the diaphragm pump 22 and the inlet of the waste liquid tank 13. The simulated wellbore 11 is fixed by a clamping device to ensure that the simulated wellbore 11 is structurally stable when impacted by the sand-carrying fluid. The tail pipe 12 is located inside the simulated wellbore 11 and is coaxially arranged with the simulated wellbore 11. An annulus is formed between the tail pipe 12 and the simulated wellbore 11. The tail pipe 12 includes a blind pipe section 121 and a perforated pipe section 122, wherein the perforated pipe section 122 is connected to the outlet end of the simulated wellbore 11, and the blind pipe section 121 is closed at one end away from the perforated pipe section 122 (i.e., close to the inlet end of the simulated wellbore 11).
[0040] The data acquisition system 30 is configured to monitor the differential pressure at both ends of the simulated wellbore 11 and the flow data of the sand-carrying fluid entering the simulated wellbore 11, and specifically includes a differential pressure sensor 32, a flow meter 31 and a data acquisition device 34, wherein the two measuring points of the differential pressure sensor 32 are respectively located at both ends of the simulated wellbore 11, for monitoring the differential pressure at both ends of the simulated wellbore 11.
[0041] The model of the differential pressure sensor 32 in this embodiment is MS-111. The working principle of the differential pressure sensor 32 is that the measured pressure directly acts on the diaphragm of the sensor, causing the diaphragm to produce a micro-displacement proportional to the water pressure, causing the capacitance value of the differential pressure sensor 32 to change, and using an electronic circuit to detect this change, and convert and output a standard measurement signal of the corresponding pressure. It is also possible to respectively set pressure gauges at both ends of the simulated wellbore 11, and obtain the pressure difference at both ends of the simulated wellbore 11 by calculating the difference between the two pressure gauges; the flow meter 31 is located between the diaphragm pump 22 and the simulated wellbore 11, and is used to measure the flow rate of the sand-carrying liquid. The flow meter 31 and the differential pressure sensor 32 are respectively connected to the data acquisition device 34. The analog signals output by the flow meter 31 and the differential pressure sensor 32 are converted by the data acquisition device 34 into digital signals that can be processed by the computer 4 and then sent to the data acquisition software configured on the computer 4, and the data is stored on the computer 4 for subsequent analysis. The data acquisition device 34 can be a flow acquisition card, model PCI-1716L.
[0042] The simulated wellbore 11 includes a barrel and a barrel cover. The barrel is provided with a transparent observation window at least at the position corresponding to the perforated pipe section 122 or is made of a transparent material as a whole, so as to observe the accumulation of rock cuttings particles in the annulus in real time. For example, the barrel can be made of transparent plexiglass, and its light transmittance and pressure resistance meet the test requirements. It can be understood that the observation can be carried out through manual on-site observation or through a camera. The barrel cover can be made of metal and is located at both ends of the barrel and is detachably connected to the barrel to facilitate the filling of rock cuttings particles into the annulus. The barrel covers located at both ends of the barrel are connected to the infusion system 20 and the waste liquid tank 13 through pipe joints respectively.
[0043] The tail pipe 12 can be made of iron material, wherein the blind pipe section 121 is a smooth pipe, and the perforated pipe section 122 is perforated according to the actual tail pipe 1290 holes / foot and is arranged spirally on the pipe wall of the perforated pipe section 122.
[0044] The infusion system 20 also includes a throttle valve 23 and a throttle tube 24. The throttle valve 23 is connected to the outlet of the diaphragm pump 22, the inlet of the simulated wellbore 11 and the inlet of the throttle tube 24 through a three-way valve. The outlet of the throttle tube 24 is connected to the liquid storage tank 21. When the flow rate of the sand-carrying liquid is too large and exceeds the carrying capacity of the simulated wellbore 11, the throttle valve 23 can be used to allow the excess sand-carrying liquid to be returned to the liquid storage tank 21 through the throttle tube 24. A pressure sensor 33 is also installed between the throttle valve and the simulated wellbore 11. The pressure sensor 33 is also connected to the data acquisition device 34, which can be used to intuitively judge the pressure change and ensure that the test is carried out safely and smoothly.
[0045] Embodiment 2:
[0046] The present invention also includes a method for using the annular space particle migration simulation device, which is used to observe the migration and distribution pattern of the rock cuttings particles accumulated in the blind pipe section 121 in the annular space during the production process.
