Combined construction method suitable for super-large section loess tunnel
By combining the five-step single-side wall pilot tunnel method and the single-core soil three-stage seven-step method with the construction technology of extra-large cross-section loess tunnels, the problem of insufficient construction safety of extra-large cross-section loess tunnels has been solved, and the construction safety and progress have been improved.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- LANZHOU JIAOTONG UNIV
- Filing Date
- 2023-10-16
- Publication Date
- 2026-07-24
AI Technical Summary
Existing traditional tunnel construction methods suffer from insufficient construction safety, slow construction progress, and unstable surrounding rock when excavating loess tunnels with extra-large cross sections. In particular, existing methods cannot guarantee construction safety and progress for loess tunnels with extra-large cross sections.
The five-step single-side wall pilot tunnel method and the single-core soil three-stage seven-step method were adopted. The construction method was selected according to different loess conditions. By reducing the excavation span of the left area, reserving core soil and early support, combined with initial support, temporary support and secondary lining, a stable stress structure was formed, which controlled the deformation of the surrounding rock and improved the construction safety.
This approach ensures both construction safety and efficiency in large-section loess tunnels, while simplifying the construction process, reducing surrounding rock deformation, shortening the construction period, and enhancing both construction progress and safety.
Smart Images

Figure CN117266868B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of construction technology for extra-large cross-section tunnels, and in particular to a combined construction method applicable to extra-large cross-section loess tunnels. Background Technology
[0002] With the rapid development of loess tunnel construction in central and western China, traditional two-lane tunnels can no longer meet traffic demands, leading to the emergence of more and more three-lane and four-lane tunnels. However, increasing the number of lanes inevitably increases tunnel width, resulting in a larger excavation area and the creation of extra-large cross-section loess tunnels. Furthermore, due to the characteristics of loess, such as well-developed vertical fissures and low shear strength, tunnel excavation in loess strata often triggers sudden soil collapse and excessive deformation of the support structure. This is especially true for tunnels with an excavation cross-sectional area greater than 100 m². 2 The tunnel has a high risk of construction safety.
[0003] Currently, the double-sidewall pilot tunnel method is commonly used in China for the excavation of extra-large cross-section loess tunnels. The double-sidewall pilot tunnel method divides the tunnel cross-section into several parts, excavating them in stages. A cross-section constructed using the double-sidewall pilot tunnel method is shown in the attached figure. Figure 1 As shown in Table 1, the construction sequence is as follows.
[0004] Table 1 Construction sequence of traditional double-sided wall pilot tunnel method
[0005]
[0006]
[0007] It is evident that the existing double-sided wall pilot tunnel method requires the continuous erection and dismantling of temporary steel frames during construction. Furthermore, the connection process of the support structure of each small section is highly demanding, with numerous and complex procedures that are prone to mutual interference. In particular, the limited working space hinders mechanized construction, resulting in slow construction progress and difficulty in controlling the actual deformation of each procedure.
[0008] Currently, another method for tunnel construction is the traditional single-sidewall pilot tunnel method. This method divides the tunnel cross-section into four parts and excavates each part separately. The construction cross-section is shown in the attached figure. Figure 2 As shown in Table 2, the construction sequence is as follows.
[0009] Table 2 Construction Sequence of Traditional Single-Side Wall Pilot Tunnel Method
[0010]
[0011] Although the traditional single-side wall pilot tunnel method has relatively simple construction steps, it is not suitable for the excavation of loess tunnels with extra-large cross sections, as the surrounding rock is unstable and safety cannot be guaranteed.
[0012] Furthermore, the three-stage, seven-step method, due to its advantages of rapid construction and low cost, is also widely used in the excavation of loess tunnels. The existing three-stage, seven-step method uses an arc-shaped pilot tunnel excavation with core soil retention as its basic model, divided into upper, middle, and lower stages and seven excavation faces. The excavation and support of each part are carried out in parallel and staggered manner along the longitudinal direction of the tunnel. The cross-section of the three-stage, seven-step method is shown below. Figure 3 As shown in Table 3, the construction sequence is as follows.
[0013] Table 3. Construction Sequence of the Three-Step, Seven-Step Method
[0014]
[0015] It is evident that the existing three-stage seven-step method divides the tunnel cross-section into several sections for excavation and then performs initial support after excavation. However, due to the large number of excavation steps, the initial support closes into a ring relatively late, failing to form a complete load-bearing structure in time, which has a certain impact on the safety of construction. This is especially true for the excavation of loess tunnels with extra-large cross-sections, where the surrounding rock is unstable and safety cannot be guaranteed.
[0016] Therefore, it is evident that the existing traditional single-sidewall pilot tunnel method, double-sidewall pilot tunnel method, and three-step seven-stage method all have inconveniences and defects, and urgently need further improvement. The question is how to create a new combined construction method suitable for extra-large cross-section loess tunnels, allowing for the selection of different construction methods based on varying loess conditions, ensuring both construction safety and reliability, thereby overcoming the problems existing in current traditional tunnel construction methods. Summary of the Invention
[0017] The technical problem to be solved by the present invention is to provide a combined construction method applicable to loess tunnels with extra-large cross sections, which allows for the selection of different construction methods according to different loess conditions, meets the construction requirements of loess tunnels with extra-large cross sections, ensures both construction safety and construction safety, and overcomes the shortcomings of existing tunnel construction methods.
[0018] To address the aforementioned technical problems, this invention provides a combined construction method suitable for loess tunnels with extra-large cross-sections. It employs a double-sidewall pilot tunnel method, and further includes a five-step single-sidewall pilot tunnel method and a single-core soil three-step seven-step method, sequentially converted from the double-sidewall pilot tunnel method. The applicable conditions for the five-step single-sidewall pilot tunnel method are: elastic modulus greater than 50 MPa, moisture content less than 21%, and density greater than 1.50 g / cm³. 3 And less than 1.68 g / cm 3 The applicable conditions for the single-core soil three-step seven-stage method are: elastic modulus greater than 70 MPa, moisture content less than 15%, and density greater than 1.60 g / cm³. 3 And less than 1.76 g / cm 3 .
[0019] Further improvements include the following steps in the five-step single-sidewall guide pit method:
[0020] S1. Divide the soil within the tunnel excavation section into the upper left region, the lower left region, the upper right region, and the lower right region. Excavate the upper left region and simultaneously provide initial support for the upper half of the left side wall after excavation of the upper left region, as well as temporary support for its right side. The bottom width of the upper left region is less than 50% of the width of the entire tunnel excavation section.
[0021] S2. Excavate the lower left area, and simultaneously provide initial support for the lower half of the left side wall after excavation of the lower left area, as well as temporary support for the right side section; wherein, the top width of the lower left area is equal to the bottom width of the upper left area;
[0022] S3. Excavate the upper right area, leaving core soil. The bottom of the core soil is less than 40% of the width of the entire tunnel excavation section. At the same time, provide initial support for the upper half of the right side wall after the excavation of the upper right area.
[0023] S4. Excavate the core soil;
[0024] S5. Excavate the lower right area and simultaneously provide initial support for the lower half of the right side wall after the excavation of the lower right area;
[0025] S6. Remove the central partition wall formed by the temporary support, and then carry out the secondary lining of the full-section inverted arch, the filling of the full-section inverted arch, and the secondary lining of the full-section arch wall in sequence to complete the construction of the extra-large section loess tunnel.
[0026] Further improvements include the following: in the five-step single-side-wall pilot tunnel method, the bottom width of the upper left area accounts for 40-45% of the total tunnel excavation cross-section width, the bottom of the core soil accounts for 34-40% of the total tunnel excavation cross-section width, and the height of the core soil accounts for 22-30% of the total tunnel excavation cross-section width.
[0027] Further improvements include: in step S1, the excavation of the pilot tunnel in the upper left area is 4-6m ahead of the excavation of the pilot tunnel in the lower left area in step S2, and 12-14m ahead of the excavation of the pilot tunnel in the upper right area in step S3; in step S3, the excavation of the pilot tunnel in the upper right area is 2-4m ahead of the core soil excavation in step S4; in step S4, the core soil excavation is 1-3m ahead of the excavation of the pilot tunnel in the lower right area in step S5; and the distance between each excavation face remains unchanged during construction, with an excavation advance of 1m in each step.
