A whole installation displacement method of substation protection control upgrading and reconstruction panel cabinet

By using temporary transition overhead steel frame foundations in substations to protect the overall displacement of control panels, the problems of multiple power outages and cable cleaning during substation upgrades and renovations were solved, achieving efficient and low-cost equipment replacement and cable trench maintenance.

CN115603211BActive Publication Date: 2026-06-19西北水利水电工程有限责任公司

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
西北水利水电工程有限责任公司
Filing Date
2022-11-15
Publication Date
2026-06-19

AI Technical Summary

Technical Problem

Existing technologies require multiple power outages with long durations during the upgrading and renovation of substation protection and control equipment, which affects production and daily life. Furthermore, it is difficult to efficiently replace old equipment and clean cables.

Method used

A temporary transitional overhead steel frame foundation was used to erect multiple protection control cabinets to be replaced on it, and then the entire cabinets were moved to the permanent foundation channel steel via slide rails. Combined with the removal of cables and wiring debugging, the overall displacement of the cabinets was achieved.

Benefits of technology

It reduced power outage time, lowered construction costs, simplified operating procedures, avoided the tangling of old and new cables, and allowed for cable trench repair during the replacement of old control panels, laying the foundation for subsequent work.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115603211B_ABST
    Figure CN115603211B_ABST
Patent Text Reader

Abstract

This invention belongs to the field of substation equipment upgrade and renovation technology, specifically involving a method for the overall installation and displacement of substation protection and control upgrade and renovation panels. The method involves placing multiple protection and control panels to be replaced with their backs to the cable trench on a temporary transition overhead steel frame foundation; positioning and splicing adjacent panels; removing the original cables from the cable supports and placing them on both sides of the cable trench bottom; repairing or replacing the cable supports; placing the control cables to be laid on the repaired or replaced cable supports, then connecting, verifying, and debugging the cables to be replaced in the respective protection and control panels; immediately putting the replacement panels into operation while the original protection and control panels are decommissioned; removing the original panels; cleaning and repairing the cable trench; and finally moving the entire replacement protection and control panel onto the cleaned foundation channel steel of the permanent protection panel, thus completing the upgrade and renovation process. This invention features short switching time, simple operation, is not limited by narrow terrain, and ensures maximum power generation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the technical field of substation protection and control equipment upgrade and renovation, specifically relating to a method for the overall installation and displacement of substation protection and control upgrade and renovation panels. Background Technology

[0002] Substations requiring upgrades are generally old, with aging equipment, cramped protection rooms, and complex environments. Current upgrade methods involve dismantling and replacing the old protection control panels one by one, requiring a power outage for each panel replacement. This results in numerous and prolonged outages, severely impacting production and daily life in the affected areas, and affecting power generation for the owners of the substations. To minimize these issues during upgrades, the process must be time-constrained, with minimal power outages and, in special cases, uninterrupted operation. This necessitates ensuring the continued operation of existing protection control panels, minimizing power outages for each new device, and maintaining power supply to unaffected areas. Once the old and new equipment are operational, the old protection control panels and cables are removed, and the new equipment is moved from the temporary steel frame to the permanent foundation steel, completing the upgrade. Summary of the Invention

[0003] This invention provides a method for the overall installation and displacement of substation protection and control upgrade and renovation panels. The purpose is to provide a method for the overall displacement of panels that is simple to construct in complex environments, has low cost, and can minimize the impact of construction on production, daily life, and power supply.

[0004] To achieve the above objectives, the technical solution adopted by the present invention is as follows:

[0005] A method for the overall installation and displacement of substation protection and control upgrade and renovation panels includes the following steps.

[0006] Step 1: Construct a temporary transitional overhead steel frame foundation;

[0007] Step 2: Erect multiple protection control panels to be replaced on a temporary transition overhead steel frame foundation, with the back of the protection control panels to be replaced facing the foundation channel steel of the permanent protection panel;

[0008] Step 3: Connect the adjacent protection control panel cabinets to be replaced;

[0009] Step 4: Remove all original cables from the cable brackets and place them on both sides of the bottom of the cable trench;

[0010] Step 5: Repair or replace the cable brackets;

[0011] Step 6: Place the control cables to be laid on the repaired or replaced cable brackets, and then connect, verify, and debug the control cables to be laid to the protection control panel to be replaced.

[0012] Step 7: De-energize and take out the operation of the original protection panels one by one, and put the corresponding protection control panels to be replaced into operation one by one, until all the original protection panels in the entire row are taken out and all the protection control panels to be replaced are put into operation.

