A method, device and system for intelligent management and control of major safety risks in an enterprise
By setting up local service nodes and central platforms at various bases of the enterprise, collecting and analyzing real-time data, and generating risk warning items, the problem of enterprise security risk data dispersion and lack of intelligent management and control is solved, and multi-base risk management and real-time coordination are realized. monitor.
Patent Information
- Application Number
- CN202410888858.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-04
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-07-04
AI Technical Summary
In the existing technology, the security risk data of enterprises are scattered, and there is a lack of intelligent and scientific risk analysis and early warning means. It is difficult to achieve complete risk monitoring and event tracing at the enterprise level, especially in multi-industry sector enterprises.
Set up local service nodes and central platforms at each base to collect and analyze real-time data, including video data and equipment monitoring data, determine abnormalities by comparing thresholds, generate risk warning items, and transmit the data to terminals and central platforms for display and control , using streaming media and RESTFUL protocols for data transmission, establishing base risk management and control entries, and realizing coordinated risk management of multiple bases.
It realizes real-time data collection and analysis, generates risk warning items, facilitates risk management and control on terminals and central platforms, and improves enterprises' real-time monitoring and overall management capabilities of security risks.
Smart Images

Figure CN118411040B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of risk management and control technology, and in particular to a method, device and system for intelligent management and control of major safety risks of an enterprise. Background Art
[0002] With the continuous development of science and technology, people have put forward new demands for the monitoring and control of safety risks. They require that online monitoring be provided in addition to conventional control measures, and that the data generated by monitoring be integrated and analyzed so as to timely grasp the real-time status of production safety risks.
[0003] In addition, in the existing technology, the security risk data of some industrial sectors are scattered, making it difficult to accumulate and form a large security risk database and use it. In addition, there is a lack of scientific risk assessment, prediction, and early warning models, and most of them rely on manual statistics and analysis. There is a lack of intelligent and scientific risk analysis and early warning methods to provide scientific decision-making support for major risk management. Especially for enterprises with many industrial sectors, each sector usually conducts risk monitoring independently, making it difficult to achieve complete risk monitoring at the enterprise level and trace the situation after an incident occurs.
[0004] In view of this, overcoming the defects of the prior art is an urgent problem to be solved in the field of this technology. Summary of the invention
[0005] The technical problem to be solved by the present invention is to provide an intelligent management and control method for major safety risks of an enterprise.
[0006] The present invention adopts the following technical solution:
[0007] In a first aspect, the present invention provides an intelligent management and control method for major security risks of an enterprise, which sets a local service node at each base and sets a central platform for multiple bases, including:
[0008] Receive real-time data from each workshop; wherein the real-time data includes video data of different workshops and monitoring data of each device in different workshops, and the real-time data is collected by sensors;
[0009] The local service node stores the real-time data in the local data center and transmits the video data to the corresponding terminal according to the source of the video data so as to display it in the terminal;
[0010] The local service node also compares the monitoring data with the corresponding monitoring threshold to determine whether the monitoring data is abnormal. If the monitoring data is abnormal, the monitoring data is marked with a corresponding abnormal label, and an early warning item analysis is performed based on the abnormal monitoring data to obtain a risk early warning item. The risk early warning item, each monitoring data, and the abnormal label carried by the corresponding monitoring data are transmitted to the corresponding terminal for display in the terminal;
[0011] The local service node also transmits the video data, risk warning items, various monitoring data and abnormal labels carried by the corresponding monitoring data to the central platform, so that the central platform can perform risk management and control of multiple bases.
[0012] Preferably, the local service node also transmits the video data, risk warning items, various monitoring data and abnormal labels carried by the corresponding monitoring data to the central platform, specifically including:
[0013] The video data is transmitted to the central platform using the streaming protocol, and the risk warning items, each monitoring data and the abnormal labels carried by the corresponding monitoring data are transmitted to the central platform using the RESTFUL protocol.
[0014] Preferably, when the local service node is first put into use, it uses the IP address of the central platform to establish a network connection with the central platform;
[0015] When the central platform detects the presence of a newly connected local service node, it sends a base information acquisition instruction to the local service node, and the local service node returns the base information to the central platform according to the base information acquisition instruction; wherein the base information includes the base code and the codes of each plant department of the base;
[0016] Sending a device information acquisition instruction to the local service node, and the local service node returns the device information to the central platform according to the device information acquisition instruction; wherein the device information acquisition instruction carries the base code and the corresponding factory code of the base, and the device information includes the device code and device name of each device in the corresponding factory;
[0017] The central platform establishes a base risk management table item according to the base information and the equipment information, and establishes a data transmission channel with the local service node according to the base information to transmit the monitoring data and abnormal labels corresponding to each device;
[0018] The central platform analyzes monitoring data and abnormal labels according to the base risk management and control table items.
[0019] Preferably, the monitoring data is specifically peripheral data collected by an external sensor installed by a user, and the method further comprises: collecting internal data of internal sensors in each device;
[0020] When the local service node determines that the peripheral data is normal, the local service node finds the internal data associated with the peripheral data according to a preset data association model, and analyzes whether there is a mapping relationship between the peripheral data and the internal data;
[0021] If there is a mapping relationship between the peripheral data and the internal data, the mapping relationship is sent to the central platform;
[0022] For the first internal data which has no mapping relationship with the external data, synchronously sending the first internal data to the central platform according to the sending frequency of the external data;
[0023] For the second built-in data that has a mapping relationship with the peripheral data, when the local service node determines that the peripheral data is normal, the second built-in data is not sent to the central platform. The central platform generates simulated built-in data according to the mapping relationship between the second built-in data and the peripheral data, and uses the simulated built-in data to realize the monitoring of the corresponding device;
[0024] When the local service node determines that the peripheral device data is abnormal, the local service node sends the second internal device data to the central platform.
[0025] Preferably, the mapping relationship includes one or more of a linear relationship, an inverse proportional relationship and a quadratic correlation relationship.
[0026] Preferably, each mapping relationship obtained through analysis is stored in a local relationship table; wherein the local relationship table includes one or more relationship entries, each relationship entry includes a relationship ID, a data code of the external data, a data type of the external data, a data code of the internal data, a data type of the internal data, a mapping relationship type, and each variable in the mapping relationship; the analyzing whether there is a mapping relationship between the external data and the internal data specifically includes:
[0027] Searching in the local relationship table whether there is a first relationship entry that matches the data type of the external device data and the data type of the internal device data;
[0028] If there is a first relationship entry, the mapping relationship type of the first relationship entry is preferentially used to match the mapping relationship between the peripheral data and the internal data. If the mapping relationship matching using the first relationship entry fails, other mapping relationship types are used for matching.
[0029] Preferably, the monitoring data includes one or more of the equipment's temperature, pressure, liquid level, rotation speed, volume, flow rate, gas concentration, interlocking status, height, speed, wind pressure, current, voltage, material level, weight, frequency, vibration and opening degree.