[0028] Further improvements include the following steps in the single-core soil three-step seven-stage method:
[0029] T1. Divide the soil in the tunnel excavation section into three steps: upper, middle and lower. First, excavate the arc-shaped pilot tunnel of the upper step, and at the same time, provide initial support for the arc-shaped section after the excavation of the upper step.
[0030] T2. Excavate the left side area of the middle bench, and simultaneously provide initial support for the left side section of the middle bench after the left side area is excavated; wherein, the bottom width of the left side area of the middle bench is less than 25% of the width of the entire tunnel excavation section;
[0031] T3. Excavate the right side area of the middle step, and simultaneously provide initial support for the right side section of the middle step after the right side area is excavated; wherein, the bottom width of the right side area of the middle step is equal to the bottom width of the left side area of the middle step;
[0032] T4. Excavation of the core soil for the upper and middle steps;
[0033] T5. Excavate the left side area of the lower step, and at the same time provide initial support for the left side section of the lower step after the excavation of the left side area; wherein, the top width of the left side area of the lower step is smaller than the bottom width of the left side area of the middle step.
[0034] T6. Excavate the right side area of the lower step and provide initial support for the right side section of the lower step after excavation; wherein, the top width of the right side area of the lower step is equal to the top width of the left side area of the lower step.
[0035] T7. Excavate the central area of the lower step and provide initial support for the invert arch section of the lower step;
[0036] T8. The construction of the extra-large cross-section loess tunnel is completed by sequentially carrying out the secondary lining of the full-section inverted arch, the filling of the full-section inverted arch, and the secondary lining of the full-section arch wall.
[0037] In a further improvement, the bottom width of the left side region of the middle step in the single-core soil three-step seven-step method accounts for 15-25% of the total tunnel excavation cross-section width, and the bottom width of the left side region of the lower step accounts for 10-15% of the total tunnel excavation cross-section width. The dividing line between the middle step and the lower step is the tunnel arch waist.
[0038] Further improvements include: in step T1, the arc-shaped pilot tunnel excavated on the upper step is 4-6m ahead of the pilot tunnel excavated on the left side of the middle step in step T2; in step T2, the pilot tunnel excavated on the left side of the middle step is 2-4m ahead of the pilot tunnel excavated on the right side in step T3; in step T3, the pilot tunnel excavated on the right side of the middle step is 2-4m ahead of the core soil excavation in step T4; in step T4, the core soil excavation is carried out simultaneously with the pilot tunnel excavated on the left side of the lower step in step T5; in step T5, the pilot tunnel excavated on the left side of the middle step is 2-4m ahead of the pilot tunnel excavated on the right side in step T6; in step T6, the pilot tunnel excavated on the right side of the lower step is 2-4m ahead of the pilot tunnel excavated in the central area of the lower step in step T7; and the distance between each excavation face remains unchanged during construction, with an excavation advance of 1m in each step.
[0039] Further improvements were made, and the initial support parameters for each step are as follows: HW175 steel arch frame is used, with a longitudinal spacing of 50cm, φ8 steel mesh is hung at 20cm×20cm, and C25 concrete is sprayed at 30cm.
[0040] The temporary support parameters are as follows: I20a type steel arch frame is used, with a longitudinal spacing of 50cm, φ6 steel mesh is hung at 20cm×20cm, and C25 concrete is sprayed at 22cm.
[0041] The support parameters for the secondary lining are: main reinforcement φ25, distribution reinforcement φ14, and sprayed C35 concrete 70cm. Further improvements include the following steps: in both the five-step single-sidewall pilot tunnel method and the single-core soil three-step seven-step method, anchor pipes are installed at the arch waist, upper arch waist, and lower arch waist after the initial cross-section support. The anchor pipes are φ60*5mm, 400cm long, and have a vertical outward inclination angle of 30-45°.
[0042] Further improvements include an excavation width of less than 20m, an excavation height of less than 14m, and an excavation cross-sectional area of less than 190m² for the extra-large cross-section loess tunnel. 2 .
[0043] With this design, the present invention has at least the following advantages:
[0044] The five-step single-sidewall pilot tunnel method in this invention improves upon the traditional single-sidewall pilot tunnel method. By reducing the span of the excavation in the left area, it reduces the settlement of the arch crown and the deformation of the surrounding rock during the excavation of the left side. Furthermore, by reserving core soil during the excavation of the upper right area, it can better control the deformation of the surrounding rock. It is suitable as an alternative to the double-sidewall pilot tunnel method and as a conversion method between the double-sidewall pilot tunnel method and the single-core soil three-stage seven-step method. It can ensure the construction safety of extra-large cross-section loess tunnels, ensure the construction progress, and improve construction efficiency.
[0045] The single-core soil three-stage seven-step method in this invention improves upon the traditional three-stage seven-step method. Based on the principles of "less disturbance, early support, frequent measurement, and tight closure," it simplifies the construction process of the core soil, reduces disturbance to the surrounding rock, and helps to give full play to the self-supporting capacity of the surrounding rock. It also shortens the distance between the invert arch and the tunnel face, allowing the support to close into a ring earlier, which helps to control the deformation of the surrounding rock, improves the stress on the support structure, and enables the support and surrounding rock to enter a good working state. This further shortens the construction period and ensures the construction safety of the extra-large cross-section loess tunnel. Attached Figure Description
[0046] The above is merely an overview of the technical solution of the present invention. In order to better understand the technical means of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
[0047] Figure 1 This is a schematic diagram of the construction cross-section of the existing double-sided wall pilot tunnel method.
[0048] Figure 2 This is a schematic diagram of the construction cross-section of the existing traditional single-sidewall pilot tunnel method.
[0049] Figure 3 This is a schematic diagram of the construction cross-section of the existing three-stage, seven-step method.
[0050] Figure 4 This is a cross-sectional comparison diagram of the traditional single-sidewall guide tunnel method and the five-step single-sidewall guide tunnel method of this application.
[0051] Figure 5 This is a schematic diagram of the lining structure of the five-step single-side wall guide tunnel method of the present invention.
[0052] Figure 6 This is a diagram showing the excavation step distance and excavation sequence of the five-step single-sidewall pilot tunnel method of the present invention.
[0053] Figure 7 This is a schematic diagram of the initial support section structure of the five-step single-side wall pilot tunnel method of the present invention. Figure 5 (Section 1-1)
[0054] Figure 8 These are schematic diagrams of the finite element calculation models for the traditional single-sidewall pilot hole method, the five-step single-sidewall pilot hole method, and the double-sidewall pilot hole method. Figure 8 a represents the traditional single-sidewall pilot tunnel method. Figure 8 b represents the five-step single-side-wall pilot tunnel method. Figure 8 c represents the double-sided wall guide tunnel method.
[0055] Figure 9 These are settlement convergence curves for the traditional single-sidewall pilot tunnel method, the five-step single-sidewall pilot tunnel method, and the double-sidewall pilot tunnel method. Figure 9 a represents the traditional single-sidewall pilot tunnel method. Figure 9 b represents the five-step single-side-wall pilot tunnel method. Figure 9 c represents the double-sided wall guide tunnel method.
[0056] Figure 10 This is a tunnel cross-sectional displacement cloud map (m) of the five-step single-side wall pilot tunnel method of the present invention.
[0057] Figure 11 It is a radar image (MPa) of the steel arch stress of the tunnel section using the traditional single-side-wall pilot tunnel method, the five-step single-side-wall pilot tunnel method, and the double-side-wall pilot tunnel method.
[0058] Figure 12 It is a stress cloud diagram (Pa) of the steel arch frame of the traditional single-side wall guide tunnel method and the five-step single-side wall guide tunnel method.
[0059] Figure 13This is a schematic diagram of the installation points for the arch crown settlement and horizontal convergence observation points and the steel arch strain gauges, using the five-step single-side wall guide pit method of this invention.
[0060] Figure 14 This is a numerical simulation of the arch settlement and horizontal convergence curves using the five-step single-side-wall pilot tunnel method of this invention.
[0061] Figure 15 This is a graph showing the settlement and horizontal convergence curves of the arch crown during on-site monitoring using the five-step single-side wall pilot tunnel method of this invention.
[0062] Figure 16 The stress radar diagram (MPa) of the steel arch frame was obtained by numerical simulation and on-site monitoring at section I using the five-step single-side wall guide pit method of this invention.
