Tunnel vault settlement monitoring and early warning method

By classifying and arranging monitoring points according to geological conditions in tunnel construction, and combining long and short-term memory neural networks and linear regression methods for data analysis, the problem of fast or slow change rate of tunnel vault settlement is solved, and more accurate prediction is achieved and early warning, improving construction safety and quality.

CN118997850AActive Publication Date: 2024-11-22THE FIRST ENGINEERING COMPANY OF CCCC FOURTH HARBOUR ENGINEERING CO LTD +2

Patent Information

Application Number
CN202411086796.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-22
Estimated Expiration
2044-08-08

AI Technical Summary

Technical Problem

The existing tunnel vault settlement monitoring method fails to fully consider the changes and the prediction algorithm, resulting in the prediction results not meeting the actual construction, affecting construction safety and quality.

Method used

Monitoring points are classified and arranged according to tunnel excavation methods and geological conditions, and data analysis methods combined with long and short-term memory neural networks and linear regression methods are used to build a prediction model for fast changes and slow changes to obtain more accurate prediction values.

Benefits of technology

By comprehensively considering the conformity between the settlement changes of tunnel vaults and the prediction algorithm, more effective prediction values ​​can be obtained, construction can be guided, and monitoring accuracy and safety can be improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997850A_ABST
    Figure CN118997850A_ABST
Patent Text Reader

Abstract

The invention provides a tunnel vault settlement monitoring and early warning method, which is suitable for the field of tunnel construction monitoring and comprises point location arrangement, data acquisition, data analysis and early warning. The tunnel vault settlement monitoring and early warning method provided by the invention has the advantages of high accuracy and high comprehensiveness, and can be widely applied to the field of tunnel construction monitoring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a tunnel vault settlement monitoring and early warning method, which is applicable to the field of tunnel construction monitoring. Background Art

[0002] Tunnel construction monitoring is an important part of ensuring the safety, quality and progress of tunnel projects. During tunnel construction, vault settlement is a key monitoring indicator because it is directly related to the stability of the tunnel structure and construction safety. The research and application of tunnel vault settlement monitoring and early warning methods are of great significance for preventing accidents during tunnel construction, protecting personnel safety and extending the service life of tunnels.

[0003] At present, with the continuous development of computer technology and the continuous extension of multidisciplinary cross-applications, the use of advanced algorithms for analysis and prediction in tunnel vault settlement analysis is a hot topic in the current industry research. At present, people in the industry mainly think of tunnel vault settlement monitoring data as time series data, and use some algorithms for time series data to analyze or build models, etc., and finally obtain predicted values ​​to guide construction.

[0004] However, in the current research status, the fit between the changes in tunnel vault settlement and the adopted prediction algorithm is not fully considered, resulting in the prediction results not being in line with the actual construction, and even hindering the normal progress of construction. The main reason is that the fit between the changes in tunnel vault settlement and the adopted prediction algorithm is not considered. The change rate of tunnel vault settlement changes in some cases is relatively fast, such as the monitoring results of the vault settlement of sections with shallow burial depth and poor surrounding rock conditions. The change rate of tunnel vault settlement changes in some cases is slow, such as the monitoring results of the vault settlement of sections with good surrounding rock conditions. At the same time, there are many algorithms for time series data, some of which are good at analyzing fast-changing data, while others are good at capturing and analyzing slow-changing data. Therefore, there is an urgent need for a tunnel vault settlement monitoring and early warning method that fully considers the fit between the changes in tunnel vault settlement and the adopted prediction algorithm. Summary of the invention

[0005] The purpose of the present invention is to solve the problem that a tunnel vault settlement monitoring and early warning method that fully considers the fit between the tunnel vault settlement change and the adopted prediction algorithm is urgently needed, and a tunnel vault settlement monitoring and early warning method is proposed.

[0006] The purpose of the present invention can be achieved by adopting the following technical solutions:

[0007] A tunnel vault settlement monitoring and early warning method, characterized in that the tunnel vault settlement monitoring and early warning method comprises the following steps:

[0008] S101, point arrangement;

[0009] The point arrangement includes arranging the arch settlement monitoring points in a targeted manner according to the excavation method adopted by the tunnel. The number of the arch settlement monitoring points is i, represented by M i , the distance between the vault settlement monitoring points is adjusted according to the actual excavation situation;

[0010] S102, data acquisition;

[0011] The data acquisition includes classifying the vault monitoring points according to the different sections where they are located and dividing them into two categories: deformation expectation high vault settlement monitoring points H j and deformation expectation low arch settlement monitoring point L k , where j+k=i, the classification method is: a) exploring and collecting data on the buried depth and topographic geological conditions of the section where the arch settlement monitoring point is located, b) when the buried depth of the section is greater than or equal to x meters, and the surrounding rock grade of the section is level Ⅰ~Ⅳ, the arch settlement monitoring point of the section is a low arch settlement monitoring point with deformation expectation, c) when the buried depth of the section is less than x meters or the surrounding rock grade is less than or equal to level Ⅴ, the arch settlement monitoring point of the section is a high arch settlement monitoring point with deformation expectation, where x=40 when the surrounding rock grade is level Ⅵ, and x=30 when the surrounding rock grade is level Ⅴ;

[0012] The data acquisition also includes the following steps: j and deformation expectation low arch settlement monitoring point L k The monitoring frequency required by the relevant specifications is used to obtain the data sets containing monitoring timestamps, which are the deformation expectation high data sets C j and the low deformation expectation dataset D k ;

[0013] S103, data analysis;

[0014] The data analysis includes performing classified directional data analysis on the obtained data set containing the monitoring timestamp to obtain a predicted value P corresponding to each vault settlement monitoring point. The steps of the classified directional data analysis are:

[0015] d) arranging the data set containing the monitoring timestamps, wherein the arranging includes arranging the data set containing the monitoring timestamps into data sets with consistent time intervals,

[0016] e) When the data set containing the monitoring timestamp is a high deformation expectation data set C j When the prediction value is obtained, a prediction model is constructed using a long short-term memory neural network that can capture fast changes.

[0017] f) When the data set containing the monitoring timestamp is a low deformation expectation data set D k When , the linear regression method capable of capturing slow changes is used to obtain the predicted value;

[0018] S104, the early warning purpose is achieved;

[0019] The achievement of the warning purpose includes judging its stable state according to the obtained prediction value P in combination with its corresponding arch settlement monitoring and early warning standard, so as to achieve the purpose of early warning, wherein the corresponding arch settlement monitoring and early warning standard is comprehensively formulated according to the topographic and geological conditions of the section where the monitoring point where the prediction value P is obtained is located and the excavation conditions;

[0020] Further, in the above S103, in the data analysis, the time interval is 0.5 day or 1 day;

[0021] Furthermore, in the above S103, the steps of constructing the prediction model of the long short-term memory neural network to obtain the prediction value are: a) data normalization processing, b) dividing the data set into a training set and a test set, c) constructing a long short-term memory neural network prediction model, d) model training, e) model evaluation, f) model deployment and application, and obtaining the prediction value;

[0022] Furthermore, the above-mentioned construction of the long short-term memory neural network prediction model includes using a smoothed corrected linear unit function as an activation function, and the expression of the smoothed corrected linear unit function is formula (1),

[0023] f(x)=ln(1+e x ) (1)

[0024] Where x is the input and f(x) is the output;

[0025] Furthermore, in the above S103, the steps of obtaining the predicted value by the linear regression method are: a) data preprocessing, including data cleaning and conversion, b) data partitioning, c) establishing a univariate linear regression model, e) using the least squares method to evaluate model parameters, f) using a test set to evaluate model performance, g) model optimization, and h) model prediction to obtain a predicted value.

[0026] The beneficial effects of the present invention are:

[0027] The beneficial effect of the present invention is that the compatibility between the change of tunnel vault settlement and the adopted prediction algorithm is comprehensively considered, so that the prediction value obtained by using the method can guide the construction more effectively. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 : A flow chart of a tunnel vault settlement monitoring and early warning method of the present invention;

[0029] Figure 2 : The measured value and predicted value curve diagram of section number TJ-12 of the embodiment of the present invention;

[0030] Figure 3 : Measured value and predicted value curve diagram of section number TJ-12 of an embodiment of the present invention. DETAILED DESCRIPTION

[0031] The specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings; it should be understood that the specific embodiments given here are only used to illustrate and explain the present invention and cannot be used to limit the present invention.

[0032] The following is a specific embodiment of a tunnel vault settlement monitoring and early warning method.

[0033] like Figure 1 FIG. 1 is a flow chart of a tunnel vault settlement monitoring and early warning method according to the present invention.

[0034] A tunnel vault settlement monitoring and early warning method, characterized in that the tunnel vault settlement monitoring and early warning method comprises the following steps:

[0035] S101, point arrangement;

[0036] The point arrangement includes arranging the arch settlement monitoring points in a targeted manner according to the excavation method adopted by the tunnel. The number of the arch settlement monitoring points is i, represented by M i , the distance between the vault settlement monitoring points is adjusted according to the actual excavation situation;

[0037] In this embodiment, the project name is the Gombak 1# Tunnel of the Eighth Division of the General Manager's Office of the East Coast Railway Project of China Communications Construction Corporation Malaysia. The total length of the tunnel is 935m, of which the import mileage is CH516+955 and the export mileage is CH517+890. The section from the start of the tunnel to CH517+000 is -3‰, and the section from CH517+000 to the end of the tunnel is 5.8‰. The maximum burial depth is 74m and the minimum burial depth is 9m. The CH517+160-CH517+260 section is a shallow buried section of the tunnel body, with the shallowest burial depth of 10.5m. The tunnel is designed as a composite lining structure with a standard line spacing of 4.2m. The entrance portal is an end wall type and the exit portal is an oblique cut type. The geological lithology of the tunnel is mainly medium-weathered granite, and the rock mass is relatively broken. The surface vegetation of the Gombak Tunnel is well developed, all of which are formed tree forests. The import end is located under the high-voltage line corridor, and the high-voltage line needs to be relocated; the export end has convenient transportation conditions, close to the E8 Expressway, and adjacent to the existing local roads. The entrance and exit and shallow buried section of Ema Tunnel are mainly composed of fully weathered to moderately weathered residual alluvial clay, fine sand and granite. The rock mass is broken to extremely broken. The predicted normal seepage volume is 2361.18m3 / day. The deep buried section of the tunnel is mainly composed of moderately weathered granite. The rock mass is relatively broken. The predicted normal seepage volume is 2361.18m3 / day and the maximum seepage volume is 9131.62m3 / day.

[0038] In this embodiment, the Ema 1# tunnel is arranged with vault settlement monitoring points in accordance with the specification requirements.

[0039] S102, data acquisition;

[0040] The data acquisition includes classifying the vault monitoring points according to the different sections where they are located and dividing them into two categories: deformation expectation high vault settlement monitoring points H j and deformation expectation low arch settlement monitoring point L k , where j+k=i, the classification method is: a) exploring and collecting data on the buried depth and topographic geological conditions of the section where the arch settlement monitoring point is located, b) when the buried depth of the section is greater than or equal to x meters, and the surrounding rock grade of the section is level Ⅰ~Ⅳ, the arch settlement monitoring point of the section is a low arch settlement monitoring point with deformation expectation, c) when the buried depth of the section is less than x meters or the surrounding rock grade is less than or equal to level Ⅴ, the arch settlement monitoring point of the section is a high arch settlement monitoring point with deformation expectation, where x=40 when the surrounding rock grade is level Ⅵ, and x=30 when the surrounding rock grade is level Ⅴ;

[0041] The data acquisition also includes the following steps: j and deformation expectation low arch settlement monitoring point L k The monitoring frequency required by the relevant specifications is used to obtain the data sets containing monitoring timestamps, which are the deformation expectation high data sets Cj and the low deformation expectation dataset D k ;

[0042] In this embodiment, the vault settlement monitoring points of the tunnel are divided into deformation expected high vault settlement monitoring points and deformation expected low vault settlement monitoring points according to requirements. After classification according to requirements, the typical point number of the deformation expected high vault settlement monitoring point is TJ-12 and the typical monitoring point number of the deformation expected low vault settlement monitoring point is TJ-35, and monitoring is carried out according to relevant specifications to obtain its monitoring data set;