[0047] Before the test, the rock cuttings particles configured in proportion to the formation sand particle size test results are loaded into the simulated wellbore 11, and then the sand-carrying fluid is configured. The sand-carrying fluid enters the simulated wellbore 11 under the suction action of the diaphragm pump 22. After the rock cuttings particles migrate in the blind pipe section and the perforated pipe section, the waste liquid is discharged into the waste liquid tank 13. During the migration process, the flow meter 31 and the pressure difference sensor 32 monitor the migration situation, and the data acquisition device 34 collects various types of data and transmits them to the computer 4 for data processing.
[0048] The movement trajectory of the cuttings particles in the completion simulation system 10 is as follows: the sand-carrying fluid enters the annulus of the blind pipe section 121 from the wellhead of the simulated wellbore 11. During the flow of the sand-carrying fluid, the cuttings particles accumulated in the blind pipe section 121 migrate toward the perforated pipe section 122. A portion of the cuttings particles enter the perforated pipe section 122 through the holes opened in the perforated pipe section 122, and then flow out from the outlet of the perforated pipe section 122 through the outlet of the simulated wellbore 11. Another portion of the cuttings particles accumulate in the annulus of the perforated pipe section 122 and gradually block the holes on the perforated pipe section 122.
[0049] The specific steps are as follows:
[0050] (1) Clean the entire well completion simulation system 10 with clean water and remove the bubbles in the simulated wellbore 11;
[0051] (2) preparing a sand-carrying liquid, loading it into the liquid storage tank 21 or directly preparing it in the liquid storage tank 21, wherein the sand-carrying liquid is an oil-water mixture, and the viscosity may be 5.2 mPa.s;
[0052] (3) configuring rock cuttings particles. Multiple groups of rock cuttings particles with different components and / or different particle sizes can be configured according to different stratum gravel degrees to study the effect of mud content on the migration of rock cuttings particles.
[0053] (4) loading rock cuttings into the simulated wellbore 11. The amount of rock cuttings can be reduced proportionally based on the size of the simulated wellbore 11 according to the amount of rock cuttings caused by wellbore shrinkage or collapse during actual production.
[0054] (5) Turn on the diaphragm pump 22 and pump the sand-carrying fluid into the simulated wellbore 11 to observe the accumulation and blockage of the rock cuttings particles in the perforated pipe section 122; the pumping frequency of the diaphragm pump 22 is adjusted according to the rated flow rate of the sand-carrying fluid required for the test, so that the initial flow rate of the sand-carrying fluid entering the simulated wellbore 11 is the same as the rated flow rate. The rated flow rate can be calculated based on the average daily production of multiple production wells statistically collected at the oil field site, and then calculated based on the size of the simulated wellbore 11;
[0055] Multiple rated flow rates can be obtained according to the flow rates at different oil field sites. By observing the accumulation and blockage of rock cuttings particles in the perforated pipe section 122 at different flow rates, it can be used to study the accumulation and blockage rules caused by the migration of annular particles at different flow rates;
[0056] (6) Clean the entire annular particle migration simulation device for next use.
[0057] Different flow rates of the sand-carrying fluid, different sizes of the rock cuttings particles, and different mud contents of the rock cuttings particles will all lead to different laying lengths of the rock cuttings particles on the perforated pipe section. The migration and accumulation patterns of the rock cuttings particles on the perforated pipe section can be obtained by length comparison. During the test, the flow meter 31 and the pressure difference sensor 32 collect the flow value and the pressure difference value in real time through the data acquisition device 34. As the sand-carrying fluid continues to enter the simulated wellbore 11, the rock cuttings accumulate in the annulus and block the perforated pipe section 122. The pressure difference and flow rate tend to be stable (the data fluctuates up and down by no more than 5%), and it can be determined that blockage has occurred.
[0058] Specifically, the blockage of the perforated pipe section can be evaluated by the ratio of the permeability change to the initial permeability (defined as the permeability index r in the present invention). Assuming that the initial permeability is k0 and the final permeability is k5, the formula of the permeability index is:
[0059]
[0060] The permeability formula is
[0061]
[0062] Where Q represents the flow rate of fluid through the porous medium per unit time, u represents the viscosity of the fluid, L represents the length of the porous medium, and A represents the cross-sectional area of the fluid through the porous medium.
[0063] Embodiment three:
[0064] The present invention also includes a method for using the annular space particle migration simulation device, which is used to observe the migration and distribution law of rock cutting particles in the annular space during the simulated well completion process.