[0063] Figure 17 The stress radar diagram (MPa) of the steel arch frame was obtained by numerical simulation and on-site monitoring at section II using the five-step single-side wall guide pit method of this invention.
[0064] Figure 18 The stress radar diagram (MPa) of the steel arch frame was obtained by numerical simulation and on-site monitoring at section III using the five-step single-side wall guide pit method of this invention.
[0065] Figure 19 This paper describes the influence of elastic modulus on the stress of steel arch frame in tunnel surrounding rock when using the five-step single-side wall pilot tunnel method of this invention for numerical simulation analysis.
[0066] Figure 20 This paper describes the influence of elastic modulus on the settlement and horizontal convergence of the tunnel surrounding rock arch when using the five-step single-side wall pilot tunnel method of this invention for numerical simulation analysis.
[0067] Figure 21 This paper describes the influence of density on the stress of the steel arch frame in the surrounding rock of a tunnel when using the five-step single-side wall pilot tunnel method of this invention for numerical simulation analysis.
[0068] Figure 22 This paper describes the influence of density on the settlement of the tunnel arch and horizontal convergence when using the five-step single-side wall pilot tunnel method of this invention for numerical simulation analysis.
[0069] Figure 23 This is a cross-sectional comparison diagram between the traditional three-step seven-stage method and the single-core soil three-step seven-stage method of this application.
[0070] Figure 24 This is a schematic diagram of the lining structure of the single-core soil three-stage seven-step method of the present invention.
[0071] Figure 25 This is a diagram showing the excavation step distance and excavation sequence of the single-core soil three-step seven-step method of the present invention.
[0072] Figure 26 This is a schematic diagram of the finite element calculation model of the traditional three-step seven-step method and the single-core soil three-step seven-step method. Figure 26 A represents the traditional three-step, seven-stage method. Figure 26 b represents the three-stage, seven-step method for single-core soil.
[0073] Figure 27 These are settlement convergence curves for the traditional three-step seven-stage method and the single-core soil three-step seven-stage method. Figure 27 A represents the traditional three-step, seven-stage method. Figure 27 b represents the three-stage, seven-step method for single-core soil.
[0074] Figure 28 This is a tunnel cross-sectional displacement cloud map (m) based on the single-core soil three-step seven-step method of this invention.
[0075] Figure 29 It is a radar image (MPa) of the steel arch stress of the tunnel section in the traditional three-stage seven-step method and the single-core soil three-stage seven-step method.
[0076] Figure 30 This is the stress cloud diagram (Pa) of the steel arch frame of the single-core soil three-step seven-step method of the present invention.
[0077] Figure 31 This is a numerical simulation of the crown settlement and horizontal convergence curves using the single-core soil three-step seven-step method of this invention.
[0078] Figure 32 This is a graph showing the crown settlement and horizontal convergence curves obtained by applying the single-core soil three-step seven-step method of this invention for on-site monitoring.
[0079] Figure 33 The stress radar map (MPa) of the steel arch frame was obtained by numerical simulation and field monitoring at section I using the single-core soil three-step seven-step method of this invention.
[0080] Figure 34 The stress radar map (MPa) of the steel arch frame was obtained by numerical simulation and field monitoring at section II using the single-core soil three-step seven-step method of this invention.
[0081] Figure 35 The stress radar map (MPa) of the steel arch frame was obtained by numerical simulation and field monitoring at section III using the single-core soil three-step seven-step method of this invention.
[0082] Figure 36 This invention relates to the influence of elastic modulus on the stress of steel arch frame in tunnel surrounding rock when using the single-core soil three-step seven-step method for numerical simulation analysis.
[0083] Figure 37This invention relates to the influence of elastic modulus on the settlement and horizontal convergence of the tunnel surrounding rock arch when using the single-core soil three-step seven-step method for numerical simulation analysis.
[0084] Figure 38 This invention relates to the influence of density on the stress of steel arch frames in tunnel surrounding rock when using the single-core soil three-step seven-step method for numerical simulation analysis.
[0085] Figure 39 This invention relates to the influence of density on the settlement of the tunnel surrounding rock arch and horizontal convergence when using the single-core soil three-step seven-step method for numerical simulation analysis. Detailed Implementation
[0086] Example 1
[0087] This embodiment first improves the traditional single-sidewall pilot tunnel method, transforming it into a five-step single-sidewall pilot tunnel method that can be quickly converted from the double-sidewall pilot tunnel method. This five-step single-sidewall pilot tunnel method can meet the excavation conditions of extra-large cross-section loess tunnels, ensuring the construction safety of extra-large cross-section loess tunnels. (See attached...) Figure 4 As shown, in the traditional single-sidewall pilot tunnel method, the central diaphragm is located at half the width of the excavation tunnel, meaning the bottom width of the upper left area accounts for 50% of the total tunnel excavation cross-section width. For extra-large cross-section tunnels, this results in an excessively large excavation cross-section, easily leading to significant settlement of the arch and deformation of the surrounding rock. This application addresses this shortcoming with a five-step single-sidewall pilot tunnel method, as detailed in the following embodiment.
[0088] The extra-large cross-section loess tunnel described in this embodiment has a maximum excavation width of 17.89m, a maximum excavation height of 12.05m, and an excavation cross-sectional area of 183m². 2 .
[0089] This embodiment of the five-step single-side-wall guide tunnel method first improves the position of the central diaphragm wall, as shown in the attached figure. Figure 4 As shown, this embodiment first shortens the width of the left excavation area, such as making the bottom width of the upper left area only 45% of the total tunnel excavation cross-section width. This reduces the span of the left excavation area, decreases crown settlement, and avoids surrounding rock deformation. Another improvement of this embodiment is that, based on shortening the left excavation distance, the distance of the central partition wall to the right pilot tunnel cross-section is inevitably increased. To prevent large settlement of the right crown, a core soil step is reserved during the excavation of the upper right pilot tunnel to control the deformation of the surrounding rock and ensure the construction safety of the extra-large cross-section loess tunnel.
[0090] See attached document Figure 5 As shown, the more specific implementation steps of the five-step single-sidewall guide tunnel method in this embodiment include:
[0091] S1. Divide the soil within the tunnel excavation section into upper left region A, lower left region B, upper right region C, and lower right region D. Excavate upper left region A, and simultaneously provide initial support I for the upper half of the left side wall after excavation of upper left region A, and temporary support II for its right side section; wherein, the bottom width of upper left region A accounts for 40-45% of the width of the entire tunnel excavation section.
[0092] S2. Excavate the lower left area B, and simultaneously provide initial support I for the lower half of the left side wall after the excavation of the lower left area B, and temporary support II for its right side section; wherein, the top width of the lower left area B is equal to the bottom width of the upper left area A.
[0093] S3. Excavate the upper right area C, leaving core soil C1. The bottom of the core soil C1 accounts for 34-40% of the width of the entire tunnel excavation section, and the height of the core soil C1 accounts for 22-30% of the width of the entire tunnel excavation section. At the same time, perform initial support I on the upper half of the right side wall after the excavation of the upper right area C.
[0094] S4. Excavate the core soil C1;
[0095] S5. Excavate the lower right area D, and simultaneously provide initial support I to the lower half of the right side wall after the excavation of the lower right area D;
[0096] S6. Remove the central partition wall formed by temporary support II, and then carry out the secondary lining of the full-section inverted arch III, the filling of the full-section inverted arch IV, and the secondary lining of the full-section arch wall III in sequence to complete the construction of the extra-large section loess tunnel.
[0097] During the specific construction process, as shown in the attached document... Figure 6 As shown, in step S1, the excavation of the pilot tunnel in the upper left area A precedes the excavation of the pilot tunnel in the lower left area B in step S2 by 4-6m, preferably 5m, and precedes the excavation of the pilot tunnel in the upper right area C in step S3 by 12-14m, preferably 13m; in step S3, the excavation of the pilot tunnel in the upper right area C precedes the excavation of the core soil C1 in step S4 by 2-4m, preferably 3m; in step S4, the excavation of the core soil C1 precedes the excavation of the pilot tunnel in the lower right area D in step S5 by 1-3m, preferably 2m. The excavation advance in each step is 1m, and the distance between each excavation surface remains unchanged during the construction process.
[0098] Furthermore, before implementing step S1 above, there is also a step of constructing the upper part of the tunnel excavation section using a pre-construction guide pipe E. The pre-construction guide pipe E is a φ60cm×5cm pre-construction guide pipe, 350cm long, with a ring spacing of 40cm and a horizontal upward inclination angle of 5-12°.
