Electric vehicle and power grid interaction control method and system

By acquiring and analyzing the real-time load data of the charging station, designing the optimal charging control curve and implementing local charging strategies, the peak load problem caused by electric vehicles being connected to the power grid is solved, and the smoothing of the power grid load and the improvement of charging efficiency is achieved, ensuring that The power grid stability and user charging experience.

CN119037222APending Publication Date: 2024-11-29ELECTRIC POWER RES INST OF GUANGXI POWER GRID CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410933914.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

The large-scale access of electric vehicles to the power grid leads to peak load peaks, which may cause problems such as heavy loading and overloading of transmission lines or distribution transformers. The existing intelligent and orderly charging control has a control scale and speed limit, and the indirect guidance mode may be The charging electricity price switching period triggers a new load peak.

Method used

By obtaining real-time load data of the charging station and charging equipment data, the optimal charging control curve is designed, and the charging plan for each charging pile is generated based on the transformer situation in the local distribution station area, and it is executed when the load exceeds the limit or high load is detected. Local charging strategy implements dynamic adjustments to smooth grid load.

Benefits of technology

It effectively reduces the load fluctuations in the power grid caused by electric vehicle charging, improves the grid stability and charging pile efficiency, ensures the satisfaction of grid equipment utilization and user charging needs, and also has fault monitoring functions to ensure charging safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119037222A_ABST
    Figure CN119037222A_ABST
Patent Text Reader

Abstract

The invention discloses an electric vehicle and power grid interaction control method and system. The method comprises the steps that real-time load data of a charging station and the charging state, voltage, current and electric quantity data of charging equipment are obtained; and designing a first charging plan according to the real-time data, and generating an optimal charging control curve of each charging pile. Under the platform charging strategy, the optimal charging control curve is sent to the charging pile; and when the load exceeds the limit or the residual load is high, executing a local strategy, and periodically controlling charging. Through the mode, the stability of a power grid can be effectively improved, the operation cost is reduced, meanwhile, the charging requirement of an electric vehicle user is guaranteed, and harmonious symbiosis of a power system and an electric vehicle is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electric vehicle and power grid interactive control, and in particular to an electric vehicle and power grid interactive control method and system. Background Art

[0002] Electric vehicles account for an increasing proportion of the motor vehicle market in my country. The large-scale use of electric vehicles has alleviated the increasing shortage of fossil energy and the deteriorating environment to a certain extent, but at the same time has also brought many problems in the operation of the power grid. Since the power source of electric vehicles is electricity, and with the disorderly charging and discharging of large-scale electric vehicles connected to the power grid, the power quality, reliability and economic operation of the distribution network will be affected, especially the peak load may be aggravated, bringing peak load pressure to the power grid, which may easily cause problems such as heavy load and overload of transmission lines or distribution transformers.

[0003] Through intelligent and orderly charging control and by utilizing the characteristics of electric vehicle energy loads, the charging load of electric vehicles can be matched with the power supply capacity of the distribution network. This can ensure the safety of electric vehicle power supply and grid operation, improve the utilization rate of grid equipment, and promote the consumption of clean energy.

[0004] At present, there are two main modes for realizing intelligent and orderly charging of electric vehicles. One is the indirect guidance mode, that is, through the transmission of charging peak and valley electricity prices, the charging demand of users during the peak load period is guided to the night load valley for charging; the other is the direct control mode, that is, when electric vehicle users connect to charging piles for charging, they sign an orderly charging order contract with the charging operator. The charging operator directly regulates the charging period and charging power on the premise of meeting the charging needs of users. However, there are still some problems with the above orderly charging control: in the indirect guidance mode, because it is transmitted through prices, it is easy to cause new load peaks during the low charging electricity price period, especially during the switching period between the peak and valley charging electricity prices. In the direct control mode, the charging operation platform performs centralized regulation, which has certain limitations in terms of regulation scale and regulation speed. Summary of the invention

[0005] The purpose of this section is to summarize some aspects of embodiments of the present invention and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and the invention title of this application to avoid blurring the purpose of this section, the specification abstract and the invention title, and such simplifications or omissions cannot be used to limit the scope of the present invention.

[0006] In view of the above existing problems, the present invention is proposed.

[0007] Therefore, the present invention provides an electric vehicle and power grid interactive control method and system, which can solve the problems mentioned in the background technology.

[0008] In order to solve the above technical problems, the present invention provides the following technical solutions:

[0009] In a first aspect, the present invention provides a method for interactive control of an electric vehicle and a power grid, comprising:

[0010] Obtaining real-time load data of the area where the charging station is located and relevant charging data of the charging equipment, wherein the relevant charging data at least includes charging status, voltage, current and power data;

[0011] Designing a first charging plan based on the real-time load data of the area where the charging station is located and the relevant charging data of the charging equipment, wherein the first charging plan includes generating an optimal charging control curve for each charging pile in combination with the transformer conditions of the local distribution area;

[0012] When the platform charging strategy is executed, the generated optimal charging control curve for each charging pile is sent to the corresponding charging pile;

[0013] When the local load is detected to be overloaded or the remaining load is high, the local charging strategy is executed, and the local charging control is performed periodically according to the locally configured charging plan curve or load overload control strategy.