[0030] In a second aspect, the present invention further provides an intelligent management and control device for major safety risks of an enterprise, which is used to implement the intelligent management and control method for major safety risks of an enterprise described in the first aspect, and the device includes:
[0031] At least one processor; and a memory communicatively connected to the at least one processor; wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the processor to execute the method for intelligent management and control of major security risks of an enterprise as described in the first aspect.
[0032] In a third aspect, the present invention further provides a non-volatile computer storage medium, wherein the computer storage medium stores computer executable instructions, which are executed by one or more processors to complete the method for intelligent management and control of major enterprise security risks described in the first aspect.
[0033] In a fourth aspect, the present invention also provides an intelligent management and control system for major security risks of an enterprise, including sensors, local service nodes and a central platform;
[0034] The sensor is used to collect real-time data in the workshop and transmit the real-time data to the local service node; wherein the real-time data includes video data of different workshops and monitoring data of each device in different workshops;
[0035] The local service node is used to receive real-time data from each work shop;
[0036] The local service node stores the real-time data in the local data center and transmits the video data to the corresponding terminal according to the source of the video data so as to display it in the terminal;
[0037] The local service node also compares the monitoring data with the corresponding monitoring threshold to determine whether the monitoring data is abnormal. If the monitoring data is abnormal, the monitoring data is marked with a corresponding abnormal label, and an early warning item analysis is performed based on the abnormal monitoring data to obtain a risk early warning item. The risk early warning item, each monitoring data, and the abnormal label carried by the corresponding monitoring data are transmitted to the corresponding terminal for display in the terminal;
[0038] The local service node also transmits the video data, risk warning items, various monitoring data and abnormal labels carried by the corresponding monitoring data to the central platform, so that the central platform can perform multi-base risk management and control;
[0039] The central platform is used for risk management and control of multiple bases.
[0040] The present invention collects monitoring data and video data, obtains corresponding anomalies and warning items after analysis, and sends the anomalies, warning items and data to the central platform and terminal for display, thereby facilitating risk control by terminal staff and facilitating the overall management of all base risks on the enterprise side. BRIEF DESCRIPTION OF THE DRAWINGS
[0041] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments of the present invention. Obviously, the drawings described below are only some embodiments of the present invention, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0042] Figure 1 It is a schematic diagram of a first method for intelligent management and control of major security risks of an enterprise provided by an embodiment of the present invention;
[0043] Figure 2 This is a flow chart of a first method for intelligent management and control of major security risks of an enterprise provided by an embodiment of the present invention;
[0044] Figure 3 Schematic diagram of a second method for intelligent management and control of major security risks of an enterprise provided by an embodiment of the present invention;
[0045] Figure 4 It is a schematic diagram of an interactive interface of a terminal in a method for intelligent management and control of major security risks of an enterprise provided by an embodiment of the present invention;
[0046] Figure 5 It is a schematic diagram of the interaction of local service nodes in the first method for intelligent management and control of major security risks of an enterprise provided by an embodiment of the present invention;
[0047] Figure 6 It is a schematic diagram of an interactive interface of a central platform in an intelligent management and control method for major security risks of an enterprise provided by an embodiment of the present invention;
[0048] Figure 7 is a schematic diagram of a third method for intelligent management and control of major security risks of an enterprise provided by an embodiment of the present invention;
[0049] Figure 8 It is a flow chart of a second method for intelligent management and control of major security risks of an enterprise provided by an embodiment of the present invention;
[0050] Fig. 9 It is a flowchart of a third method for intelligent management and control of major security risks of an enterprise provided by an embodiment of the present invention;
[0051] Fig.10is a schematic diagram of a fourth method for intelligent management and control of major security risks of an enterprise provided by an embodiment of the present invention;
[0052] Fig.11 It is a schematic diagram of the interactive interface of the central platform in the second method for intelligent management and control of major security risks of an enterprise provided by an embodiment of the present invention;
[0053] Fig.12 It is a flowchart of a fourth method for intelligent management and control of major security risks of an enterprise provided by an embodiment of the present invention;
[0054] Fig.13 It is a schematic diagram of a production line included in a base model in an intelligent management and control method for major safety risks of an enterprise provided by an embodiment of the present invention;
[0055] Fig.14 It is a schematic diagram of an early warning disposal tree in an intelligent management and control method for major safety risks of an enterprise provided by an embodiment of the present invention;
[0056] Fig.15 It is a schematic diagram of an interactive interface of a terminal in another intelligent management and control method for major security risks of an enterprise provided by an embodiment of the present invention;
[0057] Fig.16 It is a schematic diagram of an interactive interface of a central platform in an intelligent management and control method for major security risks of an enterprise provided by an embodiment of the present invention;
[0058] Fig.17 It is a schematic diagram of an interactive interface of a central platform in another intelligent management and control method for major security risks of an enterprise provided by an embodiment of the present invention;
[0059] Fig.18 It is a schematic diagram of an interactive interface of a central platform in another intelligent management and control method for major security risks of an enterprise provided by an embodiment of the present invention;
[0060] Fig.19 This is a schematic diagram of the architecture of an intelligent management and control system for major security risks of an enterprise provided by an embodiment of the present invention;
[0061] Fig. 20 It is a schematic diagram of the architecture of an intelligent management and control device for major security risks of an enterprise provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0062] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.
[0063] The terms "first", "second", etc. in the present invention are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first", "second", etc. may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.
[0064] In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0065] Embodiment 1:
[0066] Embodiment 1 of the present invention provides an intelligent management and control method for major security risks of an enterprise, such as Figure 1 As shown, local service nodes are set up in each base, and a central platform is set up for multiple bases. An enterprise can set up a central platform for risk management and control of all bases of the enterprise, such as Figure 2 As shown, the method includes:
[0067] In step 201, real-time data is received from each workshop; wherein the real-time data includes video data of different workshops and monitoring data of each equipment in different workshops, and the real-time data is collected by sensors; the monitoring data includes one or more of the equipment's temperature, pressure, liquid level, rotation speed, volume, flow rate, gas concentration, interlocking status, height, speed, wind pressure, current, voltage, material level, weight, frequency, vibration and opening degree.
[0068] In step 202, the local service node stores the real-time data in the local data center and transmits the video data to a corresponding terminal according to the source of the video data, so as to display the video data in the terminal.
[0069] In step 203, the local service node also compares the monitoring data with the corresponding monitoring threshold to determine whether the monitoring data is abnormal. If the monitoring data is abnormal, the monitoring data is marked with a corresponding abnormal label, and the warning item analysis is performed based on the abnormal monitoring data to obtain the risk warning item, and the risk warning item, each monitoring data and the abnormal label carried by the corresponding monitoring data are transmitted to the corresponding terminal for display in the terminal; the monitoring threshold of each monitoring data is obtained by technical personnel in this field based on empirical analysis. In actual use, the upper and lower monitoring thresholds are usually set. When the monitoring data is greater than the lower monitoring threshold and less than the upper monitoring threshold, the monitoring data is normal, otherwise, the monitoring data is abnormal. The risk warning item is the warning item for the current risk.