[0013] Step 8: Remove the entire row of existing protection panels and clean and repair the cable trench;

[0014] Step 9: Connect and debug the multiple protection control cabinets to be replaced on the temporary transition overhead steel frame foundation, and then move them as a whole to the cleaned foundation channel steel of the permanent protection cabinet through the temporary transition overhead steel frame foundation.

[0015] The aforementioned overhead steel frame foundation is a linear integrated structure consisting of multiple control cabinet seats with an operating space at the bottom; each control cabinet seat includes a base and a slide rail; the slide rail for moving multiple protection control panels to be replaced into the cable trench as a whole is fixedly connected to the rear side of the base facing the cable trench.

[0016] The platform is a rectangular frame consisting of four columns, two upper crossbeams, two lower crossbeams, one upper purlin, and two lower purlins, with an open rear top. The two upper crossbeams, two lower crossbeams, one upper purlin, and two lower purlins are all fixedly connected to the adjacent columns, and one upper purlin is horizontally connected to the top of the two columns on the front side.

[0017] It also includes a detachable purlin; the detachable purlin is horizontally arranged and detachably connected to the top of the two columns on the rear side; the detachable purlin is made of angle iron.

[0018] The columns, upper crossbeam, lower crossbeam, upper purlin, lower purlin, and slide rails are all made of angle iron.

[0019] The length of the column is 18-30cm.

[0020] The base also includes multiple diagonal braces; the multiple diagonal braces are respectively fixedly connected to the left and right sides and the front.

[0021] The slide rail includes two sets of slide rails; the two sets of slide rails are respectively fixedly connected to both sides of the rear side of the base.

[0022] Each set of slide rails is an integral structure of a right triangle made of three angle irons; the slide rail is set perpendicular to the rear side of the base, and the height of one right-angled side is the same as the height of the base, and the right-angled side is fixedly connected to the rear side of the base.

[0023] The connection between the top of the slide rail and the top of the base is arc-shaped.

[0024] Beneficial effects:

[0025] (1) The overall installation displacement of the substation protection and control upgrade and renovation panel using the present invention not only has a short power outage time and low cost in the relevant area, but also is simple to operate and is not limited by complex and narrow terrain.

[0026] (2) The overall installation displacement of the substation protection and control upgrade panel using the present invention will not cause the problem of old and new cables to become tangled and difficult to clean.

[0027] (3) The overall installation displacement of the substation protection and control upgrade panel can be carried out by using the present invention. While replacing the old panel, the cable trench and its internal aging equipment can also be painted and repaired, laying the foundation for the continuous and stable operation of the substation.

[0028] (4) The use of temporary transition overhead steel frame foundation in this invention not only makes it convenient to connect, test and move multiple protection control cabinets to be replaced as a whole, but also the temporary transition overhead steel frame foundation has a simple structure, is easy to obtain materials, has a low cost and can be reused.

[0029] The above description is merely an overview of the technical solution of the present invention. In order to better understand the technical means of the present invention and to implement it in accordance with the contents of the specification, the preferred embodiments of the present invention are described in detail below with reference to the accompanying drawings. Attached Figure Description

[0030] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0031] Figure 1 This is a flowchart of the present invention.

[0032] Figure 2 This is a schematic diagram of the temporary transitional overhead steel frame foundation of the present invention in use.

[0033] Figure 3 This is a schematic diagram of the control cabinet base structure of the present invention.

[0034] Figure 4 This is a schematic diagram of the control cabinet base of the present invention when the detachable purlin is not connected.

[0035] Figure 5 This is a partial enlarged view of the connection between the top of the slide rail and the top of the base in this invention.

[0036] In the diagram: 1. Base; 2. Slide rail; 3. Upper crossbeam; 4. Lower crossbeam; 5. Column; 6. Upper purlin; 7. Lower purlin; 8. Diagonal brace; 9. Control cable; 10. Foundation channel steel of permanent protection cabinet; 11. Protection control cabinet to be replaced; 12. Removable purlin. Detailed Implementation

[0037] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the scope of protection of the present invention.

[0038] Example 1:

[0039] according to Figures 1-5 The method for overall installation and displacement of substation protection and control upgrade and renovation panels, as shown, includes the following steps:

[0040] Step 1: Construct a temporary transitional overhead steel frame foundation;

[0041] Step 2: Erect multiple protection control panels 11 to be replaced on a temporary transition overhead steel frame foundation, with the back of the protection control panels 11 to be replaced facing the foundation channel steel 10 of the permanent protection panel;

[0042] Step 3: Connect the adjacent protection control panel 11 to be replaced;

[0043] Step 4: Remove all original cables from the cable brackets and place them on both sides of the bottom of the cable trench;

[0044] Step 5: Repair or replace the cable brackets;

[0045] Step 6: Place the control cable 9 to be laid on the repaired or replaced cable bracket, and then connect the control cable 9 to the protection control panel 11 to be replaced, and then connect, verify and debug it.

