Diagonal concrete beam-column joint structure and construction method thereof
Patent Information
- Application Number
- CN202410179756.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-18
- Publication Date
- 2026-10-16
- Estimated Expiration
- 2044-02-18
AI Technical Summary
[0003]为克服现有技术所存在的缺陷,现提供一种斜交混凝土梁柱节点构造及其施工方法,以解决多向斜交框架梁与混凝土柱连接节点,由于钢筋密集交叉无法正常浇筑的问题
[0023]The beneficial effects of this invention are as follows: the oblique concrete beam-column joint structure of this invention uses a column core tube and core pipe at the top of the concrete column as a steel frame structure to reliably ensure the anchorage of the support reinforcement of the orthogonal and oblique beams. The support reinforcement of the oblique beam welded to the core pipe effectively transfers the tensile force of the reinforcement to the steel frame structure that forms an integral part with the concrete column, replacing the method of using reinforcement and concrete anchorage for force transfer, which has the advantages of safety and reliability. The support reinforcement of the orthogonal beam is connected to the column core tube through the reinforcement plate. When the support reinforcement of the oblique beam encounters the core tube, the reinforcement bends downward and welds to the pre-welded core pipe inside. The reinforcement is welded to the plate on both sides, with a length of 5d. The support reinforcement of the surrounding oblique beams can be bent and welded into the column core tube and core pipe. The support reinforcement of the orthogonal beam is bent downward in advance before connecting to the reinforcement plate, ensuring that the support reinforcement of the oblique beam and the support reinforcement of the orthogonal beam do not intersect at the same elevation, and each is properly positioned. The support reinforcement of orthogonal and oblique beams does not overlap at the column joint, avoiding the phenomenon of reinforcement occupying space and being too dense to pour concrete. There is sufficient space inside the core tube for welding reinforcement and pouring and vibrating concrete at the top of the column. The reinforcement is arranged in an orderly and reasonable manner, which is safe, reliable, and convenient for construction, and improves the structural bearing capacity of the core area of the orthogonal beam, oblique beam and column joint.