[0070] In step 204, the local service node also transmits the video data, risk warning items, each monitoring data and the abnormal tags carried by the corresponding monitoring data to the central platform, so that the central platform can perform multi-base risk management. In this embodiment, the architecture diagram between the local service node, each sensor and the terminal is as follows: Figure 3 shown.
[0071] In actual use, the local service node and the central platform are both corresponding servers. This embodiment collects monitoring data and video data, and after analysis, obtains corresponding anomalies and warning items, and sends the anomalies, warning items and data to the central platform and terminal for display, so as to facilitate the terminal side staff to carry out risk management and control, and facilitate the enterprise side to carry out the overall management of all base risks. Among them, the interactive interface of the corresponding terminal is as follows Figure 4 As shown, the risk warning items are displayed on the left, and the monitoring data are displayed on the right. The display form of each monitoring data is set by technicians in this field according to needs, and can be one or more of the multiple display forms such as real-time values, displaying the location of the real-time values in the warning bar box, or displaying in the form of waveforms. The interactive interface of the local service node is as follows Figure 5 As shown in the figure, the interactive interface of the central platform is as follows Figure 6 shown.
[0072] The warning item can be understood as the reason that causes the corresponding monitoring data to be abnormal. In actual use, the number of warning items and the number of monitoring data are often large. If a traversal analysis is performed in sequence, a large amount of resources will be occupied and a long time will be spent, which is not conducive to real-time monitoring of the equipment. In order to solve this problem, the present embodiment also provides a preferred implementation method for warning item analysis, which specifically includes: each monitoring data corresponds to a data number, and the data numbers of all monitoring data are arranged in a preset order; warning items are managed using warning entry tables, the warning entry tables include multiple warning items, each warning item includes a warning item and an associated monitoring code corresponding to the warning item; wherein the associated monitoring code is obtained by setting the bit corresponding to the monitoring data associated with the warning item to 1 and the bit corresponding to the monitoring data not related to the warning item to 0 in the first bit code with a length of Num bits.
[0073] The risk warning items are obtained by analyzing the warning items based on the abnormal monitoring data, specifically including:
[0074] According to the use of the monitoring data with abnormalities and the preset order, a second bit code B with a length of Num bits is generated; wherein, B[i]=1, B[j]=0, B[i] represents the i-th byte in the second bit code B, i is the sequential number of the data number of the monitoring data with abnormalities, B[j] represents the j-th byte in the second bit code B, j is the sequential number of the data number of the monitoring data without abnormalities, and Num is the number of monitoring data.
[0075] The associated monitoring code of each warning item is used to perform an AND operation with the second bit code B to obtain the actual associated code of each warning item, and it is determined whether the actual associated code is consistent with the corresponding associated monitoring code. If they are consistent, the warning item corresponding to the warning item is a risk warning item.
[0076] The preset sequence is obtained by those skilled in the art based on empirical analysis. In actual use, each monitoring data is often expressed in the form of an enumerated variable in the program. Each enumerated variable has a unique integer value, which can be used as the data number of the monitoring data. In actual use, the integer values of multiple enumerated variables belonging to the same enumerated data type are often increased in sequence. For example, when three enumerated variables are defined as CO concentration, cooling water inlet flow rate and cooling water outlet flow rate, the integer values of these three enumerated variables are 1, 2 and 3 respectively, so that the sequence number of the corresponding monitoring data in the preset sequence can be determined according to the data number of the monitoring data.
[0077] For example, there are 8 monitoring data, and the data numbers of these 8 monitoring data are 1, 2, 3, 4, 5, 6, 7 and 8 in a preset order. Figure 7 As shown in , if there are 3 warning items in the warning item table, they correspond to 3 warning items, such as warning item 1, warning item 2 and warning item 3. Among them, the associated monitoring code of warning item 1 is Figure 7 The associated monitoring code 1 and the associated monitoring code of the warning item 2 are shown as follows: Figure 7 The associated monitoring code 2 and the associated monitoring code of the warning item 3 are shown as follows: Figure 7The associated monitoring codes 3 shown are all pre-analyzed by technicians in this field and written into the early warning entry table. It is analyzed by technicians in this field that early warning item 1 is associated with the monitoring data of data number 1 and data number 3, that is, when the monitoring data of data number 1 and data number 3 are all abnormal, it can be considered that there is a risk in early warning item 1, and the associated monitoring code generated for early warning item 1 is 0b10100000; early warning item 2 is associated with the monitoring data of data number 4, data number 5, data number 6, and data number 7, that is, when the monitoring data of data number 4, data number 5, data number 6, and data number 7 are all abnormal, it can be considered that there is a risk in early warning item 2, and the associated monitoring code generated for early warning item 2 is 0b00011110; and so on, early warning item 3 is associated with the monitoring data of data number 3, data number 5, and data number 6, that is, when the monitoring data of data number 3, data number 5, and data number 6 are all abnormal, it can be considered that there is a risk in early warning item 3, and the associated monitoring code generated for early warning item 3 is 0b00101100.
[0078] Correspondingly, when at the corresponding moment, the monitoring data of data number 1, data number 3, data number 5, data number 6 and data number 7 are all abnormal, the second bit code is generated as 0b10101110, and the second bit code is used to perform AND operation with the associated monitoring code of each warning item, and the actual associated codes obtained are as follows Figure 7 As shown, it can be seen that the actual association code of warning item 1 is consistent with the associated monitoring code 1, the actual association code of warning item 2 is inconsistent with the associated monitoring code 2, and the actual association code of warning item 3 is consistent with the associated monitoring code 3. Therefore, the final analysis shows that the risk warning items are warning item 1 and warning item 3.
[0079] This embodiment improves the efficiency of warning item analysis by converting the analysis of warning items into operations between bit codes. As for storage resources, since the bit code is calculated in space with bit as the smallest unit, that is, the bit code with a length of Num bits occupies a space of Num bits, the storage resources are also less.
[0080] In actual application scenarios, the local service node also transmits video data, risk warning items, various monitoring data and abnormal labels carried by the corresponding monitoring data to the central platform, specifically including: using the streaming media protocol to transmit the video data to the central platform, and using the RESTFUL protocol to transmit the risk warning items, various monitoring data and abnormal labels carried by the corresponding monitoring data to the central platform.
[0081] As the enterprise develops, the number of bases is not fixed. In order to ensure the flexibility of use, this embodiment also provides the following preferred implementation methods: Figure 8 As shown, specifically including:
[0082] In step 301, when the local service node is put into use for the first time, it uses the IP address of the central platform to establish a network connection with the central platform.