[0046] Step 7: De-energize and take out the operation of the original protection panels one by one, and put the corresponding protection control panels 11 to be replaced into operation one by one, until all the original protection panels in the row are taken out and all the protection control panels 11 to be replaced are put into operation.

[0047] Step 8: Remove the entire row of existing protection panels and clean and repair the cable trench;

[0048] Step 9: Connect and debug the multiple protection control cabinets 11 to be replaced on the temporary transition overhead steel frame foundation, and then move them as a whole to the cleaned foundation channel steel 10 of the permanent protection cabinet.

[0049] In practical use, the technical solution of this invention is used to carry out the overall displacement of the protection and control panel to be replaced in the substation protection and control upgrade and renovation. This not only results in short power outage time and low cost in the relevant areas, but also simple operation and is not limited by complex or narrow terrain.

[0050] The overall displacement of the substation protection and control cabinets using this invention avoids the problems of old and new cables becoming tangled and difficult to clean. Furthermore, while replacing the old cabinets, it also allows for the painting and repair of cable trenches and related aging equipment inside, laying the foundation for the continuous and stable operation of the substation.

[0051] The use of an overhead steel frame foundation in this invention not only facilitates the connection, testing, and overall movement of multiple protection control cabinets to be replaced, but also makes the overhead steel frame foundation simple in structure, easy to obtain materials, inexpensive, and reusable.

[0052] Example 2:

[0053] according to Figures 2-4 The method for overall installation and displacement of substation protection and control upgrade and renovation panels shown differs from Embodiment 1 in that: the overhead steel frame foundation is a one-piece structure with an operating space at the bottom, consisting of multiple control cabinet seats; each control cabinet seat includes a base 1 and a slide rail 2; the slide rail 2, used for the overall movement of multiple protection and control panels 11 to be replaced toward the foundation channel steel 10 of the permanent protection panel, is fixedly connected to the rear side of the base 1 facing the foundation channel steel 10 of the permanent protection panel.

[0054] In practical use, the number of control panel seats set in the overhead steel frame foundation can be determined according to the number of old panels that need to be replaced during the substation protection and control upgrade.

[0055] Multiple protection control panels 11 to be replaced are placed one by one on the base 1 of the control cabinet seat. The length and width of the base 1 match the length and width of the protection control panels 11 to be replaced. Each protection control panel 11 to be replaced faces away from the foundation channel steel 10 of the permanent protection panel, so that the multiple protection control panels 11 to be replaced are arranged in a straight line according to the order after they are placed on the foundation channel steel 10 of the permanent protection panel, and the adjacent protection control panels 11 to be replaced are connected together. After each protection control panel 11 to be replaced is connected and debugged, the multiple protection control panels 11 to be replaced are moved as a whole from the slide 2 to the foundation channel steel 10 of the permanent protection panel. The whole process is simple and convenient.

[0056] Example 3:

[0057] according to Figure 2 and Figure 4 The method for overall installation and displacement of the substation protection and control upgrade and renovation panel shown differs from Embodiment 2 in that: the base 1 is a rectangular frame consisting of four columns 5, two upper crossbeams 3, two lower crossbeams 4, one upper purlin 6, and two lower purlins 7, with an open upper rear section; the two upper crossbeams 3, two lower crossbeams 4, one upper purlin 6, and two lower purlins 7 are all fixedly connected to the adjacent columns 5, and one upper purlin 6 is horizontally connected to the top of the two columns 5 on the front side.

[0058] In actual use, the base 1 adopts the above technical solution. After the protection control panel 11 to be replaced is placed on the base 1, there is an operating space between the bottom of the protection control panel 11 to be replaced and the ground, which facilitates the connection and debugging of the protection control panel 11 to be replaced and the cable.

[0059] The base 1 adopts a frame structure, which is simple in structure and easy to manufacture while ensuring that it has the required load-bearing capacity.

[0060] Example 4:

[0061] according to Figure 2 and Figure 3 The method for overall installation and displacement of the substation protection and control upgrade and renovation panel shown differs from Embodiment 3 in that it also includes a detachable purlin 12; the detachable purlin 12 is horizontally arranged and detachably connected to the top of the two columns 5 on the rear side; the detachable purlin 12 is made of angle iron.

