Parameter testing device, method and equipment of remote control system and medium

By using the timing device and time synchronization module in the mine remote control system to measure the business delay time, the problem of untimely equipment control caused by video transmission delay is solved, the system's quality control ability is improved, and investment waste is avoided.

CN119087985APending Publication Date: 2024-12-06BEIJING BEIKUANG INTELLIGENT TECH CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411265599.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The excessive delay in video transmission in the mine remote remote control system leads to untimely issuance of equipment control instructions, affecting the safety and efficiency of the system and causing waste of investment.

Method used

The parameter testing device using a remote control system, including two timing devices and a time synchronization module, measures and determines the service processing delay time through the time synchronization and data processing system, adjusts the timing accuracy and transmission delay to improve the system quality control capability.

Benefits of technology

Effectively measure and adjust the business delay time of the remote control system, improve the system's quality control capabilities, avoid investment waste, and ensure the safe and efficient operation of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119087985A_ABST
    Figure CN119087985A_ABST
Patent Text Reader

Abstract

The invention provides a parameter testing device, method and equipment for a remote control system and a medium, and the system comprises a time synchronization module which carries out the time synchronization of a first timing device and a second timing device, so as to enable the first timing device and the second timing device to start timing with a preset initial time as a starting point; the first acquisition device acquires first time of the first timing device and second time of the second timing device at a target moment; wherein the target moment is a completion moment after the remote control system performs service processing from the initial time; and the data processing system can read the first time and the second time acquired by the first acquisition device and determine target business delay time of business processing of the remote control system so as to quantitatively test parameters of the remote control system and help an enterprise to judge whether business requirements are met or not. The quality control capability of an enterprise on the remote control system is effectively improved, and the construction investment waste of the remote control system is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of data detection technology, and in particular to a parameter testing device, method, equipment and medium for a remote control system. Background Art

[0002] With the continuous acceleration of the process of intelligent mining, mine remote control and unmanned driving have been increasingly used, and video transmission delay is one of the key indicators that affect the use of various types of mining equipment. Excessive video delay may cause operators to see the status of a period of time ago, which in turn leads to the phenomenon that equipment control instructions are not issued in time, bringing risks to equipment safety control and affecting the efficiency of the system. As a result, mines have built mining equipment remote control systems, but their use is limited in actual production, resulting in a waste of investment. Summary of the invention

[0003] In view of this, the purpose of the present application is to provide a parameter testing device, method, equipment and medium for a remote control system to overcome the problems in the prior art.

[0004] In a first aspect, an embodiment of the present application provides a remote control system including a remote control system and a local control system; the parameter testing device includes: a first timing device, a second timing device, a time synchronization module, a first acquisition device and a data processing system; there is a preset distance interval between the remote control system and the local control system; during parameter acquisition, the first timing device and the remote control system are set at the same position, and the second timing device and the local control system are set at the same position; The time synchronization module is used to synchronize the time of the first timing device and the second timing device, so that the first timing device and the second timing device both start timing from a preset initial time; The first collecting device is used to collect the first time of the first timing device and the second time of the second timing device at a target time; wherein the target time is the completion time after the remote control system starts the business processing from the initial time; The data processing system is used to display the second time of the second timing device, and is also used to determine the target service delay time for the remote control system to perform service processing based on the first time and the second time.

[0005] In some technical solutions of the present application, the time synchronization module is used to synchronize the first timing device and the second timing device so that both the first timing device and the second timing device start timing from a preset initial time, including: The time synchronization module is used to generate an initial time in response to a time setting operation; and control the first timing device and the second timing device to start timing with the initial time as the starting point; Alternatively, the data processing system is used to generate a time control instruction according to the current third time of the first timing device and the current fourth time of the second timing device; The time synchronization module is used to synchronize the first timing device and the second timing device according to the time control instruction, so that the first timing device and the second timing device both start timing with a preset initial time as the starting point.

[0006] In some technical solutions of the present application, the above-mentioned time control instructions include time keeping instructions and time synchronization instructions; The data processing system is used to generate a time control instruction according to the current third time of the first timing device and the current fourth time of the second timing device, including: If the interval between the third time and the fourth time is less than or equal to a preset interval threshold, a time keeping instruction is generated; wherein the time keeping instruction is used to control the first timing device and the second timing device to maintain their own timing states; If the interval between the third time and the fourth time is greater than a preset interval threshold, a time synchronization instruction is generated; wherein the time synchronization instruction is used to control the first timing device and the second timing device to start timing from a preset initial time.

[0007] In some technical solutions of the present application, if the interval between the third time and the fourth time is greater than a preset interval threshold, a time synchronization instruction is generated; wherein the time synchronization instruction is used to control the first timing device and the second timing device to start timing from a preset initial time, including: determining a transmission delay between the first timing device and the second timing device; Generate a first time synchronization instruction for the first timing device according to the preset time and the transmission delay; wherein the first time synchronization instruction is used to control the first timing device to start timing as a preset initial time; A second time synchronization instruction for the second timing device is generated according to the preset time, wherein the second time synchronization instruction is used to control the second timing device to start timing with the preset initial time as the starting point.

[0008] In some technical solutions of the present application, the parameter testing device of the remote control system further includes: an adjustment device; the adjustment device is connected to the first timing device and the second timing device respectively; The data processing system is used to detect a first timing accuracy of the first timing device and a second timing accuracy of the second timing device; If the first timing accuracy or the second timing accuracy does not meet the preset accuracy requirement, the data processing system is used to send an adjustment instruction to the adjustment device; The adjustment device is used to adjust the accuracy of the first timing device or the second timing device according to the adjustment instruction, so that the first timing accuracy and the second timing accuracy both meet the accuracy requirement.

[0009] In some technical solutions of the present application, the first acquisition device is used to collect the first time of the first timing device and the second time of the second timing device at a target time; wherein the target time is the completion time after the remote control system starts business processing from the initial time, including: The first acquisition device is used to obtain a plurality of the first times and the corresponding second times; The data processing system is used to determine a target service delay time for service processing by the remote control system according to a plurality of the first times and the second times.

[0010] In some technical solutions of the present application, the above-mentioned data processing system is also used to debug the remote control system based on the target service delay time, so that the remote control system meets the service requirements.

[0011] In a second aspect, an embodiment of the present application provides a parameter testing method for a remote control system, which is applied to a parameter testing device for a remote control system, wherein the remote control system includes a remote control system and a local control system; the parameter testing device includes: a first timing device, a second timing device, a time synchronization module, a first acquisition device, and a data processing system; there is a preset distance interval between the remote control system and the local control system; during parameter acquisition, the first timing device and the remote control system are set at the same position, and the second timing device and the local control system are set at the same position; the method includes: The time synchronization module performs time synchronization on the first timing device and the second timing device, so that both the first timing device and the second timing device start timing from a preset initial time; The first collecting device collects the first time of the first timing device and the second time of the second timing device at the target time; wherein the target time is the completion time after the remote control system starts the business processing from the initial time; The data processing system displays the second time of the second timing device, and determines the target service delay time for the remote control system to perform service processing according to the first time and the second time.

[0012] In a third aspect, an embodiment of the present application provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the above-mentioned parameter testing method of the remote control system when executing the computer program.

[0013] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of the parameter testing method of the remote control system are executed.

[0014] The technical solution provided by the embodiments of the present application may have the following beneficial effects: The remote control system in the present application includes a remote control system and a local control system; the parameter testing device includes: a first timing device, a second timing device, a time synchronization module, a first acquisition device and a data processing system; there is a preset distance interval between the remote control system and the local control system; when collecting parameters, the first timing device and the remote control system are set at the same position, and the second timing device and the local control system are set at the same position; the time synchronization module is used to synchronize the time of the first timing device and the second timing device, so that the first timing device and the second timing device both start timing from a preset initial time; the first acquisition device is used to collect the first time of the first timing device and the second time of the second timing device at a target time; wherein the target time is the completion time after the remote control system starts business processing from the initial time; the data processing system is used to display the second time of the second timing device, and is also used to determine the target business delay time for the remote control system to perform business processing based on the first time and the second time.