[0083] In step 302, when the central platform detects the presence of a newly connected local service node, it sends a base information acquisition instruction to the local service node, and the local service node returns the base information to the central platform according to the base information acquisition instruction; wherein the base information includes the base code and the codes of each plant department of the base; in actual use, the command and information interaction between the central platform and the local service node is implemented using the RESTFUL protocol, and a specific example of base information is as follows:
[0084] [{
[0085] " BaseCode ": "1001",
[0086] " DeptList ": [
[0088] { "DeptCode":"01","DeptName":"Ironworks"},
[0089] { "DeptCode":"02","DeptName":"Steel Plant"},
[0090] { "DeptCode":"03","DeptName":"Energy and Environment Department"} ]
[0092] } ]
[0094] Among them, BaseCode is the base code, and DeptList is the plant list of the base, including the plant code DeptCode and the field name DeptNane. The base code is obtained by technicians in this field in advance according to the number of bases in the enterprise, so that each base in an enterprise has a unique base code.
[0095] In step 303, a device information acquisition instruction is sent to the local service node, and the local service node returns the device information to the central platform according to the device information acquisition instruction; wherein the device information acquisition instruction carries the base code and the corresponding factory code of the base, and the device information includes the device code and device name of each device in the corresponding factory; a specific example of device information is as follows:
[0096] [{
[0097] " BaseCode ": "1001",
[0098] "DeptCode": "01",
[0099] "DeptName": "Ironworks",
[0100] "EquList": [
[0102] { "EquCode":"1001101000101","EquName":"1# Blast furnace"},
[0103] { "EquCode":"1001101000201","EquName":"2# blast furnace"},
[0104] { "EquCode":"1001101000301","EquName":"3# blast furnace"} ]
[0106] } ]
[0108] The base code and the corresponding factory code of the base are also carried in the device information to facilitate the local service node to distinguish the source of the message. EquList is the device list, EquCode is the device code, and EquName is the device name.
[0109] In step 304, the central platform establishes a base risk management table according to the base information and equipment information, and establishes a data transmission channel with the local service node according to the base information to transmit the monitoring data and abnormal labels corresponding to each device.
[0110] In step 305, the central platform parses the monitoring data and abnormal labels according to the base risk control table items. The base risk control table items include the base codes of each base, the codes of each plant in each base, and the codes of each device in each plant of each base. In addition, for the local service node, when transmitting the monitoring data to the central platform, the data code of the monitoring data and the device code of the device corresponding to the monitoring data are also transmitted, so that the central platform can use the device code of the device corresponding to the monitoring data when receiving the corresponding monitoring data to parse which device the monitoring data belongs to.
[0111] This embodiment actively obtains various codes from local service nodes through the central platform, and dynamically establishes base risk management and control representations, thereby increasing the flexibility of coding and base establishment, so that when a new base is added, the central platform side does not need to follow up with changes.
[0112] In actual use, some devices may have built-in sensors, but these sensors may not meet the user's monitoring needs. Therefore, the user will also set up additional sensors to collect monitoring data of the required indicators. In this case, the monitoring data is specifically the peripheral data collected by the external sensors installed by the user, such as Fig. 9 As shown, the method also includes:
[0113] In step 401, built-in data of built-in sensors in each device are collected; the built-in sensors are sensors provided in the device itself.
[0114] In step 402, when the local service node determines that the peripheral data is normal, it finds the internal data associated with the peripheral data according to a preset data association model, and analyzes whether there is a mapping relationship between the external data and the internal data.
[0115] In step 403, if there is a mapping relationship between the peripheral data and the internal data, the mapping relationship is sent to the central platform.
[0116] In step 404, for the first internal device data that has no mapping relationship with the external device data, the first internal device data is synchronously sent to the central platform according to the sending frequency of the external device data.
[0117] In step 405, for the second built-in data that has a mapping relationship with the external data, when the local service node determines that the external data is normal, the second built-in data is not sent to the central platform. The central platform generates simulated built-in data based on the mapping relationship between the second built-in data and the external data, and uses the simulated built-in data to monitor the corresponding equipment.
[0118] In step 406, when the local service node determines that the peripheral device data is abnormal, the local service node sends the second internal device data to the central platform.
[0119] The data association model can be understood as a cluster of multiple association networks, such as Fig.10As shown, each associated network includes peripheral data and internal data that are associated with each other. The association between each other can be understood as data collected from the same device, or collected from pipelines or other areas closely related to the device. For example, a blast furnace hot blast stove has its own feeding system and instrument control system. These two systems are equipped with corresponding sensors inside the hot blast stove for measuring the cold air flow rate, cold air temperature, fuel flow rate, hot air flow rate and hot air temperature of the hot blast stove. However, for users, in order to ensure the safety of workers in the production process, it may be necessary to monitor the CO concentration in the environment or the outer wall temperature of the hot blast stove. In this case, it is necessary to install an additional temperature sensor on the outer wall of the hot blast stove, and to set a CO detector at a position close to the hot blast stove in the workshop where the hot blast stove is located. In this case, the temperature sensor and CO detector installed on the outer wall of the hot blast stove are external sensors, and the sensors for measuring the cold air flow rate, cold air temperature, fuel flow rate, hot air flow rate and hot air temperature of the hot blast stove are internal sensors, and the temperature sensor, CO detector, and sensors for measuring the cold air flow rate, cold air temperature, fuel flow rate, hot air flow rate and hot air temperature of the hot blast stove installed on the outer wall of the hot blast stove are all included in an associated network. The internal data is used to analyze the cause of the abnormality when the corresponding external data is abnormal.
[0120] In actual use, which data are internal data and which are external data can be specified by technical personnel in this field, such as setting data that directly affects important safety indicators of personnel or production processes as external data, and setting other data as internal data.
[0121] The mapping relationship includes one or more of a linear relationship, an inverse proportional relationship, and a quadratic correlation relationship. The analysis of whether there is a mapping relationship between the external data and the internal data can be understood as a process of fitting the relationship between the external data and the internal data. The linear relationship is y=kx+b; wherein x is the value of the external data, y is the value of the internal data, k and b are coefficients in the linear relationship, obtained by fitting. The inverse proportional relationship is ; Where x is the value of the external data, y is the value of the internal data, k and b are the coefficients in the inverse proportional relationship, obtained by fitting. The quadratic correlation is ; Where x is the value of the external data, y is the value of the internal data, , and b are the coefficients in the quadratic correlation, obtained by fitting.