[0062] In practical use, the detachable purlin 12, when the protection control panel 11 to be replaced is placed on the base 1, not only improves the load-bearing capacity of the base 1, but also makes the placement of the protection control panel 11 to be replaced more stable. When it is necessary to move the entire row of protection control panel 11 to the foundation channel steel 10 of the permanent protection panel, the detachable purlin 12 can be removed, making it easy to move the entire row of protection control panel 11 to be replaced.

[0063] The detachable purlin 12 is made of angle iron, which meets the strength requirements and is easy to source.

[0064] Example 5:

[0065] according to Figures 2-4 The method for overall installation and displacement of the substation protection and control upgrade and renovation panel shown differs from Embodiment 3 in that the column 5, upper beam 3, lower beam 4, upper purlin 6, lower purlin 7 and slide rail 2 are all made of angle iron.

[0066] In actual use, the column 5, upper crossbeam 3, lower crossbeam 4, upper purlin 6, lower purlin 7 and slide rail 2 adopt a technical solution made of angle iron, which meets the strength requirements during use and is convenient to obtain materials and has a low cost.

[0067] Example 6:

[0068] according to Figures 2-4 The method for overall installation and displacement of the substation protection and control upgrade and renovation panel shown is different from that in Embodiment 3 or Embodiment 4 in that the length of the column 5 is 18-30cm.

[0069] In practical use, the length of column 5 is 18-30cm, which not only facilitates the connection and testing of the lower cables of the protection control panel 11 to be replaced, but also saves costs. If the length of column 5 is too large, although it is convenient for the cable connection and testing of the protection control panel 11 to be replaced, it will cause inconvenience for the subsequent row of protection control panel 11 to be replaced. If the length of column 5 is too small, although it is convenient for the row of protection control panel 11 to be replaced, it will be inconvenient for cable connection and testing.

[0070] Example 7:

[0071] according to Figures 2-4 The method for overall installation and displacement of the substation protection and control upgrade and renovation panel shown is different from Embodiment 3 in that: the base 1 also includes multiple diagonal braces 8; the multiple diagonal braces 8 are respectively fixedly connected to the left and right sides and the front.

[0072] In practical use, the diagonal braces 8 effectively enhance the load-bearing capacity of the protection control panel 11 to be replaced, preventing accidental losses caused by insufficient load-bearing capacity of the base 1. The specific number of diagonal braces 8 can be determined based on the actual weight of the protection control panel 11 to be replaced.

[0073] In this embodiment, three diagonal braces 8 are provided, and the three diagonal braces 8 are respectively fixedly connected at an angle to the rectangular frame on the left, right and front sides.

[0074] Example 8:

[0075] according to Figures 2-4 The method for overall installation and displacement of the substation protection and control upgrade and renovation panel shown is different from the second embodiment in that: the slide rail 2 includes two sets of slide rails; the two sets of slide rails are respectively fixedly connected to the two sides of the rear side of the base 1.

[0076] In actual use, the slide 2 adopts the above technical solution, which can easily move multiple connected protection control cabinets 11 to be replaced in a row onto the foundation channel steel 10 of the permanent protection cabinet.

[0077] Example 9:

[0078] according to Figures 2-4 The method for overall installation and displacement of the substation protection and control upgrade and renovation panel shown is different from Embodiment 8 in that: each set of slide rails is an integral structure of a right triangle made of three angle irons; the slide rail is set perpendicular to the rear side of the base 1, and the height of one right-angled side is the same as the height of the base 1, and the right-angled side is fixedly connected to the rear side of the base 1.

[0079] In practical use, the slide rail adopts the above technical solution, which can not only perform the load-bearing function well, but also facilitate the movement of multiple connected protection control panel cabinets 11 to be replaced in a row onto the foundation channel steel 10 of the permanent protection panel cabinet.

[0080] Example 10:

[0081] according to Figure 5 The method for overall installation and displacement of the substation protection and control upgrade and renovation panel shown is different from Embodiment Nine in that the connection between the top of the slide rail and the top of the base 1 is arc-shaped.

[0082] In actual use, because the connection between the top of the slide rail and the top of the base 1 adopts an arc-shaped technical solution, when multiple connected protective control panels 11 to be replaced are moved in a row to the foundation channel steel 10 of the permanent protective panel, there will be no problem of the protective control panels 11 to be replaced or the cables being scratched by sharp corners, ensuring the smooth progress of the overall displacement.

[0083] Where there is no conflict, those skilled in the art can combine the relevant technical features in the above examples according to the actual situation to achieve the corresponding technical effects. Specific details of the various combinations will not be elaborated here.

[0084] It should be noted that all directional indications (such as up, down, left, right, front, back, etc.) in the embodiments of the present invention are only used to explain the relative positional relationship and movement of each component in a certain specific posture (as shown in the figure). If the specific posture changes, the directional indication will also change accordingly.