[0065] What is different from the second embodiment is that the rock cuttings particles are not put into the simulated wellbore 11 in advance. Instead, the configured rock cuttings particles are added to the liquid storage tank 21 after the configuration is completed, fully mixed with the sand-carrying fluid, and then enter the simulated wellbore 11 together with the sand-carrying fluid. In contrast, an agitator with a motor can be set in the liquid storage tank 21 to ensure that the sand-carrying fluid and the rock cuttings particles are always mixed.
[0066] The movement trajectory of the cuttings particles in the completion simulation system 10 is as follows: the cuttings particles fully mixed with the sand-carrying fluid enter the annulus of the blind pipe section 121 from the wellhead of the simulated wellbore 11. During the flow of the sand-carrying fluid, a part of the cuttings particles migrate to the perforated pipe section 122, a part of the cuttings particles enter the perforated pipe section 122 through the holes opened in the perforated pipe section 122, and then flow out from the outlet of the perforated pipe section 122 through the outlet of the simulated wellbore 11, and another part of the cuttings particles accumulate in the annulus of the perforated pipe section 122 and gradually block the holes on the perforated pipe section 122.
[0067] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the protection scope of the present invention. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.
Claims
1. A method for using an annular particle migration simulation device, wherein: The annular space particle migration simulation device comprises: A well completion simulation system (10), the well completion simulation system (10) comprising a simulated wellbore (11) and a tail pipe (12), the tail pipe (12) being located in the simulated wellbore (11) and comprising a blind pipe section (121) and a perforated pipe section (122), the perforated pipe section (122) being connected to the outlet end of the simulated wellbore (11), the blind pipe section (121) being closed at one end away from the perforated pipe section (122), and the position of the simulated wellbore (11) corresponding to the perforated pipe section (122) being transparent; A fluid delivery system (20) configured to deliver sand-carrying fluid into the simulated wellbore (11); A data acquisition system (30) is configured to monitor the pressure difference between the two ends of the simulated wellbore (11) and the flow rate of the sand-carrying fluid entering the simulated wellbore (11); The tail pipe (12) is located in the simulated wellbore (11) and is coaxially arranged with the simulated wellbore (11), and an annulus is formed between the tail pipe (12) and the simulated wellbore (11); It is characterized by comprising the following steps: configuring the sand-carrying fluid; Disposing rock cuttings particles and loading them into the simulated wellbore (11); Controlling the fluid delivery system (20) to deliver the sand-carrying fluid to the simulated wellbore (11), so that the sand-carrying fluid enters the simulated wellbore (11) to impact the rock cuttings particles, and observing the accumulation and migration distribution of the rock cuttings particles in the perforated pipe section (122); The sand-carrying fluid enters the annulus of the blind pipe section (121) from the wellhead of the simulated wellbore (11). During the flow of the sand-carrying fluid, the rock cuttings particles accumulated in the blind pipe section (121) migrate toward the perforated pipe section (122). A portion of the rock cuttings particles enter the perforated pipe section (122) through the holes opened in the perforated pipe section (122), and then flow out from the outlet of the perforated pipe section (122) through the outlet of the simulated wellbore (11). Another portion of the rock cuttings particles accumulate in the annulus of the perforated pipe section (122) and gradually block the holes on the perforated pipe section (122).
2. The method for using the annular particle migration simulation device according to claim 1, characterized in that: The liquid infusion system (20) comprises a liquid storage tank (21) and a diaphragm pump (22) which are connected in sequence, and the outlet of the diaphragm pump (22) is connected to the inlet of the simulated wellbore (11).
3. The method for using the annular particle migration simulation device according to claim 2, characterized in that: The infusion system (20) further comprises a throttle valve (23) and a throttle tube (24); the throttle valve (23) is respectively connected to the outlet of the diaphragm pump (22), the inlet of the simulated wellbore (11) and the inlet of the throttle tube (24) through a three-way valve; the outlet of the throttle tube (24) is connected to the liquid storage tank (21).
4. The method for using the annular particle migration simulation device according to claim 1, characterized in that: The annular space particle migration simulation device also includes a computer (4); the data acquisition system (30) includes a differential pressure sensor (32), a flow meter (31) and a data acquisition device (34); the two measuring points of the differential pressure sensor (32) are respectively located at two ends of the simulated wellbore (11); the flow meter (31) is located between the infusion system (20) and the simulated wellbore (11); the data acquisition device (34) is connected to the differential pressure sensor (32) and the flow meter (31) and can send the signals collected by the flow meter (31) and the differential pressure sensor (32) to the computer (4).