[0122] This embodiment first analyzes the mapping relationship between the peripheral data and the internal data, and uses the existence of the mapping relationship as the basis for whether to transmit the internal data. That is, if the analysis shows that the mapping relationship exists, the internal data is sent to the central platform only when the corresponding peripheral data is abnormal, otherwise the internal data is not sent, thereby reducing the amount of data transmitted, and instead the central platform generates simulated internal data according to the mapping data for corresponding monitoring. In this implementation, the central platform can adjust the mode of displaying the internal data by itself, such as switching the mode to Figure 6 In the overall planning mode shown, internal data is not displayed, only external data is displayed. Switch the mode to Fig.11 In the professional mode shown, internal data (i.e., data monitored by sensors inside the device) and external data (i.e., data monitored by sensors outside the device) are displayed.
[0123] In order to improve the analysis efficiency of the mapping relationship, this embodiment also provides a preferred implementation method, that is, the local service node stores the mapping relationships obtained by analysis in a local relationship table; wherein the local relationship table includes one or more relationship entries, each relationship entry includes a relationship id, a data code of the external data, a data type of the external data, a data code of the internal data, a data type of the internal data, a mapping relationship type, and each variable in the mapping relationship; the analysis of whether there is a mapping relationship between the external data and the internal data, such as Fig.12 As shown, specifically including:
[0124] In step 501, it is searched whether there is a first relational entry matching the data type of the peripheral data and the data type of the internal data in the local relational table; wherein the data type includes one or more of temperature, pressure, liquid level, rotation speed, volume, flow rate, gas concentration, interlocking state, height, speed, wind pressure, current, voltage, material level, weight, frequency, vibration and opening degree. The mapping relationship type includes one or more of linear relationship, inverse proportional relationship and quadratic correlation relationship. The first relational entry matching the data type of the peripheral data and the data type of the internal data is specifically: the data type of the peripheral data in the first relational entry is the same data type as the peripheral data to be analyzed, and the data type of the internal data in the first relational entry is the same data type as the internal data to be analyzed. For example, if the mapping relationship between the outer wall temperature (peripheral data) and the hot air temperature (internal data) of the hot blast furnace is to be analyzed, and in the local relational table, there is a relational entry in which the data type of the peripheral data is temperature, and the data type of the internal data in the relational entry is also temperature, then the relational entry is the first relational entry.
[0125] In step 502, if there is a first relationship entry, the mapping relationship type of the first relationship entry is preferentially used to match the mapping relationship between the external data and the internal data. If the mapping relationship matching using the first relationship entry fails, other mapping relationship types are used for matching.
[0126] In step 503, if the first relationship entry does not exist, the mapping relationships are matched in sequence according to the preset order until the match is successful; wherein, the preset order is obtained by a technician in this field based on the complexity of each mapping relationship type. For example, in actual use, the preset order can be a linear relationship, an inverse proportional relationship, and a quadratic correlation relationship arranged in sequence, so that the linear relationship is matched first. If the match fails, the inverse proportional relationship is matched, and finally the quadratic correlation relationship is matched.
[0127] The above implementation can be understood as giving priority to using the existing mapping relationship types of the same type of data to analyze the mapping relationship. If the analysis does not conform to the mapping relationship type, other mapping relationship types are used to analyze the mapping relationship. This is because there may be multiple types of the same or similar devices on the same base. For these devices, the relationship type between their peripheral data and internal data is relatively fixed. The only difference is the change in the coefficient in the mapping relationship caused by the different installation positions of the peripheral sensors. Therefore, the mapping relationship types that have been analyzed for the same data type are given priority for analysis, thereby improving the efficiency of the mapping relationship analysis.
[0128] In actual use, there may be multiple peripheral data in an associated network. In this case, the user can specify a peripheral data as the subject for mapping relationship analysis with the corresponding internal data, such as Fig.10 In the embodiment, the external data 1 is set as the subject of the mapping relationship analysis of each internal data in the associated network 1, so that both the internal data 1 and the internal data 2 analyze the mapping relationship with the external data 1; there is also an implementation method as follows:
[0129] The temporary mapping relationship between each peripheral device data and the first internal device data in the associated network within a first time length is analyzed and obtained; the first time length is obtained by a technician in this field based on experience analysis.
[0130] Calculate the difference between each temporary mapping relationship and the first internal data; use the external device data corresponding to the temporary mapping relationship with the smallest difference as the subject of the mapping relationship analysis with the first internal data, and perform the mapping relationship analysis; wherein the first time length is less than the data time length required for the mapping relationship analysis. It can be understood that the data within the first time length is used to perform a rough mapping relationship analysis, so as to determine which external device data has the highest correlation with the first internal data, and then use the external device data with the highest correlation within a longer time period to perform the actual mapping relationship analysis with the first internal data.
[0131] The difference between each temporary mapping relationship and the first internal data is specifically: ; Where D is the difference, is the temporary internal data value at the i-th moment calculated using the temporary mapping relationship, is the internal data value actually collected at the i-th moment, i is the sampling moment, and n is the total number of samples.
[0132] This embodiment also provides a preferred implementation, that is, the method further includes: after receiving the first mapping relationship from the first local service node, the central platform matches the base model of the first local service node with the base models of each second local service node.
[0133] If the corresponding second local service node matches the first local service node successfully, the first mapping relationship is sent to the second local service node, so that the second local service node can use the first mapping relationship to verify the internal data and peripheral data of its own base. If it is verified that the relevant data of its own base satisfies the first mapping relationship, a verification success message is sent to the central platform, and the second local service node no longer analyzes its own mapping relationship, but uses the first mapping relationship instead.
[0134] The central platform establishes a corresponding relationship between the first mapping relationship and the relevant data in the second local service node according to the verification success message, so as to realize the monitoring of the equipment of the second local service node using the first mapping relationship. The relevant data is obtained after the second local service node successfully matches the first local service node, specifically:
[0135] The base model includes the production line of the corresponding base, as well as the type (i.e., the type of equipment, such as a blast furnace, hot blast stove, or other equipment) and model of each equipment on the production line. The production line is actually represented by the production line connection relationship between the equipment, such as Fig.13 The figure shows a schematic diagram of an ironmaking production line in actual use, wherein the base model of the first local service node is matched with the base models of each second local service node, specifically including:
[0136] For the first device associated with the first mapping relationship, if there is a second device of the same type and model as the first device in the second base model, and the first upstream devices of the production line where the second device is located match the second upstream devices of the production line where the first device is located, then the second local service node matches the first local service node successfully, and the same type of peripheral data and the same type of internal data associated with the second device (that is, located in the associated network corresponding to the second device) are data of the same category as the peripheral data in the first mapping relationship, and the same type of internal data is data of the same category as the internal data in the first mapping relationship. The same category means that the meaning of the collected data is consistent. For example, when the first mapping relationship is the hot air temperature (internal data) and the outer wall temperature (external data) of a hot air furnace, the second device should also be a hot air furnace, and the hot air temperature and the outer wall temperature of the hot air furnace are the above-mentioned related data.