[0043] S103, data analysis;

[0044] The data analysis includes performing classified directional data analysis on the obtained data set containing the monitoring timestamp to obtain a predicted value P corresponding to each vault settlement monitoring point. The steps of the classified directional data analysis are:

[0045] a) arranging the data set containing the monitoring timestamps, wherein the arranging includes arranging the data set containing the monitoring timestamps into data sets with consistent time intervals,

[0046] b) When the data set containing the monitoring timestamp is a high deformation expectation data set C j When the prediction value is obtained, a prediction model is constructed using a long short-term memory neural network that can capture fast changes.

[0047] c) When the data set containing the monitoring timestamp is a low deformation expectation data set D k When , the linear regression method capable of capturing slow changes is used to obtain the predicted value;

[0048] Further, in the above S103, in the data analysis, the time interval is 0.5 day or 1 day;

[0049] Furthermore, in the above S103, the steps of constructing the prediction model of the long short-term memory neural network to obtain the prediction value are: a) data normalization processing, b) dividing the data set into a training set and a test set, c) constructing a long short-term memory neural network prediction model, d) model training, e) model evaluation, f) model deployment and application, and obtaining the prediction value;

[0050] Furthermore, the above-mentioned construction of the long short-term memory neural network prediction model includes using a smoothed corrected linear unit function as an activation function, and the expression of the smoothed corrected linear unit function is formula (1),

[0051] f(x)=ln(1+e x ) (1)

[0052] Where x is the input and f(x) is the output;

[0053] Furthermore, in the above S103, the steps of obtaining the predicted value by the linear regression method are: a) data preprocessing, including data cleaning and conversion, b) data partitioning, c) establishing a univariate linear regression model, e) using the least squares method to evaluate model parameters, f) using a test set to evaluate model performance, g) model optimization, and h) model prediction to obtain a predicted value.

[0054] In this embodiment, for typical sections numbered TJ-12 and TJ-35, the section numbered TJ-12 is the expected high point of deformation, and a prediction model is constructed using a long short-term memory neural network that can capture rapid changes to obtain a predicted value. The measured value and predicted value curve of the section numbered TJ-12 are shown in FIG. Figure 2 As shown, the section number TJ-35 is the expected low point of deformation, and the linear regression method capable of capturing slow changes is used to obtain the predicted value. The measured value and predicted value curve of the section number TJ-12 are shown in Figure 3 As shown;

[0055] S104, the early warning purpose is achieved;

[0056] The achievement of the warning purpose includes judging its stable state according to the obtained prediction value P in combination with its corresponding arch settlement monitoring and early warning standard, so as to achieve the purpose of early warning, wherein the corresponding arch settlement monitoring and early warning standard is comprehensively formulated according to the topographic and geological conditions of the section where the monitoring point where the prediction value P is obtained is located and the excavation conditions;

[0057] In this embodiment, the vault settlement monitoring standard is shown in Table 1. The predicted values ​​of the sections numbered TJ-12 and TJ-35 do not exceed the vault settlement monitoring standard, and it is judged that they are in a stable state.

[0058] Table 1 Vault settlement monitoring standards

[0059]

[0060] In the above embodiments, the present invention discloses a tunnel vault settlement monitoring and early warning method, including point arrangement, data acquisition, data analysis and the achievement of early warning purposes; a tunnel vault settlement monitoring and early warning method proposed in the present invention has the advantages of high accuracy and comprehensiveness, and can be widely used in the field of tunnel construction monitoring.