[0014] In a second aspect, the present invention provides an electric vehicle and power grid interactive control system, the system comprising: a distribution transformer, a three-phase meter, a vehicle-grid interactive control platform, a vehicle-grid interactive control terminal, and a plurality of charging piles including a charging and discharging control unit;

[0015] The vehicle-grid interactive control terminal is electrically connected to the three-phase meter to obtain real-time load data of the area where the charging station is located, and is also communicatively connected to the charging and discharging control units in different charging piles to obtain relevant charging data of the charging equipment, wherein the relevant charging data at least includes charging status, voltage, current and power data, and transmits the data obtained by the electrical connection and the data obtained by the communication connection to the vehicle-grid interactive control platform through the communication connection;

[0016] When there is a charging demand instruction, the vehicle-network interactive control terminal determines whether to execute the platform charging strategy or the local charging strategy;

[0017] If the platform charging strategy is executed, the vehicle-grid interactive control terminal receives the charging plan instruction issued by the vehicle-grid interactive control platform, and generates the optimal charging control curve for each charging pile in combination with the transformer conditions of the local distribution station area, and sends it to the charging and discharging control unit;

[0018] When the local load is detected to be overloaded or the remaining load is high, the local charging strategy is executed. The vehicle-grid interactive control terminal performs local charging control periodically according to the locally configured charging plan curve or load overload control strategy, without the need for charging plan instructions from the vehicle-grid interactive control platform;

[0019] The vehicle-grid interactive management and control terminal sends a charging plan instruction to the charging and discharging management and control unit. When the charging and discharging management and control unit receives the charging plan instruction from the vehicle-grid interactive management and control terminal, it communicates with the charging pile to realize charging start and stop, charging power control and charging pile information measurement operations.

[0020] As a preferred solution of the electric vehicle and power grid interactive control system described in the present invention, the vehicle-grid interactive control terminal includes: a data acquisition and upload module, a local strategy management module, a charging optimization control module, a fault abnormality alarm protection module and a remote control start-stop function module;

[0021] The data collection and upload module is used to send query instructions to all devices at a certain period to query information. The information in the information query includes status information, alarm information and fault information. It is also used to upload data to the vehicle network interactive control platform. The upload includes position upload, periodic upload and event upload.

[0022] The position change transmission is used to actively transmit the status information, warning information and fault information of various devices to the vehicle-network interactive control platform when the position change occurs;

[0023] The periodic uploading is used to package and upload the real-time telemetry information of various devices to the vehicle-grid interactive control platform at a fixed period;

[0024] The event uploading is used to actively upload charging records to the vehicle-grid interactive control platform when there is a charging event, and store the charging records in the history library of the vehicle-grid interactive control platform.

[0025] As a preferred solution of the electric vehicle and power grid interactive control system of the present invention, the local strategy management module is used for setting local strategy time period, setting strategy power value, generating local strategy, and load over-limit control;

[0026] Periodically obtain the current system time and compare it with the local policy time period;

[0027] If the current system time is during the policy change period, the local policy is updated at this time, and the power setting value of each charging pile is calculated and sent to the corresponding charging pile;

[0028] If the current system time is not during the policy change period, the local policy is maintained and the power corresponding to the local policy is sent to the corresponding charging pile;

[0029] The load over-limit control includes obtaining the real-time load of the substation and the maximum load of the substation, and determining the size of the real-time load of the substation and the maximum load of the substation;

[0030] If the real-time load of the area is greater than the maximum load of the area, it is considered that the load exceeds the limit, and the power setting value of each charging pile is reduced at this time;

[0031] If the real-time load of the area is not greater than the maximum load of the area, it is determined that the load has not exceeded the limit, and the power setting value of each charging pile is maintained at this time.

[0032] As a preferred solution of the electric vehicle and power grid interactive control system described in the present invention, the charging optimization control module includes:

[0033] The charging optimization control module is used for platform charging strategy storage, platform charging strategy execution, orderly plan termination, and local remote switching operations;

[0034] When there is a charging demand instruction, the charging optimization control module gives priority to executing the platform charging strategy. When executing the platform charging strategy, the charging optimization control module retrieves the stored platform charging strategy for execution based on the charging plan instruction issued by the vehicle-grid interactive control platform and the transformer conditions of the local distribution station area;

[0035] When the local load is detected to be overloaded or the residual load is high, the charging optimization control module performs a local remote switching operation. The charging optimization control module executes local charging control periodically according to the locally configured charging plan curve or load overload control strategy, without the need for charging plan instructions from the vehicle-grid interactive control platform.

[0036] As a preferred solution of the electric vehicle and power grid interactive control system described in the present invention, the fault abnormality alarm protection module includes:

[0037] The fault abnormality alarm protection module is used to send out an alarm signal and perform a locking protection action in time when an abnormality or fault occurs in the charging pile or itself during operation, and record the fault alarm event and report it to the upper platform;

[0038] The terminal collects the alarm fault telemetering quantity from the real-time database. When the alarm fault telemetering quantity changes, the terminal sends out an alarm signal in real time and makes an audible and visual alarm. When the module determines that control and protection operations are required, it immediately performs protection actions.

[0039] As a preferred solution of the electric vehicle and power grid interactive control system described in the present invention, the remote control start-stop function module includes: the remote control start-stop function module includes a terminal remote start-stop control function and a local remote control start-stop switching function.

[0040] As a preferred solution of the electric vehicle and power grid interactive control system described in the present invention, the vehicle-grid interactive control platform includes: generating a charging plan for each pile, and sending the charging plan for each pile to the vehicle-grid interactive management and control terminal, and the terminal stores the charging plan for each pile.

[0041] In a third aspect, the present invention provides a computer device, comprising a memory and a processor, wherein the memory stores a computer program, and the processor implements the steps of the above-mentioned method when executing the computer program.

[0042] In a fourth aspect, the present invention provides a computer-readable storage medium having a computer program stored thereon, wherein the computer program implements the steps of the method described above when executed by a processor.

[0043] Compared with the prior art, the invention has the following beneficial effects: the invention proposes a method and system for interactive control of electric vehicles and power grids, obtains real-time load data of the area where the charging station is located and relevant charging data of the charging equipment, and the relevant charging data at least includes charging state, voltage, current and power data; designs a first charging plan according to the real-time load data of the area where the charging station is located and the relevant charging data of the charging equipment, and the first charging plan includes generating the optimal charging control curve for each charging pile in combination with the transformer situation of the local distribution area; when the platform charging strategy is executed, the generated optimal charging control curve for each charging pile is sent to the corresponding charging pile; when the local load is detected to be overloaded or the residual load is high, the local charging strategy is executed, and the local charging control is periodically executed according to the charging plan curve or load over-limit control strategy configured locally. By configuring the vehicle-grid interactive control terminal at the charging station, the hierarchical interactive control of large-scale electric vehicles is realized, which has the advantages of small control deviation and fast control speed. The vehicle-grid interactive control terminal has the dual control functions of executing the platform plan and the local charging strategy at the same time. When executing the platform plan, the load over-limit situation of the local area can also be considered, and the control needs of regional and local distribution networks can be realized. The vehicle-grid interactive control terminal also has a fault monitoring function, which can provide fault alarms and ensure charging safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor. Among them:

[0045] Figure 1 A method flow chart of an electric vehicle and power grid interactive control method and system provided by an embodiment of the present invention;

[0046] Figure 2 A system architecture diagram of an electric vehicle and power grid interactive control method and system provided by an embodiment of the present invention;

[0047] Figure 3 An internal structural diagram of a computer device of an electric vehicle and power grid interactive control method and system provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0048] In order to make the above-mentioned purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the drawings of the specification. Obviously, the described embodiments are part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary persons in the art without creative work should fall within the scope of protection of the present invention.

[0049] Example 1

[0050] Reference Figure 1-Figure 3 , is the first embodiment of the present invention, which provides an electric vehicle and a power grid interactive control method and system, including an electric vehicle and a power grid interactive control method and an electric vehicle and a power grid interactive control system, wherein an electric vehicle and a power grid interactive control method includes:

[0051] Before describing the embodiments of the present application in detail, some related concepts are first explained for the sake of clarity.

[0052] Charging plan curve: The charging plan curve is a preset time series chart that defines how the charging pile should adjust its charging power within a specific time period. This curve is usually designed by the vehicle-grid interactive control platform based on the real-time status and predicted load of the power grid, the available capacity of the charging pile, the needs of users and other factors. The charging plan curve aims to balance the supply and demand of the power grid, avoid excessive pressure on the power grid during peak hours, and ensure that electric vehicle users can receive timely and effective charging services. For example, during low-power consumption periods, the charging plan curve may instruct the charging pile to increase the charging power to make full use of excess power resources; during peak power consumption periods, the curve may instruct the charging pile to reduce the charging power to reduce the burden on the power grid.

[0053] Optimal charging control curve: The optimal charging control curve is an idealized form of the charging plan curve, which not only takes into account the real-time status of the power grid and the characteristics of the charging pile, but also further optimizes the charging efficiency and energy utilization efficiency. This curve is calculated through mathematical models and algorithms, aiming to minimize charging costs, maximize grid stability, or achieve other optimization goals (such as reducing carbon emissions). The generation of the optimal charging control curve needs to consider more complex factors, such as battery charging characteristics, user charging demand forecasts, electricity price fluctuations, and the availability of renewable energy. It dynamically adjusts the charging power of the charging pile to ensure that the charging behavior at each moment is the best choice under current conditions, thereby achieving efficient coordination between the power grid and electric vehicle charging.

[0054] In the relevant technologies, there is a problem that the charging management of electric vehicles is not flexible enough and it is difficult to meet the real-time dispatch of the power grid and the needs of electric vehicle users. Traditional charging management methods often rely on fixed charging plans and cannot be dynamically adjusted according to the power grid load and the real-time needs of electric vehicles. This may not only cause excessive fluctuations in the power grid load and affect the stable operation of the power grid, but may also fail to meet the charging needs of electric vehicle users and reduce user experience.

[0055] The present application provides a method for effectively solving the above-mentioned problems. Next, multiple embodiments will be combined to explain in detail how to implement the electric vehicle and power grid interactive control method.

[0056] Figure 1 A method flow chart of an electric vehicle and a power grid interactive control method and system is shown, including:

[0057] S101, obtaining real-time load data of the area where the charging station is located and relevant charging data of the charging equipment, wherein the relevant charging data at least includes charging status, voltage, current and power data;

[0058] S102, designing a first charging plan based on the real-time load data of the area where the charging station is located and the relevant charging data of the charging equipment, wherein the first charging plan includes generating an optimal charging control curve for each charging pile in combination with the transformer conditions of the local distribution area;

[0059] In the embodiment of the present application, the steps of designing the first charging plan may be as follows:

[0060] Step 1: Collect real-time load data, including obtaining real-time power demand data from the power grid. Collect charging equipment data, including collecting charging status, voltage, current and power data from charging piles. Transformer data includes the rated capacity, current load and maximum allowable load of the transformer.

[0061] Step 2: Design an objective function for the purpose of this application, namely, minimizing the peak load of the grid under the local transformer load limit and reducing the charging cost.

[0062] The specific objective function is as follows:

[0063]

[0064] Where M is the number of transformers, P transformer,j is the baseline load of the jth transformer, C max,j is the maximum permissible load of the jth transformer; λ1 and λ2 are the penalty coefficients for grid overload and transformer overload, respectively. N is the number of time intervals. c(t i ) is at time t i The electricity price. charge,i is at time t i The total charging power. grid is the baseline power of the grid. max is the maximum allowable power of the power grid.

[0065] Step 3: Establish constraints for the purpose of this application, as follows:

[0066] Power Constraint: Ensure that all vehicles are fully charged at the end of the program.

[0067]

[0068] Power constraint: The charging power of a single charging pile cannot exceed its maximum power.

[0069] 0≤P charge,i (t)≤P max,i

[0070] Transformer load constraints:

[0071]

[0072] Among them, T j is the set of all charging piles connected to the jth transformer.

[0073] Step 4: Use an appropriate optimization algorithm (such as mixed integer linear programming) to solve the above problem and find the optimal charging control curve that meets all constraints.

[0074] Step 5: Generate a Charging Plan

[0075] Based on the solution results, the optimal charging control curve is generated for each charging pile to ensure that the load capacity of the transformer is not exceeded.

[0076] It should be noted that S102 can dynamically adjust the charging strategy according to the real-time status of the power grid and the operating data of the charging equipment to achieve smoothing of the power grid load and maximize the efficiency of the charging piles. It can not only reduce the load fluctuation of the power grid caused by electric vehicle charging and improve the stability of the power grid, but also ensure that electric vehicle users can enjoy lower charging costs while meeting their charging needs.

[0077] In an optional embodiment, the optimized charging control curve can be further adjusted taking into account electricity price fluctuations and the use of renewable energy. For example, when there is an excess of renewable energy such as solar or wind power, the charging piles can be encouraged to increase the charging power and absorb this part of clean electricity, thereby improving the utilization rate of renewable energy, reducing dependence on fossil fuels, and achieving more green and sustainable energy use.

[0078] In an optional embodiment, in terms of user demand forecasting, the charging needs of electric vehicle users can be predicted through historical data and real-time behavior patterns, and the charging plan can be adjusted in advance to avoid concentrated charging at specific time points, further reducing the pressure on the power grid.

[0079] S103, when executing the platform charging strategy, sending the generated optimal charging control curve for each charging pile to the corresponding charging pile;

[0080] S104, when the local load is detected to be overloaded or the remaining load is high, the local charging strategy is executed, and the local charging control is periodically performed according to the locally configured charging plan curve or load overload control strategy.

[0081] This embodiment also provides an electric vehicle and power grid interactive control system, characterized in that the system includes: a distribution transformer, a three-phase meter, a vehicle-grid interactive control platform, a vehicle-grid interactive control terminal, and a plurality of charging piles including a charging and discharging control unit;

[0082] In the embodiment of the present application, the vehicle-grid interactive control terminal is electrically connected through a three-phase meter to obtain real-time load data of the area where the charging station is located, and is simultaneously connected to the charging and discharging control units in different charging piles in communication to obtain relevant charging data of the charging equipment, the relevant charging data at least including charging status, voltage, current and power data, and transmits the data obtained by the electrical connection and the data obtained by the communication connection to the vehicle-grid interactive control platform through the communication connection;

[0083] When there is a charging demand instruction, the vehicle-network interactive control terminal determines whether to execute the platform charging strategy or the local charging strategy;

[0084] If the platform charging strategy is executed, the vehicle-grid interactive control terminal receives the charging plan instructions issued by the vehicle-grid interactive control platform, and generates the optimal charging control curve for each charging pile based on the transformer conditions of the local distribution area, and sends it to the charging and discharging control unit;

[0085] In the embodiment of the present application, when the local load is detected to be overloaded or the remaining load is high, the local charging strategy is executed, and the vehicle-grid interactive control terminal performs local charging control periodically according to the locally configured charging plan curve or load overload control strategy, without the need for the charging plan instruction of the vehicle-grid interactive control platform;

[0086] The vehicle-grid interactive control terminal sends a charging plan instruction to the charging and discharging control unit. When the charging and discharging control unit receives the charging plan instruction from the vehicle-grid interactive control terminal, it communicates with the charging pile to realize charging start and stop, charging power control and charging pile information measurement operations.

[0087] In the embodiment of the present application, the hardware structure of the vehicle-grid interactive management and control terminal consists of three parts: a core board, an expansion board, and an external structure. The core board realizes functions such as data processing, data storage, and an expansion interface. The expansion board can be easily expanded according to different needs such as the number of connected charging piles and data collection.

[0088] In the embodiment of the present application, the vehicle-network interactive management and control terminal includes: a data collection and upload module, a local policy management module, a charging optimization control module, a fault abnormality alarm protection module, and a remote control start-stop function module;

[0089] In the embodiment of the present application, the data collection and upload module is used to send query instructions to all devices at a certain period to query information. The information in the information query includes status information, alarm information and fault information. It is also used to upload data to the vehicle network interactive control platform. The upload includes position upload, periodic upload and event upload.

[0090] The position change transmission is used to actively send the status information, warning information and fault information of various devices to the vehicle network interactive control platform when the position changes;

[0091] Periodic uploading is used to package and upload the real-time telemetry information of various devices to the vehicle-grid interactive control platform at a fixed period.

[0092] Event uploading is used to actively upload charging records to the vehicle-grid interactive control platform when there is a charging event, and store them in the history library of the vehicle-grid interactive control platform.

[0093] In the embodiment of the present application, the local policy management module is used for local policy period setting, policy power value setting, local policy generation, and load over-limit control;

[0094] Periodically obtain the current system time and compare it with the local policy time period;

[0095] If the current system time is during the policy change period, the local policy is updated at this time, and the power setting value of each charging pile is calculated and sent to the corresponding charging pile;

[0096] If the current system time is not during the policy change period, the local policy is maintained and the power corresponding to the local policy is sent to the corresponding charging pile;

[0097] In the embodiment of the present application, the load over-limit control includes obtaining the real-time load of the substation and the maximum load of the substation, and determining the magnitude of the real-time load of the substation and the maximum load of the substation;

[0098] If the real-time load of the area is greater than the maximum load of the area, it is considered that the load exceeds the limit, and the power setting value of each charging pile is reduced at this time;

[0099] If the real-time load of the area is not greater than the maximum load of the area, it is determined that the load has not exceeded the limit, and the power setting value of each charging pile is maintained at this time.

[0100] In the embodiment of the present application, the charging optimization control module includes:

[0101] The charging optimization control module is used for platform charging strategy storage, platform charging strategy execution, orderly plan termination, and local remote switching operations;

[0102] When there is a charging demand instruction, the charging optimization control module will give priority to executing the platform charging strategy. When executing the platform charging strategy, the charging optimization control module will retrieve the stored platform charging strategy for execution based on the charging plan instruction issued by the vehicle-grid interactive control platform and the transformer conditions of the local distribution station area;

[0103] When the local load is detected to be overloaded or the remaining load is high, the charging optimization control module performs local remote switching operations. The charging optimization control module executes local charging control periodically according to the locally configured charging plan curve or load over-limit control strategy, without the need for charging plan instructions from the vehicle-grid interactive control platform.

[0104] In the embodiment of the present application, the fault abnormality alarm protection module includes:

[0105] The fault abnormality alarm protection module is used to send out an alarm signal and perform a locking protection action in time when an abnormality or fault occurs in the charging pile or itself during operation. At the same time, it records the fault alarm event and reports it to the upper-level platform;

[0106] The terminal collects the alarm fault telemetering quantity from the real-time database. When the alarm fault telemetering quantity changes, the terminal sends out an alarm signal in real time and makes an audible and visual alarm. When the module determines that control and protection operations are required, it immediately performs protection actions.

[0107] In an embodiment of the present application, the remote control start-stop function module includes: the remote control start-stop function module includes a terminal remote start-stop control function and a local remote control start-stop switching function. The specific switching steps are as follows: receiving a charging request from the user, determining the type of charging request, that is, judging whether it is scheduled charging or instant charging according to the content of the request. If it is a scheduled charging request, add it to the scheduled charging queue. If it is an instant charging request, add it to the instant charging queue. According to the order of requests in the charging queue, the charging instructions are sent to the charging piles in sequence.

[0108] In an embodiment of the present application, the vehicle-grid interactive control platform includes: generating a charging plan for each pile, and sending the charging plan for each pile to the vehicle-grid interactive control terminal, and the terminal stores the charging plan for each pile.

[0109] Specifically, the judgment logic of the vehicle-grid interactive control platform includes: the vehicle-grid interactive control platform judges whether there is a charging demand: first check whether there is a charging demand. If there is a charging demand, go to the next step; if not, the process ends.

[0110] Determine whether there is a platform charging plan: If there is a charging demand, then check whether there is a charging plan from the platform. If so, adopt the platform charging plan; otherwise, continue to execute the local charging strategy.

[0111] Calculate local charging plan: In the absence of a platform charging plan, calculate the local charging plan. This may include taking into account the transformer situation and generating the optimal charging control curve for each charger.

[0112] Determine whether there is a work plan: Check whether there is an existing work plan. If so, update the work plan; otherwise, continue to create a new work plan.

[0113] Update work plan: If there is a work plan, update the work plan to reflect the new charging needs and transformer conditions.

[0114] Create new work plan: If there is no work plan, create a new work plan taking into account the charging demand and transformer condition.

[0115] Determine whether there is a work plan: Check again whether there is a work plan. If there is, issue the power distribution change; otherwise, the process ends.

[0116] Issue power distribution changes: If there is a work plan, issue the power distribution changes according to the work plan and notify the charging piles to perform the corresponding charging tasks.

[0117] It should be noted that the data collection and upload module realizes the real-time and accuracy of data, ensuring that the vehicle-grid interactive control platform can make accurate charging strategy decisions based on the latest data. At the same time, the module also has three upload modes: variable upload, periodic upload and event upload, ensuring the timely transmission and effective management of different types of information, providing strong support for the smooth control of power grid load and the maximization of charging pile efficiency.

[0118] In terms of the local strategy management module, it is responsible for formulating and executing the corresponding charging plan according to the actual situation and load conditions of the local distribution station area transformer. When the local load is detected to be overloaded or the residual load is high, the module can quickly switch to the local charging strategy and periodically execute local charging control according to the locally configured charging plan curve or load overload control strategy, thereby ensuring the stable operation of the power grid and the safe use of charging piles.

[0119] The charging optimization control module receives the charging plan instructions issued by the vehicle-grid interactive control platform, combines the local distribution station area transformer conditions, generates the optimal charging control curve for each charging pile, and sends it to the charging and discharging control unit. The module uses advanced optimization algorithms and real-time data to finely control the charging process, achieve smooth grid load and maximize charging pile efficiency, reduce grid load fluctuations caused by electric vehicle charging, and improve grid stability.

[0120] The fault abnormality alarm protection module is responsible for monitoring the operating status of the charging pile. Once a fault or abnormality is found, it will immediately issue an alarm and take corresponding protection measures. This module ensures the safe and reliable operation of the charging pile and protects the charging safety of users by real-time detection of key parameters such as voltage, current, and temperature of the charging pile.

[0121] The remote control start-stop function module allows the vehicle-grid interactive control platform to remotely start and stop the charging pile. When the charging pile needs to be stopped urgently or for remote maintenance, the module can quickly respond and execute the corresponding control instructions to ensure the safety and controllability of the charging pile.

[0122] In summary, the present invention proposes a method and system for interactive control of electric vehicles and power grids, which obtains real-time load data of the area where the charging station is located and relevant charging data of the charging equipment, wherein the relevant charging data at least includes charging status, voltage, current and power data; according to the real-time load data of the area where the charging station is located and the relevant charging data of the charging equipment, a first charging plan is designed, wherein the first charging plan includes generating an optimal charging control curve for each charging pile in combination with the transformer situation of the local distribution area; when the platform charging strategy is executed, the generated optimal charging control curve for each charging pile is sent to the corresponding charging pile; when the local load is detected to be overloaded or the residual load is high, the local charging strategy is executed, and the local charging control is periodically executed according to the charging plan curve or load over-limit control strategy configured locally. By configuring the vehicle-grid interactive control terminal at the charging station, the hierarchical interactive control of large-scale electric vehicles is realized, which has the advantages of small control deviation and fast control speed. The vehicle-grid interactive control terminal has the dual control functions of executing the platform plan and the local charging strategy at the same time. When executing the platform plan, the load over-limit situation of the local area can also be considered, and the control requirements of the regional and local distribution networks can be realized. The vehicle-grid interactive control terminal also has a fault monitoring function, which can provide fault alarms and ensure charging safety.

[0123] The above-mentioned unit modules may be embedded in or independent of the processor in the computer device in the form of hardware, or may be stored in the memory in the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above-mentioned modules.

[0124] This embodiment also provides a computer device, which may be a terminal, and its internal structure diagram may be as shown in FIG. Figure 3 As shown. The computer device includes a processor, a memory, a communication interface, a display screen and an input device connected through a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system and a computer program. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The communication interface of the computer device is used to communicate with an external terminal in a wired or wireless manner, and the wireless manner can be achieved through WIFI, an operator network, NFC (near field communication) or other technologies. When the computer program is executed by the processor, a method for interactive control of an electric vehicle and a power grid is implemented. The display screen of the computer device can be a liquid crystal display screen or an electronic ink display screen, and the input device of the computer device can be a touch layer covered on the display screen, or a button, a trackball or a touchpad set on the housing of the computer device, or an external keyboard, touchpad or mouse, etc.

[0125] This embodiment further provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the following steps are implemented:

[0126] Obtain real-time load data of the area where the charging station is located and relevant charging data of the charging equipment, which at least includes charging status, voltage, current and power data;

[0127] Design a first charging plan based on the real-time load data of the area where the charging station is located and the relevant charging data of the charging equipment. The first charging plan includes generating an optimal charging control curve for each charging pile in combination with the transformer conditions of the local distribution area;

[0128] When the platform charging strategy is executed, the generated optimal charging control curve for each charging pile is sent to the corresponding charging pile;

[0129] When the local load is detected to be overloaded or the remaining load is high, the local charging strategy is executed, and the local charging control is performed periodically according to the locally configured charging plan curve or load overload control strategy.

[0130] Example 2

[0131] Reference Figure 1-Figure 3 , which is an embodiment of the present invention, provides an electric vehicle and power grid interactive control method and system. In order to verify the beneficial effects of the present invention, scientific demonstration is carried out through experiments.

[0132] During the experiment, several charging stations with different transformer conditions and load conditions in different distribution areas were selected as experimental objects. These charging stations cover a variety of scenarios from urban core areas to suburbs, from commercial areas to residential areas, ensuring the comprehensiveness and representativeness of the experiment.

