By connecting preset resistors to the power system and analyzing the steady-state projection amount and correlation coefficient of the zero-sequence current, the problem of high-resistance grounding fault positioning of the power system is solved, and the accurate identification of the fault segment is achieved.

CN119024102AActive Publication Date: 2024-11-26GUANGDONG POWER GRID CO LTD +2
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411244023.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-05
Publication Date
2024-11-26
Estimated Expiration
2044-09-05

AI Technical Summary

Technical Problem

In power systems, when high-resistance grounding fails, due to the weak fault characteristic amount, the existing transient characteristic methods are difficult to accurately extract the fault characteristic amount, resulting in difficulty in positioning the fault.

Method used

By connecting the preset resistor into the power system, obtaining the bus zero-sequence voltage and the zero-sequence current at multiple monitoring points, calculate the steady-state projection amount and correlation coefficient of the zero-sequence current, and divide the sections of the power system based on these data. Position the faulty area.

Benefits of technology

It effectively solves the problem of difficulty in positioning faults in power system. Through the analysis of steady-state projection quantity and correlation coefficient, the section where the fault occurs is accurately judged, which improves the accuracy of fault positioning.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119024102A_ABST
    Figure CN119024102A_ABST
Patent Text Reader

Abstract

The invention discloses a fault detection method and device of a power system and electronic equipment. The method comprises the steps that a preset resistor is connected into the electric power system in response to a fault of the electric power system, the bus zero-sequence voltage of the electric power system and multiple zero-sequence currents on multiple monitoring points in the electric power system are obtained, and the preset resistor is connected with a neutral point of the electric power system in parallel; projecting the plurality of zero-sequence currents to the bus zero-sequence voltage to obtain steady-state projection quantities of the plurality of zero-sequence currents; according to the steady-state projection quantities of the plurality of zero-sequence currents, determining a correlation coefficient between the zero-sequence currents on any two adjacent monitoring points; based on the positions of the multiple monitoring points and the correlation coefficient between the zero-sequence currents on any two adjacent monitoring points, a fault section is determined from multiple sections of the electric power system, and the multiple sections are obtained by dividing lines of the electric power system through the multiple monitoring points. According to the invention, the technical problem of high fault positioning difficulty of the power system is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of power systems, and in particular to a fault detection method, device and electronic equipment for a power system. Background Art

[0002] For flexible grounding systems, when a fault occurs in the system, transient feature methods such as wavelet method and energy method can be used to locate the fault location. However, in some scenarios, such as when a high-resistance grounding fault occurs, the fault feature quantity is relatively weak, so the transient feature method cannot accurately extract the fault feature quantity, making it difficult to locate the location of the system fault.

[0003] To address the above-mentioned problems, no effective solution has been proposed yet. Summary of the invention

[0004] The embodiments of the present invention provide a method, a device and an electronic device for detecting a fault in an electric power system, so as to at least solve the technical problem that it is difficult to locate a fault in the electric power system.

[0005] According to one aspect of an embodiment of the present invention, a fault detection method for an electric power system is provided, comprising: in response to a fault in the electric power system, connecting a preset resistor to the electric power system, and obtaining a bus zero-sequence voltage of the electric power system and a plurality of zero-sequence currents at a plurality of monitoring points in the electric power system, wherein the preset resistor is connected in parallel with a neutral point of the electric power system; projecting the plurality of zero-sequence currents onto the bus zero-sequence voltage respectively to obtain steady-state projection quantities of the plurality of zero-sequence currents; determining a correlation coefficient between the zero-sequence currents at any two adjacent monitoring points based on the steady-state projection quantities of the plurality of zero-sequence currents; and determining a fault section from a plurality of sections of the electric power system based on the positions of the plurality of monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, wherein the plurality of sections are obtained by dividing the lines of the electric power system by the plurality of monitoring points.

[0006] Optionally, multiple zero-sequence currents are respectively projected onto the bus zero-sequence voltage to obtain steady-state projection quantities of the multiple zero-sequence currents, including: for any zero-sequence current among the multiple zero-sequence currents, converting the bus zero-sequence voltage into a voltage vector, and converting the zero-sequence current into a current vector; determining the vector angle between the voltage vector and the current vector; and determining the steady-state projection quantity of the zero-sequence current based on the voltage vector, the current vector and the vector angle.

[0007] Optionally, based on the positions of multiple monitoring points and the correlation coefficient between the zero-sequence current at any two adjacent monitoring points, the fault section is determined from multiple sections of the power system, including: determining the line type of the power system; based on the line type, the positions of multiple monitoring points and the correlation coefficient between the zero-sequence current at any two adjacent monitoring points, the fault section is determined from multiple sections of the power system.

