Investment cost estimation method for reversible transformation of conventional cascade power station

Through detailed technical parameter determination and cost calculation methods, the accuracy of investment cost assessment of reversible transformation of conventional cascade power plants is solved, and a comprehensive investment cost assessment is provided, ensuring the reliability of investment decisions.

CN118967199AInactive Publication Date: 2024-11-15HUAZHONG UNIV OF SCI & TECH
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411179467.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-15
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing technology cannot conduct a refined evaluation of the investment costs of reversible transformation in domestic conventional cascade power plants, and there is a lack of accurate cost estimation methods.

Method used

By constructing an investment cost estimation method, including determining technical parameters, calculating investment costs of hub projects and summarizing other expenses, the specific steps include estimating the rated head, distance ratio, stand-alone capacity and unit number, computer electrical equipment, water transmission systems and underground The construction cost of the factory building, and independent costs and basic reserve costs are considered.

Benefits of technology

A comprehensive and accurate assessment of the investment costs of reversible transformation of conventional cascade power plants is achieved, and a reliable basis for investment decisions is provided, ensuring the feasibility of investors' assessment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118967199A_ABST
    Figure CN118967199A_ABST
Patent Text Reader

Abstract

The invention relates to an investment cost estimation method for reversible transformation of a conventional cascade power station, and the method comprises the following steps: S1, estimating the technical parameters of reversible transformation according to the geographic position and reservoir conditions of the conventional cascade power station to be transformed and evaluated; s2, obtaining the total investment cost of the hub project according to the technical parameters of reversible transformation; and S3, according to the total investment cost of the reversible transformation hub project, other fees are calculated, the other fees comprise independent fees and basic reserve fees, and the total investment cost of reversible transformation of the conventional cascade power station is obtained. According to the method, the investment cost is comprehensively estimated by carefully considering all aspects of reversible transformation of the conventional cascade power station, so that researchers can more accurately evaluate and analyze the technical and economic feasibility of reversible transformation of the conventional cascade power station.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of electrical engineering, and more particularly to an investment cost estimation method for reversibly transforming a conventional cascade power station. Background Art

[0002] With the development of clean energy, hybrid pumped storage power stations play an important role in energy storage and peak load regulation. Investment cost estimation is crucial for the feasibility analysis of reversible transformation of conventional cascade power stations. However, the current investment cost estimation method cannot make a detailed assessment of the cost of reversible transformation of domestic conventional cascade power stations. Therefore, it is necessary to provide a more accurate and comprehensive investment cost estimation method for reversible transformation of conventional cascade power stations. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a method for estimating the investment cost of reversible transformation of conventional cascade power plants, which can more comprehensively and accurately evaluate the investment cost of reversible transformation of conventional cascade power plants.

[0004] The technical solution adopted by the present invention to solve the technical problem is: constructing an investment cost estimation method for reversible transformation of a conventional cascade power station, comprising the following steps:

[0005] S1. Determination of technical parameters: Estimate the technical parameters of reversible transformation based on the geographical location and reservoir conditions of the conventional cascade power stations to be evaluated for transformation;

[0006] S2. Calculation of investment cost of hub project: Based on the technical parameters of reversible transformation, estimate the construction cost of the infrastructure of the water delivery system and underground powerhouse, and the purchase and installation cost of electromechanical equipment of turbines and generators, and obtain the total investment cost of the hub project;

[0007] S3. Calculation of other expenses and cost summary: Based on the total investment cost of the reversible transformation hub project, other expenses are calculated. The other expenses include independent expenses and basic reserve fees to obtain the total investment cost of the reversible transformation of conventional cascade power stations.

[0008] According to the above scheme, in step S1, the technical parameters of the reversible transformation include rated water head, distance-to-height ratio, single-machine capacity, single-machine maximum flow and number of units.