[0085] Furthermore, the use of terms such as "first" and "second" in this invention is for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated. Therefore, a feature defined with "first" or "second" may explicitly or implicitly include at least one of those features.

[0086] The above description is merely a preferred embodiment of the present invention. The present invention is not limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features disclosed herein. Any simple modifications, equivalent variations, and alterations made to the above embodiments based on the technical essence of the present invention shall still fall within the scope of the present invention.

Claims

1. A method for overall installation displacement of a substation protection and control upgrade panel cabinet, characterized in that: Includes the following steps Step 1: Construct a temporary transitional overhead steel frame foundation; the overhead steel frame foundation is a one-piece structure with an operating space at the bottom, consisting of multiple control cabinet seats; each control cabinet seat includes a base (1) and a slide rail (2); the slide rail (2) is fixedly connected to the rear side of the base channel steel (10) of the base seat (1) facing the permanent protection cabinet, for multiple protection control cabinets (11) to move as a whole to the foundation channel steel (10) of the permanent protection cabinet; Step 2: Erect multiple protection control panels (11) to be replaced on a temporary transition overhead steel frame foundation, with the protection control panels (11) to be replaced facing away from the foundation channel steel (10) of the permanent protection panel. Step 3: Connect the adjacent protection control panel (11) to be replaced; Step 4: Remove all original cables from the cable brackets and place them on both sides of the bottom of the cable trench; Step 5: Repair or replace the cable brackets; Step 6: Place the control cable (9) to be laid on the repaired or replaced cable bracket, and then use the bottom operating space of the temporary transition overhead steel frame foundation to connect the control cable (9) to be laid to the protection control panel (11) to be replaced, and then connect, verify and debug. Step 7: De-energize and take out the operation of the original protection panel cabinets one by one, and put the corresponding protection control panel cabinets (11) to be replaced into operation one by one until all the original protection panel cabinets in the row are taken out and all the protection control panel cabinets (11) to be replaced into operation. Step 8: Remove the entire row of existing protection panels and clean and repair the cable trench; Step 9: Connect and debug the multiple protection control cabinets (11) to be replaced on the temporary transition overhead steel frame foundation, and move them as a whole to the foundation channel steel (10) of the cleaned permanent protection cabinet through the temporary transition overhead steel frame foundation.

2. A method for overall installation displacement of a substation protection and control upgrade bay as claimed in claim 1, characterized in that: The platform (1) is a rectangular frame consisting of four columns (5), two upper crossbeams (3), two lower crossbeams (4), one upper purlin (6) and two lower purlins (7), with an open rear top. The two upper crossbeams (3), two lower crossbeams (4), one upper purlin (6) and two lower purlins (7) are all fixedly connected to the adjacent columns (5), and one upper purlin (6) is horizontally connected to the top of the two columns (5) on the front side.

3. A method of overall installation displacement of a substation protection and control upgrade bay as claimed in claim 2, characterized in that: It also includes a detachable purlin (12); the detachable purlin (12) is horizontally arranged and detachably connected to the top of the two columns (5) on the rear side; the detachable purlin (12) is made of angle iron.

4. A method for overall installation displacement of a substation protection and control upgrade bay as claimed in claim 2, characterized in that: The column (5), upper crossbeam (3), lower crossbeam (4), upper purlin (6), lower purlin (7) and slide (2) are all made of angle iron.

5. A method for the overall installation and displacement of a substation protection and control upgrade panel as described in claim 2 or 3, characterized in that: The length of the column (5) is 18-30cm.

6. A method for overall installation displacement of a substation protection and control upgrade bay as claimed in claim 2, characterized in that: The base (1) also includes multiple diagonal braces (8); the multiple diagonal braces (8) are respectively fixedly connected to the left and right sides and the front.

7. A method for overall installation displacement of a substation protection and control upgrade bay as recited in claim 1, characterized by: The slide (2) includes two sets of slide rails; the two sets of slide rails are fixedly connected to the two sides of the rear side of the base (1).

8. The method for overall installation and displacement of substation protection and control upgrade and renovation panels as described in claim 7, characterized in that: Each set of slide rails is an integral structure of a right triangle made of three angle irons; the slide rail is set perpendicular to the rear side of the base (1), and the height of one right-angled side is the same as the height of the base (1), and the right-angled side is fixedly connected to the rear side of the base (1).

9. The overall installation displacement method for substation protection and control upgrade and renovation panels as described in claim 8, characterized in that: The connection between the top of the slide rail and the top of the base (1) is arc-shaped.