[0008] Optionally, based on the line type, the locations of multiple monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, a fault section is determined from multiple sections of the power system, including: when the line type is a branchless line, based on the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, two target monitoring points are determined from multiple monitoring points, wherein the two target monitoring points are adjacent monitoring points and the correlation coefficient between the zero-sequence currents at the two target monitoring points is a negative value; and the section between the two target monitoring points is determined as the fault section.

[0009] Optionally, in response to the correlation coefficients between the zero-sequence currents at any two adjacent monitoring points being positive values, the method further includes: determining, from the multiple sections, the last section along the current direction as a fault section.

[0010] Optionally, based on the line type, the locations of multiple monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, a fault section is determined from multiple sections of the power system, including: when the line type is a branch line, a first monitoring point and a second monitoring point are determined from multiple monitoring points, wherein the first monitoring point is located on the main line of the power system and is adjacent to the monitoring points on multiple branch lines, and the second monitoring point is located on any branch line and is adjacent to the first monitoring point; in response to the correlation coefficients between the zero-sequence currents at the first monitoring point and the second monitoring point being negative values, and the absolute value of the correlation coefficient between the zero-sequence currents at the first monitoring point and the second monitoring point being within a preset range, the section between the first monitoring point and the second monitoring point is determined to be a fault section.

[0011] Optionally, acquiring a plurality of zero-sequence currents at a plurality of monitoring points in the power system includes: collecting the plurality of zero-sequence currents by means of phasor measurement units installed at the plurality of monitoring points.

[0012] Optionally, in the case where the power system includes a plurality of branch lines, the plurality of monitoring points include: at least one monitoring point arranged on a main line of the power system, and at least one monitoring point arranged on each branch line.

[0013] According to another aspect of an embodiment of the present invention, a fault detection device for an electric power system is also provided, comprising: an acquisition module, for connecting a preset resistor to the electric power system in response to a fault in the electric power system, and acquiring a bus zero-sequence voltage of the electric power system and a plurality of zero-sequence currents at a plurality of monitoring points in the electric power system, wherein the preset resistor is connected in parallel with a neutral point of the electric power system; a projection module, for projecting a plurality of zero-sequence currents onto the bus zero-sequence voltage respectively, to obtain a plurality of steady-state projection quantities of the zero-sequence currents; determining a correlation coefficient between the zero-sequence currents at any two adjacent monitoring points according to the steady-state projection quantities of the plurality of zero-sequence currents; a first determination module, for determining a correlation coefficient between the zero-sequence currents at any two adjacent monitoring points according to the steady-state projection quantities of the plurality of zero-sequence currents; and a second determination module, for determining a fault section from a plurality of sections of the electric power system based on the positions of the plurality of monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, wherein the plurality of sections are obtained by dividing the lines of the electric power system by a plurality of monitoring points.

[0014] According to another aspect of an embodiment of the present invention, there is further provided an electronic device, comprising: a memory storing an executable program; and a processor for running the program, wherein the above-mentioned power system fault detection method is executed when the program is running.

[0015] According to another aspect of an embodiment of the present invention, a computer-readable storage medium is provided, the computer-readable storage medium including a stored executable program, wherein when the executable program runs, the device where the storage medium is located is controlled to execute the above-mentioned power system fault detection method.

[0016] According to another aspect of an embodiment of the present invention, a computer program product is provided, including a computer program, and when the computer program is executed by a processor, the above-mentioned fault detection method of the power system is implemented.

[0017] In an embodiment of the present invention, in response to a fault in the power system, a preset resistor is connected to the power system, and a bus zero-sequence voltage of the power system and a plurality of zero-sequence currents at a plurality of monitoring points in the power system are obtained; the plurality of zero-sequence currents are respectively projected onto the bus zero-sequence voltage to obtain steady-state projection quantities of the plurality of zero-sequence currents; the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points is determined according to the steady-state projection quantities of the plurality of zero-sequence currents; based on the positions of the plurality of monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, a fault section is determined from a plurality of sections of the power system. It is easy to notice that by determining the steady-state projection quantities of the plurality of zero-sequence currents at different monitoring points on the bus zero-sequence voltage, the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points can be further determined, thereby judging the correlation relationship between the upstream and downstream zero-sequence currents of any section, judging the section where the fault occurs according to the correlation relationship presented by the correlation coefficient, thereby achieving the purpose of locating the fault location, and further solving the technical problem of the high difficulty in locating power system faults. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0019] Figure 1 is a flow chart of a fault detection method for a power system according to an embodiment of the present invention;

[0020] Figure 2 is a schematic diagram of an optional branchless line according to an embodiment of the present invention;

[0021] Figure 3 is a schematic diagram of an optional branch line according to an embodiment of the present invention;

[0022] Figure 4 is a flow chart of an optional fault detection method according to an embodiment of the present invention;

[0023] Figure 5 is a schematic diagram of a fault detection device for an electric power system according to an embodiment of the present invention. DETAILED DESCRIPTION

[0024] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0025] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0026] Example 1

[0027] According to an embodiment of the present invention, an embodiment of a fault detection method for an electric power system is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0028] Figure 1 is a flow chart of a method for fault detection of a power system according to an embodiment of the present invention. Figure 1 As shown, the method comprises the following steps:

[0029] Step S102, in response to a fault in the power system, a preset resistor is connected to the power system, and a bus zero-sequence voltage of the power system and multiple zero-sequence currents at multiple monitoring points in the power system are obtained, wherein the preset resistor is connected in parallel with the neutral point of the power system.

[0030] The preset resistor in the above steps is a preset resistor, and the specific resistance value of the preset resistor can be preset according to the actual application situation, and the specific resistance value of the preset resistor is not limited here. The preset resistor is connected to the power system and connected in parallel with the neutral point of the power system. The neutral point is also the common point connected to the three-phase voltage source in the AC power system. After the preset resistor is connected in parallel with the neutral point, the zero-sequence current upstream of the fault point increases the resistive component compared to before the preset resistor is put into use, while the zero-sequence current downstream of the fault point is not affected by the parallel preset resistor. Therefore, after the preset resistor is connected in parallel with the neutral point, it can be determined whether there is a fault in the section between the monitoring points based on the relationship between the upstream and downstream zero-sequence currents of the monitoring points.

[0031] The bus zero-sequence voltage in the above steps is the zero-sequence voltage generated on the bus of the power system due to asymmetric current or fault conditions. The zero-sequence voltage is the voltage generated when the power system fails. In a three-phase power system, the three-phase voltage is symmetrical under normal circumstances, and there is no zero-sequence voltage. However, when a ground fault occurs in the system, such as a single-phase ground fault, due to asymmetry, a voltage will be generated at the zero sequence of the system, that is, the neutral point. This voltage is called zero-sequence voltage.

[0032] The monitoring points in the above steps are points for monitoring zero-sequence current, and the monitoring points divide the power system into multiple sections.

[0033] The zero-sequence current in the above steps is the current generated when the power system fails. In a normal three-phase power system, the three-phase currents are symmetrical, and the vector sum of the three-phase currents is zero at any time, so there is no zero-sequence current. However, when a ground fault occurs in the power system, due to the asymmetry of the system, the vector sum of the three-phase currents is no longer zero, thus generating a zero-sequence current.

[0034] In an optional embodiment, after a fault occurs in the power system, the fault location device in the power system starts over-limit after monitoring that the zero-sequence voltage exceeds the threshold value, closes the preset resistor switching switch in the power system, and connects the preset resistor to the circuit, so that the preset resistor is connected in parallel with the neutral point. The preferred value of the preset resistor is 10 ohms, but other resistance values ​​can also be selected as the preset resistor according to actual application conditions, and the resistance value of the preset resistor may not be limited to 10 ohms.

[0035] When obtaining the bus zero-sequence voltage of the power system and multiple zero-sequence currents at multiple monitoring points in the power system, a zero-sequence voltage sensor can be installed on the bus of the power system, and a zero-sequence current sensor can be installed at each monitoring point of the power system. The bus zero-sequence voltage of the power system is obtained through the zero-sequence voltage sensor, and the zero-sequence current at the monitoring point is obtained through the zero-sequence current sensor.

[0036] In another optional embodiment, a zero-sequence voltmeter can be used to obtain the bus zero-sequence voltage, and a synchronous phasor measurement unit (Phasor Measurement Unit, PMU) can be installed at each monitoring point to obtain the zero-sequence current at the monitoring point through the PMU. It should be noted that the zero-sequence current changes with time, and the zero-sequence current collection cycle can be designed to collect the zero-sequence current within a cycle, and the zero-sequence current can be expressed as a function with time as a variable.

[0037] Step S104, projecting the multiple zero-sequence currents onto the bus zero-sequence voltage respectively to obtain steady-state projection quantities of the multiple zero-sequence currents.

[0038] The steady-state projection quantity in the above steps is the projection component of the zero-sequence current on the bus zero-sequence voltage. By projecting the zero-sequence current onto the zero-sequence voltage, the steady-state component reflecting the fault characteristics can be extracted, which helps to more accurately identify and locate the fault.

[0039] In an optional embodiment, there are multiple monitoring points in the power system, a zero-sequence current is obtained from each monitoring point, each zero-sequence current is projected onto the bus zero-sequence voltage, and a steady-state projection amount is obtained, thereby obtaining multiple steady-state projection amounts. When the zero-sequence current is projected onto the bus zero-sequence voltage, the inner product of the bus zero-sequence voltage and the zero-sequence current is calculated, and the unit vector of the bus zero-sequence voltage is calculated, and the steady-state projection amount of the bus zero-sequence voltage is determined according to the inner product of the bus zero-sequence voltage and the zero-sequence current, and the unit vector of the bus zero-sequence voltage.

[0040] Step S106, determining the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points according to the steady-state projection quantities of the multiple zero-sequence currents.

[0041] The correlation coefficient in the above steps is used to evaluate the degree of correlation between the zero-sequence currents at any two adjacent monitoring points, which can be a Pearson correlation coefficient, but is not limited to this. The calculation result of the correlation coefficient ranges from a closed interval of -1 to 1. When the correlation coefficient is greater than 0, the zero-sequence currents at the two adjacent monitoring points are positively correlated; when the correlation coefficient is less than 0, the zero-sequence currents at the two adjacent monitoring points are negatively correlated. When the absolute value of the correlation coefficient is equal to 1, it means that the zero-sequence currents at the two adjacent monitoring points are completely correlated, that is, the zero-sequence currents at the two adjacent monitoring points are completely consistent; when the correlation coefficient is equal to zero, it means that the zero-sequence currents at the two adjacent monitoring points are completely independent and have no correlation; when the absolute value of the correlation coefficient is between 0 and 1, it means that there is a certain correlation between the zero-sequence currents at the two adjacent monitoring points, and the closer the absolute value of the correlation coefficient is to 1, the higher the correlation between the zero-sequence currents at the two adjacent monitoring points; the closer the absolute value of the correlation coefficient is to 0, the lower the correlation between the zero-sequence currents at the two adjacent monitoring points.

[0042] In an optional embodiment, the correlation coefficient between the zero-sequence currents at two adjacent monitoring points may be calculated according to the steady-state projection of the zero-sequence currents at the two adjacent monitoring points. The calculation formula is as follows:

[0043]

[0044] Among them, r ij is the correlation coefficient between the zero-sequence currents at two adjacent monitoring points, t is the time, T is the period of collecting zero-sequence current, I i.P (t) is the steady-state projection of the zero-sequence current at the monitoring point i, I j.P(t)dt is the steady-state projection of the zero-sequence current at monitoring point j. Monitoring point i is adjacent to monitoring point j. The zero-sequence current is a quantity that changes continuously with time t. Therefore, the steady-state projection of the zero-sequence current is a function of time t and can be integrated.

[0045] Step S108, based on the positions of the multiple monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, determine the fault section from the multiple sections of the power system, wherein the multiple sections are obtained by dividing the lines of the power system through the multiple monitoring points.

[0046] The fault section in the above steps is a section where a fault exists in the power system, and can be determined based on the positive or negative value of the correlation coefficient.

[0047] In an optional embodiment, for a section without branches, every two monitoring points form a section, and if the correlation coefficients corresponding to two adjacent monitoring points are positive or negative, it is determined whether the section between the two adjacent monitoring points is a fault section. For a section with branches, the method for determining whether it is a fault section at a location that does not include a branch point is the same as that for a section without branches, but at a location that includes a branch point, the monitoring points on the main line and multiple monitoring points on multiple adjacent branch lines form a section. When determining whether the section is a fault section, the zero-sequence current corresponding to the monitoring points on the main line is respectively calculated with the zero-sequence current corresponding to the monitoring points on each branch line to calculate a correlation coefficient, and it is necessary to determine whether the section is a fault section based on the positive or negative of multiple correlation coefficients.

[0048] In an embodiment of the present invention, in response to a fault in the power system, a preset resistor is connected to the power system, and a bus zero-sequence voltage of the power system and a plurality of zero-sequence currents at a plurality of monitoring points in the power system are obtained; the plurality of zero-sequence currents are respectively projected onto the bus zero-sequence voltage to obtain steady-state projection quantities of the plurality of zero-sequence currents; the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points is determined according to the steady-state projection quantities of the plurality of zero-sequence currents; based on the positions of the plurality of monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, a fault section is determined from a plurality of sections of the power system. It is easy to notice that by determining the steady-state projection quantities of the plurality of zero-sequence currents at different monitoring points on the bus zero-sequence voltage, the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points can be further determined, thereby judging the correlation relationship between the upstream and downstream zero-sequence currents of any section, judging the section where the fault occurs according to the correlation relationship presented by the correlation coefficient, thereby achieving the purpose of locating the fault location, and further solving the technical problem of the high difficulty in locating power system faults.

[0049] Optionally, multiple zero-sequence currents are respectively projected onto the bus zero-sequence voltage to obtain steady-state projection quantities of the multiple zero-sequence currents, including: for any zero-sequence current among the multiple zero-sequence currents, converting the bus zero-sequence voltage into a voltage vector, and converting the zero-sequence current into a current vector; determining the vector angle between the voltage vector and the current vector; and determining the steady-state projection quantity of the zero-sequence current based on the voltage vector, the current vector and the vector angle.

[0050] The voltage vector in the above steps is the bus zero-sequence voltage in vector form, and the current vector is the zero-sequence current in vector form. The vector form can better describe the relative relationship between the bus zero-sequence voltage and zero-sequence current in the power system, which is convenient for analysis and calculation.

[0051] The vector angle in the above steps is the angle between the voltage vector and the current vector, and is used to describe the directional relationship between the voltage vector and the current vector.

[0052] In an optional embodiment, it is necessary to calculate the steady-state projection vector between the zero-sequence current and the bus zero-sequence voltage at each monitoring point. When calculating the steady-state projection vector between the zero-sequence current and the bus zero-sequence voltage, the bus zero-sequence voltage is converted into a voltage vector, and the zero-sequence current is converted into a current vector, the vector angle between the voltage vector and the current vector is measured, and then the size of the projection value of the current vector on the voltage vector is calculated, and the calculation formula is as follows:

[0053]

[0054] Where P is the projection value of the current vector on the voltage vector, is the vector angle, and I is the magnitude of the current vector.

[0055] Then, according to the projection value of the current vector on the voltage vector and the unit vector of the voltage vector, the steady-state projection of the zero-sequence current is calculated. The calculation formula is as follows:

[0056]

[0057] in, is the steady-state projection of the zero-sequence current, P is the projection value of the current vector on the voltage vector, is the voltage vector, U is the magnitude of the voltage vector, The ratio of |U is the unit vector of the voltage vector.

[0058] Combining the above two formulas, the calculation formula for the steady-state projection of zero-sequence current can be obtained as follows:

[0059]

[0060] in, is the steady-state projection of the zero-sequence current, is the inner product of the voltage vector and the current vector, is the voltage vector, U is the magnitude of the voltage vector, The ratio of |U is the unit vector of the voltage vector.

[0061] Optionally, based on the positions of multiple monitoring points and the correlation coefficient between the zero-sequence current at any two adjacent monitoring points, the fault section is determined from multiple sections of the power system, including: determining the line type of the power system; based on the line type, the positions of multiple monitoring points and the correlation coefficient between the zero-sequence current at any two adjacent monitoring points, the fault section is determined from multiple sections of the power system.

[0062] The line type in the above steps is the type of line in the power system. It can be divided into line without branches and line with branches according to whether there are branch lines. It can also be divided into high-voltage lines, medium-voltage lines, and low-voltage lines according to voltage levels. It can also be divided into trunk lines, branch lines, and terminal lines according to the line-carrying current, but is not limited to this.

[0063] In an optional embodiment, the line type is divided into non-branched lines and branched lines according to whether the line in the power system has branches. Since the branch line contains branches, the setting of the monitoring point at the branch point is relatively special, and it is necessary to set monitoring points on both the main line and the branch line, and the monitoring points divide an area including the branch point. Since the location of the monitoring point determines the various sections in the power system, and the location of the monitoring point is set differently when the line type is different, when determining the fault section, not only the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points is needed, but also the line type and the location of the monitoring point are needed to locate the section with the fault.

[0064] Optionally, based on the line type, the locations of multiple monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, a fault section is determined from multiple sections of the power system, including: when the line type is a branchless line, based on the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, two target monitoring points are determined from multiple monitoring points, wherein the two target monitoring points are adjacent monitoring points and the correlation coefficient between the zero-sequence currents at the two target monitoring points is a negative value; and the section between the two target monitoring points is determined as the fault section.

[0065] The non-branch line in the above steps is a line without branch lines and only one main line;

[0066] The two target detection points in the above steps are adjacent, and a section can be determined. Each section of the branchless line corresponds to two target monitoring points. The correlation coefficient between the zero-sequence currents at the two target monitoring points can be used to determine whether the section between the two target monitoring points is a fault section.

[0067] In an optional embodiment, Figure 2 is a schematic diagram of an optional branchless line according to an embodiment of the present invention, such as Figure 2 As shown in the figure, the direction of the arrow is the direction of the current. Monitoring points 1, 2 and 3 are all monitoring points on the branchless line. Sections 1 and 2 are two of the multiple sections divided by the monitoring points. Among them, the two target monitoring points corresponding to section 1 are monitoring point 1 and monitoring point 2. If the correlation coefficient between the zero-sequence currents at monitoring point 1 and monitoring point 2 is negative, it means that the zero-sequence currents at monitoring point 1 and monitoring point 2 are negatively correlated and will not affect each other. Therefore, section 1 is determined to be the fault section.

[0068] Optionally, in response to the correlation coefficients between the zero-sequence currents at any two adjacent monitoring points being positive values, the method further includes: determining, from the multiple sections, the last section along the current direction as a fault section.

[0069] In an optional embodiment, Figure 2 is a schematic diagram of an optional branchless line according to an embodiment of the present invention, such as Figure 2 As shown, if Figure 2 If the correlation coefficients between the zero-sequence currents at any two adjacent monitoring points are positive, it can be determined that the last section along the current direction, that is, section 2, is the fault section.

[0070] Optionally, based on the line type, the locations of multiple monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, a fault section is determined from multiple sections of the power system, including: when the line type is a branch line, a first monitoring point and a second monitoring point are determined from multiple monitoring points, wherein the first monitoring point is located on the main line of the power system and is adjacent to the monitoring points on multiple branch lines, and the second monitoring point is located on any branch line and is adjacent to the first monitoring point; in response to the correlation coefficients between the zero-sequence currents at the first monitoring point and the second monitoring point being negative values, and the absolute value of the correlation coefficient between the zero-sequence currents at the first monitoring point and the second monitoring point being within a preset range, the section between the first monitoring point and the second monitoring point is determined to be a fault section.

[0071] The preset range in the above steps is a pre-set numerical range. A preferred value of the preset range is a closed interval from -0.9 to -1, but it is not limited to this and can be preset according to actual application conditions. The specific value of the preset range is not limited here.

[0072] In an optional embodiment, Figure 3 is a schematic diagram of an optional branch line according to an embodiment of the present invention, such as Figure 3 As shown, the direction of the arrow is the direction of the current, and monitoring point 1, monitoring point 2, and monitoring point 3 are all monitoring points on branch lines, wherein monitoring point 1 is located on the main line, and monitoring point 2 and monitoring point 3 are located on the branch line, and monitoring point 1 is adjacent to monitoring point 2, and is also adjacent to monitoring point 3. It can be determined that monitoring point 1 is the first monitoring point, and monitoring point 2 and monitoring point 3 are the second monitoring point. The section composed of monitoring point 1, monitoring point 2, and monitoring point 3 is section 1. When the correlation coefficient between the zero-sequence current at monitoring point 1 and monitoring point 2 is negative and within the preset range, and the correlation coefficient between the zero-sequence current at monitoring point 1 and monitoring point 3 is also negative and within the preset range, the section between the first monitoring point and the second monitoring point, that is, section 1, is determined to be the fault section.

[0073] Optionally, acquiring a plurality of zero-sequence currents at a plurality of monitoring points in the power system includes: collecting the plurality of zero-sequence currents by means of phasor measurement units installed at the plurality of monitoring points.

[0074] The phasor measurement unit in the above steps can be a PMU, which uses the global positioning system (GPS) second pulse as a synchronous clock and can be used in the fields of dynamic monitoring, system protection, system analysis and prediction of power systems. It is an important equipment to ensure the safe operation of the power grid.

[0075] In an optional embodiment, a phasor measurement unit is installed at each monitoring point, and the phasor measurement unit is debugged to ensure that the phasor measurement unit can accurately measure the zero-sequence current. These phasor measurement units are then connected to a data acquisition system, which can be a centralized data acquisition device connected to each phasor measurement unit through a network or wireless communication. By connecting multiple phasor measurement units to the data acquisition system, multiple zero-sequence current data of multiple monitoring points can be collected simultaneously, and the data can be analyzed and processed.

[0076] Optionally, in the case where the power system includes a plurality of branch lines, the plurality of monitoring points include: at least one monitoring point arranged on a main line of the power system, and at least one monitoring point arranged on each branch line.

[0077] In an optional embodiment, when the power system includes multiple branch lines, the main line is connected to the multiple branch lines at the branch point. It is necessary to set at least one monitoring point on the main line and at least one monitoring point on each branch line, so that the existing monitoring point on the main line is adjacent to the detection point on each branch line, so as to determine the fault condition of the section including the branch point based on the collected zero-sequence current.

[0078] A preferred embodiment is described below. Figure 4 is a flow chart of an optional fault detection method according to an embodiment of the present invention. Figure 4 As shown, it can be determined whether the bus zero-sequence voltage is greater than the threshold value. If not, it means that there is no fault in the power system, and the bus zero-sequence voltage is continued to be monitored to see if it is greater than the threshold value; if so, it means that there is a fault in the power system, and the following steps are continued. Then the bus zero-sequence voltage and the zero-sequence current of the monitoring point are collected, and the projection components of each zero-sequence current are calculated according to the collected fault information. The collected fault information is also the bus zero-sequence voltage and the zero-sequence current of the monitoring point. The projection component is also the steady-state projection quantity mentioned above, and then the correlation coefficients of the projection components corresponding to the adjacent zero-sequence currents are calculated, and the correlation coefficients obtained are compared. Then it is determined whether the line has branches. If so, it is necessary to determine whether the section is a fault section according to the multiple correlation coefficients corresponding to the section, determine the multiple correlation coefficients corresponding to the zero-sequence current of the monitoring point on the main line and the zero-sequence current of the monitoring point on the multiple branch lines, and determine whether the section is a fault section according to the positive and negative and absolute values ​​of the multiple correlation coefficients. If not, determine whether the section is a fault section according to a correlation coefficient corresponding to the section, and determine whether the section is a fault section according to the correlation coefficients corresponding to the zero-sequence currents of the two monitoring points at the left and right ends of the section. Then the process ends.