[0099] In this embodiment, the initial support parameters for each step are as follows: HW175 steel arch frame with a longitudinal spacing of 50cm, 20cm x 20cm φ8 steel mesh, and 30cm of C25 shotcrete. (See attached...) Figure 7 The diagram shows the cross-sectional view of the initial support. The support parameters for temporary support II are: I20a type steel arch frame, longitudinal spacing 50cm, 20cm×20cm φ6 steel mesh, and 22cm of shotcrete C25. The support parameters for secondary lining III are: main reinforcement φ25, distribution reinforcement φ14, and 70cm of shotcrete C35.
[0100] In addition, to further improve the reliability of the support, step S1 also includes the step of constructing two anchor pipes F at the arch waist and upper part of the left side wall upper section after the initial support I, and at the arch waist of the temporary support II; step S2 also includes the step of constructing two anchor pipes F at the lower part of the arch waist of the left side wall lower section after the initial support I, and at the bottom of the temporary support II; step S3 also includes the step of constructing two anchor pipes F at the arch waist and upper part of the right side wall upper section after the initial support I; step S4 also includes the step of constructing two anchor pipes F at the lower part of the arch waist of the right side wall lower section after the initial support I. The anchor pipe F is 400cm long and has a vertical outward inclination angle of 30-45°. The anchor pipe F used on the tunnel sidewall section is a φ60*5mm anchor pipe, and the anchor pipe F used on the temporary support section is a φ42*4mm anchor pipe.
[0101] This embodiment also compares the improved five-step single-sidewall guide tunnel method with the traditional single-sidewall guide tunnel method and double-sidewall guide tunnel method through numerical simulation calculation, on-site monitoring and analysis and indoor tests, and finally determines the applicable conditions of the five-step single-sidewall guide tunnel method.
[0102] (I) Analysis of Numerical Simulation Calculation Methods
[0103] Numerical simulations were performed on the traditional single-side-wall pilot tunnel method, the five-step single-side-wall pilot tunnel method, and the double-side-wall pilot tunnel method to analyze the deformation of the surrounding rock and the stress changes of the steel arch frame during the construction process.
[0104] ① Model Establishment
[0105] Numerical simulation was conducted using finite element method software, with the tracing element method as the modeling approach. To eliminate the influence of boundary effects on the calculation results, the calculation models for all three methods were designed with a longitudinal length of 60m. The surrounding rock of the models was Upper Pleistocene loess, classified as Class V, with the following parameters: elastic modulus 80MPa, Poisson's ratio 0.4, cohesion 35kPa, internal friction angle 29°, and density 1.57g / cm³. 3According to Saint-Venant's principle, stress redistribution caused by excavation only occurs within a range of 3-5 times the excavation width from the center of the tunnel. Therefore, the model was selected with a width of 138m and a height of 133m (burial depth of 60m). The established model is attached. Figure 8 As shown. Among them, Figure 8 'a' represents the finite element calculation model of the traditional single-sidewall pilot tunnel method. Figure 8 b is the finite element calculation model of the five-step single-sidewall pilot tunnel method. Figure 8 c represents the finite element calculation model of the double-sidewall guide tunnel method.
[0106] In this model, the surrounding rock is simulated using the Mohr-Coulomb constitutive model. Both the initial support and secondary lining are simulated using solid elements (C3D8R). The steel reinforcement parameters of the secondary lining are converted into concrete based on the equivalent stiffness principle. The steel arch of the initial support is embedded in the shotcrete using built-in commands. Both the steel arch and the anchor pipes are simulated using beam elements. The model uses the equivalent stiffness principle to simulate the reinforcement effect of the pre-excavated small guide pipes and the base jet grouting piles on the surrounding rock. Due to the disturbance caused by tunnel excavation, the stress in the surrounding rock redistributes, resulting in partial stress release. In the numerical simulation, the method of reducing the elastic modulus of the soil in the excavation area is used to simulate the stress release in the surrounding rock. The surrounding rock density and shear strength indices are obtained from indoor tests at the end of the double-sided pilot tunnel, and are also obtained with reference to the "Specifications for Design of Highway Tunnels" (JTG 3370.1-2018) and relevant existing data.
[0107] ②Results Analysis
[0108] Data on crown settlement, horizontal convergence, and steel arch stress were extracted from a section 5m from the opening of models using the traditional single-sidewall pilot tunnel method, the five-step single-sidewall pilot tunnel method, and the double-sidewall pilot tunnel method. The numerical simulation results were then analyzed. (This 5m section location is consistent with the 5m interval between sections in the field monitoring and analysis methods.)
[0109] like Figure 9 The curves showing the changes in crown settlement and horizontal convergence values as a function of excavation progress for three construction method models are presented. Figure 9 'a' represents the curves showing the changes in crown settlement and horizontal convergence values using the traditional single-sidewall pilot tunnel method. Figure 9 b represents the curves showing the changes in crown settlement and horizontal convergence values using the five-step single-sidewall pilot tunnel method. Figure 9 c represents the curves showing the changes in crown settlement and horizontal convergence values using the double-sidewall pilot tunnel method.
[0110] from Figure 9As can be seen from the traditional single-sidewall pilot tunnel method, the crown settlement gradually increases and then stabilizes, with a maximum settlement of 12.29 cm. The horizontal convergence of the surrounding rock shows a trend of gradually increasing, then decreasing, and then stabilizing, with a maximum value of 6.92 cm and a subsequent convergence of 2.41 cm. The horizontal convergence gradually decreases after the initial support closure in the right lower pilot tunnel excavation phase because the surrounding rock pressure causes the lining to deform outwards, leading to a reduction in horizontal convergence. Figure 9 As shown in b, during the five-step single-sidewall pilot tunnel construction, the arch settlement exhibited a trend of gradually increasing and then stabilizing, with a maximum value of 8.7cm. The curve shows two points of significant increase: before the excavation of the upper left pilot tunnel and after the excavation of the upper right pilot tunnel. Additionally, a sudden increase in settlement occurred around analysis step 60. This was due to the removal of the central diaphragm wall, which altered the original balance between the surrounding rock and the support, leading to a sudden increase in surrounding rock settlement. The trend of horizontal convergence of the surrounding rock was initially increasing, then decreasing, and then stabilizing, with a maximum value of 5cm and a subsequent convergence to 1.1cm. Before the excavation of the lower right pilot tunnel, the horizontal convergence of the surrounding rock continuously increased, and the convergence amplitude increased after the excavation of the upper right pilot tunnel. However, the horizontal convergence subsequently decreased and then stabilized. This was because after the excavation of the lower right pilot tunnel, the initial lining at that section closed into a ring, and the surrounding rock pressure caused the lining to exert a reaction force on the surrounding rock, resulting in a decrease in horizontal convergence. A sudden change also occurred in the convergence descent section, which was caused by the removal of the central diaphragm wall. Figure 9 As shown in section c, during the double-sided wall pilot tunnel construction, the crown settlement and horizontal convergence exhibit similar trends to those of the five-step single-sided wall pilot tunnel method. Crown settlement gradually increases during excavation, reaching a maximum of 7.3 cm. A sudden change occurs during the removal of the central diaphragm. Horizontal convergence gradually increases before the excavation of the upper step of the central wall, reaching a maximum of 5.9 cm. After the excavation of the lower step of the central wall, the initial lining closes into a ring, applying a support reaction force to the surrounding rock, leading to a decrease in horizontal convergence until it stabilizes at a value of 0.51 cm.
[0111] Please refer to the appendix. Figure 10 As shown, the tunnel displacement cloud map of the five-step single-sidewall pilot tunnel method is illustrated. Figure 10 It can be seen that the maximum arch settlement of the tunnel after the completion of the five-step single-side wall pilot tunnel method is 9.11cm.
[0112] According to the Technical Specification for Highway Tunnel Construction (JTGT3660-2020), the measured displacement value should not be greater than the designed reserved deformation amount U0 of the tunnel. The designed reserved deformation amount of this tunnel is 30cm. The calculated maximum displacement of the five-step single-side wall pilot tunnel method is less than U0 / 3, which belongs to the Class III management level, indicating that the surrounding rock is in a stable state.