[0137] Among them, the second base model is the base model of the second local service node, the production line where the first device is located is included in the first base model, the first base model is the base model of the first local service node, and the first device associated with the first mapping relationship is the device corresponding to the associated network where the internal data and external data involved in the first mapping relationship are located.
[0138] The first upstream devices of the production line where the second device is located match the second upstream devices of the production line where the first device is located, including: the first production line connection relationship is consistent with the second production line connection relationship, and the type of equipment located at the corresponding position on the first production line is the same as the type of equipment located at the same position on the second production line; wherein, the first production line connection relationship is the production line connection relationship between each first upstream device and the first device, and the second production line connection relationship is the production line connection relationship between each second upstream device and the second device.
[0139] The first base model includes Fig.13 For example, if the production line shown in the figure is a blast furnace, then in the corresponding second base model, there is a production line a which also has a blast equipment, a hot blast furnace, a pulverized coal preparation and blowing equipment, an oxygen supply equipment and a blast furnace, and the blast furnace has the same model as the first equipment, and at the same time, the production line connection relationship between the blast equipment, the hot blast furnace, the pulverized coal preparation and blowing equipment, the oxygen supply equipment and the blast furnace in the production line a is also as follows: Fig.13 As shown, the output of the blast equipment, the output of the hot blast stove, the output of the pulverized coal preparation and blowing equipment, and the output of the oxygen supply equipment are all input into the blast furnace, and the second base model successfully matches the first base model.
[0140] The second local service node verifies the internal data and the external data of the base where the second local service node is located by using the first mapping relationship, specifically including:
[0141] Find a second device located at the same position on the same production line as the first device, and find out from the associated network corresponding to the second device whether there is second built-in data of the same type as the first built-in data involved in the first mapping relationship, and second peripheral data of the same type as the first peripheral data involved in the first mapping relationship, use the second peripheral data and the first mapping relationship to calculate the simulated built-in data, and calculate the difference between the first mapping relationship and the second built-in data. The specific implementation of the difference has been described in the above embodiment, that is, ; Where D is the difference, is the temporary internal data value at the i-th moment calculated using the first mapping relationship, is the second internal data value actually collected at the i-th moment, i is the sampling moment, and n is the total number of samples.
[0142] If the calculated difference is less than the preset difference, it is verified that the relevant data of the base where the user is located satisfies the first mapping relationship; wherein the preset difference is obtained by those skilled in the art based on empirical analysis.
[0143] In actual application scenarios, after the risk warning item is displayed, the staff is still required to handle the warning. During the warning handling process, there may be some precautions. For this scenario, this embodiment also provides a preferred implementation method, which specifically includes:
[0144] Find the warning treatment tree corresponding to the risk warning item; wherein the warning treatment tree has the risk warning item as the root node, the operation step information for warning treatment as the first-level child node, and the precautions information of the operation step as the second-level child node; the second-level child node is the subordinate node of the first-level child node, such as Fig.14 shown.
[0145] The operation step information and precaution information in the early warning disposal tree are sent to the terminal, so that the terminal can display the operation step information and precaution information on the interactive interface, so that the user can perform early warning disposal according to the operation step information and precaution information.
[0146] In a preferred embodiment, the first-level sub-node further stores first monitoring data associated with the operation step and change information of the first monitoring data, the first monitoring data can be understood as monitoring data that will be affected by the execution of the operation step, and the second-level sub-node further stores consequence information of precautions, second monitoring data associated with the precautions, and monitoring safety range of the second monitoring data, the second monitoring data can be understood as data that will cause the data value to exceed the monitoring safety range if the precautions are not followed; the method further includes:
[0147] After obtaining the risk warning item, each first monitoring data in the warning disposal tree of the risk warning item is monitored; when the corresponding first monitoring data is monitored to have changed, and the change is consistent with the corresponding change information, it is considered that the user has executed the operation steps corresponding to the first monitoring data; the change information can be a change in the state of the corresponding monitoring data, such as from an abnormal state to a normal state, or a change in the numerical value of the monitoring data. In actual use, the safety information can be presented in the form of a tuple, with the value close to the front side of the tuple as the value before the change, and the value close to the back side of the tuple as the value after the change, such as using a binary tuple X=(x1,x2), where x1 is greater than x2, and the binary tuple represents that the value of the monitoring data changes from greater than x1 to less than x2, and the compliance with the change information, that is, the value of the first monitoring data changes from greater than x1 to less than x2, at this time, it is determined that the user has executed the operation steps corresponding to the change information (that is, the operation steps located in the same first-level child node as the change information).
[0148] The second monitoring data corresponding to the operation step is selected to determine whether the second monitoring data within the preset time period before the corresponding operation step is executed is within the monitoring safety range; the preset time period before the execution of the corresponding operation step actually refers to the time when the user is determined to have executed the corresponding operation step as t1, and the preset time period before t1 is the preset time period before the execution of the corresponding operation step. The preset time period is obtained by those skilled in the art based on demand analysis, and when the second monitoring data within the preset time period is within the monitoring safety range, it is considered that the user has followed the precautions.
[0149] If it is determined that the second monitoring data is outside the monitoring safety range, it is determined that the user did not follow the precautions when taking early warning measures, and the consequence information in the secondary subnode where the second monitoring data is located is sent to the terminal so that the terminal can display the consequence information on the interactive interface, such as Fig.15 As shown, an emergency prompt is displayed in the warning box, in which the precautions and consequences of not following are explained. The warning box is obtained by clicking on the detailed information position of the corresponding warning item to expand it or automatically popping up according to the warning level of the risk warning item.
[0150] It should be noted here that Figure 4 , Figure 5 , Figure 6 , Fig.11 and Fig.15 All of them are schematic diagrams of the corresponding interactive interfaces. In actual application scenarios, the interactive interface is actually presented in a more vivid form. The interactive interface is divided into four parts: navigation bar, left display area, right display area, central area and warning area. Among them, the navigation bar is used to display some rough information, the left display area and the right display area are used to display corresponding data, the central area is used for graphical map display of multiple workshops or multiple bases, and displays the status of the corresponding workshops or bases, and the warning area displays relevant information of the risk warning items.
[0151] In some views, the left display area of the central platform displays the warning status of all bases in a coordinated manner, including the total number of risk warning items with the highest warning level of all bases (i.e. the number of red warnings), the bases with risk warning items with the highest warning level, and the number of risk warning items in history of each base. The right display area conducts risk assessment based on the risk warning items of each base, displays the risk status of each base in a visual form, and displays equipment with risks. The central area displays the total number of risk warning items today in a graphical form, divides the risk warning items according to the industry in which each base is located, and displays the number of risk warning items in each industry in a graphical form. The warning area displays the number of risk warning items of each warning level of each base.