5. The method for using the annular particle migration simulation device according to claim 4, characterized in that: The data acquisition system (30) further comprises a pressure sensor (33), wherein the pressure sensor (33) is connected to the data acquisition device (34).
6. The method for using the annular particle migration simulation device according to claim 1, characterized in that: The simulated wellbore (11) comprises a barrel and a barrel cover, and the barrel is made of transparent organic glass.
7. The method for using the annular particle migration simulation device according to claim 1, characterized in that: The well completion simulation system (10) further comprises a waste liquid tank (13), wherein the waste liquid tank (13) is connected to the outlet of the simulated wellbore (11).
8. A method for using an annular particle migration simulation device, wherein: The annular space particle migration simulation device comprises: A well completion simulation system (10), the well completion simulation system (10) comprising a simulated wellbore (11) and a tail pipe (12), the tail pipe (12) being located in the simulated wellbore (11) and comprising a blind pipe section (121) and a perforated pipe section (122), the perforated pipe section (122) being connected to the outlet end of the simulated wellbore (11), the blind pipe section (121) being closed at one end away from the perforated pipe section (122), and the position of the simulated wellbore (11) corresponding to the perforated pipe section (122) being transparent; A fluid delivery system (20) configured to deliver sand-carrying fluid into the simulated wellbore (11); A data acquisition system (30) is configured to monitor the pressure difference between the two ends of the simulated wellbore (11) and the flow rate of the sand-carrying fluid entering the simulated wellbore (11); The tail pipe (12) is located in the simulated wellbore (11) and is coaxially arranged with the simulated wellbore (11), and an annulus is formed between the tail pipe (12) and the simulated wellbore (11); It is characterized by comprising the following steps: configuring the sand-carrying fluid; Configuration of rock cuttings particles; After mixing the configured rock cuttings particles with the configured sand-carrying fluid, controlling the fluid infusion system (20) to input them together into the simulated wellbore (11), and observing the accumulation and blockage of the rock cuttings particles in the perforated pipe section (122); The rock cuttings particles are fully mixed with the sand-carrying fluid and enter the annulus above the blind pipe section (121) from the wellhead of the simulated wellbore (11). During the flow of the sand-carrying fluid, a portion of the rock cuttings particles migrate toward the perforated pipe section (122).
9. The method for using the annular particle migration simulation device according to claim 8, characterized in that: The liquid infusion system (20) comprises a liquid storage tank (21) and a diaphragm pump (22) which are connected in sequence, and the outlet of the diaphragm pump (22) is connected to the inlet of the simulated wellbore (11).
10. The method for using the annular particle migration simulation device according to claim 9, characterized in that: The infusion system (20) further comprises a throttle valve (23) and a throttle tube (24); the throttle valve (23) is respectively connected to the outlet of the diaphragm pump (22), the inlet of the simulated wellbore (11) and the inlet of the throttle tube (24) through a three-way valve; the outlet of the throttle tube (24) is connected to the liquid storage tank (21).
11. The method for using the annular particle migration simulation device according to claim 8, characterized in that: The annular space particle migration simulation device also includes a computer (4); the data acquisition system (30) includes a differential pressure sensor (32), a flow meter (31) and a data acquisition device (34); the two measuring points of the differential pressure sensor (32) are respectively located at two ends of the simulated wellbore (11); the flow meter (31) is located between the infusion system (20) and the simulated wellbore (11); the data acquisition device (34) is connected to the differential pressure sensor (32) and the flow meter (31) and can send the signals collected by the flow meter (31) and the differential pressure sensor (32) to the computer (4).
12. The method for using the annular particle migration simulation device according to claim 11, characterized in that: The data acquisition system (30) further comprises a pressure sensor (33), wherein the pressure sensor (33) is connected to the data acquisition device (34).
13. The method for using the annular particle migration simulation device according to claim 8, characterized in that: The simulated wellbore (11) comprises a barrel and a barrel cover, and the barrel is made of transparent organic glass.
14. The method for using the annular particle migration simulation device according to claim 8, characterized in that: The well completion simulation system (10) further comprises a waste liquid tank (13), wherein the waste liquid tank (13) is connected to the outlet of the simulated wellbore (11).
15. The method for using the annular particle migration simulation device according to claim 8, characterized in that: The clogging of the rock cuttings particles in the perforated pipe section (122) is evaluated by the permeability index r. Assuming that the initial permeability is k0 and the final permeability is k5, the formula for the permeability index r is: