A self-adaptive heat dissipation control method for electric energy meter

By building a multi-state data set and temperature prediction module, combining the standard timing characteristics of the power meter, the adaptive heat dissipation control of the power meter is realized, which solves the problems of low heat dissipation efficiency and high energy consumption in the existing technology, and improves the reliability of the equipment and lifespan.

CN118829174BActive Publication Date: 2024-11-26JIANGSU DADIAN ENERGY TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411195280.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-11-26
Estimated Expiration
2044-08-29

AI Technical Summary

Technical Problem

The existing power meters cannot adaptively adjust the heat dissipation control parameters under different working conditions, resulting in low heat dissipation efficiency and high energy consumption, making it difficult to cope with complex working environments and load changes.

Method used

By constructing a multi-state data set, fit the impact relationship between temperature and load, obtain the standard timing characteristics of the power meter, build a temperature prediction module and an adaptive activation mechanism, and adjust the heat dissipation equipment in real time to achieve adaptive control.

Benefits of technology

It improves the heat dissipation efficiency and reliability of the power meter, ensures stable operation under different working conditions, extends the equipment life and reduces the risk of failure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118829174B_ABST
    Figure CN118829174B_ABST
Patent Text Reader

Abstract

The present invention discloses an adaptive heat dissipation control method for an electric energy meter, which belongs to the technical field of heat dissipation control for electric energy meters, wherein the method comprises: constructing a multi-state data set; fitting the temperature influence relationship and load influence relationship of each working state according to the multi-state data set; obtaining the standard timing characteristics of the electric energy meter; adaptively allocating the real-time working demand according to the temperature influence relationship, load influence relationship and standard timing characteristics of the electric energy meter of each working state; constructing a temperature prediction module, which is associated with the response time of the working demand; constructing an adaptive activation mechanism using a temperature monitoring module and a temperature prediction module, and the adaptive control module is connected to a heat dissipation controller for adaptively controlling the heat dissipation device. The present application solves the technical problem that the electric energy meter in the prior art cannot adaptively adjust the heat dissipation control parameters according to different working states, thereby resulting in low heat dissipation efficiency and high energy consumption of the electric energy meter under different working conditions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of heat dissipation control of electric energy meters, and in particular to an adaptive heat dissipation control method for electric energy meters. Background Art

[0002] The energy meter is a key device used to measure and record energy consumption in the power system and is widely used in residential, commercial and industrial fields. With the development of smart grids, modern energy meters are not only simple energy metering devices, but also integrate functions such as communication, data analysis and remote control. These new functions cause the energy meter to generate higher internal temperature during long-term operation, especially under high load conditions, and the heat dissipation problem is particularly important.

[0003] Traditional energy meters mainly rely on natural heat dissipation or simple heat sinks to dissipate heat. These methods work well when the load is low or the operation is short-term, but when the energy meter is running at high load for a long time, the heat dissipation effect is often unsatisfactory, which can easily cause the internal temperature of the energy meter to be too high, thus affecting its normal operation and service life. The working environment of modern energy meters is complex and changeable, and the load changes significantly in different time periods. Existing fixed heat dissipation strategies are difficult to cope with these changes, resulting in low heat dissipation efficiency or excessive energy consumption.

[0004] Therefore, there is an urgent need for a heat dissipation control method that can adaptively adjust according to the actual working state and environmental conditions of the electric energy meter to improve the heat dissipation efficiency, reduce energy consumption, and ensure the reliability of the electric energy meter under various working conditions. Summary of the invention

[0005] The present application provides an adaptive heat dissipation control method for an electric energy meter, aiming to solve the technical problem in the prior art that the electric energy meter cannot adaptively adjust the heat dissipation control parameters according to different working states, thereby resulting in low heat dissipation efficiency and high energy consumption of the electric energy meter under different working conditions.

[0006] In view of the above problems, the present application provides an adaptive heat dissipation control method for an electric energy meter.

[0007] The first aspect disclosed in the present application provides an adaptive heat dissipation control method for an electric energy meter, the method comprising constructing a multi-state data set, wherein the multi-state data set is data of the electric energy meter under multiple working states, including current, voltage, and temperature; fitting the temperature influence relationship and load influence relationship of each working state according to the multi-state data set; acquiring the standard timing characteristics of the electric energy meter, wherein the standard timing characteristics of the electric energy meter reflect the state characteristics of the electric energy meter within a daily cycle, including a high-load area, a standard area, and a low-load area; adaptively allocating real-time work demands according to the temperature influence relationship, load influence relationship of each working state and the standard timing characteristics of the electric energy meter, and determining the response time of the work demands; constructing a temperature prediction module, wherein the temperature prediction module is associated with the response time of the work demands; constructing an adaptive activation mechanism using a temperature monitoring module and the temperature prediction module, and generating an adaptive control module, wherein the adaptive control module is connected to a heat dissipation controller for adaptively controlling a heat dissipation device.

[0008] One or more technical solutions provided in this application have at least the following technical effects or advantages:

[0009] By constructing a multi-state data set and collecting data under various working states such as current, voltage and temperature, the operation of the electric energy meter can be accurately grasped. Based on these data, the temperature influence relationship and load influence relationship under each working state are fitted to clarify the influence of different working states on temperature and load. Furthermore, by obtaining the standard time series characteristics of the electric energy meter, reflecting its state characteristics in the daily cycle, including high-load area, standard area and low-load area, the load condition of the electric energy meter in different time periods can be accurately predicted, which solves the technical problem that the electric energy meter in the prior art cannot adaptively adjust the heat dissipation control parameters according to different working states, resulting in low heat dissipation efficiency and high energy consumption of the electric energy meter under different working conditions, and realizes intelligent control of the heat dissipation of the electric energy meter, which effectively improves the reliability and efficiency of the electric energy meter.

[0010] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application, it can be implemented in accordance with the contents of the specification. In order to make the above and other purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are listed below. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 A flow chart of a method for adaptive heat dissipation control of an electric energy meter is provided for an embodiment of the present application.

[0012] Figure 2 A schematic flow chart of determining the response time of working requirements in an adaptive heat dissipation control method for an electric energy meter is provided for an embodiment of the present application; DETAILED DESCRIPTION

[0013] The overall idea of ​​the technical solution provided by this application is as follows:

[0014] The embodiment of the present application provides an adaptive heat dissipation control method for an electric energy meter. By constructing a multi-state data set, data under various working states such as current, voltage and temperature are collected to accurately understand the operation of the electric energy meter. Based on these data, the influence relationship between temperature and load is fitted, and combined with the standard timing characteristics of the electric energy meter, its state changes within the daily cycle are reflected. Based on these influence relationships and timing characteristics, real-time work requirements are adaptively allocated to determine the response time. A temperature prediction module is constructed to associate it with the response time of the work requirements, and an adaptive activation mechanism is constructed using the temperature monitoring module and the prediction module. The heat dissipation controller is connected through the adaptive control module to achieve adaptive control of the heat dissipation device, thereby improving the heat dissipation efficiency and equipment safety of the electric energy meter.

[0015] After introducing the basic principles of the present application, various non-limiting implementation methods of the present application will be specifically described below in conjunction with the drawings in the specification.

[0016] Example

[0017] like Figure 1 As shown, an embodiment of the present application provides an adaptive heat dissipation control method for an electric energy meter, the method comprising:

[0018] Step S100: construct a multi-state data set, which is data of the electric energy meter under various working states, including current, voltage, and temperature.

[0019] Specifically, during the operation of the energy meter, appropriate sensors are installed inside and outside the energy meter to monitor the current, voltage and temperature in real time. During the daily operation of the energy meter, the current, voltage and temperature data are continuously collected. Among them, it is necessary to ensure that the frequency of data collection is high enough to capture the changes in the operating status of the energy meter. For example, data is collected once every second.

[0020] Secondly, in order to obtain comprehensive data, it is necessary to collect data under various working conditions of the energy meter. The definition of specific working conditions can be divided according to the specific range of current and voltage. Among them, various working conditions refer to different working conditions, such as different load levels, different time periods, etc., including:

[0021] Normal working state: The energy meter operates under standard working conditions, and parameters such as current, voltage and temperature are within the normal range. Example: In factory energy consumption monitoring, when a certain device is working stably, the DC energy meter monitors a current of 5A, a voltage of 220V, and a temperature of 30°C, which remain stable. At this time, the energy meter is in normal working state.

[0022] Overload state: The circuit or equipment load connected to the energy meter exceeds its rated carrying capacity, causing parameters such as current, voltage or temperature to exceed the normal range. Example: In the energy-saving management of commercial buildings, a merchant's power consumption surged due to equipment failure. The DC energy meter detected that the current suddenly rose to 15A (exceeding the rated value), the voltage fluctuated to 240V, and the temperature also rose rapidly. At this time, the energy meter entered the overload state.

[0023] Abnormal state: The energy meter itself fails or the connected device fails, causing the energy meter to fail to work properly or data to be abnormal. Example 1: In home energy management, the energy consumption of home appliances cannot be accurately measured due to damage to the internal components of the DC energy meter. At this time, the energy meter is in an abnormal state. Example 2: During the calibration of the energy meter, if the energy meter does not start or the disk does not rotate, it is found that the newly replaced current coil is installed in reverse. At this time, the energy meter is also in an abnormal state.

[0024] Energy-saving status: Through data analysis and management measures, the circuits or equipment connected to the energy meter have achieved energy-saving operation, and energy consumption has been significantly reduced. In factory energy consumption monitoring, by introducing DC energy meters and implementing energy-saving measures, such as replacing high-efficiency equipment and optimizing production plans, the energy consumption of the equipment has been reduced from the original 100kWh / h to 80kWh / h. At this time, the data monitored by the energy meter reflects the energy-saving status.

[0025] Finally, the collected data is stored to form a multi-state data set, which contains detailed data records of the energy meter under various working conditions.

[0026] In this step, by constructing a multi-state data set, detailed data of the electric energy meter under different working states can be obtained, so that the operating characteristics of the electric energy meter can be analyzed and understood, and basic data can be provided for the subsequent fitting of temperature influence relationship and load influence relationship.

[0027] Step S200: fitting the temperature influence relationship and load influence relationship of each working state according to the multi-state data set.

[0028] Specifically, first, the current, voltage, and temperature data under each working state are extracted from the multi-state data set. The data is classified by working state, and the data of normal working state, overload state, abnormal state, and energy-saving state are processed separately. Among them, feature engineering includes: temperature features (temperature is the response variable, which is affected by current and voltage); load features (load is usually represented by the product of current and voltage, that is, power (P=IV).) Then, the classified data is preprocessed. First, the missing data is filled or deleted. Then the current, voltage, and temperature data are normalized to facilitate model fitting.

[0029] Then, select an appropriate regression model, such as linear regression, polynomial regression, decision tree regression, etc., to fit the relationship between temperature and load. According to the data characteristics and requirements, select the best model for fitting. Among them, fitting the temperature influence relationship is to use temperature as the dependent variable, current and voltage as independent variables, and perform regression analysis. Then train the model to obtain the influence relationship between current and voltage on temperature.

[0030] Fitting the load influence relationship is to calculate the power (P = IV) as the load feature, take the load as the dependent variable, and the current and voltage as the independent variables, and perform regression analysis. Then train the model to obtain the influence relationship of current and voltage on the load.

[0031] Finally, use cross-validation or holdout method to evaluate the performance of the model to ensure the generalization ability of the model. The fitting effect of the model is evaluated by evaluation indicators (such as mean square error, R², etc.).

[0032] Based on this step, the temperature influence relationship and load influence relationship of the energy meter under different working conditions can be fitted. These models will help understand the behavior of the energy meter under various conditions and provide data support for adaptive heat dissipation control.

[0033] Step S300: obtaining standard time series characteristics of the electric energy meter, wherein the standard time series characteristics of the electric energy meter reflect the state characteristics of the electric energy meter in a daily cycle, including a high-load area, a standard area, and a low-load area.

[0034] Specifically, collect the current, voltage, and temperature data of the energy meter over a longer period of time (such as one month) to ensure that the data covers all time periods of 24 hours a day. Divide the 24 hours of a day into multiple time periods (such as one time period per hour). Count the current, voltage, and temperature data in each time period.

[0035] Calculate the average current, voltage and temperature in each time period. Identify the high-load area, standard area and low-load area. The high-load area refers to the electric energy meter working under high load conditions, with high current and voltage. The standard area: the electric energy meter works under normal load conditions, and the current and voltage are within the normal range. The low-load area: the electric energy meter works under low load conditions, with low current and voltage.

[0036] Based on the calculated average value, each time period is labeled as a high-load, standard, or low-load area. The regional division is further optimized through clustering algorithms (such as K-means). One month of data is analyzed to extract the typical state characteristics of the electric energy meter in the daily cycle. A standard time series feature chart is generated to show the distribution of high-load, standard, and low-load areas in a day.

[0037] Based on this step, the standard time series characteristics of the energy meter can be obtained, and the high-load area, standard area, and low-load area in the daily cycle can be identified. These characteristics help to understand the load situation of the energy meter and provide a reference for subsequent adaptive control.

[0038] Step S400: According to the temperature influence relationship and load influence relationship of each working state and the standard timing characteristics of the electric energy meter, the real-time working demand is adaptively allocated to determine the response time of the working demand.

[0039] Specifically, input temperature influence relationship: the temperature change model of the energy meter under different current and voltage conditions. Load influence relationship: the load condition model of the energy meter under different current and voltage conditions. Standard time series characteristics of the energy meter: describes the typical state of the energy meter in various time periods of the day, including high-load area, standard area and low-load area.

[0040] Then, the current, voltage and temperature data of the energy meter are collected in real time. The current time is obtained to determine the current time period. According to the current time period, the corresponding standard timing characteristics are matched to determine whether the current time period belongs to the high-load area, standard area or low-load area. Using the current and voltage data collected in real time, the current temperature is predicted through the temperature impact relationship model. The current load condition is predicted through the load impact relationship model.

[0041] Among them, the adaptive allocation means that if the predicted temperature approaches or exceeds the safety threshold, the load is appropriately reduced to prevent overheating. When the temperature and load are both within the normal range, the current load is maintained to maintain stable operation. If the predicted temperature is low, the load can be increased to improve efficiency. Then, the corresponding time is determined, that is, in the high-load area, if the predicted temperature is about to exceed the safety threshold, the load needs to be adjusted immediately. In the low-load area, the load is flexibly adjusted according to the actual situation, and the response time can be longer. When the temperature and load are both within the normal range, no adjustment is required.

[0042] Based on this step, the energy meter can be adaptively adjusted under different working conditions to avoid overheating under high load conditions, improve efficiency under low load conditions, and maintain stable operation under standard load conditions. This method combines the temperature influence relationship, load influence relationship and standard timing characteristics, and realizes the adaptive allocation of work demand and determination of response time through real-time prediction and adjustment.

[0043] Step S500: constructing a temperature prediction module, wherein the temperature prediction module is associated with the response time of the work demand.

[0044] Specifically, collect a large amount of historical data, including current, voltage, and temperature data, as well as the corresponding timestamps. Divide the data into training and test sets to ensure that the model can be effectively verified after training. Select relevant features, including current, voltage, time (hours), etc. Select a suitable machine learning model for temperature prediction, such as linear regression, decision tree regression, random forest regression, or other advanced models (such as neural networks). Use the training set data to train the model to fit the relationship between temperature and current, voltage, and other features. Use the test set data to evaluate the model performance and adjust the model parameters to improve the prediction accuracy. Common evaluation indicators include mean square error (MSE), root mean square error (RMSE), and determination coefficient (R²).

[0045] Furthermore, data such as current, voltage, and current time are collected in real time. The temperature prediction module is used to predict the current temperature. Based on the predicted temperature, the response time and adjustment strategy are determined. For example, when the predicted temperature is close to the safety threshold, the response is immediate; when the predicted temperature is low, the adjustment is flexible. The temperature prediction results are monitored in real time, and the load is dynamically adjusted to meet the work requirements. Safety and efficiency are ensured under different load conditions.