[0015] This application determines the service delay time of the remote control system through two timing devices, effectively improves the enterprise's quality control ability of the remote control system, and avoids waste of investment in the construction of the remote control system.

[0016] In order to make the above-mentioned objects, features and advantages of the present application more obvious and easy to understand, preferred embodiments are specifically cited below and described in detail with reference to the attached drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0018] Figure 1 A schematic diagram of a parameter testing device for a remote control system provided in an embodiment of the present application is shown; Figure 2 A schematic diagram of a timing device provided in an embodiment of the present application is shown; Figure 3 A schematic diagram of a flow chart of a parameter testing method of a remote control system provided in an embodiment of the present application is shown; Figure 4 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0019] To make the purpose, technical scheme and advantages of the embodiments of the present application clearer, the technical scheme in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. It should be understood that the drawings in the present application only serve the purpose of explanation and description and are not used to limit the scope of protection of the present application. In addition, it should be understood that the schematic drawings are not drawn in real proportion. The flowchart used in this application shows the operations implemented according to some embodiments of the present application. It should be understood that the operations of the flowchart can be implemented out of sequence, and the steps without logical context can be reversed in order or implemented simultaneously. In addition, those skilled in the art can add one or more other operations to the flowchart under the guidance of the content of the present application, or remove one or more operations from the flowchart.

[0020] In addition, the described embodiments are only a part of the embodiments of the present application, rather than all the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various configurations. Therefore, the following detailed description of the embodiments of the present application provided in the drawings is not intended to limit the scope of the application claimed for protection, but merely represents the selected embodiments of the present application. Based on the embodiments of the present application, all other embodiments obtained by those skilled in the art without making creative work belong to the scope of protection of the present application.

[0021] It should be noted that the term "comprising" will be used in the embodiments of the present application to indicate the existence of the features declared thereafter, but does not exclude the addition of other features.

[0022] With the continuous acceleration of the process of intelligent mining, mine remote control and unmanned driving have been increasingly used, and video transmission delay is one of the key indicators that affect the use of various types of mining equipment. Excessive video delay may cause operators to see the status of a period of time ago, which in turn leads to the phenomenon that equipment control instructions are not issued in time, bringing risks to equipment safety control and affecting the efficiency of the system. As a result, mines have built mining equipment remote control systems, but their use is limited in actual production, resulting in a waste of investment.

[0023] Based on this, the embodiments of the present application provide a parameter test device, method, equipment and medium for a remote control system, which are described below by way of embodiments. Some implementation methods of the present application are described in detail below. In the absence of conflict, the following embodiments and features in the embodiments may be combined with each other.

[0024] Figure 1 A schematic diagram of a parameter testing device of a remote control system provided in an embodiment of the present application is shown, which includes a remote control system and a local control system; the parameter testing device includes: a first timing device, a second timing device, a time synchronization module, a first acquisition device and a data processing system; there is a preset distance interval between the remote control system and the local control system; during parameter acquisition, the first timing device and the remote control system are set at the same position, and the second timing device and the local control system are set at the same position; The time synchronization module is used to synchronize the time of the first timing device and the second timing device, so that the first timing device and the second timing device both start timing from a preset initial time; The first collecting device is used to collect the first time of the first timing device and the second time of the second timing device at a target time; wherein the target time is the completion time after the remote control system starts the business processing from the initial time; The data processing system is used to display the second time of the second timing device, and is also used to determine the target service delay time for the remote control system to perform service processing based on the first time and the second time.

[0025] This application determines the service delay time of the remote control system through two timing devices, effectively improving the enterprise's quality control ability of the remote control system and avoiding waste of investment in the construction of the remote control system.