[0009] According to the above scheme, in step S1, the estimation formula of the rated water head is as follows:

[0010] H r =K×(H max -H min )-H min

[0011] Among them, H r represents the rated water head, K represents the drawdown depth coefficient, which is 0.4 to 0.5, and H max Indicates the maximum water head, H min Indicates the minimum water head;

[0012] For the maximum and minimum heads, the water levels of the upper and lower reservoirs are determined by the following formulas;

[0013]

[0014]

[0015] in, Indicates the normal water level of the upper reservoir. Indicates the dead water level of the upper reservoir. Indicates the normal water level of the lower reservoir. Indicates the dead water level of the lower reservoir;

[0016] The estimation formula of the distance-to-height ratio is as follows:

[0017] λ=L / H r

[0018] Among them, λ represents the distance-to-height ratio, and L represents the horizontal distance between the inlet and outlet of the upper and lower reservoirs. For the horizontal distance, when the boundary of the perennial backwater area of ​​the upper and lower reservoirs is known, it is determined by the shortest distance between the perennial backwater areas of the upper and lower reservoirs. When the boundary of the upper and lower reservoirs is unknown, it is determined by other parameters, and the formula is as follows:

[0019]

[0020] in, Indicates the height of the lower reservoir dam, L R It indicates the length of the river channel between the upper and lower reservoir dams;

[0021] The capacity of a single unit and the number of units are determined by the installed capacity of the existing upstream and downstream conventional hydropower stations. The formula is as follows:

[0022]

[0023]

[0024]

[0025] Among them, P T represents the total installed capacity of reversible transformation, represents the total installed capacity of upstream conventional hydropower stations, represents the total installed capacity of downstream conventional hydropower stations, P represents the capacity of a single reversible unit, and N represents the number of reversible units;

[0026] The maximum flow rate of a single machine is determined by the rated head and the capacity of the single machine. The formula is as follows:

[0027]

[0028] Where Q represents the maximum flow rate of a single reversible unit, in m 3 / s, P is the capacity of the reverse unit, in MW, g is the acceleration of gravity, η is the energy conversion efficiency, which is 0.88, H r is the rated head, in m.

[0029] According to the above scheme, in step S2, the estimation formula of the total investment cost of the hub project is as follows:

[0030] C HP =C EM +C W +C PS +C CA

[0031] Among them, C HP represents the total investment cost of the reversible transformation hub project, C EM Represents the cost of electromechanical equipment, C W represents the cost of the water delivery system, C PS represents the underground plant cost, C CA It represents other construction costs, and all costs are in ten thousand yuan;

[0032] The cost estimation formula for electromechanical equipment is as follows:

[0033] C EM =C E +C PT

[0034] C E =367×P 0.66 n -0.25 N

[0035]

[0036]

[0037]

[0038] Among them, C E represents the cost of electrical equipment, C PT represents the pump turbine cost, n represents the rated speed of the reversible unit, It represents the unit capacity cost of the pump turbine;

[0039] The formula for estimating the cost of the water delivery system is as follows:

[0040] C W =C T +C P +C ME

[0041] C T =(0.0606×S T +1.7634)L T N / 2

[0042] S T =2×Q / V T

[0043] L T =LH r

[0044] V T =4.2m / s

[0045] C P =(0.3972×S P +7.3271)L P N / 2

[0046] S P =2×Q / V P

[0047] L P =2×H r

[0048]

[0049] C ME =260.42×NQ-54265

[0050] Among them, C T represents the tunnel cost, C P Indicates the cost of pressure pipes, C ME Indicates other equipment costs, S T represents the cross-sectional area of ​​the tunnel, L T represents the tunnel length, V T represents the water flow velocity in the tunnel, S P Indicates the cross-sectional area of ​​the pressure pipe, L P Indicates the length of the pressure pipe, V P Indicates the water flow velocity in the pressure pipe;

[0051] The formula for estimating the cost of underground plant and other buildings is as follows:

[0052]

[0053] C CA =43.09×NP+44815.

[0054] According to the above scheme, in step S3, the total investment cost estimation formula for reversible transformation is as follows:

[0055] C=C HP +C IF +C PH

[0056] C IF =0.1456×C HP +4771

[0057] C PH =0.06×(C HP +C IF )

[0058] Where C represents the total investment cost of reversible transformation, C IF Indicates independent cost, C PH Indicates basic reserve.

