Inter-provincial spot goods and in-provincial spot goods fusion clearing method and system considering multi-type market subject standby reservation
By building an optimization model of multiple types of market entities, the problem of unclear reserve assessment and market profit in the power system is solved, and the backup reserve assessment and market profit balance of the power system in the province is realized, ensuring the optimal economy of the power system run.
Patent Information
- Application Number
- CN202411003675.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-11-15
AI Technical Summary
In power systems, it is difficult for the existing technology to effectively evaluate the backup reserve capacity of the power system in the province, and the profit margin of the provincial unit when participating in the inter-provincial spot market is unclear, which affects the safe operation of the power system and the balance of market returns.
The inter-provincial spot and intra-provincial spot clearing method is adopted for joint bidding by multiple types of market entities and demand-side resources participating in bidding. By constructing an optimization model and objective function, it combines physical operation of thermal power, pumping, dispatchable loads, new energy units, etc. Characteristics: build an inter-provincial spot trading model to achieve accurate assessment of backup reservations for power systems within the province and balance market returns.
Achieve accurate assessment of the available reserved capacity of the power system, ensure the balance of returns of market entities in the province in the spot and inter-provincial spot markets, provide references for purchasing/selling electricity for participating in the inter-provincial spot market, and achieve the optimal power system Economic operation.
Smart Images

Figure CN118967209A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of power systems and automation technologies thereof, and in particular to a method and system for integrating inter-provincial spot and intra-provincial spot clearing taking into account the reserve reserves of multiple types of market entities. Background Art
[0002] At present, the construction of power markets in various provinces and cities across the country is in full swing. The power markets in Guangdong, Gansu and other provinces have entered the year-round settlement operation mode, and the second batch of power market pilot provinces have also successively carried out simulation trial operation and settlement trial operation. Under the current operation mode, the provincial spot market generally conducts a preliminary clearing in the morning, formulates the inter-provincial transaction demand or supply, and participates in the inter-provincial spot clearing. After obtaining the inter-provincial clearing results, the clearing results are superimposed on the clearing boundary of the provincial spot market, and then the formal clearing of the provincial spot market is carried out. For the power system, the reserve reserve is related to the safe operation of the power system. Participating in the inter-provincial spot market to purchase electricity during the evening peak period is also an important means to ensure the reserve reserve in the province. Therefore, how to evaluate the effective reserve capacity of the power system in the province is crucial to formulating the sales and purchase of electricity in the inter-provincial spot market. At the same time, when the units in the province participate in the inter-provincial spot market, they also face the problem of comparing the profit space of participating in the inter-provincial market or the intra-provincial market. Summary of the invention
[0003] Purpose of the invention: The present invention aims to provide a method for integrating inter-provincial spot and intra-provincial spot clearing that takes into account joint bidding by multiple types of market entities, participation of demand-side resources in bidding, and standby reservation; another purpose of the present invention is to provide a system for integrating inter-provincial spot and intra-provincial spot clearing that takes into account standby reservation by multiple types of market entities.
[0004] Technical solution: The inter-provincial spot and intra-provincial spot fusion clearing method considering the reserve of multiple types of market entities described in the present invention includes the following steps:
[0005] (1) Construct a data set for the calculation boundary of the spot market on day D+1, including the operating parameters of thermal power units, the quantity-price curve reported by thermal power units, network topology parameters, reservoir capacity data of pumped storage units, dispatchable load operation data, and inter-provincial spot market quantity-price curves;
[0006] (2) Constructing the constraints of the day-ahead spot market optimization model;
[0007] (3) Constructing constraints for the inter-provincial spot market optimization model;
[0008] (4) Based on the constraints of the day-ahead spot market optimization model and the inter-provincial spot market optimization model, and taking maximizing social welfare as the optimization goal, a clearing objective function for the integration of the inter-provincial spot market and the intra-provincial spot market is constructed.
[0009] Furthermore, the constraints of the day-ahead spot market optimization model are constructed, including constraints on thermal power units, network security constraints, system balance constraints, pumped storage unit operation constraints, new energy unit operation constraints, dispatchable load operation constraints, virtual power plant operation constraints and effective reserve demand constraints.
[0010] Furthermore, the constraints of the thermal power unit are as follows:
[0011] The output constraints of thermal power units are:
[0012]
[0013] Among them, a i,t is the start / stop status mark of thermal power unit i in time period t. If the thermal power unit is shut down, then α i,t =0; when the thermal power unit is turned on, α i,t =1; is the upper limit of the output of thermal power unit i at time t, is the lower limit of the output of thermal power unit i at time t; P i,t is the planned output of thermal power unit i at time t, R i,t Reserve spare capacity for thermal power unit i at time t;
[0014] When the thermal power unit is climbing up or down a slope, the climbing constraints of the thermal power unit are as follows:
[0015]
[0016]
[0017] in, is the maximum ramp rate of thermal power unit i, is the maximum ramp rate of thermal power unit i, η i,t is the startup status mark of thermal power unit i at time t, γ i,t is the shutdown status identifier of thermal power unit i at time t;
[0018] When the thermal power unit is in normal operation,
[0019]
[0020]
[0021] In the formula, R i is the ramp rate of the thermal power unit, D i is the landslide rate of the thermal power unit;
[0022] When the thermal power unit is at the start-up time, the range of the thermal power unit output is determined by the allowable startup rate of the thermal power unit, i.e. Decide;
[0023] When the thermal power unit is at the shutdown moment, the range of the thermal power unit's output is determined by the allowable shutdown rate of the thermal power unit.
[0024] The operating time constraints of thermal power units are:
[0025]
[0026]
[0027] Among them, T U , T D The minimum continuous start time and minimum continuous shutdown time of the unit; is the continuous start-up time and continuous shutdown time of unit i in period t, as follows:
[0028]
[0029]
[0030] Furthermore, the network security constraints are as follows:
[0031]
[0032] in, are the power flow transmission limits of section s; G s-i is the generator output power transfer distribution factor of unit i to section s; G s-k is the output power transfer distribution factor of bus load k to section s; G s-j is the output power transfer distribution factor of the tie line equivalent machine j to section s. are the positive and negative flow relaxation variables of section s respectively. k,t The output of bus load, including dispatchable load;
[0033] The system balance constraint is
[0034]
[0035] Among them, P i,t represents the output of unit i in period t, L j,t represents the planned power of tie line j in time period t, NT is the total number of tie lines, D t is the system load during period t.
[0036] The tie line and other value machines should meet the output limit constraints as follows:
[0037]
[0038] in, is the output upper limit of the tie line equal value machine j at time t, is the lower limit of the output of the tie line equivalent machine j at time t.
[0039] Furthermore, the operation constraints of the pumped storage unit are as follows:
[0040]
[0041]
[0042] Where: is the power consumed by the virtual motor of pumped storage unit i in time period t; m represents the power point of the virtual motor of pumped storage unit i; M is the number of power points of the virtual motor of pumped storage unit i; Indicates whether the virtual motor of pumped storage unit i is at power point m during period t; P i,m is the power value of the pumped storage unit i at power point m; is the pumping capacity of the virtual motor of pumped storage unit i in period t; Q i,m is the water flow rate when the pumped storage unit i is at power point m;
[0043] The output characteristics of the pumped storage unit are
[0044]
[0045]
[0046]
[0047] Where: P i,t is the output of pumped storage unit i in period t; is the output of the virtual generator of pumped storage unit i in period t; Q i,t is the water consumption of pumped storage unit i in period t; is the water consumption of the virtual generator of pumped storage unit i in period t; It is a 0 / 1 quantity, indicating whether the virtual generator of pumped storage unit i is running during period t, that is, whether unit i is in the power generation state during period t. i is the water-to-electricity conversion coefficient of unit i during power generation;
[0048] The conversion of electrical energy and potential energy is reflected by the increase and decrease of water volume in the upper and lower reservoirs. For the upper reservoir of the pumped storage unit, the increase and decrease of water volume is as follows:
[0049]
[0050] Where: α i is the water loss rate of pumped storage unit i in the pumping state; is the water level of the upstream reservoir of pumped storage unit i;
[0051] The upper reservoir water volume limit is:
[0052]
[0053] Where: is the lower limit of the water level of the upstream reservoir, It is the upper limit of the water level of the upstream reservoir.
[0054] For the lower reservoir of the pumped storage unit, the model is as follows:
[0055]
[0056]
[0057] Where: β i is the water loss rate of pumped storage unit i in power generation state, is the water level of the downstream reservoir of pumped storage unit i. is the lower limit of the water level of the downstream reservoir, is the upper limit of the water level of the downstream reservoir;
[0058] The reserve constraints of pumped storage units are described as follows:
[0059]
[0060] In the formula, is the water consumption of unit i in period t after considering the standby reserve; is the water level of the upstream reservoir of pumped storage unit i; is the water level of the downstream reservoir of pumped storage unit i.
[0061] Furthermore, the operation constraints of the new energy units are as follows:
[0062]
[0063] in, is the output upper limit of the new energy unit i at time t, that is, the power prediction value of the new energy unit i at time t; R i,t Reserve spare capacity for renewable energy unit i at time t;
[0064] The dispatchable load operation constraints are as follows:
[0065] Dispatchable load output limit constraints:
[0066]
[0067] Among them, B k,t is the output of the dispatchable bus load, is the upper limit of the output of the dispatching bus load, is the lower limit of the dispatchable load output. k,t Calling mark for dispatchable bus load;
[0068] Constraints on the ramping capability of dispatchable loads:
[0069]
[0070]
[0071] In the formula, is the maximum ramp rate of the dispatchable load k, is the maximum ramp-down rate of dispatchable load k.
[0072] Power Constraints:
[0073]
[0074] in, is the upper limit of the power of the dispatching bus load, is the lower limit of the amount of electricity that can be dispatched;
[0075] Fixed output constraint:
[0076]
[0077] in, Fixed output for bus load, including conventional bus load prediction value;
[0078] The total bus load should satisfy the constraint of being equal to the system load forecast value:
[0079]
[0080] The virtual power plant operation constraints are as follows:
[0081]
[0082] in, is the output upper limit of the virtual power plant equivalent unit i at time t, that is, the total rated capacity of the power generation equipment of the virtual power plant equivalent unit i at time t, is the lower limit of the output of the virtual power plant equivalent unit i at time t, that is, the total predicted capacity of the power load of the virtual power plant equivalent unit i at time t; R i,t Reserve spare capacity for the virtual power plant equivalent unit i at time t;
[0083] The effective standby demand constraints are as follows:
[0084]
[0085] In the formula, SR t The system backup demand.
[0086] Furthermore, the constraints of the inter-provincial spot market optimization model are constructed, including the inter-provincial spot market winning transaction constraints and the maximum transmission capacity constraints of the interconnection line transmission channel.
[0087] Furthermore, the inter-provincial spot market bidding transaction constraints are
[0088]
[0089] Among them, L j,t represents the planned power of tie line j in time period t, E a,t is the exchange power between province a and province a in time period t;
[0090] The tie line transmission channel is defined as a critical section, and the maximum transmission capacity constraint of the tie line transmission channel is equivalent to the above network security constraint.
[0091] Furthermore, the objective function of the fusion clearing of the inter-provincial spot market and the intra-provincial spot market is:
[0092]
[0093] Where N is the total number of units; T is the number of D+1 time periods considered; P i,t represents the output of unit i in time period t; A represents the total number of provinces and cities participating in the inter-provincial spot market; E a,t represents the exchange power between province a and province a in time period t; C i,t (P i,t ), are the operating cost and startup cost of unit i in period t, respectively. i,t (P i,t ) is a multi-segment linear function related to the output ranges reported by the unit and the corresponding energy prices; C i,t (E a,t ) is the electricity selling / buying cost with province a in period t, which is the product of the average price of the province participating in the inter-provincial spot market clearing and the winning bid amount; C k,t (B k,t ) is the winning bid cost of user-side demand response clearing, which is the product of the bid price and winning bid amount of dispatchable load k in time period t; M is the network power flow constraint relaxation penalty factor used for market clearing optimization; are the positive and negative flow relaxation variables of section s respectively; NS is the total number of sections.
[0094] The inter-provincial spot and intra-provincial spot fusion clearing system considering the reserve of multiple types of market entities described in the present invention includes:
[0095] The data collection module is used to collect and construct the D+1 day spot market calculation boundary data set, including the operating parameters of thermal power units, the quantity and price curves reported by thermal power units, network topology parameters, pumped storage unit reservoir capacity data, dispatchable load operation data and inter-provincial spot market quantity and price curves;
[0096] The day-ahead spot market optimization module is used to construct the constraints of the day-ahead spot market optimization model;
[0097] Inter-provincial spot market optimization module, used to construct constraints for the inter-provincial spot market optimization model;
[0098] The calculation module is used to take the maximization of social welfare as the optimization goal, construct the objective function of the fusion and clearing of the inter-provincial spot market and the intra-provincial spot market, and calculate the results of the fusion and clearing of the inter-provincial spot market and the intra-provincial spot market.
[0099] Beneficial effect: Compared with the prior art, the present invention has the following significant advantages: the present invention combines the mathematical models of the physical operation characteristics of multiple types of market entities such as thermal power, pumped storage, dispatchable loads, and new energy units to construct available reserve calculation models for conventional thermal power, pumped storage, and dispatchable loads, and accurately evaluates the system's available reserved reserve capacity; constructs an inter-provincial spot trading model that takes into account the transmission capacity of inter-provincial transmission channels; constructs an optimization algorithm that considers the joint bidding of multiple types of market entities, the participation of demand-side resources in bidding, and the integration and clearing of the inter-provincial spot market and the provincial spot actual measurement that take into account the available reserve reserve within the province, so as to achieve accurate evaluation of the reserve reserve of the provincial power system, ensure the balance of benefits between the market entities within the province participating in the provincial spot market and the inter-provincial spot market, and at the same time provide a reference for purchasing / selling electricity for those participating in the inter-provincial spot market, so as to achieve optimal economic operation of the power system. BRIEF DESCRIPTION OF THE DRAWINGS
[0100] Figure 1 It is a flow chart of the present invention. DETAILED DESCRIPTION
[0101] The present invention will be further described below in conjunction with the accompanying drawings.
[0102] The inter-provincial spot and intra-provincial spot fusion clearing method considering the reserve of multiple types of market entities described in the present invention comprises the following steps:
[0103] (1) Construct a data set for calculating the boundary of the spot market on day D+1, including the operating parameters of thermal power units, the quantity-price curves reported by thermal power units, network topology parameters, reservoir capacity data of pumped-storage units, dispatchable load operating data, and inter-provincial spot market quantity-price curves.
[0104] (2) Construct the constraints of the day-ahead spot market optimization model, including constraints on thermal power units, network security constraints, system balance constraints, pumped storage unit operation constraints, new energy unit operation constraints, dispatchable load operation constraints, virtual power plant operation constraints, and effective reserve demand constraints.
[0105] The constraints of the thermal power unit are as follows:
[0106] The output constraints of thermal power units are:
[0107]
[0108] Among them, a i,t is the start / stop status mark of thermal power unit i in time period t. If the thermal power unit is shut down, then α i,t =0; when the thermal power unit is turned on, α i,t =1; is the upper limit of the output of thermal power unit i at time t, is the lower limit of the output of thermal power unit i at time t; P i,t is the planned output of thermal power unit i at time t, R i,t Reserve spare capacity for thermal power unit i at time t;
[0109] When the thermal power unit is climbing up or down a slope, the climbing constraints of the thermal power unit are as follows:
[0110]
[0111]
[0112] in, is the maximum ramp rate of thermal power unit i, is the maximum ramp rate of thermal power unit i, η i,t is the startup status mark of thermal power unit i at time t, γ i,t is the shutdown status identifier of thermal power unit i at time t;
[0113] When the thermal power unit is in normal operation,
[0114]
[0115]
[0116] In the formula, R i is the ramp rate of the thermal power unit, D i is the landslide rate of the thermal power unit;
[0117] When the thermal power unit is at the start-up time, the range of the thermal power unit output is determined by the allowable startup rate of the thermal power unit, i.e. Decide;
[0118] When the thermal power unit is at the shutdown moment, the range of the thermal power unit's output is determined by the thermal power unit's allowable shutdown rate;
[0119] The operating time constraints of thermal power units are:
[0120]
[0121]
[0122] Among them, T U , T D The minimum continuous start time and minimum continuous shutdown time of the unit; is the continuous start-up time and continuous shutdown time of unit i in period t, as follows:
[0123]
[0124]
[0125] The constraints of the thermal power unit are as follows:
[0126] The output constraints of thermal power units are:
[0127]
[0128] Among them, a i,t is the start / stop status mark of thermal power unit i in time period t. If the thermal power unit is shut down, then α i,t =0; when the thermal power unit is turned on, α i,t =1; is the upper limit of the output of thermal power unit i at time t, is the lower limit of the output of thermal power unit i at time t; P i,t is the planned output of thermal power unit i at time t, R i,t Reserve spare capacity for thermal power unit i at time t;
[0129] When the thermal power unit is climbing up or down a slope, the climbing constraints of the thermal power unit are as follows:
[0130]
[0131]
[0132] in, is the maximum ramp rate of thermal power unit i, is the maximum ramp rate of thermal power unit i, η i,t is the startup status mark of thermal power unit i at time t, γi,t is the shutdown status identifier of thermal power unit i at time t;
[0133] When the thermal power unit is in normal operation,
[0134]
[0135]
[0136] In the formula, R i is the ramp rate of the thermal power unit, D i is the landslide rate of the thermal power unit;
[0137] When the thermal power unit is at the start-up time, the range of the thermal power unit output is determined by the allowable startup rate of the thermal power unit, i.e. Decide;
[0138] When the thermal power unit is at the shutdown moment, the range of the thermal power unit's output is determined by the thermal power unit's allowable shutdown rate;
[0139] The operating time constraints of thermal power units are:
[0140]
[0141]
[0142] Among them, T U , T D The minimum continuous start time and minimum continuous shutdown time of the unit; is the continuous start-up time and continuous shutdown time of unit i in period t, as follows:
[0143]
[0144]
[0145] The network security constraints are as follows:
[0146]
[0147] in, are the power flow transmission limits of section s; G s-i is the generator output power transfer distribution factor of unit i to section s; G s-k is the output power transfer distribution factor of bus load k to section s; G s-j is the output power transfer distribution factor of the tie line equivalent machine j to section s. are the positive and negative flow relaxation variables of section s respectively. k,t The output of bus load, including dispatchable load;
[0148] The system balance constraint is
[0149]
[0150] Among them, P i,t represents the output of unit i in period t, L j,t represents the planned power of tie line j in time period t (input is positive, output is negative), NT is the total number of tie lines, D t is the system load during period t.
[0151] The tie line and other value machines should meet the output limit constraints as follows:
[0152]
[0153] in, is the output upper limit of the tie line equal value machine j at time t, is the lower limit of the output of the tie line equivalent machine j at time t.
[0154] The two working states of the pumped storage unit are virtualized as generator and motor respectively. The virtual generator model is similar to that of the ordinary unit. For the virtual motor, it absorbs power from the power grid, and the power value is in one of several power states. The operating constraints of the pumped storage unit are as follows:
[0155]
[0156]
[0157] Where: is the power consumed by the virtual motor of pumped storage unit i in time period t; m represents the power point of the virtual motor of pumped storage unit i; M is the number of power points of the virtual motor of pumped storage unit i; Indicates whether the virtual motor of pumped storage unit i is at power point m during period t; P i,m is the power value of the pumped storage unit i at power point m; is the pumping capacity of the virtual motor of pumped storage unit i in period t; Q i,m is the water flow rate when the pumped storage unit i is at power point m;
[0158] The output characteristics of the pumped storage unit are
[0159]
[0160]
[0161]
[0162] Where: P i,t is the output of pumped storage unit i in period t; is the output of the virtual generator of pumped storage unit i in period t; Q i,t is the water consumption of pumped storage unit i in period t; is the water consumption of the virtual generator of pumped storage unit i in period t; It is a 0 / 1 quantity, indicating whether the virtual generator of pumped storage unit i is running during period t, that is, whether unit i is in the power generation state during period t. i is the water-to-electricity conversion coefficient of unit i during power generation;
[0163] From the working principle of the pumped storage unit, it can be known that the water volume of the upper and lower reservoirs is used as the medium for converting electric energy. Therefore, this article reflects the conversion of electric energy and potential energy through the increase and decrease of the water volume of the upper and lower reservoirs. Therefore, the increase and decrease of the water volume of the upper and lower reservoirs is used to reflect the conversion of electric energy and potential energy. For the upper reservoir of the pumped storage unit, the increase and decrease of the water volume is as follows:
[0164]
[0165] Where: α i is the water loss rate of pumped storage unit i in the pumping state; is the water level of the upstream reservoir of pumped storage unit i;
[0166] The upper reservoir water volume limit is:
[0167]
[0168] Where: is the lower limit of the water level of the upstream reservoir, It is the upper limit of the water level of the upstream reservoir.
[0169] For the lower reservoir of the pumped storage unit, the model is as follows:
[0170]
[0171]
[0172] Where: β i is the water loss rate of pumped storage unit i in power generation state, is the water level of the downstream reservoir of pumped storage unit i. is the lower limit of the water level of the downstream reservoir, is the upper limit of the water level of the downstream reservoir;
[0173] The reserve constraints of pumped storage units are described as follows:
[0174]
[0175] In the formula, is the water consumption of unit i in period t after considering the standby reserve; is the water level of the upstream reservoir of pumped storage unit i. is the water level of the downstream reservoir of pumped storage unit i.
[0176] The operating constraints of the new energy units are as follows:
[0177]
[0178] in, is the output upper limit of the new energy unit i at time t, that is, the power prediction value of the new energy unit i at time t; R i,t Reserve spare capacity for renewable energy unit i at time t;
[0179] The dispatchable load operation constraints are as follows:
[0180] Dispatchable load output limit constraints
[0181]
[0182] Among them, B k,t is the output of the dispatchable bus load, is the upper limit of the output of the dispatching bus load, is the lower limit of the dispatchable load output. k,t Calling mark for dispatchable bus load;
[0183] Constraints on the ramping capability of dispatchable loads
[0184]
[0185]
[0186] In the formula, is the maximum ramp rate of the dispatchable load k, is the maximum ramp rate of dispatchable load k;
[0187] Power Constraints:
[0188]
[0189] in, is the upper limit of the power of the dispatching bus load, is the lower limit of the amount of electricity that can be dispatched;
[0190] Fixed output constraint
[0191]
[0192] in, Fixed output for bus load, including conventional bus load prediction value;
[0193] The total bus load should satisfy the constraint of being equal to the system load forecast value:
[0194]
[0195] The virtual power plant operation constraints are as follows:
[0196]
[0197] in, is the output upper limit of the virtual power plant equivalent unit i at time t, that is, the total rated capacity of the power generation equipment of the virtual power plant equivalent unit i at time t, is the lower limit of the output of the virtual power plant equivalent unit i at time t, that is, the total predicted capacity of the power load of the virtual power plant equivalent unit i at time t; R i,t Reserve spare capacity for the virtual power plant equivalent unit i at time t;
[0198] The effective standby demand constraints are as follows:
[0199]
[0200] In the formula, SR t The system backup demand.
[0201] (3) Construct constraints for the optimization model of the inter-provincial spot market.
[0202] Construct the constraints of the inter-provincial spot market optimization model, including the inter-provincial spot market winning transaction constraints and the maximum transmission capacity constraints of the interconnection line transmission channel.
[0203] The inter-provincial spot market bidding transaction constraints are
[0204]
[0205] Among them, L j,t represents the planned power of tie line j in time period t, E a,t for;
[0206] The tie line transmission channel is defined as a critical section, and the maximum transmission capacity constraint of the tie line transmission channel is equivalent to the above network security constraint.
[0207] (4) Based on the constraints of the day-ahead spot market optimization model and the inter-provincial spot market optimization model, and taking maximizing social welfare as the optimization goal, a clearing objective function for the integration of the inter-provincial spot market and the intra-provincial spot market is constructed.
[0208] The objective function of the fusion clearing of the inter-provincial spot market and the intra-provincial spot market is:
[0209]
[0210] Where N is the total number of units; T is the number of D+1 time periods considered; P i,t represents the output of unit i in time period t; A represents the total number of provinces and cities participating in the inter-provincial spot market; E a,t represents the exchange power between province a and province a in time period t; C i,t (P i,t ), are the operating cost and startup cost of unit i in period t, respectively. i,t (P i,t ) is a multi-segment linear function related to the output ranges reported by the unit and the corresponding energy prices; C i,t (E a,t ) is the electricity selling / buying cost with province a in period t, which is the product of the average price of the province participating in the inter-provincial spot market clearing and the winning bid amount; C k,t (B k,t ) is the winning bid cost of user-side demand response clearing, which is the product of the bid price and winning bid amount of dispatchable load k in time period t; M is the network power flow constraint relaxation penalty factor used for market clearing optimization; are the positive and negative flow relaxation variables of section s respectively; NS is the total number of sections.
[0211] The inter-provincial spot and intra-provincial spot fusion clearing system considering the reserve of multiple types of market entities described in the present invention includes:
[0212] The data collection module is used to collect and construct the D+1 day spot market calculation boundary data set, including the operating parameters of thermal power units, the quantity and price curves reported by thermal power units, network topology parameters, pumped storage unit reservoir capacity data, dispatchable load operation data and inter-provincial spot market quantity and price curves;
[0213] The day-ahead spot market optimization module is used to construct the constraints of the day-ahead spot market optimization model;
[0214] Inter-provincial spot market optimization module, used to construct constraints for the inter-provincial spot market optimization model;
[0215] The calculation module is used to take the maximization of social welfare as the optimization goal, construct the objective function of the fusion and clearing of the inter-provincial spot market and the intra-provincial spot market, and calculate the results of the fusion and clearing of the inter-provincial spot market and the intra-provincial spot market.
Claims
1. A method for clearing inter-provincial spot and intra-provincial spot products by considering the reserve reserves of multiple types of market players. It is characterized in that The following steps are involved: (1) Construct a data set for the calculation boundary of the spot market on day D+1, including the operating parameters of thermal power units, the quantity-price curve reported by thermal power units, network topology parameters, reservoir capacity data of pumped storage units, dispatchable load operation data, and inter-provincial spot market quantity-price curves; (2) Constructing the constraints of the day-ahead spot market optimization model; (3) Constructing constraints for the inter-provincial spot market optimization model; (4) Based on the constraints of the day-ahead spot market optimization model and the inter-provincial spot market optimization model, and taking maximizing social welfare as the optimization goal, a clearing objective function for the integration of the inter-provincial spot market and the intra-provincial spot market is constructed.