[0113] Figure 11 The image shows radar plots of steel arch frame stress at different locations along a 5m cross-section for three different construction method models. Figure 11It can be seen that under all three construction methods, the steel arch frame is under pressure, and the force is roughly symmetrically distributed. In the traditional single-side-wall pilot tunnel method, the left arch shoulder experiences the greatest force, while the invert arch experiences less. In the five-step single-side-wall pilot tunnel method, the areas of greatest stress on the steel arch frame are mainly at and above the arch waist, with the two arch shoulders experiencing the greatest stress, exceeding that at the arch crown and arch waist, resulting in a "U"-shaped pressure distribution. Below the arch waist, the middle sections on both sides of the invert arch experience the least stress, while the pressure is greatest at the arch bottom, resulting in a "convex"-shaped pressure distribution. When using the double-side-wall pilot tunnel method, the stress distribution on the steel arch frame below the arch waist is similar to that in the five-step single-side-wall pilot tunnel method, with the arch bottom experiencing greater stress than the sides, resulting in a "convex"-shaped pressure distribution. Above the arch waist, the stress on the steel arch frame gradually increases from the arch crown to the sides, with the greatest stress at the arch waist.
[0114] From again Figure 12 The stress cloud diagrams of the steel arch frame shown in the traditional single-side-wall guide tunnel method and the five-step single-side-wall guide tunnel method show that the maximum stress of the steel arch frame in the traditional single-side-wall guide tunnel method is 181.5 MPa, and the maximum stress of the steel arch frame in the five-step single-side-wall guide tunnel method is 163.6 MPa.
[0115] The "Technical Specification for Highway Tunnel Construction" (JTGT3660-2020) stipulates that the measured stress of the initial support should not exceed the allowable value (235 MPa) by more than 0.8. The ratio of the maximum stress of the steel arch to the yield strength of the steel obtained by the traditional single-sidewall pilot tunnel method is 181.5 / 235 = 0.77, while the ratio of the maximum stress of the steel arch to the yield strength of the steel obtained by the five-step single-sidewall pilot tunnel method is 163.6 / 235 = 0.69. This indicates that the surrounding rock stability obtained by the five-step single-sidewall pilot tunnel method is better than that obtained by the traditional single-sidewall pilot tunnel method.
[0116] Based on the above analysis results, it is evident that the crown settlement and horizontal convergence of the five-step single-sidewall pilot tunnel method of this application are both less than those of the traditional single-sidewall pilot tunnel method, clearly achieving a superior effect. Furthermore, the stress of the steel arch frame in the traditional single-sidewall pilot tunnel method is closer to the specification requirements, and the surrounding rock may become unstable during construction using this method, posing a safety hazard.
[0117] Furthermore, although the crown settlement and horizontal convergence of the five-step single-sidewall pilot tunnel method in this application are greater than those of the double-sidewall pilot tunnel method, exceeding them by 1.4 cm and 0.59 cm respectively, they are both within the range required by the specifications. The stress of the steel arch frame is greater than that of the double-sidewall pilot tunnel method only at the two arch shoulders, exceeding by 45.91 MPa and 37.88 MPa respectively, while the stress at other locations is less than that of the double-sidewall pilot tunnel method, with a maximum reduction of 70 MPa (right arch waist). Moreover, the stress-to-yield strength ratio of the steel also meets the specifications. In terms of construction, the five-step single-sidewall pilot tunnel method has a simpler procedure and does not require frequent removal of temporary supports, making it more advantageous in terms of construction speed and cost compared to the double-sidewall pilot tunnel method. Therefore, compared to the double-sidewall pilot tunnel method, the five-step single-sidewall pilot tunnel method in this application can reduce the stress of the steel arch frame, accelerate the construction progress, and reduce construction costs while controlling the deformation of the surrounding rock, making it feasible for excavation in large-section loess tunnels.
[0118] (II) On-site monitoring and analysis
[0119] To ensure construction safety, a 30m test section was set up when using the five-step single-sidewall pilot tunnel method. Three monitoring sections were established within the test section to monitor surrounding rock deformation and internal forces in the support structure. Each section was equipped with arch crown settlement and horizontal convergence observation points, as well as steel arch strain gauges, to monitor the condition of the surrounding rock and lining. The distribution of the monitoring points on site is as follows: Figure 13 As shown.
[0120] Comparison of numerical simulation calculations and field monitoring data
[0121] Cross-sections at 10m, 15m, and 20m in the numerical simulation model were selected to extract the settlement and horizontal convergence of the surrounding rock arch, as well as the stress values of the steel arch frame. Settlement and horizontal convergence monitoring points were set up at the upper right pilot tunnel of these three cross-sections after excavation, and data were collected. Stress values of the steel arch frame were extracted from stable data after excavation.
[0122] Appendix Figure 14 The figure shows the settlement of the tunnel arch and the horizontal convergence curves during tunnel excavation in the numerical simulation model. Figure 15 The diagram shows the settlement and horizontal convergence curves of the arch crown at the on-site monitoring section after the excavation of the upper right pilot tunnel.
[0123] Depend on Figure 14 It can be seen that the maximum settlement of the arch crown in the three sections of the numerical simulation model is 9cm, the maximum horizontal convergence value is 5.4cm, and it then stabilizes at 2.6cm. The results after the excavation of the pilot tunnel in the upper right section of the three sections in the numerical simulation model are compared with the field monitoring data. Figure 15A comparison reveals that both methods exhibit similar trends in crown settlement and horizontal convergence. The numerically simulated crown settlement ultimately converged to 9cm, less than the maximum value of 12cm observed in the field. The numerically simulated horizontal convergence ultimately stabilized at 2.6cm, less than the maximum value of 3.5cm observed in the field. Through comparison... Figure 13 and Figure 14 It can be seen that the numerical simulation results can accurately reflect the on-site situation.
[0124] Appendix Figure 16 The stress radar diagrams of the steel arch frame, obtained by numerical simulation and field monitoring at section 1 (10m) using the five-step single-side wall guide tunnel method, are shown. Figure 17 The stress radar diagrams of the steel arch frame, obtained by numerical simulation and field monitoring at section II (15m) using the five-step single-side wall guide pit method, are shown. Figure 18 The stress radar diagrams of the steel arch frame obtained by numerical simulation and field monitoring at section III (20m) using the five-step single-sidewall pilot tunnel method are shown. Table 4 below lists the comparison of the average stress values of the steel arch frame obtained by numerical simulation and field monitoring at the three sections.
[0125] Table 4 Comparison of Simulated and Measured Data on Stress in Steel Arch Frames
[0126]
[0127] from Figure 16 , 17 As shown in Table 18, the trends of numerical simulation and field monitoring results are largely consistent in each cross-section. The steel arch frame is under pressure at all locations, and the stress is roughly symmetrically distributed along the tunnel axis. Among them, the areas with the highest stress on the steel arch frame are the arch shoulder, arch crown, and arch waist, while the stress is lowest in the middle of the two inverted arches. Table 4 shows that the data results of numerical simulation and field monitoring are largely consistent, with errors within 20%, indicating that the numerical simulation results can accurately describe the field conditions. Furthermore, it can be concluded that the five-step single-sidewall pilot tunnel method is superior to the traditional single-sidewall pilot tunnel method and the double-sidewall pilot tunnel method in the construction of extra-large cross-section loess tunnels.
[0128] (III) Indoor Testing
[0129] To explore the applicability of the five-step single-sidewall pilot tunnel method, soil samples were collected every 2 meters along a 30m test section for laboratory testing. The moisture content at the sampling points was obtained according to the "Specifications for Geotechnical Testing of Highways" (JTG3430-2020). Simultaneously, numerical simulations were used to analyze the effects of cohesion, internal friction angle, density, and elastic modulus on the stress of the steel arch frame in the tunnel surrounding rock, arch crown settlement, and horizontal convergence. The results are shown in the appendix. Figures 19 to 22 .
[0130] The results show that the elastic modulus and density have significant effects on the stress of the steel arch frame in the tunnel surrounding rock, the settlement of the arch crown, and the horizontal convergence, while the cohesion and internal friction angle have relatively small effects. Therefore, based on indoor experiments and numerical simulations, the applicable range of the five-step single-sidewall pilot tunnel method is further determined to be: elastic modulus greater than 50 MPa, moisture content less than 21%, and density greater than 1.50 g / cm³. 3 And less than 1.68 g / cm 3 .
[0131] Example 2
[0132] This embodiment improves upon the existing three-stage, seven-step method. Based on the New Austrian Tunneling Method's principles of "minimal disturbance, early support, frequent measurement, and tight closure," and considering the favorable surrounding rock conditions of the Zhonghe Tunnel, it proposes a single-core soil three-stage, seven-step construction method. This method further strengthens the control of surrounding rock deformation, improves initial support stress, enables early support closure, shortens the construction period, and is suitable for the excavation of extra-large cross-section loess tunnels, offering high safety. (Appendix) Figure 23 The construction process steps are compared between the traditional three-step, seven-stage method (23a) and the single-core soil three-step, seven-stage method (23b) of this application. From... Figure 23 As can be seen, the single-core soil three-stage seven-step method of this application is an improvement on the traditional three-stage seven-step method. It combines the upper, middle and lower core soils, significantly reducing the construction cross-section, simplifying the construction process, reducing disturbance to the surrounding rock, and shortening the distance between the invert and the working face. This allows the support to close into a ring earlier, which is beneficial for controlling the deformation of the surrounding rock, improving the stress on the support structure, and enabling the support and surrounding rock to enter a good working state. The specific embodiments of the single-core soil three-stage seven-step method of this application are as follows.
[0133] See attached document Figure 24 As shown, the more specific implementation steps of the single-core soil three-step seven-step method in this embodiment include:
[0134] T1. Divide the soil in the tunnel excavation section into three steps: upper, middle and lower. First, excavate the arc-shaped pilot tunnel A of the upper step, and at the same time, carry out initial support I on the arc-shaped section after the excavation of the upper step.
[0135] T2. Excavate the left side area B of the middle bench, and at the same time carry out initial support I on the left side section of the middle bench after the excavation of the left side area B; wherein, the bottom width of the left side area B of the middle bench accounts for 15-25% of the width of the entire tunnel excavation section, and the bottom of the middle bench is the tunnel arch waist.
[0136] T3. Excavate the right side region C of the middle step, and simultaneously provide initial support I for the right side section of the middle step after the excavation of the right side region C; wherein, the bottom width of the right side region C of the middle step is equal to the bottom width of the left side region B of the middle step;
[0137] T4. Excavate the core soil D of the upper and middle steps;
[0138] T5. Excavate the left side area E of the lower step, and at the same time, carry out initial support I on the left side section of the lower step after the excavation of the left side area E; wherein, the top width of the left side area E of the lower step is smaller than the bottom width of the left side area B of the middle step, accounting for 10-15% of the width of the entire tunnel excavation section.
[0139] T6. Excavate the right side region F of the lower step, and provide initial support I for the right side section of the lower step after the excavation of the right side region F; wherein, the top width of the right side region F of the lower step is equal to the top width of the left side region E of the lower step;
[0140] T7. Excavate the central area G of the lower step and provide initial support I for the invert arch section of the lower step;
[0141] T8. The construction of the extra-large cross-section loess tunnel is completed by sequentially carrying out the full-section invert arch secondary lining II, the full-section invert arch filling, and the full-section arch wall secondary lining II.
[0142] During the specific construction process, as shown in the attached document... Figure 25 As shown, in step T1, the arc-shaped pilot tunnel excavated on the upper step precedes the pilot tunnel excavated on the left side of the middle step in step T2 by 4-6m, preferably 5m; in step T2, the pilot tunnel on the left side of the middle step precedes the pilot tunnel on the right side of the middle step in step T3 by 2-4m, preferably 3m; in step T4, the pilot tunnel on the right side of the middle step precedes the core soil excavation in step T4 by 2-4m, preferably 3m; in step T4, the core soil excavation is carried out simultaneously with the pilot tunnel excavated on the left side of the lower step in step T5; in step T5, the pilot tunnel on the left side of the middle step precedes the pilot tunnel on the right side of the middle step in step T6 by 2-4m, preferably 3m; in step T6, the pilot tunnel on the right side of the lower step precedes the pilot tunnel in the center area of the lower step in step T7 by 2-4m, preferably 3m. The excavation advance in each step is 1m, and the distance between each excavation face remains unchanged during construction.
[0143] Furthermore, the support parameters for the initial support and secondary lining in each step of this embodiment are the same as those in Embodiment 1. In each step, anchor pipes are constructed at the arch waist, upper arch waist, and lower arch waist after the initial support of the cross-section, which is also the same as in Embodiment 1.
[0144] This embodiment also compares the improved three-step seven-step method for single-core soil with the traditional three-step seven-step method through numerical simulation calculation, field monitoring and analysis, and indoor tests, and finally determines the applicable conditions of the three-step seven-step method for single-core soil.
[0145] (I) Analysis of Numerical Simulation Calculation Methods
[0146] Numerical simulations were performed on the traditional three-step seven-stage method and the single-core soil three-step seven-stage method to analyze the deformation of the surrounding rock and the stress changes of the steel arch during the construction process.
[0147] ① Model Establishment
[0148] Numerical simulation was conducted using finite element method software, with the tracing element method as the modeling approach. To eliminate the influence of boundary effects on the calculation results, the calculation models for both methods were designed with a longitudinal length of 60m. The surrounding rock of the models was Upper Pleistocene loess, classified as Class V, with the following parameters: elastic modulus 90MPa, Poisson's ratio 0.4, cohesion 40kPa, internal friction angle 32°, and density 1.68g / cm³. 3 According to Saint-Venant's principle, stress redistribution caused by excavation only occurs within a range of 3-5 times the excavation width from the center of the tunnel. Therefore, the model was selected with a width of 138m and a height of 133m (burial depth of 60m). The established model is attached. Figure 26 As shown. Among them, Figure 26 'a' represents the finite element calculation model of the traditional three-step, seven-stage method. Figure 26 b represents the finite element calculation model of the three-step, seven-step method for single-core soil.
[0149] In this model, the surrounding rock is simulated using the Mohr-Coulomb constitutive model. Both the initial support and secondary lining are simulated using solid elements (C3D8R). The steel reinforcement parameters of the secondary lining are converted into concrete based on the equivalent stiffness principle. The steel arch of the initial support is embedded in the shotcrete using built-in commands. Both the steel arch and the anchor pipes are simulated using beam elements. The model uses the equivalent stiffness principle to simulate the reinforcement effect of the pre-excavated small guide pipes and the base jet grouting piles on the surrounding rock. Due to the disturbance caused by tunnel excavation, the stress in the surrounding rock redistributes, resulting in partial stress release. In the numerical simulation, the method of reducing the elastic modulus of the soil in the excavation area is used to simulate the stress release in the surrounding rock. The surrounding rock density and shear strength indices are obtained from indoor tests at the end of the double-sided pilot tunnel, and are also obtained with reference to the "Specifications for Design of Highway Tunnels" (JTG 3370.1-2018) and relevant existing data.
[0150] ②Results Analysis
[0151] Data on crown settlement, horizontal convergence, and steel arch stress were extracted from a section 5m from the opening of both the traditional three-step seven-step method and the single-core soil three-step seven-step method model. The numerical simulation results were then analyzed. (This 5m section location is consistent with the 5m interval between sections in the field monitoring and analysis method.)
[0152] like Figure 27 The curves showing the variation of crown settlement and horizontal convergence values with excavation progress for two construction method models are presented. Figure 27 'a' represents the curves showing the changes in crown settlement and horizontal convergence values using the traditional three-step, seven-step method. Figure 27 b represents the curves showing the changes in crown settlement and horizontal convergence values for a single-core soil using the three-step, seven-stage method.
[0153] from Figure 27 As shown in curve b, the crown settlement during the single-core soil three-stage seven-step excavation process in this embodiment exhibits a trend of first increasing and then stabilizing, with a maximum value of 9.52 cm. Before the invert excavation, the crown settlement continuously increases. After the invert excavation, the initial support closes into a ring, forming a complete load-bearing structure, and the crown settlement tends to stabilize. The horizontal convergence trend is first increasing, then decreasing, and then stabilizing, with a maximum value of 2.77 cm and a stable value of 0.9 cm. Before the invert excavation, the horizontal convergence continuously increases. After the invert excavation, the initial support closes into a ring, forming a complete load-bearing structure. Under the pressure of the surrounding rock above the tunnel, the lining deforms outward, causing the horizontal convergence to decrease. Figure 27 Figure 'a' shows the crown settlement and horizontal convergence curves during the traditional three-stage seven-step excavation process. As can be seen from the figure, the crown settlement and horizontal convergence trends of the traditional three-stage seven-step method are consistent with those of the single-core soil three-stage seven-step method. Crown settlement continuously increases before invert excavation and then stabilizes, with a maximum value of 10.41 cm. Horizontal convergence also continuously increases before invert excavation. After the initial lining of the invert is closed into a ring, horizontal convergence decreases and stabilizes, with a stable value of 3.67 cm.