[0133] First, we conducted a detailed field survey of each charging station and collected a large amount of real-time load data and charging data related to charging equipment. These data include key parameters such as charging status, voltage, current, and power of charging equipment, as well as the real-time load status of transformers in distribution stations.

[0134] Then, based on the collected data, the first charging plan was designed for each charging station using the electric vehicle and power grid interactive control method proposed in the present invention. In the process of plan design, the actual situation and load conditions of the transformer in the local distribution area were fully considered, and the optimal charging control curve for each charging pile was generated by combining advanced optimization algorithms and real-time data.

[0135] During the experiment, the execution of the platform charging strategy and the local charging strategy were simulated respectively. When the platform charging strategy was executed, the optimal charging control curve for each charging pile was sent to the corresponding charging pile, and the charging process of the charging pile was monitored in real time. The experimental results show that by accurately controlling the charging process of each charging pile, the smooth control of the grid load and the maximization of the efficiency of the charging pile can be effectively achieved.

[0136] When the local load is detected to be overloaded or the residual load is high, it quickly switches to the local charging strategy and periodically executes local charging control according to the locally configured charging plan curve or load overload control strategy. By adjusting the charging power and charging time of the charging pile in real time, the grid load is successfully controlled within a safe range, ensuring the stable operation of the grid and the safe use of the charging pile.

[0137] After the experiment, the experimental results were analyzed and evaluated in detail. The experimental results show that the electric vehicle and power grid interactive control method and system proposed in the present invention can significantly improve the stability of the power grid and the efficiency of charging piles. Through hierarchical interactive regulation and refined charging control, the load fluctuation of the power grid caused by electric vehicle charging was successfully reduced, and the power supply quality and reliability of the power grid were improved.

[0138] Table 1: Schematic diagram of experimental results.

[0139]

[0140]

[0141] The grid load fluctuation rate is used to measure the magnitude of load changes in the grid during the charging process of electric vehicles. After the experiment, due to the adoption of a sophisticated charging control strategy, the grid load fluctuation was greatly reduced from 15% to 5%, showing the effectiveness of the control method.

[0142] The average charging efficiency of a charging pile refers to the proportion of effective charging capacity that a charging pile can provide per unit time. After the experiment, the charging efficiency of the charging pile was significantly improved from 80% to 90%, which means less power waste and higher energy utilization.

[0143] The average charging waiting time is used to reflect the time users wait for available charging piles at charging stations. After the experiment, due to the optimization of charging plans, the average waiting time was shortened by half, improving the user experience.

[0144] The failure rate of charging piles is used to indicate how often a charging pile fails. After the experiment, the failure rate dropped significantly, from 0.5% to 0.1%, showing the positive impact of the control method on the safe operation of charging piles.

[0145] The power supply quality index is an indicator used to comprehensively evaluate the stability and quality of power supply in the power grid. After the experiment, the power supply quality index increased from 92 to 97, reflecting the improvement of the overall performance of the power grid.

[0146] The user satisfaction score is used for subjective evaluation based on user feedback. After the experiment, user satisfaction with the charging experience increased significantly, from 3.5 / 5 to 4.5 / 5, which shows the effectiveness of the control method in improving user experience.

[0147] In addition, the present invention also has a fault monitoring function, which can monitor the operating status of the charging pile in real time and issue a fault alarm. Once a fault or abnormality of the charging pile is detected, corresponding protective measures can be quickly taken to ensure the safe and reliable operation of the charging pile and the charging safety of the user.

[0148] In summary, the electric vehicle and power grid interactive control method and system proposed in the present invention have the advantages of small control deviation, fast control speed, safety and reliability. Through application and verification in actual charging stations, the feasibility and effectiveness of the method have been proved, providing a new solution for the interactive control of electric vehicles and power grids.

[0149] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.

[0150] Those skilled in the art will appreciate that the embodiments of the present application can be provided as methods, systems, or computer program products. Therefore, the present application can adopt the form of complete hardware embodiments, complete software embodiments, or embodiments in combination with software and hardware. Moreover, the present application can adopt the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that contain computer-usable program code. The scheme in the embodiments of the present application can be implemented in various computer languages, for example, object-oriented programming language Java and literal scripting language JavaScript, etc.

[0151] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0152] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0153] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0154] Although the preferred embodiments of the present application have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present application.

[0155] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.

Claims

1. A method for interactive control of electric vehicles and power grids, characterized in that: include: Obtaining real-time load data of the area where the charging station is located and relevant charging data of the charging equipment, wherein the relevant charging data at least includes charging status, voltage, current and power data; Designing a first charging plan based on the real-time load data of the area where the charging station is located and the relevant charging data of the charging equipment, wherein the first charging plan includes generating an optimal charging control curve for each charging pile in combination with the transformer conditions of the local distribution area; When the platform charging strategy is executed, the generated optimal charging control curve for each charging pile is sent to the corresponding charging pile; When the local load is detected to be overloaded or the remaining load is high, the local charging strategy is executed, and the local charging control is performed periodically according to the locally configured charging plan curve or load overload control strategy.