[0026] The remote control system in the embodiment of the present application may be a mine remote control device, and the remote control system includes a remote control system and a local control system. The remote control system includes a second acquisition device, an operation and maintenance system, an industrial transmission network, a coding system, etc. The acquisition device (including a first acquisition device and a second acquisition device) in the embodiment of the present application is a device with an image acquisition function, such as a camera, a webcam, etc. The second acquisition device is used to acquire images of business scenes and send the images to the coding module. The coding module encodes the image. The encoded image is then transmitted to the operation and maintenance system via the industrial transmission network. The operation and maintenance system decodes the encoded image and sends the decoded image to the local processing system for business use. When the remote control system performs business processing, there will be delays. The technical purpose of the embodiment of the present application is to test the delay of the remote control system when performing business processing.

[0027] In order to measure the service delay of the above-mentioned remote control system, the embodiment of the present application sets two timing devices (a first timing device and a second timing device), wherein the first timing device and the remote control system are set at the same position, and the second timing device and the local control system are set at the same position. The same position here indicates that the distance between the first timing device and the remote control system is relatively close (less than a preset distance threshold, where the distance threshold is generally set to a few meters, such as five meters, seven meters, etc.), and the distance between the second timing device and the local control system is relatively close (less than a preset distance threshold, where the distance threshold is generally set to a few meters, such as five meters, seven meters, etc.). In the specific implementation, the timing device here can select a device such as a timing clock.

[0028] Specifically, Figure 2 As shown, the timing clock includes a local clock module, a core processing module, a display module, a power module and a time synchronization module. Among them, the local clock module is used to generate local time calculations based on the reference time after clock synchronization. The core processing module is used to drive the time synchronization module and the local clock module and the display module, and realize operation management. The time synchronization module is used to realize clock synchronization between various time synchronization modules. The main implementation methods include external time service and local time synchronization: external time service can be accurately timed through external clock sources such as Beidou and GPS; local time synchronization can use buttons, voice and other interactive units to issue time synchronization instructions, and accurately synchronize time between two or more devices through the core processing module. After the time synchronization is completed, the local clock continues to maintain the time operation calculation based on the synchronized reference time to obtain the accurate time at different times; the accuracy of the local clock should meet the time error within a certain time of no more than 1ms. The display module displays the current time of the device, and the display module must support the device time display accurate to at least ms. The power module realizes power supply to each functional module.

[0029] In actual work, the timing device, especially the timing device displayed through a display screen, generally has a timing accuracy of seconds. The timing accuracy of seconds does not meet the actual working requirements of the remote control system. In order to ensure the accuracy of the test, an adjustment device is also provided in the embodiment of the present application, and the adjustment device is connected to the timing device (including a first timing device and a second timing device). The data processing system measures the timing accuracy of the timing device. If the timing accuracy of the timing device does not meet the preset accuracy requirements of the group, the data processing system generates an adjustment instruction and sends the adjustment instruction to the adjustment device. After receiving the adjustment instruction sent by the data processing system, the adjustment device adjusts the timing accuracy of the timing device to meet the accuracy requirements. In the specific implementation, the adjustment device here includes a single-chip microcomputer, a crystal oscillator, etc.

[0030] When the first timing device and the second timing device are used to test the remote control system, the first timing device and the second timing device need to ensure that the timing time is consistent. In order to ensure that the timing time of the two is consistent, the embodiment of the present application first obtains the current third time of the first timing device and the current fourth time of the second timing device. The third time and the fourth time here include no timing time and timing time. No timing time specifically means that the timing device is not working, or the timing device is displayed as 00:00:00, etc. The timing time includes any time of normal timing. After obtaining the third time and the fourth time, it is necessary to calculate the time interval between the third time and the fourth time. When both are high-precision clocks and both are timing normally, there is a situation where the timing time (the third time and the fourth time) of the two are relatively close (less than or equal to the preset interval threshold). For this situation, the embodiment of the present application believes that the current status of the two is already in a synchronized state, so if synchronization is performed again at this time, it will cause a waste of resources. At this time, the time keeping instruction generated by the data processing system sends the time keeping instruction to the time synchronization module. The time synchronization module controls the first timing device and the second timing device to continue timing according to the current timing state of itself.