[0152] In another view, the left display area of the central platform displays the number of risk warning items at each warning level for all bases, the bases with risk warning items, and the number of risk warning items for corresponding equipment in history. The right display area displays the risk situation of each base in a visual form, and displays statistics in units of months, and displays equipment with risks. The central area displays the location of each base on a graphical map, and displays the number of risk warning items at each warning level for each base. The warning area still displays the number of risk warning items at each warning level for each base. The central area supports users to perform operations such as dragging and zooming. By double-clicking the corresponding base location on the graphical map, you can enter the base and enter the base display view.
[0153] In the base display view of the central platform, the central area displays each plant or workshop in the form of an actual bird's-eye view map, and adds graphic marks to the plants or workshops with corresponding risk warning items. The left display area displays the number of risk warning items of each warning level of the corresponding base and the number of risk warning items of the corresponding equipment in history. The right display area displays the risk situation of the base in a visual form, and displays statistics in units of months, and also displays the equipment with risks in the base. The warning area displays the number of risk warning items of each warning level of each plant or workshop in the base.
[0154] The interfaces of the local service node are basically consistent with the base display view of the central platform. For the terminal, its display interface is consistent with that of the local service node. The only difference is that the monitoring data and risk warning items displayed and analyzed by the two are different. For example, for a terminal that manages a factory, it only displays the monitoring data and risk warning items of each workshop in the factory and the equipment in each workshop. For the local service node, it displays the monitoring data and risk warning items of each workshop in all factories and all workshop equipment.
[0155] In actual use, the interactive interface of the central platform also provides a horizontal comparison function for users to compare and view the warning status of the two devices, including the number of risk warning items of the two devices in the current month, the current number of risk warning items, the warning duration and a graphical display of important data.
[0156] The central platform and local service nodes also provide an early warning box, which displays detailed information of risk warning items. For devices, a risk point details box is also provided to display important data of the equipment, risk warning items, and the location of the workshop or factory where the equipment is located, and a traceability function is provided. The traceability function interface displays the impact of each risk warning item on the current risk situation, that is, the current overall risk situation.
[0157] In some views, the central platform also displays each risk warning item in the form of a list, and displays the historical warning situation in a graphical form. It also provides a warning evaluation function, in which the historical warning situation curve is displayed in the warning evaluation function interface. It also provides a warning information statistics function, in which the warning statistics in the corresponding base are displayed in the warning information function interface, including the proportion of risk warning items at each warning level, the number of risk warning items at different warning levels in each plant, the total number of risk warning items in each plant, and the historical number change curve of risk warning items.
[0158] Since in some scenarios, it is also necessary to meet the need for risk management and control on the terminal, this embodiment also provides the following Fig.16 , Fig.17 and Fig.18The interactive interface of the central platform shown in the figure should be explained here. Figure 16-Figure 18 These are all schematic diagrams of interactive interfaces in actual application scenarios, which only represent a possible presentation form and do not limit the actual use of this embodiment to be presented in this way.
[0159] In an actual application scenario, the second-level sub-node also stores a first warning item associated with the precautions; the method further includes:
[0160] Before sending the consequence information in the secondary sub-node where the second monitoring data is located to the terminal, check whether the first warning item in the secondary sub-node has been diagnosed as a risk warning item; if so, add the consequence information as a cause label of the risk warning item, and send the risk warning item carrying the cause label to the terminal, so that the terminal can display the consequence information as a cause of the risk warning item in the warning box of the risk warning item.
[0161] Embodiment 2:
[0162] Based on Example 1, this embodiment also provides an intelligent management and control system for major security risks of an enterprise, such as Fig.19 As shown, it includes sensors, local service nodes and central platform.
[0163] The sensor is used to collect real-time data in the workshop and transmit the real-time data to the local service node; wherein the real-time data includes video data of different workshops and monitoring data of each device in different workshops.
[0164] The local service node is used to receive real-time data from each work workshop; while storing the real-time data in the local data center, the local service node also transmits the video data to the corresponding terminal according to the source of the video data for display in the terminal; the local service node also compares the monitoring data with the corresponding monitoring threshold to determine whether there is an abnormality in the monitoring data. If there is an abnormality in the monitoring data, the monitoring data is marked with a corresponding abnormal label, and an early warning item analysis is performed based on the abnormal monitoring data to obtain risk early warning items. The risk warning items, each monitoring data and the abnormal label carried by the corresponding monitoring data are transmitted to the corresponding terminal for display in the terminal.
[0165] The local service node also transmits the video data, risk warning items, various monitoring data and abnormal labels carried by the corresponding monitoring data to the central platform; the central platform is used to perform risk management and control of multiple bases.
[0166] This embodiment also provides an intelligent management and control device for major security risks of an enterprise, such as Fig. 20, is a schematic diagram of the architecture of an intelligent management and control device for major security risks of an enterprise according to an embodiment of the present invention. The intelligent management and control device for major security risks of an enterprise according to this embodiment includes one or more processors 21 and a memory 22. Fig. 20 A processor 21 is taken as an example.
[0167] The processor 21 and the memory 22 may be connected via a bus or other means. Fig. 20 The example of connecting through bus is taken in the following.
[0168] The memory 22 is a non-volatile computer-readable storage medium that can be used to store non-volatile software programs and non-volatile computer executable programs, such as the intelligent management and control method for major safety risks of enterprises in Example 1. The processor 21 executes the intelligent management and control method for major safety risks of enterprises by running the non-volatile software programs and instructions stored in the memory 22.
[0169] The memory 22 may include a high-speed random access memory, and may also include a non-volatile memory, such as at least one disk storage device, a flash memory device, or other non-volatile solid-state storage devices. In some embodiments, the memory 22 may optionally include a memory remotely arranged relative to the processor 21, and these remote memories may be connected to the processor 21 via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0170] The program instructions / modules are stored in the memory 22, and when executed by the one or more processors 21, the method for intelligent management and control of major enterprise security risks in the above-mentioned embodiment 1 is executed.
[0171] It is worth noting that the information interaction, execution process, etc. between the modules and units within the above-mentioned devices and systems are based on the same concept as the processing method embodiment of the present invention. The specific contents can be found in the description of the method embodiment of the present invention and will not be repeated here.
[0172] A person skilled in the art may understand that all or part of the steps in the various methods of the embodiments may be completed by instructing related hardware through a program, and the program may be stored in a computer-readable storage medium, and the storage medium may include: a read-only memory (ROM), a random access memory (RAM), a disk or an optical disk, etc.