2. A system using the electric vehicle and power grid interactive control method as claimed in claim 1, characterized in that: The system includes: a distribution transformer, a three-phase meter, a vehicle-grid interactive control platform, a vehicle-grid interactive control terminal, and a number of charging piles including a charging and discharging control unit; The vehicle-grid interactive control terminal is electrically connected to the three-phase meter to obtain real-time load data of the area where the charging station is located, and is also communicatively connected to the charging and discharging control units in different charging piles to obtain relevant charging data of the charging equipment, wherein the relevant charging data at least includes charging status, voltage, current and power data, and transmits the data obtained by the electrical connection and the data obtained by the communication connection to the vehicle-grid interactive control platform through the communication connection; When there is a charging demand instruction, the vehicle-network interactive control terminal determines whether to execute the platform charging strategy or the local charging strategy; If the platform charging strategy is executed, the vehicle-grid interactive control terminal receives the charging plan instruction issued by the vehicle-grid interactive control platform, and generates the optimal charging control curve for each charging pile in combination with the transformer conditions of the local distribution station area, and sends it to the charging and discharging control unit; When the local load is detected to be overloaded or the remaining load is high, the local charging strategy is executed. The vehicle-grid interactive control terminal performs local charging control periodically according to the locally configured charging plan curve or load overload control strategy, without the need for charging plan instructions from the vehicle-grid interactive control platform; The vehicle-grid interactive management and control terminal sends a charging plan instruction to the charging and discharging management and control unit. When the charging and discharging management and control unit receives the charging plan instruction from the vehicle-grid interactive management and control terminal, it communicates with the charging pile to realize charging start and stop, charging power control and charging pile information measurement operations.

3. The electric vehicle and power grid interactive control method according to claim 2, characterized in that: The vehicle-network interactive control terminal includes: a data collection and upload module, a local policy management module, a charging optimization control module, a fault abnormality alarm protection module, and a remote control start-stop function module; The data collection and upload module is used to send query instructions to all devices at a certain period to query information. The information in the information query includes status information, alarm information and fault information. It is also used to upload data to the vehicle network interactive control platform. The upload includes position upload, periodic upload and event upload. The position change transmission is used to actively transmit the status information, warning information and fault information of various devices to the vehicle-network interactive control platform when the position change occurs; The periodic uploading is used to package and upload the real-time telemetry information of various devices to the vehicle-grid interactive control platform at a fixed period; The event uploading is used to actively upload charging records to the vehicle-grid interactive control platform when there is a charging event, and store the charging records in the history library of the vehicle-grid interactive control platform.

4. The electric vehicle and power grid interactive control method according to claim 3, characterized in that: The local policy management module is used for local policy time period setting, policy power value setting, local policy generation, and load over-limit control; Periodically obtain the current system time and compare it with the local policy time period; If the current system time is during the policy change period, the local policy is updated at this time, and the power setting value of each charging pile is calculated and sent to the corresponding charging pile; If the current system time is not during the policy change period, the local policy is maintained and the power corresponding to the local policy is sent to the corresponding charging pile; The load over-limit control includes obtaining the real-time load of the substation and the maximum load of the substation, and determining the size of the real-time load of the substation and the maximum load of the substation; If the real-time load of the area is greater than the maximum load of the area, it is considered that the load exceeds the limit, and the power setting value of each charging pile is reduced at this time; If the real-time load of the area is not greater than the maximum load of the area, it is determined that the load has not exceeded the limit, and the power setting value of each charging pile is maintained at this time.

5. The electric vehicle and power grid interactive control method according to claim 4, characterized in that: The charging optimization control module includes: The charging optimization control module is used for platform charging strategy storage, platform charging strategy execution, orderly plan termination, and local remote switching operations; When there is a charging demand instruction, the charging optimization control module gives priority to executing the platform charging strategy. When executing the platform charging strategy, the charging optimization control module retrieves the stored platform charging strategy for execution based on the charging plan instruction issued by the vehicle-grid interactive control platform and the transformer conditions of the local distribution station area; When the local load is detected to be overloaded or the residual load is high, the charging optimization control module performs a local remote switching operation. The charging optimization control module executes local charging control periodically according to the locally configured charging plan curve or load overload control strategy, without the need for charging plan instructions from the vehicle-grid interactive control platform.

6. The electric vehicle and power grid interactive control method according to claim 5, characterized in that: The fault abnormality alarm protection module includes: The fault abnormality alarm protection module is used to send out an alarm signal and perform a locking protection action in time when an abnormality or fault occurs in the charging pile or itself during operation, and record the fault alarm event and report it to the upper platform; The terminal collects the alarm fault telemetering quantity from the real-time database. When the alarm fault telemetering quantity changes, the terminal sends out an alarm signal in real time and makes an audible and visual alarm. When the module determines that control and protection operations are required, it immediately performs protection actions.

7. The electric vehicle and power grid interactive control method according to claim 6, characterized in that: The remote control start-stop function module includes: the remote control start-stop function module includes a terminal remote start-stop control function and a local remote control start-stop switching function.

8. The electric vehicle and power grid interactive control method according to claim 7, characterized in that: The vehicle-grid interactive control platform includes: generating a charging plan for each pile, and sending the charging plan for each pile to the vehicle-grid interactive control terminal, and the terminal stores the charging plan for each pile.

9. A computer device comprising a memory and a processor, wherein the memory stores a computer program, wherein: When the processor executes the computer program, the steps of the method according to claim 1 are implemented.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to claim 1 are implemented.