[0154] Please refer to the appendix. Figure 28 As shown, the tunnel displacement cloud map of the single-core soil three-step seven-step method is illustrated. Figure 28 It can be seen that the maximum arch settlement of the tunnel after the completion of the three-stage seven-step excavation method for a single core soil is 9.55cm.
[0155] According to the Technical Specification for Highway Tunnel Construction (JTGT3660-2020), the measured displacement value should not be greater than the designed reserved deformation amount U0 of the tunnel. The designed reserved deformation amount of this tunnel is 30cm. The calculated maximum displacement of the single core soil using the three-step seven-step method is less than U0 / 3, which belongs to the Class III management level, indicating that the surrounding rock is in a stable state.
[0156] Figure 29 The image shows radar plots of the steel arch frame stress at different locations along a 5m cross-section, representing two different construction methods. Figure 29 It can be seen that, under both construction methods, the stress on the steel arch frame in the single-core soil three-step seven-step method of this application is lower than that in the traditional three-step seven-step method, and the steel arch frame is under compression with a symmetrical stress distribution. In the traditional three-step seven-step method, the arch crown experiences the greatest stress, followed by the left and right arch shoulders, and the invert arch experiences the least stress. In the single-core soil three-step seven-step method of this application, the stress on the steel arch frame is similar to that of the traditional three-step seven-step method, with the arch crown experiencing the greatest stress, followed by the left and right arch shoulders, and the invert arch experiencing the least stress.
[0157] Appendix Figure 30This paper presents a stress cloud diagram of the steel arch frame using the three-step, seven-stage method for single-core soil in this application. Figure 30 It can be seen that the maximum stress of the steel arch frame with a single core soil three-stage seven-step method is 164MPa.
[0158] The "Technical Specification for Highway Tunnel Construction" (JTGT3660-2020) stipulates that the measured stress of the initial support shall not exceed the allowable value (235 MPa) by more than 0.8. The ratio of the maximum stress of the steel arch frame to the yield strength of the steel, calculated using the three-step, seven-stage method for single-core soil, is 164 / 235 = 0.7, indicating that the surrounding rock obtained using the three-step, seven-stage method for single-core soil is in a stable state.
[0159] Based on the above analysis, it can be found that the crown settlement and horizontal convergence of the single-core soil three-step seven-step method are both smaller than those of the traditional three-step seven-step method, decreasing by 0.89 cm and 2.77 cm respectively. Furthermore, the surrounding rock is in a stable state during excavation using the single-core soil three-step seven-step method. Except for the arch bottom, where the stress of the steel arch frame is higher than that of the traditional three-step seven-step method, the stress at other locations using the single-core soil three-step seven-step method is lower, with a maximum reduction of 37.77 MPa. The stress-to-yield strength ratio of the steel in the single-core soil three-step seven-step method meets the specification requirements. Adhering to the New Austrian Tunneling Method's principle of "minimal disturbance and tight closure," the single-core soil three-step seven-step method simplifies the construction process, shortens the time for initial support closure, and improves the stress on the initial support, making it more advantageous than the traditional three-step seven-step method in terms of surrounding rock deformation and steel arch frame stress. In summary, the single-core soil three-stage seven-step method can better control the deformation of the surrounding rock and reduce the stress on the steel arch frame compared with the traditional three-stage seven-step method. It is feasible to use the single-core soil three-stage seven-step method for excavation in loess tunnels with extra-large cross sections.
[0160] (II) On-site monitoring and analysis
[0161] To verify the feasibility of the three-step, seven-stage excavation method for single-core soil, a 30m test section using this method was set up in the Zhonghe Tunnel. Three monitoring sections were established at chainages ZK57+186.8, ZK57+191.8, and ZK57+196.8 to monitor surrounding rock deformation and internal forces in the support structure. Each section was equipped with arch crown settlement and horizontal convergence observation points, as well as steel arch strain gauges, to monitor the condition of the surrounding rock and lining. The on-site monitoring results are as follows: Figure 13 As shown.
[0162] Comparison of numerical simulation calculations and field monitoring data
[0163] Cross-sections at 10m, 15m, and 20m in the numerical simulation model were selected to extract the settlement and horizontal convergence of the surrounding rock arch, as well as the stress values of the steel arch frame. Since the horizontal convergence measuring points were arranged after the excavation of the right-side middle bench, the settlement and horizontal convergence data of the arch crown after the excavation of the right side of the middle bench were taken, and the stress values of the steel arch frame were extracted from the stable data after the excavation was completed.
[0164] Figure 31 The figure shows the crown settlement and horizontal convergence curves during the three-step, seven-stage tunnel excavation process in a single-core soil system, based on a numerical simulation model. Figure 32 The data shows the crown settlement and horizontal convergence after the excavation of the middle bench on the right side of the on-site monitoring section. Figure 31 It can be seen that the maximum settlement of the arch crown in the three cross-sections of the numerical simulation was 9 cm, the maximum horizontal convergence was 2.77 cm, and it later stabilized at 1.15 cm. The results after excavation of the middle bench on the right side of the three cross-sections in the numerical simulation were compared with the field monitoring data. Figure 32 A comparison reveals that both methods exhibit similar trends in crown settlement and horizontal convergence. The numerically simulated crown settlement ultimately converged to 9 cm, less than the maximum value of 12 cm observed in the field. The numerically simulated horizontal convergence ultimately stabilized at 1.15 cm, less than the maximum value of 2.33 cm observed in the field. Through comparison... Figure 31 and Figure 32 It can be seen that the settlement and horizontal convergence trends of the arch in the numerical simulation results are consistent with the monitoring data, which shows that the numerical simulation can accurately reflect the on-site situation.
[0165] Regarding construction progress, according to on-site construction statistics, the monthly progress of the single-core soil three-stage seven-step method can reach 80m or more, which is significantly better than the 70m monthly progress of the traditional three-stage seven-step method. This indicates that the single-core soil three-stage seven-step method can not only better control the deformation of the surrounding rock and improve the stress of the steel arch frame, but also accelerate the construction progress and save costs.
[0166] Appendix Figure 33 The stress radar diagrams of the steel arch frame, obtained by numerical simulation and field monitoring at section 1 (10m), are shown using the single-core soil three-step seven-step method. Figure 34 The stress radar diagrams of the steel arch frame, obtained by numerical simulation and field monitoring at section II (15m), are shown using the single-core soil three-step seven-step method. Figure 35 The stress radar plots of the steel arch frame obtained by numerical simulation and field monitoring at section III (20m) using the single-core soil three-step seven-step method are shown. Table 5 below lists the comparison of the average stress values of the steel arch frame obtained by numerical simulation and field monitoring at the three sections.
[0167] Table 5 Comparison of Simulated and Measured Data on Stress in Steel Arch Frames
[0168]
[0169] from Figure 33 , 34As shown in Table 35, the trends of numerical simulation and field monitoring results are largely consistent in each cross-section. The steel arch frame is under pressure at all locations, and the stress distribution is roughly symmetrical along the tunnel axis. Among them, the areas of higher stress in the steel arch frame are the arch crown and the left and right arch shoulders, while the stress at the invert arch is relatively low. Table 5 shows that the data results of numerical simulation and field monitoring are largely consistent, with errors within 20%, indicating that the numerical simulation results can accurately describe the field conditions. Furthermore, it can be concluded that the single-core soil three-stage seven-step method is superior to the traditional three-stage seven-step method in the construction of extra-large cross-section loess tunnels.
[0170] (III) Indoor Testing
[0171] To explore the applicability of the three-step, seven-stage method for single-core soil, soil samples were collected every 2 meters along a 30m test section for laboratory testing. The moisture content at the sampling points was obtained according to the "Specifications for Geotechnical Testing of Highways" (JTG3430-2020). Simultaneously, numerical simulations were used to analyze the effects of cohesion, internal friction angle, density, and elastic modulus on the stress of the steel arch frame in the tunnel surrounding rock, arch crown settlement, and horizontal convergence. The results are shown in the appendix. Figures 36 to 39 .