[0031] On the other hand, there may still be a situation where the timing time (third time and fourth time) between the first timing device and the second timing device is relatively different (greater than the preset interval threshold), and in this case, the first timing device and the second timing device need to be synchronized. When synchronizing the first timing device and the second timing device, the embodiment of the present application sets different synchronization methods: the first is manual synchronization: the time synchronization module generates an initial time in response to the time setting operation; controls the first timing device and the second timing device to start timing from the initial time; the second is instruction synchronization: the data processing system generates a time synchronization instruction; the time synchronization module is used to synchronize the first timing device and the second timing device according to the time control instruction, so that the first timing device and the second timing device both start timing from the preset initial time.

[0032] In the embodiment of the present application, the first timing device and the remote control system are arranged at the same position, the second timing device and the local control system are arranged at the same position, and there is a preset distance interval between the remote control system and the local control system. The distance interval here is generally tens of meters or hundreds of meters. The distance between the first timing device and the second timing device in the embodiment of the present application is relatively large, and there will be a transmission delay when data is transmitted. Therefore, when the embodiment of the present application performs time synchronization through the time synchronization instruction, the transmission delay here needs to be considered.

[0033] In the prior art, in order to measure the transmission delay, the patent (202210152151.3) provides a transmission delay measurement method: the first image data is collected by a first camera module, the first image data is sent to the display module for display, and the second image data is collected when the display module displays. The transmission delay is determined by the two times contained in the second image data. Unlike the existing patents, this application adopts multiple test methods when testing the transmission delay, and tests the selected delays respectively through multiple test methods, and calculates the transmission delay based on multiple selected delays. The multiple test methods here include a first test method (the method of the patent in the above-mentioned prior art) and a second test method (a method calculated by distance interval and transmission protocol, etc.). The transmission delay can be obtained by averaging multiple selected delays.

[0034] After obtaining the transmission delay between the first timing device and the second timing device, the data processing system needs to generate a first time synchronization instruction for the first timing device and a second time synchronization instruction for the second timing device when generating a time synchronization instruction. Specifically, the first time synchronization instruction needs to consider the preset time and the transmission delay, and the second time synchronization instruction needs to consider only the preset time. For example, the preset time received by the data processing system is 10:00:00, and the time delay for the data processing system to send an instruction to the first timing device is 00:00:30, then the synchronization time of the first timing device is 10:00:30, and the synchronization time of the second timing device is 10:00:00.

[0035] After the time of the first timing device and the second timing device are synchronized, the first timing module and the second timing module start timing at the same time when the remote control system performs business processing. The second acquisition device acquires an image of the second timing device, and the image contains the initial time of the second timing device. After acquiring the image of the second timing device, the second acquisition device sends the image to the encoding module. The encoding module encodes the image. Then the encoded image is transmitted to the operation and maintenance system through the industrial transmission network. The operation and maintenance system decodes the encoded image and sends the encoded image to the local control system, which displays the image, which contains the second time of the second timing device after the business processing. When the business processing of the remote control system is completed, the first acquisition device acquires the first time of the first timing device and the second time of the second timing device. Then, based on the first time and the second time, the target business delay time for the remote control system to perform business processing is determined.

[0036] Furthermore, in order to ensure the accuracy of the results, the embodiment of the present application needs to conduct multiple tests to obtain multiple service delays to be selected, calculate the target service delay based on the multiple service delays to be selected, and then debug the remote control system. Specifically, the average value of multiple service delays to be selected can be calculated, or the target service delay can be obtained by fitting multiple service delays to be selected. The remote control system is debugged according to the target service delay. For example, the target service delay obtained is a, and a is greater than the preset delay threshold, indicating that the delay of the remote control system is too large.