[0079] Example 2

[0080] According to an embodiment of the present invention, an embodiment of a fault detection method device for an electric power system is provided. The device can execute the fault detection method for the electric power system provided in the above-mentioned embodiment 1. The specific implementation method and preferred application scenario are the same as those of the above-mentioned embodiment 1, and will not be repeated here.

[0081] Figure 5 is a schematic diagram of a fault detection device for a power system according to an embodiment of the present invention. Figure 5 As shown:

[0082] An acquisition module 50 is used for connecting a preset resistor to the power system in response to a fault in the power system, and acquiring a bus zero-sequence voltage of the power system and a plurality of zero-sequence currents at a plurality of monitoring points in the power system, wherein the preset resistor is connected in parallel with a neutral point of the power system;

[0083] The projection module 52 is used to project the multiple zero-sequence currents onto the bus zero-sequence voltage respectively to obtain the steady-state projection quantities of the multiple zero-sequence currents; and determine the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points according to the steady-state projection quantities of the multiple zero-sequence currents;

[0084] A first determination module 54 is used to determine the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points according to the steady-state projection quantities of the multiple zero-sequence currents;

[0085] The second determination module 56 is used to determine the fault section from multiple sections of the power system based on the positions of multiple monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, wherein the multiple sections are obtained by dividing the lines of the power system through multiple monitoring points.

[0086] Optionally, the projection module includes: a conversion unit, used to convert the bus zero-sequence voltage into a voltage vector and convert the zero-sequence current into a current vector for any one of multiple zero-sequence currents; a first determination unit, used to determine the vector angle between the voltage vector and the current vector; and a second determination unit, used to determine the steady-state projection amount of the zero-sequence current based on the voltage vector, the current vector and the vector angle.

[0087] Optionally, the second determination module includes: a third determination unit, used to determine the line type of the power system; and a fourth determination unit, used to determine the fault section from multiple sections of the power system based on the line type, the locations of multiple monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points.

[0088] Optionally, the fourth determination unit is also used to determine two target monitoring points from multiple monitoring points based on the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points when the line type is a branchless line, wherein the two target monitoring points are adjacent monitoring points and the correlation coefficient between the zero-sequence currents at the two target monitoring points is a negative value; and determine that the section between the two target monitoring points is a fault section.

[0089] Optionally, the fourth determining unit is further configured to determine, from the multiple sections, the last section along the current direction as the fault section.

[0090] Optionally, the fourth determination unit is also used to determine a first monitoring point and a second monitoring point from multiple monitoring points when the line type is a branch line, wherein the first monitoring point is located on the main line of the power system and is adjacent to the monitoring points on multiple branch lines, and the second monitoring point is located on any branch line and is adjacent to the first monitoring point; in response to the correlation coefficients between the zero-sequence currents at the first monitoring point and the second monitoring point being negative values, and the absolute value of the correlation coefficient between the zero-sequence currents at the first monitoring point and the second monitoring point being within a preset range, the section between the first monitoring point and the second monitoring point is determined to be a fault section.

[0091] Optionally, the acquisition unit is further configured to collect multiple zero-sequence currents through phasor measurement units installed at multiple monitoring points.

[0092] Optionally, the multiple monitoring points in the acquisition unit include: at least one monitoring point set on a main line of the power system, and at least one monitoring point set on each branch line.

[0093] Example 3

[0094] According to an embodiment of the present invention, there is also provided an electronic device, comprising: a memory storing an executable program; and a processor for running the program, wherein the fault detection method for the power system in Embodiment 1 is executed when the program is running.

[0095] Example 4

[0096] An embodiment of the present application further provides a computer-readable storage medium, which includes a stored executable program, wherein when the executable program is running, the device where the computer-readable storage medium is located is controlled to execute the power system fault detection method in each embodiment of the present invention.

[0097] Example 5

[0098] An embodiment of the present application further provides a computer program product, including a computer program, which implements the fault detection method of the power system in various embodiments of the present invention when executed by a processor.

[0099] Example 6

[0100] An embodiment of the present application also provides a computer program product, including a non-volatile computer-readable storage medium, wherein the non-volatile computer-readable storage medium is used to store a computer program, and when the computer program is executed by a processor, the fault detection method of the power system in each embodiment of the present invention is implemented.

[0101] The serial numbers of the above embodiments of the present invention are only for description and do not represent the advantages or disadvantages of the embodiments.

[0102] In the above embodiments of the present invention, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0103] In the several embodiments provided in this application, it should be understood that the disclosed technical content can be implemented in other ways. Among them, the device embodiments described above are only schematic. For example, the division of the units can be a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of units or modules, which can be electrical or other forms.

[0104] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple units. Some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.

[0105] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0106] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for a computer device (which can be a personal computer, a server or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), mobile hard disk, magnetic disk or optical disk and other media that can store program codes.