[0059] The investment cost estimation method for reversible transformation of conventional cascade power plants according to the present invention has the following beneficial effects:

[0060] The present invention comprehensively estimates the investment cost of reversible transformation by carefully considering various aspects of reversible transformation of conventional cascade power stations, from technical parameter determination to cost estimation, from hub engineering to independent costs to basic reserve, from electromechanical equipment to water supply system to underground plant and other buildings, so that investors can more accurately evaluate the feasibility of reversible transformation of conventional cascade power stations; the method comprehensively considers the cost factors of each link under the influence of various technical parameters, and provides a reliable reference basis for investment decisions on reversible transformation of conventional cascade power stations. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] The present invention will be further described below with reference to the accompanying drawings and embodiments, in which:

[0062] Figure 1 It is a flow chart of the investment cost estimation method of the present invention for reversible transformation of conventional cascade power plants. DETAILED DESCRIPTION

[0063] In order to have a clearer understanding of the technical features, purposes and effects of the present invention, specific embodiments of the present invention are now described in detail with reference to the accompanying drawings.

[0064] like Figure 1 As shown, the investment cost estimation method for reversible transformation of conventional cascade power plants of the present invention comprises the following steps:

[0065] S1. Determination of technical parameters

[0066] According to the geographical location and reservoir conditions of the conventional cascade power stations to be evaluated for transformation, the technical parameters of reversible transformation are estimated, including rated head, distance-to-height ratio, single-unit capacity, single-unit maximum flow and number of units;

[0067] The formula for estimating the rated head is as follows:

[0068] H r =K×(H max -H min )-H min

[0069] Among them, H r It indicates the rated water head, K indicates the drawdown depth coefficient, which is generally 0.4 to 0.5, and H max Indicates the maximum water head, H min Indicates the minimum water head;

[0070] The maximum and minimum heads can be determined by the water levels of the upper and lower reservoirs using the following formulas;

[0071]

[0072]

[0073] in, Indicates the normal water level of the upper reservoir. Indicates the dead water level of the upper reservoir. Indicates the normal water level of the lower reservoir. Indicates the dead water level of the lower reservoir;

[0074] The estimation formula of the distance-to-height ratio is as follows:

[0075] λ=L / H r

[0076] Among them, λ represents the distance-to-height ratio, and L represents the horizontal distance between the inlet and outlet of the upper and lower reservoirs. For the horizontal distance, when the boundary of the perennial backwater area of ​​the upper and lower reservoirs is known, it can be determined by the shortest distance between the perennial backwater areas of the upper and lower reservoirs; when the boundary of the upper and lower reservoirs is unknown, it can be determined by other parameters, and the formula is as follows:

[0077]

[0078] in, Indicates the height of the lower reservoir dam, L R It indicates the length of the river channel between the upper and lower reservoir dams;

[0079] The capacity of a single unit and the number of units are determined by the installed capacity of the existing upstream and downstream conventional hydropower stations. The formula is as follows:

[0080]

[0081]

[0082]

[0083] Among them, P T represents the total installed capacity of reversible transformation, represents the total installed capacity of upstream conventional hydropower stations, represents the total installed capacity of downstream conventional hydropower stations, P represents the capacity of a single reversible unit, and N represents the number of reversible units;

[0084] The maximum flow rate of a single machine is determined by the rated head and the capacity of the single machine. The formula is as follows:

[0085]

[0086] Where Q represents the maximum flow rate of a single reversible unit, in m 3 / s, P is the capacity of the reverse unit, in MW, g is the acceleration of gravity, η is the energy conversion efficiency, which can be taken as 0.88, H r is the rated head, in m.

[0087] S2. Calculation of investment cost of hub project

[0088] According to the technical parameters of reversible transformation, the construction cost of infrastructure such as water transmission system, underground powerhouse, other buildings, as well as the purchase and installation cost of electromechanical equipment such as turbines and generators are estimated, and the total investment cost of the hub project is obtained;

[0089] The estimation formula of the total investment cost of the hub project is as follows:

[0090] C HP =C EM +C W +C PS +C CA

[0091] Among them, C HP represents the total investment cost of the reversible transformation hub project, C EM Represents the cost of electromechanical equipment, C W represents the cost of the water delivery system, C PS represents the underground plant cost, C CA It represents other construction costs, and all costs are in ten thousand yuan;

[0092] The cost estimation formula for electromechanical equipment is as follows:

[0093] C EM =C E +C PT

[0094] C E =3767×P 0.66 n -0.25 N

[0095]

[0096]

[0097]

[0098] Among them, C E represents the cost of electrical equipment, C PT represents the pump turbine cost, n represents the rated speed of the reversible unit, It represents the unit capacity cost of the pump turbine;

[0099] The formula for estimating the cost of the water delivery system is as follows:

[0100] C W =C T +C P +C ME

[0101] C T =(0.0606×S T +1.7634)L T N / 2

[0102] S T =2×Q / V T

[0103] L T =LH r

[0104] V T =4.2m / s

[0105] C P =(0.3972×S P +7.3271)L P N / 2

[0106] S P =25×Q / V P

[0107] L P =2×H r

[0108] C ME =260.42×NQ-54265

[0109] Among them, C T represents the tunnel cost, C PIndicates the cost of pressure pipes, C ME Indicates other equipment costs, S T represents the cross-sectional area of ​​the tunnel, L T represents the tunnel length, V T represents the water flow velocity in the tunnel, S P Indicates the cross-sectional area of ​​the pressure pipe, L P Indicates the length of the pressure pipe, V P Indicates the water flow velocity in the pressure pipe;

[0110] The formula for estimating the cost of underground plant and other buildings is as follows:

[0111]

[0112] C CA =43.09×NP+44815.

[0113] S3. Calculation of other expenses and cost summary

[0114] According to the total investment cost of the reversible transformation hub project, other costs are calculated, including independent costs and basic reserve fees, to obtain the total investment cost of the reversible transformation of conventional cascade power stations.

[0115] The total investment cost estimation formula for reversible transformation is as follows:

[0116] C=C HP +C IF +C PH

[0117] C IF =0.1456×C HP +4771

[0118] C PH =0.06×(C HP +C IF )

[0119] Where C represents the total investment cost of reversible transformation, C IF Indicates independent cost, C PH Indicates basic reserve.

[0120] Example

[0121] The example analysis is carried out with simulated simplified data. The data of conventional hydropower stations are shown in the following table:

[0122] Table 1 Data of upstream and downstream conventional hydropower stations

[0123]

[0124]

[0125] According to the calculation in step S1, the reversible transformation technical parameters are as shown in the following table:

[0126] Table 2 Reversible transformation technical parameters

[0127] Rated head 195m Distance to height ratio 102 Single machine capacity 300MW Maximum flow rate of a single machine <![CDATA[214m 3 / s]]> Number of units 4

[0128] According to the above technical parameters and the calculation costs of the hub project in step S2, the following table shows:

[0129] Table 3 Summary of total cost and various costs of hub projects

[0130]

[0131]

[0132] According to the total cost of the above hub project and the calculation in step S3, the independent cost of reversible transformation of conventional cascade power stations is 1,305,425,200 yuan, the basic reserve is 596,614,700 yuan, and the total cost is 1,054,019,400 yuan.

[0133] The embodiments of the present invention are described above in conjunction with the accompanying drawings, but the present invention is not limited to the above-mentioned specific implementation modes, which are merely illustrative rather than restrictive. Under the guidance of the present invention, ordinary technicians in this field can also make many forms without departing from the scope of protection of the present invention and the claims, all of which are within the protection of the present invention.

Claims

1. A method for estimating the investment cost of reversible transformation of conventional cascade power plants, characterized in that: The following steps are involved: S1. Estimate the technical parameters of reversible transformation based on the geographical location and reservoir conditions of the conventional cascade power stations to be evaluated for transformation; S2. Based on the technical parameters of reversible transformation, estimate the construction cost of the infrastructure of the water delivery system and underground powerhouse, and the purchase and installation cost of the electromechanical equipment of the turbine and generator, and obtain the total investment cost of the hub project; S3. Calculate other costs based on the total investment cost of the reversible transformation hub project, where the other costs include independent costs and basic reserve fees, to obtain the total investment cost of the reversible transformation of the conventional cascade power station.

2. The method for estimating investment costs for reversible transformation of conventional cascade power plants according to claim 1, characterized in that: In the step S1, the technical parameters of the reversible transformation include rated water head, distance-to-height ratio, single-machine capacity, single-machine maximum flow and number of units.