2. According to claim 1, the method for clearing inter-provincial spot and intra-provincial spot that are reserved by multiple types of market entities, It is characterized in that Construct the constraints of the day-ahead spot market optimization model, including thermal power unit constraints, network security constraints, system balance constraints, pumped storage unit operation constraints, new energy unit operation constraints, dispatchable load operation constraints, virtual power plant operation constraints and effective reserve demand constraints.
3. According to claim 2, the method for clearing inter-provincial spot and intra-provincial spot that are reserved for multiple types of market entities, It is characterized in that The constraints of the thermal power unit are as follows: The output constraints of thermal power units are: Among them, a i,t is the start / stop status mark of thermal power unit i in time period t. If the thermal power unit is shut down, then α i,t =0; when the thermal power unit is turned on, α i,t =1; is the upper limit of the output of thermal power unit i at time t, is the lower limit of the output of thermal power unit i at time t; P i,t is the planned output of thermal power unit i at time t, R i,t Reserve spare capacity for thermal power unit i at time t; When the thermal power unit is climbing up or down a slope, the climbing constraints of the thermal power unit are as follows: Where ΔP i U is the maximum ramp rate of thermal power unit i, ΔP i D is the maximum ramp rate of thermal power unit i, η i,t is the startup status mark of thermal power unit i at time t, γ i,t is the shutdown status identifier of thermal power unit i at time t; When the thermal power unit is in normal operation, ΔP i U =R i ×PD t ΔP i D =D i ×PD t In the formula, R i is the ramp rate of the thermal power unit, D i is the landslide rate of the thermal power unit; When the thermal power unit is at the start-up time, the range of the thermal power unit output is determined by the allowable startup rate of the thermal power unit, i.e. Decide; When the thermal power unit is at the shutdown moment, the range of the thermal power unit's output is determined by the thermal power unit's allowable shutdown rate; The operating time constraints of thermal power units are: Among them, T U 、T D The minimum continuous start time and minimum continuous shutdown time of the unit; is the continuous start-up time and continuous shutdown time of unit i in period t, as follows:
4. According to claim 3, the method for clearing inter-provincial spot and intra-provincial spot that are reserved for multiple types of market entities, It is characterized in that The network security constraints are as follows: Among them, P s min , P s max are the power flow transmission limits of section s; G s-i is the generator output power transfer distribution factor of unit i to section s; G s-k is the output power transfer distribution factor of bus load k to section s; G s-j is the output power transfer distribution factor of tie line equivalent machine j to section s; are the positive and negative flow relaxation variables of section s respectively; B k,t The output of bus load, including dispatchable load; The system balance constraint is Among them, P i,t represents the output of unit i in period t, L j,t represents the planned power of tie line j in time period t, NT is the total number of tie lines, D t is the system load during period t; The tie line and other value machines should meet the output limit constraints as follows: in, is the output upper limit of the tie line equal value machine j at time t, is the lower limit of the output of the tie line equivalent machine j at time t.
5. According to claim 4, the method for clearing inter-provincial spot and intra-provincial spot reserves reserved by various types of market entities, It is characterized in that The operating constraints of the pumped storage unit are as follows: Where: is the power consumed by the virtual motor of pumped storage unit i in time period t; m marks the power point of the virtual motor of pumped storage unit i; M is the number of power points of the virtual motor of pumped storage unit i; Indicates whether the virtual motor of pumped storage unit i is at power point m during period t; P i,m is the power value of the pumped storage unit i at power point m; is the pumping capacity of the virtual motor of pumped storage unit i in period t; Q i,m is the water flow rate when the pumped storage unit i is at power point m; The output characteristics of the pumped storage unit are Where: P i,t is the output of pumped storage unit i in period t; is the output of the virtual generator of pumped storage unit i in period t; Q i,t is the water consumption of pumped storage unit i in period t; is the water consumption of the virtual generator of pumped storage unit i in period t; is a 0 / 1 quantity, indicating whether the virtual generator of pumped storage unit i is running during period t, that is, whether unit i is in the power generation state during period t; ω i is the water-to-electricity conversion coefficient of unit i during power generation; The conversion of electrical energy and potential energy is reflected by the increase and decrease of water volume in the upper and lower reservoirs. For the upper reservoir of the pumped storage unit, the increase and decrease of water volume is as follows: Where: α i is the water loss rate of pumped storage unit i in the pumping state; is the water level of the upstream reservoir of pumped storage unit i; The upper reservoir water volume limit is: Where: is the lower limit of the water level of the upstream reservoir, is the upper limit of the water level of the upstream reservoir; For the lower reservoir of the pumped storage unit, the model is as follows: Where: β i is the water loss rate of pumped storage unit i in power generation state, is the water level of the downstream reservoir of pumped storage unit i; is the lower limit of the water level of the downstream reservoir, is the upper limit of the water level of the downstream reservoir; The reserve constraints of pumped storage units are described as follows: In the formula, is the water consumption of unit i in period t after considering the standby reserve; is the water level of the upstream reservoir of pumped storage unit i; is the water level of the downstream reservoir of pumped storage unit i.