[0107] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A method for fault detection in a power system, characterized in that: include: In response to a fault in the power system, a preset resistor is connected to the power system, and a bus zero-sequence voltage of the power system and multiple zero-sequence currents at multiple monitoring points in the power system are obtained, wherein the preset resistor is connected in parallel with a neutral point of the power system; Projecting the multiple zero-sequence currents onto the bus zero-sequence voltage respectively to obtain steady-state projection quantities of the multiple zero-sequence currents; According to the steady-state projection quantities of multiple zero-sequence currents, the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points is determined; Based on the positions of the multiple monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, a fault section is determined from multiple sections of the power system, wherein the multiple sections are obtained by dividing the lines of the power system through the multiple monitoring points.

2. The method according to claim 1, characterized in that Projecting the multiple zero-sequence currents onto the bus zero-sequence voltage respectively to obtain steady-state projection quantities of the multiple zero-sequence currents includes: For any one of the multiple zero-sequence currents, convert the bus zero-sequence voltage into a voltage vector, and convert the zero-sequence current into a current vector; determining a vector angle between the voltage vector and the current vector; Based on the voltage vector, the current vector and the vector angle, a steady-state projection amount of the zero-sequence current is determined.

3. The method according to claim 1, characterized in that Determining a fault section from a plurality of sections of the power system based on the positions of the plurality of monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points comprises: determining a line type of the power system; A fault section is determined from among the multiple sections of the power system based on the line type, the locations of the multiple monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points.

4. The method according to claim 3, characterized in that Determining a fault section from a plurality of sections of the power system based on the line type, the locations of the plurality of monitoring points, and a correlation coefficient between zero-sequence currents at any two adjacent monitoring points comprises: In the case where the line type is a branchless line, based on the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, two target monitoring points are determined from the multiple monitoring points, wherein the two target monitoring points are adjacent monitoring points, and the correlation coefficient between the zero-sequence currents at the two target monitoring points is a negative value; The section between the two target monitoring points is determined as the fault section.

5. The method according to claim 4, characterized in that In response to the correlation coefficients between the zero-sequence currents at any two adjacent monitoring points being positive, the method further includes: A last section along the current direction is determined from the multiple sections as the fault section.

6. The method according to claim 3, characterized in that Determining a fault section from a plurality of sections of the power system based on the line type, the locations of the plurality of monitoring points, and a correlation coefficient between zero-sequence currents at any two adjacent monitoring points comprises: In the case where the line type is a branch line, determining a first monitoring point and a second monitoring point from the multiple monitoring points, wherein the first monitoring point is located on the main line of the power system and adjacent to monitoring points on multiple branch lines, and the second monitoring point is located on any one branch line and adjacent to the first monitoring point; In response to the fact that the correlation coefficients between the zero-sequence currents at the first monitoring point and the second monitoring point are both negative values, and the absolute values ​​of the correlation coefficients between the zero-sequence currents at the first monitoring point and the second monitoring point are within a preset range, the section between the first monitoring point and the second monitoring point is determined to be the fault section.

7. The method according to claim 1, characterized in that Acquiring a plurality of zero-sequence currents at a plurality of monitoring points in the power system, comprising: The multiple zero-sequence currents are collected by phasor measurement units installed at the multiple monitoring points.

8. The method according to claim 1, characterized in that In the case that the power system includes a plurality of branch lines, the plurality of monitoring points include: at least one monitoring point arranged on a main line of the power system, and at least one monitoring point arranged on each branch line.

9. A fault detection device for an electric power system, characterized in that: include: an acquisition module, configured to connect a preset resistor to the power system in response to detecting a fault signal, and acquire a bus zero-sequence voltage of the power system and a plurality of zero-sequence currents at a plurality of monitoring points in the power system, wherein the preset resistor is connected in parallel with a neutral point of the power system; A projection module, used for projecting a plurality of current vectors corresponding to the plurality of zero-sequence currents onto a voltage vector corresponding to the bus zero-sequence voltage to obtain steady-state projection quantities of the plurality of zero-sequence currents; A first determination module is used to determine the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points according to the steady-state projection quantities of the multiple zero-sequence currents; The second determination module is used to determine the fault section from the multiple sections of the power system based on the positions of the multiple monitoring points and the correlation coefficient between the zero-sequence currents at any two adjacent monitoring points, wherein the multiple sections are obtained by dividing the lines of the power system through the multiple monitoring points.

10. An electronic device, characterized in that: include: A memory storing an executable program; A processor is used to run the program, wherein the program, when running, executes the fault detection method for the power system as described in any one of claims 1 to 8.

Citation Information

Patent Citations

  • Small current grounding system high-resistance grounding fault line selection method based on comparison between transient projection component amplitude and polar relationship

    CN106443330A

  • High-resistance ground fault line selection method for small-current grounding system

    CN106526415A

  • Hausdorff distance-based low-current grounding fault positioning method and system

    CN112557812A

  • Ground fault transient line selection method for flexible grounding system

    CN118572630A