[0172] The results show that the elastic modulus and density have significant effects on the stress of the steel arch frame in the tunnel surrounding rock, the settlement at the arch crown, and the horizontal convergence, while the cohesion and internal friction angle have relatively small effects. Therefore, based on indoor experiments and numerical simulations, the applicable range of the three-step seven-stage method for single-core soil is further determined as follows: elastic modulus greater than 70 MPa, moisture content less than 15%, and density greater than 1.60 g / cm³. 3 And less than 1.76 g / cm 3 .
[0173] As can be seen from the above embodiments, the five-step single-side-wall pilot tunnel method can serve as a transitional construction method from the existing double-side-wall pilot tunnel method to the single-core soil three-stage seven-step method. It can ensure the construction safety of loess tunnels with extra-large cross-sections, as well as the construction progress and improve construction efficiency.
[0174] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any way. Any simple modifications, equivalent changes, or alterations made by those skilled in the art using the disclosed technical content shall fall within the protection scope of the present invention.
Claims
1. A combined construction method applicable to loess tunnels with extra-large cross-sections, employing the double-sidewall pilot tunnel method, characterized in that... It also includes a five-step single-sidewall pilot tunnel method and a seven-step three-stage method for single-core soil, which are sequentially converted from the double-sidewall pilot tunnel method. The applicable conditions for the five-step single-sidewall pilot tunnel method are: elastic modulus greater than 50 MPa, moisture content less than 21%, and density greater than 1.50 g / cm³. 3 And less than 1.68 g / cm 3 The applicable conditions for the single-core soil three-step seven-stage method are: elastic modulus greater than 70 MPa, moisture content less than 15%, and density greater than 1.60 g / cm³. 3 And less than 1.76 g / cm 3 ; The five-step single-sidewall guide tunnel method includes the following steps: S1. Divide the soil within the tunnel excavation section into the upper left, lower left, upper right, and lower right regions. Excavate the upper left region, and simultaneously provide initial support for the upper half of the left side wall after excavation, as well as temporary support for the right side wall. The bottom width of the upper left region is less than 50% of the total tunnel excavation section width. S2. Excavate the lower left area, and simultaneously provide initial support for the lower half of the left side wall after excavation of the lower left area, as well as temporary support for the right side section; wherein, the top width of the lower left area is equal to the bottom width of the upper left area; S3. Excavate the upper right area, leaving core soil. The bottom of the core soil is less than 40% of the width of the entire tunnel excavation section. At the same time, provide initial support for the upper half of the right side wall after the excavation of the upper right area. S4. Excavate the core soil; S5. Excavate the lower right area and simultaneously provide initial support for the lower half of the right side wall after the excavation of the lower right area; S6. Remove the central partition wall formed by the temporary support, and then carry out the secondary lining of the full-section inverted arch, the filling of the full-section inverted arch, and the secondary lining of the full-section arch wall in sequence to complete the construction of the extra-large section loess tunnel.
2. The combined construction method for loess tunnels with extra-large cross-sections according to claim 1, characterized in that, In the five-step single-side wall pilot tunnel method, the bottom width of the upper left area accounts for 40-45% of the total tunnel excavation cross-section width, the bottom of the core soil accounts for 34-40% of the total tunnel excavation cross-section width, and the height of the core soil accounts for 22-30% of the total tunnel excavation cross-section width.
3. The combined construction method for loess tunnels with extra-large cross-sections according to claim 1, characterized in that, In step S1, the pilot tunnel excavation in the upper left area precedes the pilot tunnel excavation in the lower left area of step S2 by 4-6m, and precedes the pilot tunnel excavation in the upper right area of step S3 by 12-14m. In step S3, the pilot tunnel excavation in the upper right area precedes the core soil excavation in step S4 by 2-4m. In step S4, the core soil excavation precedes the pilot tunnel excavation in the lower right area of step S5 by 1-3m. During the construction process, the distance between each excavation face remains unchanged, and the excavation advance in each step is 1m.
4. The combined construction method for loess tunnels with extra-large cross-sections according to any one of claims 1 to 3, characterized in that, The single-core soil three-step seven-step method includes the following steps: T1. Divide the soil in the tunnel excavation section into three steps: upper, middle and lower. First, excavate the arc-shaped pilot tunnel of the upper step, and at the same time, provide initial support for the arc-shaped section after the excavation of the upper step. T2. Excavate the left side area of the middle bench, and simultaneously provide initial support for the left side section of the middle bench after the left side area is excavated; wherein, the bottom width of the left side area of the middle bench is less than 25% of the width of the entire tunnel excavation section; T3. Excavate the right side area of the middle step, and simultaneously provide initial support for the right side section of the middle step after the right side area is excavated; wherein, the bottom width of the right side area of the middle step is equal to the bottom width of the left side area of the middle step; T4. Excavation of the core soil for the upper and middle steps; T5. Excavate the left side area of the lower step, and at the same time provide initial support for the left side section of the lower step after the excavation of the left side area; wherein, the top width of the left side area of the lower step is smaller than the bottom width of the left side area of the middle step. T6. Excavate the right side area of the lower step and provide initial support for the right side section of the lower step after excavation; wherein, the top width of the right side area of the lower step is equal to the top width of the left side area of the lower step. T7. Excavate the central area of the lower step and provide initial support for the invert arch section of the lower step; T8. The construction of the extra-large cross-section loess tunnel is completed by sequentially carrying out the secondary lining of the full-section inverted arch, the filling of the full-section inverted arch, and the secondary lining of the full-section arch wall.
5. The combined construction method for loess tunnels with extra-large cross-sections according to claim 4, characterized in that, In the single-core soil three-step seven-step method, the bottom width of the left side area of the middle step accounts for 15-25% of the total tunnel excavation cross-section width, and the bottom width of the left side area of the lower step accounts for 10-15% of the total tunnel excavation cross-section width. The dividing line between the middle step and the lower step is the tunnel arch waist.
6. The combined construction method for loess tunnels with extra-large cross-sections according to claim 4, characterized in that, In step T1, the arc-shaped pilot tunnel excavated on the upper step is 4-6m ahead of the pilot tunnel excavated on the left side of the middle step in step T2. In step T2, the pilot tunnel excavated on the left side of the middle step is 2-4m ahead of the pilot tunnel excavated on the right side of the middle step in step T3. In step T3, the pilot tunnel excavated on the right side of the middle step is 2-4m ahead of the core soil excavation in step T4. The core soil excavation in step T4 is carried out simultaneously with the pilot tunnel excavated on the left side of the lower step in step T5. In step T5, the pilot tunnel excavated on the left side of the middle step is 2-4m ahead of the pilot tunnel excavated on the right side of the middle step in step T6. In step T6, the pilot tunnel excavated on the right side of the lower step is 2-4m ahead of the pilot tunnel excavated in the center area of the lower step in step T7. The distance between each excavation face remains unchanged during the construction process, and the excavation advance in each step is 1m.
7. The combined construction method for loess tunnels with extra-large cross-sections according to claim 4, characterized in that, The initial support parameters in each step are as follows: HW175 steel arch frame is used, with a longitudinal spacing of 50cm, ϕ8 steel mesh is hung at 20cm×20cm, and C25 concrete is sprayed at 30cm. The temporary support parameters are as follows: I20a type steel arch frame is used, with a longitudinal spacing of 50cm, ϕ6 steel mesh is hung at 20cm×20cm, and C25 concrete is sprayed at 22cm. The support parameters for the secondary lining are: main reinforcement φ25, distribution reinforcement φ14, and sprayed C35 concrete 70cm.
8. The combined construction method for loess tunnels with extra-large cross-sections according to claim 7, characterized in that, Both the five-step single-side wall pilot tunnel method and the single-core soil three-step seven-step method include the step of constructing anchor pipes for the arch waist, upper part of the arch waist and lower part of the arch waist after the initial support of the cross section. The anchor pipes are ϕ60*5mm anchor pipes with a length of 400cm and a vertical outward inclination angle of 30-45°.
9. The combined construction method for loess tunnels with extra-large cross-sections according to claim 1, characterized in that, The excavation width of the extra-large cross-section loess tunnel is less than 20m, the excavation height is less than 14m, and the tunnel excavation cross-sectional area is less than 190m². 2 .