3. The method for estimating investment costs for reversible transformation of conventional cascade power plants according to claim 2, characterized in that: In step S1, the estimated formula of the rated water head is as follows: H r =K×(H max -H min )-H min Among them, H r represents the rated water head, K represents the drawdown depth coefficient, which is 0.4 to 0.5, and H max Indicates the maximum water head, H min Indicates the minimum water head; For the maximum and minimum heads, the water levels of the upper and lower reservoirs are determined by the following formulas; in, Indicates the normal water level of the upper reservoir. Indicates the dead water level of the upper reservoir. Indicates the normal water level of the lower reservoir. Indicates the dead water level of the lower reservoir; The estimation formula of the distance-to-height ratio is as follows: λ=L / Hr Among them, λ represents the distance-to-height ratio, and L represents the horizontal distance between the inlet and outlet of the upper and lower reservoirs. For the horizontal distance, when the boundary of the perennial backwater area of ​​the upper and lower reservoirs is known, it is determined by the shortest distance between the perennial backwater areas of the upper and lower reservoirs. When the boundary of the upper and lower reservoirs is unknown, it is determined by other parameters, and the formula is as follows: in, Indicates the height of the lower reservoir dam, L R It indicates the length of the river channel between the upper and lower reservoir dams; The capacity of a single unit and the number of units are determined by the installed capacity of the existing upstream and downstream conventional hydropower stations. The formula is as follows: Among them, P T represents the total installed capacity of reversible transformation, represents the total installed capacity of upstream conventional hydropower stations, represents the total installed capacity of downstream conventional hydropower stations, P represents the capacity of a single reversible unit, and N represents the number of reversible units; The maximum flow rate of a single machine is determined by the rated head and the capacity of the single machine. The formula is as follows: Where Q represents the maximum flow rate of a single reversible unit, in m 3 / s, P is the capacity of the reverse unit, in MW, g is the acceleration of gravity, η is the energy conversion efficiency, which is 0.88, H r is the rated head, in m.

4. The method for estimating investment costs for reversible transformation of conventional cascade power plants according to claim 1, characterized in that: In step S2, the estimation formula of the total investment cost of the hub project is as follows: C HP =EC M +C W +Cp S +C CA Among them, C HP represents the total investment cost of the reversible transformation hub project, C EM Represents the cost of electromechanical equipment, C W Indicates the cost of the water delivery system, CP S represents the underground plant cost, C CA It represents other construction costs, and all costs are in ten thousand yuan; The cost estimation formula for electromechanical equipment is as follows: WHAT M =CE+CP T C E =3767×P 0.66 n- 0.25 N Among them, C E represents the cost of electrical equipment, C PT represents the pump turbine cost, n represents the rated speed of the reversible unit, It represents the unit capacity cost of the pump turbine; The formula for estimating the cost of the water delivery system is as follows: C W =C T +CP+CM E C T =(0.0606×S T +1.7634)L T N / 2 S T =2×Q / V T L T =Contact r V T =4.2m / s C P =(0.3972×S P +7.3271)L P N / 2 S P =2×Q / V P L P =2×H r C ME =260.42×NQ-54265 Among them, C T represents the tunnel cost, C P Indicates the cost of pressure pipes, C ME Indicates other equipment costs, S T represents the cross-sectional area of ​​the tunnel, L T represents the tunnel length, V T represents the water flow velocity in the tunnel, S P Indicates the cross-sectional area of ​​the pressure pipe, L P Indicates the length of the pressure pipe, V P Indicates the water flow velocity in the pressure pipe; The formula for estimating the cost of underground plant and other buildings is as follows: C CA =43.09×NP+44815。 5. The method for estimating investment costs for reversible transformation of conventional cascade power plants according to claim 1, characterized in that: In step S3, the total investment cost estimation formula for reversible transformation is as follows: C=CH P +CI F +CP H C IF =0.1456×C HP +4771 C PH =0.06×(C HP +C IF ) Where C represents the total investment cost of reversible transformation, C IF Indicates independent cost, C PH Indicates basic reserve.

Citation Information

Patent Citations

  • Hydropower engineering investment estimation method and device

    CN112884589A