[0046] This step can realize intelligent adjustment of the energy meter under different working conditions and improve the operating efficiency and safety of the equipment by building a temperature prediction module and associating it with the work demand response time. The temperature prediction module dynamically predicts the temperature through real-time data input, and adjusts the work demand according to the prediction results and the current load area to ensure that the energy meter operates in the best state.

[0047] Step S600: construct an adaptive activation mechanism using the temperature monitoring module and the temperature prediction module to generate an adaptive control module, wherein the adaptive control module is connected to a heat dissipation controller for adaptively controlling the heat dissipation device.

[0048] Specifically, the temperature monitoring module monitors the current, voltage and temperature data of the electric energy meter in real time. The monitored data is used to detect the current temperature status in time. The temperature prediction module uses historical data and real-time data to predict future temperature changes. The temperature prediction is performed in combination with the current current and voltage data.

[0049] According to the temperature monitoring and prediction results, the operating state of the heat dissipation device is dynamically adjusted. When the temperature exceeds or approaches the preset threshold, the heat dissipation device is activated or adjusted. The decision of the adaptive activation mechanism is passed to the heat dissipation controller. The operation of the heat dissipation device is adjusted according to the actual situation to ensure that the electric energy meter operates within a safe temperature range. Among them, the adaptive activation mechanism decides whether to adjust the heat dissipation device based on the real-time monitoring data and prediction results. The adaptive control module is used to adjust the working intensity of the heat dissipation device according to the decision.

[0050] The specific implementation process is to obtain current, voltage and temperature data in real time through the temperature monitoring module. Combined with the temperature prediction module, predict the temperature changes in the future. Set the temperature threshold (such as 45°C). If the real-time temperature or predicted temperature monitored is close to or exceeds the threshold, activate the adaptive activation mechanism. According to the temperature data, decide whether to increase or reduce the working intensity of the heat dissipation device. In the high-load area, increase the heat dissipation when the temperature is high; in the low-load area, reduce the heat dissipation when the temperature is low. The adaptive control module passes the decision to the heat dissipation controller. The heat dissipation controller adjusts the operating status of the heat dissipation device according to the decision to ensure that the temperature remains within a safe range.

[0051] This step can achieve adaptive control of the heat dissipation equipment of the energy meter by building a temperature prediction module and combining it with the temperature monitoring module. This process includes real-time temperature monitoring, predicting future temperature changes, making judgments based on temperature thresholds, and dynamically adjusting the operating status of the heat dissipation equipment through the adaptive control module, thereby ensuring that the energy meter operates efficiently within a safe temperature range.

[0052] Further, such as Figure 2 As shown, the method described in the present application also includes:

[0053] According to the standard timing characteristics of the electric energy meter, the low-load area is set as the first-level time zone, the standard area is set as the second-level time zone, and the high-load area is set as the third-level time zone, and the accommodation threshold of each level time zone is set; the temperature influence relationship and load influence relationship of each work are used to calculate the load and temperature of the real-time work demand, and the load identification and temperature identification of each work demand are configured; the load proportion is evaluated according to the load identification of each work demand, and the dynamic allocation priority of each work demand is determined; based on the dynamic allocation priority of each work demand, the first-level time zone, the second-level time zone, and the third-level time zone are matched in sequence, and the accommodation threshold of each level time zone is used as a constraint to obtain the matching level time zone of each work demand, and the work demand has a load identification and a temperature identification; according to the matching level time zone, the standard timing characteristics of the electric energy meter are traced back in time to determine the response time of the work demand.

[0054] Specifically, low-load areas are set as first-level time zones: usually during low-power consumption periods, such as late at night and early morning hours. Standard areas are set as second-level time zones: usually during relatively stable power consumption periods, such as daytime working hours. High-load areas are set as third-level time zones: usually during peak power consumption periods, such as afternoon and evening hours. Set a containment threshold for each level of time zone, indicating the maximum carrying capacity of each time zone.

[0055] Collect the current, voltage and temperature data of the energy meter in real time. Use the temperature impact relationship model and load impact relationship model to analyze the real-time working data and calculate the current load and temperature. According to the calculation results, assign corresponding load identification (such as high, medium, low) and temperature identification (such as high, medium, low) to each working demand.

[0056] Evaluate the load share of all work demands. Load share refers to the share of the load of each work demand in all work demands, that is, calculate the load of each work demand. Take the sum of the loads of all work demands as the benchmark. Calculate the load share of each work demand, that is, divide the load of each work demand by the total load. Then, assign a dynamic priority to each work demand based on the load share and temperature identification. Load share: Work demands with higher load shares usually have higher priorities. Temperature identification: Work demands with high temperature identification usually have higher priorities. Considering the load share and temperature identification comprehensively, assign a dynamic priority to each work demand.

[0057] For example, suppose we have three work requirements, and their load and temperature labels are as follows: Work requirement 1: Load label is high, temperature label is medium, and load is 2200W. Work requirement 2: Load label is low, temperature label is low, and load is 1050W. Work requirement 3: Load label is medium, temperature label is high, and load is 1720W. Load share evaluation: The total load is 2200W+1050W+1720W=4970W. The load share of work requirement 1 is 2200W / 4970W≈0.443. The load share of work requirement 2 is 1050W / 4970W≈0.211. The load share of work requirement 3 is 1720W / 4970W≈0.346. Dynamic allocation priority: Work requirement 1: High load share (0.443) and medium temperature label → higher priority. Work requirement 2: Low load share (0.211) and low temperature label → lowest priority. Work requirement 3: Medium load percentage (0.346) and high temperature mark → higher priority.