[0061] The above description is a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A tunnel vault settlement monitoring and early warning method, characterized in that: The steps of the tunnel vault settlement monitoring and early warning method are as follows: 1) Point arrangement; 2) Data acquisition; 3) Data analysis; 4) Achievement of early warning objectives; The point arrangement includes arranging the arch settlement monitoring points in a targeted manner according to the excavation method adopted by the tunnel. The number of the arch settlement monitoring points is i, represented by M i , the distance between the vault settlement monitoring points is adjusted according to the actual excavation situation; The data acquisition includes classifying the vault monitoring points according to the different sections where they are located and dividing them into two categories: deformation expectation high vault settlement monitoring points H j and deformation expectation low arch settlement monitoring point L k , where j+k=i, the classification method is: a) exploring and collecting data on the buried depth and topographic geological conditions of the section where the arch settlement monitoring point is located, b) when the buried depth of the section is greater than or equal to x meters, and the surrounding rock grade of the section is level Ⅰ~Ⅳ, the arch settlement monitoring point of the section is a low arch settlement monitoring point with deformation expectation, c) when the buried depth of the section is less than x meters or the surrounding rock grade is less than or equal to level Ⅴ, the arch settlement monitoring point of the section is a high arch settlement monitoring point with deformation expectation, where x=40 when the surrounding rock grade is level Ⅵ, and x=30 when the surrounding rock grade is level Ⅴ; The data acquisition also includes the following steps: j and deformation expectation low arch settlement monitoring point L k The monitoring frequency required by the relevant specifications is used to obtain the data sets containing monitoring timestamps, which are the deformation expectation high data sets C j and the low deformation expectation dataset D k ; The data analysis includes performing classified directional data analysis on the obtained data set containing the monitoring timestamp to obtain a predicted value P corresponding to each vault settlement monitoring point. The steps of the classified directional data analysis are: a) arranging the data set containing the monitoring timestamps, wherein the arranging includes arranging the data set containing the monitoring timestamps into data sets with consistent time intervals, b) When the data set containing the monitoring timestamp is a high deformation expectation data set C j When the prediction value is obtained, a prediction model is constructed using a long short-term memory neural network that can capture fast changes. c) When the data set containing the monitoring timestamp is a low deformation expectation data set D k When , the linear regression method capable of capturing slow changes is used to obtain the predicted value; The achievement of the early warning purpose includes judging the stable state according to the obtained prediction value P in combination with its corresponding arch settlement monitoring and early warning standard to achieve the purpose of early warning. The corresponding arch settlement monitoring and early warning standard is comprehensively formulated based on the topographic and geological conditions and excavation conditions of the section where the monitoring point where the prediction value P is obtained is located.

2. A tunnel vault settlement monitoring and early warning method according to claim 1, characterized in that: In the data analysis, the time interval is 0.5 day or 1 day.

3. A tunnel vault settlement monitoring and early warning method according to claim 1, characterized in that: The steps of constructing a prediction model of the long short-term memory neural network to obtain a prediction value are: a) data normalization processing, b) dividing the data set into a training set and a test set, c) constructing a long short-term memory neural network prediction model, d) model training, e) model evaluation, and f) model deployment and application to obtain a prediction value.

4. A tunnel vault settlement monitoring and early warning method according to claim 1, characterized in that: The steps of obtaining the predicted value by the linear regression method are: a) data preprocessing, including data cleaning and conversion, b) data partitioning, c) establishing a univariate linear regression model, e) evaluating model parameters using the least squares method, f) evaluating model performance using a test set, g) model optimization, and h) model prediction to obtain the predicted value.

5. A tunnel vault settlement monitoring and early warning method according to claim 3, characterized in that: The construction of the long short-term memory neural network prediction model includes using a smoothed corrected linear unit function as an activation function, and the expression of the smoothed corrected linear unit function is formula (1): f(x)=ln(1+e x ) (1) Where x is the input and f(x) is the output.

Citation Information

Patent Citations

  • Method for determining burying depth of vault settlement monitoring point in tunnel construction

    CN111336987A

  • Tunnel monitoring system and method

    CN116678372A

  • Extremely soft rock stratum construction deformation control monitoring method

    CN118088202A

  • Surrouding rock deformation monitoring system is used in shallow tunnel construction

    CN205154262U

Cited By

  • Tunnel portal ground surface settlement monitoring and safety early warning method

    CN119063693A

  • A method for monitoring and early warning of surface subsidence at tunnel entrances

    CN119063693B

  • Rail transit tunnel settlement monitoring method and system

    CN119618162A

  • Large hydro-junction sluice deep foundation pit construction safety control method and system

    CN119830739A

  • A large water conservancy hub sluice deep foundation pit construction safety control method and system

    CN119830739B