[0173] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. An intelligent management and control method for major security risks of an enterprise, characterized in that: Set up local service nodes at each base and set up a central platform for multiple bases, including: Receive real-time data from each workshop; wherein the real-time data includes video data of different workshops and monitoring data of each device in different workshops, and the real-time data is collected by sensors; The local service node stores the real-time data in the local data center and transmits the video data to the corresponding terminal according to the source of the video data so as to display it in the terminal; The local service node also compares the monitoring data with the corresponding monitoring threshold to determine whether the monitoring data is abnormal. If the monitoring data is abnormal, the monitoring data is marked with a corresponding abnormal label, and an early warning item analysis is performed based on the abnormal monitoring data to obtain a risk early warning item. The risk early warning item, each monitoring data, and the abnormal label carried by the corresponding monitoring data are transmitted to the corresponding terminal for display in the terminal; The local service node also transmits the video data, risk warning items, various monitoring data and abnormal labels carried by the corresponding monitoring data to the central platform, so that the central platform can perform multi-base risk management and control; The monitoring data is specifically peripheral data collected by an external sensor installed by a user, and the method further comprises: collecting internal data of an internal sensor in each device; When the local service node determines that the peripheral data is normal, the local service node finds the internal data associated with the peripheral data according to a preset data association model, and analyzes whether there is a mapping relationship between the peripheral data and the internal data; If there is a mapping relationship between the peripheral data and the internal data, the mapping relationship is sent to the central platform; For the first internal data which has no mapping relationship with the external data, synchronously sending the first internal data to the central platform according to the sending frequency of the external data; For the second built-in data that has a mapping relationship with the peripheral data, when the local service node determines that the peripheral data is normal, the second built-in data is not sent to the central platform. The central platform generates simulated built-in data according to the mapping relationship between the second built-in data and the peripheral data, and uses the simulated built-in data to realize the monitoring of the corresponding device; When the local service node determines that the peripheral device data is abnormal, the local service node sends the second internal device data to the central platform.
2. The intelligent management and control method for major safety risks of an enterprise according to claim 1 is characterized in that: The local service node also transmits the video data, risk warning items, various monitoring data and abnormal labels carried by the corresponding monitoring data to the central platform, specifically including: The video data is transmitted to the central platform using the streaming protocol, and the risk warning items, each monitoring data and the abnormal labels carried by the corresponding monitoring data are transmitted to the central platform using the RESTFUL protocol.
3. The intelligent management and control method for major safety risks of an enterprise according to claim 1 is characterized in that: When the local service node is put into use for the first time, it uses the IP address of the central platform to establish a network connection with the central platform; When the central platform detects the presence of a newly connected local service node, it sends a base information acquisition instruction to the local service node, and the local service node returns the base information to the central platform according to the base information acquisition instruction; wherein the base information includes the base code and the codes of each plant department of the base; Sending a device information acquisition instruction to the local service node, and the local service node returns the device information to the central platform according to the device information acquisition instruction; wherein the device information acquisition instruction carries the base code and the corresponding factory code of the base, and the device information includes the device code and device name of each device in the corresponding factory; The central platform establishes a base risk management table item according to the base information and the equipment information, and establishes a data transmission channel with the local service node according to the base information to transmit the monitoring data and abnormal labels corresponding to each device; The central platform analyzes monitoring data and abnormal labels according to the base risk management and control table items.
4. The intelligent management and control method for major safety risks of an enterprise according to claim 1 is characterized in that: The mapping relationship includes one or more of a linear relationship, an inverse proportional relationship and a quadratic correlation relationship.
5. The intelligent management and control method for major safety risks of an enterprise according to claim 4 is characterized in that: The mapping relationships obtained through analysis are stored in a local relationship table; wherein the local relationship table includes one or more relationship entries, each relationship entry includes a relationship ID, a data code of the external data, a data type of the external data, a data code of the internal data, a data type of the internal data, a mapping relationship type, and variables in the mapping relationship; the analyzing whether there is a mapping relationship between the external data and the internal data specifically includes: Searching in the local relationship table whether there is a first relationship entry that matches the data type of the external device data and the data type of the internal device data; If there is a first relationship entry, the mapping relationship type of the first relationship entry is preferentially used to match the mapping relationship between the peripheral data and the internal data. If the mapping relationship matching using the first relationship entry fails, other mapping relationship types are used for matching.
6. The intelligent management and control method for major safety risks of an enterprise according to claim 1 is characterized in that: The monitoring data includes one or more of the temperature, pressure, liquid level, rotation speed, volume, flow rate, gas concentration, interlocking status, height, speed, wind pressure, current, voltage, material level, weight, frequency, vibration and opening degree of the equipment.
7. An intelligent management and control device for major safety risks of an enterprise, characterized in that: include: at least one processor; And, a memory communicatively connected to the at least one processor; wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the processor to execute the method for intelligent management and control of major security risks of an enterprise as described in any one of claims 1-6.
8. A non-volatile computer storage medium, characterized in that: The computer storage medium stores computer executable instructions, which are executed by one or more processors to complete the intelligent management and control method for major enterprise security risks as described in any one of claims 1-6.
9. An intelligent management and control system for major safety risks of an enterprise, characterized in that: Includes sensors, local service nodes and central platform; The sensor is used to collect real-time data in the workshop and transmit the real-time data to the local service node; wherein the real-time data includes video data of different workshops and monitoring data of each device in different workshops; The local service node is used to receive real-time data from each work shop; The local service node stores the real-time data in the local data center and transmits the video data to the corresponding terminal according to the source of the video data so as to display it in the terminal; The local service node also compares the monitoring data with the corresponding monitoring threshold to determine whether the monitoring data is abnormal. If the monitoring data is abnormal, the monitoring data is marked with a corresponding abnormal label, and an early warning item analysis is performed based on the abnormal monitoring data to obtain a risk early warning item. The risk early warning item, each monitoring data, and the abnormal label carried by the corresponding monitoring data are transmitted to the corresponding terminal for display in the terminal; The local service node also transmits the video data, risk warning items, various monitoring data and abnormal labels carried by the corresponding monitoring data to the central platform; The central platform is used to perform risk management and control on multiple bases; The monitoring data is specifically peripheral data collected by an external sensor installed by a user, and the system further comprises: collecting internal data of internal sensors in each device; When the local service node determines that the peripheral data is normal, the local service node finds the internal data associated with the peripheral data according to a preset data association model, and analyzes whether there is a mapping relationship between the peripheral data and the internal data; If there is a mapping relationship between the peripheral data and the internal data, the mapping relationship is sent to the central platform; For the first internal data which has no mapping relationship with the external data, synchronously sending the first internal data to the central platform according to the sending frequency of the external data; For the second built-in data that has a mapping relationship with the peripheral data, when the local service node determines that the peripheral data is normal, the second built-in data is not sent to the central platform. The central platform generates simulated built-in data according to the mapping relationship between the second built-in data and the peripheral data, and uses the simulated built-in data to realize the monitoring of the corresponding device; When the local service node determines that the peripheral device data is abnormal, the local service node sends the second internal device data to the central platform.
Citation Information
Patent Citations
Risk monitoring method and device
CN113487212A
Joint early warning system of shop safety production to many automobile manufacturing base
CN208522791U
Cited By
Chemical workshop safety risk online management and control system
CN120335355A