[0058] First-level time zone (low-load area): Usually during low-power consumption periods, such as late at night and early morning, the accommodation threshold is low. Second-level time zone (standard area): Usually during periods of relatively stable power consumption, such as daytime working hours, the accommodation threshold is moderate. Third-level time zone (high-load area): Usually during peak power consumption periods, such as afternoon and evening, the accommodation threshold is highest. Determine the priority of each work demand based on load and temperature identifiers. Sort all work demands from high to low according to the dynamic allocation priority. Starting from the first-level time zone, match each work demand in turn and check whether the accommodation threshold of the current time zone meets the conditions. If the accommodation threshold of the current time zone is insufficient, try the next-level time zone until a suitable time zone is found or there is no matching time zone.

[0059] Finally, according to the matching level time zone, the standard timing characteristics of the electric energy meter are traced back to determine the response time of the work demand. High-priority demands are matched first in the high-load area and have a shorter response time; low-priority demands are matched in the low-load area and have a longer response time.

[0060] This step can effectively adaptively allocate the real-time working requirements of the electric energy meter and determine the response time of the working requirements. This method uses the standard timing characteristics of the electric energy meter, the temperature influence relationship of each working state and the load influence relationship to ensure efficient and safe operation under different load conditions.

[0061] Furthermore, the method described in the present application also includes:

[0062] Obtain the work demands of all time zones of all levels; based on the load identification of each work demand, optimally allocate the work demands in each time zone with the goal of load balancing in each time zone, and obtain the work demand distribution information of each time zone; according to the temperature identification of each work demand, combined with the standard timing characteristics of the electric energy meter, with the goal of temperature balancing in each time zone, evaluate the temperature gradient of the work demand distribution information; according to the temperature gradient evaluation, adjust the work demand distribution information that does not meet the balancing goal, and finally obtain the matching level time zone of each work demand.

[0063] Specifically, all work requirements within each level time zone are collected, including load identification and temperature identification.

[0064] Based on the load identification of each work demand, with the goal of load balancing in each time zone, optimize the distribution of work demands in each level of time zone to ensure that the load in each time zone is as balanced as possible and close to the set load threshold, and obtain the work demand distribution information in each time zone. Ensure that the load in each time zone is as balanced as possible to avoid overload or underload in a certain time zone.

[0065] According to the temperature mark of each work demand and the standard time series characteristics of the electric energy meter, the work demand distribution information is evaluated for temperature gradient to ensure balanced temperature distribution in each time zone. According to the temperature gradient evaluation results, the time zones that do not meet the balance target are adjusted, for example, work demands with higher temperatures are adjusted from higher temperature time zones to lower temperature time zones to ensure a more balanced temperature distribution in each time zone, and finally determine the matching level time zone for each work demand. Ensure balanced temperature distribution in each time zone to avoid excessive temperature in a certain time zone, thereby improving the operating efficiency and safety of the equipment.

[0066] This step obtains the working requirements of all level time zones, optimizes the allocation based on the goals of load balancing and temperature balancing, and adjusts the working requirements that do not meet the balancing goals, and finally determines the matching level time zone for each working requirement. This method ensures the efficient and safe operation of the energy meter under different working conditions, optimizes resource allocation, ensures load and temperature balance, and extends the service life of the equipment.

[0067] Furthermore, the method described in the present application also includes:

[0068] Obtain the influence of the electric energy meter on the work demand, wherein the influence of the electric energy meter is obtained by analyzing each work demand through an influence analysis model; set a time constraint threshold according to the influence of the electric energy meter; set a time limit priority according to the order of the time constraint threshold from small to large; set a load priority according to the load proportion evaluation; merge the time limit priority and the load priority to obtain the dynamic allocation priority; wherein, when performing matching allocation, the time constraint threshold is used as the primary constraint condition.

[0069] Specifically, the impact analysis model is used to evaluate the impact of each work demand on the operating performance and heat dissipation requirements of the electric energy meter. Through the impact analysis, the impact of each work demand can be quantified, providing a scientific basis for subsequent priority setting and allocation.

[0070] The construction process includes: determining the key factors that affect the operating performance and heat dissipation requirements of the energy meter, such as load, current, voltage, temperature, etc.; collecting historical data of the energy meter under different working conditions, including current, voltage, temperature and load data; selecting a suitable analysis model, such as linear regression, logistic regression, decision tree or machine learning model, to quantify the impact of each influencing factor on the energy meter; using the collected data to train the model so that it can accurately predict the impact of each work demand; using the trained model to analyze each work demand and calculate its impact on the energy meter. Among them, the influencing factors include: the greater the load, the more significant the impact on the energy meter. High current will increase the temperature load of the energy meter. Voltage fluctuations will also affect the performance of the energy meter. The ambient temperature and the internal temperature of the equipment have a significant impact on the energy meter.

[0071] Then, the influence analysis model is used to analyze each work demand and obtain the influence degree of each work demand on the electric energy meter. The influence degree of the electric energy meter measures the influence degree of each work demand on the operation performance and heat dissipation demand of the electric energy meter.

[0072] According to the impact of the electric energy meter, a time constraint threshold is set for each work demand. The time constraint threshold indicates how long each work demand must be responded to in order to avoid negative impact on the electric energy meter.

[0073] According to the impact of the electric energy meter, a time constraint threshold is set for each work demand. The time constraint threshold indicates how long each work demand must be responded to in order to avoid negative impact on the electric energy meter.

[0074] According to the load proportion evaluation, set the load priority for each work demand. The load priority is based on the load size of the work demand. The larger the load, the higher the priority. The time limit priority and the load priority are combined to obtain the final dynamic allocation priority. The dynamic allocation priority takes into account the urgency of the work demand and the load size.

[0075] When performing matching and allocation, the time constraint threshold is used as the primary constraint. According to the dynamic allocation priority, the work requirements with smaller time constraint thresholds are met first, and then allocated according to the load priority.

[0076] This step obtains the influence of the energy meter, sets the time constraint threshold, sorts and sets the time limit priority, sets the load priority and merges them, and finally determines the dynamic allocation priority. When performing matching allocation, the time constraint threshold is the primary condition to ensure that each work demand has a reasonable response time and load distribution. The heat dissipation control of the energy meter is effectively optimized, and the operation efficiency and safety are improved.

[0077] Furthermore, the method described in the present application also includes:

[0078] Set a temperature threshold; obtain the monitored temperature according to the temperature monitoring module, and obtain the predicted temperature and its predicted time information through the temperature prediction module; set an adaptive activation condition based on the temperature threshold; use the adaptive activation condition to connect the monitored temperature, predicted temperature and its predicted time information, and set the adaptive activation mechanism.

[0079] Specifically, define the safe operating temperature range of the energy meter and set the upper and lower temperature thresholds. For example, the upper temperature is 45°C and the lower temperature is 25°C. Use the temperature monitoring module to obtain the current temperature of the energy meter in real time. Use the temperature prediction module to predict the temperature change in the future and record the prediction time information. For example, the current temperature is 40°C. For example, it is predicted that the temperature will rise to 46°C in the next 30 minutes.

[0080] Based on the temperature threshold, setting the adaptive activation condition means that under certain conditions, the system automatically triggers the corresponding heat dissipation control measures to ensure that the power meter operates within a safe temperature range. When the monitored temperature or predicted temperature exceeds the upper temperature threshold, the heat dissipation measures are activated; when the monitored temperature or predicted temperature is lower than the lower temperature threshold, the heat dissipation measures are reduced. For example, when the monitored temperature or predicted temperature exceeds 45°C, the heat dissipation measures are activated. When the monitored temperature or predicted temperature is lower than 25°C, the heat dissipation measures are reduced.

[0081] Integrate the data from the temperature monitoring module and the temperature prediction module to form a complete data chain: current temperature: 40°C, predicted temperature: 46°C, predicted time: 30 minutes later. Dynamically adjust the working status of the cooling device based on the integrated data and the set activation conditions: Since the predicted temperature will exceed 45°C in 30 minutes, activate the cooling device immediately to prevent the temperature from being too high. Continue to monitor and predict the temperature, and dynamically adjust the cooling measures based on real-time data.

[0082] This step establishes an adaptive activation mechanism by setting temperature thresholds, obtaining monitored and predicted temperatures, setting adaptive activation conditions, and connecting related information. This mechanism can dynamically adjust the working state of the heat dissipation equipment to ensure that the temperature of the energy meter is always within a safe range, thereby improving the operating efficiency and safety of the equipment.

[0083] Furthermore, the method described in the present application also includes:

[0084] Adaptive Activation Mechanism = , where 1 indicates that the adaptive mechanism is activated, 0 indicates that the adaptive mechanism is not activated, To monitor temperature, is the temperature threshold, To predict temperature, is the prediction time information, and t is the current time.

[0085] Specifically, the adaptive activation mechanism can effectively combine the monitored temperature, predicted temperature and its predicted time information, dynamically adjust the heat dissipation measures, and ensure the safe and efficient operation of the energy meter under different working conditions. This mechanism improves the responsiveness and intelligence level of the system and effectively avoids the risk of equipment damage caused by excessive temperature.

[0086] Furthermore, the method described in the present application also includes:

[0087] The adaptive control module includes a precondition module and a post-execution module; the adaptive activation mechanism is embedded in the precondition module as a precondition; a control relationship between the control temperature and the heat dissipation device is established; the monitored temperature or the predicted temperature is controlled and converted according to the control relationship and input into the precondition module; the activation output result of the adaptive activation mechanism and the control parameter output result of the control conversion are merged and input into the post-execution module to obtain adaptive execution information.

[0088] Specifically, the precondition module is used to determine whether the activation condition is met. The post-execution module is used to execute a specific control operation.

[0089] The adaptive activation mechanism is embedded in the precondition module as a precondition to determine whether the cooling device needs to be activated. A control relationship between temperature and cooling device is established, that is, when the temperature exceeds a certain threshold, the operating state of the cooling device needs to be adjusted. For example, when the temperature exceeds 45°C, the cooling device is started; when the temperature is below 25°C, the cooling device is turned off.

[0090] According to the control relationship, the monitored temperature or predicted temperature is converted into a control parameter. For example, if the current temperature is 40°C and the predicted temperature is 46°C, the cooling device needs to be started. The control relationship includes temperature threshold setting: setting the upper temperature threshold (for example, 45°C) and the lower temperature threshold (for example, 25°C) to determine whether the cooling device needs to be activated or shut down. Temperature monitoring and prediction: Get the current temperature through the temperature monitoring module . Get the predicted temperature at a certain point in the future through the temperature prediction module Cooling device operation: When the temperature exceeds the upper threshold, the cooling device is started. When the temperature is lower than the lower threshold, the cooling device is shut down.

[0091] The output result (1 or 0) of the adaptive activation mechanism indicates whether the heat dissipation device is activated. The control parameter of the control conversion indicates a specific control operation (such as starting or shutting down the heat dissipation device). The two results are fused to generate a comprehensive control signal. The fused control signal is input into the post-execution module to obtain the final adaptive execution information, and the corresponding control operation is executed to ensure that the electric energy meter operates within a safe temperature range. Among them, the adaptive execution information is an instruction generated in the adaptive control module by fusing the activation output result of the adaptive activation mechanism and the control parameter of the control conversion, which is used to control the specific operation of the heat dissipation device. Contains activation status information: indicates whether the adaptive mechanism is activated, and the activation status information can be in binary form: 1 indicates activation, and 0 indicates inactivation. Control parameter information: control instructions generated according to temperature monitoring and prediction results, including operations of starting, adjusting or shutting down the heat dissipation device. The control parameter information can include temperature value, time information, and operation instructions (such as starting, adjusting wind speed, shutting down, etc.).

[0092] In this step, through the collaborative work of the precondition module and the post-execution module, the adaptive control module can dynamically adjust the working state of the heat dissipation device according to the real-time monitoring temperature, predicted temperature and its time information. This mechanism embeds an adaptive activation mechanism to establish a control relationship between the control temperature and the heat dissipation device, ensuring that the energy meter operates within a safe temperature range, thereby improving the system's responsiveness and intelligence level.

[0093] Furthermore, the method described in the present application also includes:

[0094] Obtain control parameters of the heat dissipation device; collect test sample data of the heat dissipation device, including control parameters and heat dissipation effect; based on the test sample data, take the control parameters as independent variables and the heat dissipation effect as dependent variable for fitting to obtain a linear relationship; establish a control relationship between the control temperature and the heat dissipation device according to the linear relationship.

[0095] Specifically, key control parameters of the heat dissipation equipment are collected, such as fan speed, heat dissipation power, etc.

[0096] Conduct multiple tests and record the cooling effect of the cooling device under different control parameters. For example: when the fan speed (RPM) is 1000, the temperature drops by 5°C; when the fan speed (RPM) is 2000, the temperature drops by 10°C. The sample data should include: control parameters and corresponding cooling effects (such as temperature drop values).

[0097] The linear regression method is used to fit the test sample data to obtain the linear relationship between the control parameters and the heat dissipation effect. The fitted linear equation is in the form of: Y=aX+b. Among them, Y is the heat dissipation effect (temperature drop value), X is the control parameter (such as fan speed), a is the regression coefficient, which indicates the influence of the control parameter on the heat dissipation effect, and b is the intercept, which indicates the heat dissipation effect when the control parameter is zero.

[0098] According to the current temperature and the target temperature, determine the temperature drop value (target heat dissipation effect) that needs to be achieved. According to the linear equation, the required control parameters are inferred from the target heat dissipation effect. Calculation formula: X= ; Where Y is the target cooling effect (temperature drop value), and X is the calculated control parameter (such as fan speed). The calculated control parameter is used as input to adjust the operating state of the cooling device to achieve the expected cooling effect.

[0099] This step uses the control parameters of the heat dissipation device and the test sample data to fit the linear relationship and establish the control relationship between the control temperature and the heat dissipation device. This relationship ensures that the heat dissipation device can efficiently perform heat dissipation operations under different temperature conditions, thereby improving the operating efficiency and safety of the energy meter.

[0100] In summary, the adaptive heat dissipation control method of an electric energy meter provided in the embodiment of the present application has the following technical effects:

[0101] 1. By constructing a multi-state data set, data under various working states such as current, voltage, and temperature are collected to fit the influence relationship between temperature and load. Combined with the standard timing characteristics of the energy meter, its state changes within the daily cycle are reflected. According to these characteristics, real-time work needs are adaptively allocated to determine the response time. A temperature prediction module is constructed to associate it with the response time of work needs. An adaptive activation mechanism is constructed using the temperature monitoring and prediction module. The heat dissipation controller is connected through the adaptive control module to achieve adaptive control of the heat dissipation equipment. The technical effects include improving the heat dissipation efficiency of the energy meter, ensuring the safe operation of the equipment under different working conditions, extending the life of the equipment, and reducing the risk of failure.

[0102] 2. By dividing the working state of the energy meter into three time zones: low load, standard and high load, and setting the containment threshold of each level of time zone, the load and temperature are calculated for the real-time work demand according to the influence of temperature and load. By configuring the load identification and temperature identification of the work demand, the load proportion is evaluated, the dynamic allocation priority is determined, and then the three levels of time zones are matched in turn to obtain the matching level time zone and the corresponding response time. This method optimizes the heat dissipation control of the energy meter under different working conditions, ensures the accuracy and efficiency of temperature management, and improves the operating stability and life of the energy meter.

[0103] 3. Construct an adaptive activation mechanism through the temperature monitoring module and the temperature prediction module. First, set the temperature threshold as the benchmark for heat dissipation control. The current monitored temperature is obtained in real time through the temperature monitoring module, and the future predicted temperature and its predicted time information are obtained using the temperature prediction module. Based on the preset temperature threshold, set the adaptive activation conditions, associate the monitored temperature, predicted temperature and its time information, and construct an adaptive activation mechanism. This method can monitor and predict temperature changes in real time, and automatically activate the heat dissipation mechanism according to the set conditions, effectively preventing the energy meter from malfunctioning due to excessive temperature, and improving the operating efficiency and safety of the equipment. By predicting the temperature change trend, heat dissipation measures can be taken in advance to extend the service life of the energy meter and improve its reliability and stability.

[0104] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

[0105] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application belong to the scope of the present application and its equivalent technology, the present application is also intended to include these modifications and variations.

Claims

1. An adaptive heat dissipation control method for an electric energy meter, characterized in that: The electric energy meter adaptive heat dissipation control comprises: Constructing a multi-state data set, wherein the multi-state data set is data of the electric energy meter under various working states, including current, voltage, and temperature; According to the multi-state data set, fitting the temperature influence relationship and the load influence relationship of each working state; Acquire standard time series characteristics of the electric energy meter, wherein the standard time series characteristics of the electric energy meter reflect the state characteristics of the electric energy meter in a daily cycle, including a high-load area, a standard area, and a low-load area; According to the temperature influence relationship and load influence relationship of each working state and the standard timing characteristics of the electric energy meter, the real-time working demand is adaptively allocated to determine the response time of the working demand, wherein high-priority demands are preferentially matched in high-load areas with a shorter response time, and low-priority demands are matched in low-load areas with a longer response time; Constructing a temperature prediction module, wherein the temperature prediction module is associated with a response time of the work demand; An adaptive activation mechanism is constructed by using the temperature monitoring module and the temperature prediction module to generate an adaptive control module, wherein the adaptive control module is connected to a heat dissipation controller for adaptively controlling the heat dissipation device; The step of adaptively allocating the real-time work demand and determining the response time of the work demand includes: According to the standard time sequence characteristics of the electric energy meter, the low-load area is set as the first-level time zone, the standard area is set as the second-level time zone, and the high-load area is set as the third-level time zone, and the acceptance threshold of each level time zone is set; Utilizing the temperature influence relationship and load influence relationship of each work, load and temperature calculation is performed on the real-time work demand, and load identification and temperature identification of each work demand are configured; Evaluate the load proportion according to the load identification of each work demand, and determine the dynamic allocation priority of each work demand; Based on the dynamic allocation priority of each work demand, the first level time zone, the second level time zone, and the third level time zone are matched in sequence, and the accommodation threshold of each level time zone is used as a constraint to obtain the matching level time zone of each work demand, and the work demand has a load identifier and a temperature identifier; According to the matching level time zone, the standard timing characteristics of the electric energy meter are time-traced to determine the response time of the working demand.

2. The method for adaptive heat dissipation control of an electric energy meter according to claim 1, characterized in that: Obtaining the matching level time zone of each work requirement also includes: Get the job requirements for all time zones; Based on the load identification of each work demand, optimal allocation of work demand in each level of time zone is performed with the load balancing of each time zone as the goal, to obtain work demand distribution information of each time zone; According to the temperature identification of each work demand, combined with the standard time series characteristics of the electric energy meter, with the goal of balancing the temperature in each time zone, the temperature gradient of the work demand distribution information is evaluated; According to the temperature gradient evaluation, the work demand distribution information that does not meet the balance target is adjusted to obtain the final matching level time zone of each work demand.

3. The method for adaptive heat dissipation control of an electric energy meter according to claim 1, characterized in that: Determine the dynamic allocation priority of each work demand, including: Obtaining the influence of the electric energy meter on the work demand, wherein the influence of the electric energy meter is obtained by analyzing each work demand through an influence analysis model; According to the influence of the electric energy meter, a time constraint threshold is set; According to the order of the time constraint thresholds from small to large, setting the time limit priority; Setting a load priority according to the load proportion evaluation; The time limit priority and the load priority are integrated to obtain the dynamic allocation priority; When performing matching allocation, the time constraint threshold is used as the primary constraint condition.

4. The method for adaptive heat dissipation control of an electric energy meter according to claim 1, characterized in that: The use of the temperature monitoring module and the temperature prediction module to construct an adaptive activation mechanism includes: Set temperature thresholds; Acquire the monitored temperature according to the temperature monitoring module, and obtain the predicted temperature and its predicted time information through the temperature prediction module; Based on the temperature threshold, setting an adaptive activation condition; The adaptive activation condition is used to connect the monitored temperature, the predicted temperature and the predicted time information to set the adaptive activation mechanism.

5. The method for adaptive heat dissipation control of an electric energy meter according to claim 4, characterized in that: The adaptive activation condition is used to connect the monitored temperature, the predicted temperature and the predicted time information, and the adaptive activation mechanism is set, including: Adaptive Activation Mechanism = , where 1 indicates that the adaptive mechanism is activated, 0 indicates that the adaptive mechanism is not activated, To monitor temperature, is the temperature threshold, To predict temperature, is the prediction time information, and t is the current time.

6. The method for adaptive heat dissipation control of an electric energy meter according to claim 5, characterized in that: The generating of the adaptive control module comprises: The adaptive control module includes a precondition module and a post-execution module; embedding the adaptive activation mechanism into the precondition module as a precondition; Establish the control relationship between temperature control and heat dissipation equipment; Control conversion is performed on the monitored temperature or predicted temperature according to the control relationship and input into the precondition module; The activation output result of the adaptive activation mechanism and the control parameter output result of the control conversion are merged and input into the post-execution module to obtain adaptive execution information.

7. The method for adaptive heat dissipation control of an electric energy meter according to claim 6, characterized in that: The establishing of a control relationship between the control temperature and the heat dissipation device includes: Obtain control parameters of the heat dissipation device; Collecting test sample data of the heat dissipation device, including control parameters and heat dissipation effects; Based on the test sample data, the control parameter is used as an independent variable and the heat dissipation effect is used as a dependent variable for fitting to obtain a linear relationship; A control relationship between the control temperature and the heat dissipation device is established according to the linear relationship.