6. According to claim 5, the method for clearing inter-provincial spot and intra-provincial spot that are reserved for multiple types of market entities, It is characterized in that The operating constraints of the new energy units are as follows: in, is the output upper limit of the new energy unit i at time t, that is, the power prediction value of the new energy unit i at time t; R i,t Reserve spare capacity for renewable energy unit i at time t; The dispatchable load operation constraints are as follows: Dispatchable load output limit constraints Among them, B k,t is the output of the dispatchable bus load, is the upper limit of the output of the dispatching bus load, is the lower limit of the dispatchable load output; μ k,t Calling mark for dispatchable bus load; Constraints on the ramping capability of dispatchable loads In the formula, is the maximum ramp rate of the dispatchable load k, is the maximum ramp rate of dispatchable load k; Power Constraints: in, is the upper limit of the power of the dispatching bus load, is the lower limit of the amount of electricity that can be dispatched; Fixed output constraint in, Fixed output for bus load, including conventional bus load prediction value; The total bus load should satisfy the constraint of being equal to the system load forecast value: The virtual power plant operation constraints are as follows: in, is the output upper limit of the virtual power plant equivalent unit i at time t, that is, the total rated capacity of the power generation equipment of the virtual power plant equivalent unit i at time t, is the lower limit of the output of the virtual power plant equivalent unit i at time t, that is, the total predicted capacity of the power load of the virtual power plant equivalent unit i at time t; R i,t Reserve spare capacity for the virtual power plant equivalent unit i at time t; The effective standby demand constraints are as follows: In the formula, SR t The system backup demand.
7. According to claim 6, the method for clearing inter-provincial spot and intra-provincial spot that are reserved for multiple types of market entities, It is characterized in that Construct the constraints of the inter-provincial spot market optimization model, including the inter-provincial spot market winning transaction constraints and the maximum transmission capacity constraints of the interconnection line transmission channel.
8. According to claim 7, the method for clearing inter-provincial spot and intra-provincial spot that are reserved by multiple types of market entities, It is characterized in that The inter-provincial spot market bidding transaction constraints are Among them, L j,t represents the planned power of tie line j in time period t, E a,t is the exchange power between province a and province a in time period t; The tie line transmission channel is defined as a critical section, and the maximum transmission capacity constraint of the tie line transmission channel is equivalent to the above network security constraint.
9. According to claim 1, the method for clearing inter-provincial spot and intra-provincial spot that are reserved by multiple types of market entities, It is characterized in that The objective function of the fusion clearing of the inter-provincial spot market and the intra-provincial spot market is: Where N is the total number of units; T is the number of D+1 time periods considered; P i,t represents the output of unit i in time period t; A represents the total number of provinces and cities participating in the inter-provincial spot market; E a,t represents the exchange power between province a and province a in time period t; C i,t (P i,t ), are the operating cost and startup cost of unit i in period t, respectively. i,t (P i,t ) is a multi-segment linear function related to the output ranges reported by the unit and the corresponding energy prices; C i,t (E a,t ) is the electricity selling / buying cost with province a in period t, which is the product of the average price of the province participating in the inter-provincial spot market clearing and the winning bid amount; C k,t (B k,t ) is the winning bid cost of user-side demand response clearing, which is the product of the bid price and winning bid amount of dispatchable load k in time period t; M is the network power flow constraint relaxation penalty factor used for market clearing optimization; are the positive and negative flow relaxation variables of section s respectively; NS is the total number of sections.
10. A fusion clearing system for inter-provincial spot and intra-provincial spot that takes into account the reserve of multiple types of market entities. It is characterized in that include: The data collection module is used to collect and construct the D+1 day spot market calculation boundary data set, including the operating parameters of thermal power units, the quantity and price curves reported by thermal power units, network topology parameters, pumped storage unit reservoir capacity data, dispatchable load operation data and inter-provincial spot market quantity and price curves; The day-ahead spot market optimization module is used to construct the constraints of the day-ahead spot market optimization model; Inter-provincial spot market optimization module, used to construct constraints for the inter-provincial spot market optimization model; The calculation module is used to take the maximization of social welfare as the optimization goal, construct the objective function of the fusion and clearing of the inter-provincial spot market and the intra-provincial spot market, and calculate the results of the fusion and clearing of the inter-provincial spot market and the intra-provincial spot market.