[0037] When debugging the remote control system, in order to improve the debugging efficiency. The embodiment of the present application first estimates the delay of each business device contained in the remote control system (such as the above-mentioned operation and maintenance system, encoding module, etc.). For example, by analyzing the properties of each business device (refresh rate, transmission rate, calculation rate, etc.), the sub-business delay of each business device is calculated. For example, by calculation, the sub-business delay of the operation and maintenance system is t1, the sub-business delay of the encoding module is t2, and the sub-business delay of the industrial transmission network is t3, and the calculated target business delay time is T. If T=t2, it is determined that the business device to be debugged in the remote control system is the operation and maintenance system. If T=t1, it is determined that the business device to be debugged in the remote control system is the encoding module. If T=t3, it is determined that the business device to be debugged in the remote control system is the industrial transmission network. If T=t1+t2, it is determined that the business device to be debugged in the remote control system is the operation and maintenance system and the encoding module. If T=t1+t3, it is determined that the business device to be debugged in the remote control system is the operation and maintenance system and the industrial transmission network. If T=t2+t3, it is determined that the business equipment to be debugged in the remote control system is the encoding module and the industrial transmission network. If T=t1+t2+t3, it is determined that the business equipment to be debugged in the remote control system is the operation and maintenance system, the encoding module and the industrial transmission network.

[0038] After the service equipment to be debugged is determined, it can be adjusted or replaced to reduce the target service delay time of the remote control system.

[0039] Figure 3 A flow chart of a parameter testing method for a remote control system provided by an embodiment of the present application is shown, and a parameter testing device for a remote control system is applied. The remote control system includes a remote control system and a local control system; the parameter testing device includes: a first timing device, a second timing device, a time synchronization module, a first acquisition device and a data processing system; there is a preset distance interval between the remote control system and the local control system; the first timing device and the remote control system are arranged at the same position, and the second timing device and the local control system are arranged at the same position; the method includes; wherein the method includes steps S101-S104; specifically: S101, the time synchronization module performs time synchronization on the first timing device and the second timing device, so that the first timing device and the second timing device both start timing from a preset initial time; S102, the first collecting device collects the first time of the first timing device and the second time of the second timing device at a target time; wherein the target time is the completion time after the remote control system starts the business processing from the initial time; S103: The data processing system displays the second time of the second timing device, and determines the target service delay time for service processing by the remote control system according to the first time and the second time.

[0040] The time synchronization module synchronizes the time of the first timing device and the second timing device so that both the first timing device and the second timing device start timing from a preset initial time, including: The time synchronization module generates an initial time in response to the time setting operation; controls the first timing device and the second timing device to start timing with the initial time as the starting point; Alternatively, the data processing system generates a time control instruction according to the current third time of the first timing device and the current fourth time of the second timing device; The time synchronization module performs time synchronization on the first timing device and the second timing device according to the time control instruction, so that both the first timing device and the second timing device start timing with a preset initial time as a starting point.

[0041] The time control instructions include time keeping instructions and time synchronization instructions; The data processing system generates a time control instruction according to the current third time of the first timing device and the current fourth time of the second timing device, including: If the interval between the third time and the fourth time is less than or equal to a preset interval threshold, a time keeping instruction is generated; wherein the time keeping instruction is used to control the first timing device and the second timing device to maintain their own timing states; If the interval between the third time and the fourth time is greater than a preset interval threshold, a time synchronization instruction is generated; wherein the time synchronization instruction is used to control the first timing device and the second timing device to start timing from a preset initial time.

[0042] If the interval between the third time and the fourth time is greater than a preset interval threshold, a time synchronization instruction is generated; wherein the time synchronization instruction is used to control the first timing device and the second timing device to start timing from a preset initial time, including: determining a transmission delay between the first timing device and the second timing device; Generate a first time synchronization instruction for the first timing device according to the preset time and the transmission delay; wherein the first time synchronization instruction is used to control the first timing device to start timing as a preset initial time; A second time synchronization instruction for the second timing device is generated according to the preset time, wherein the second time synchronization instruction is used to control the second timing device to start timing with the preset initial time as the starting point.

[0043] The parameter testing device of the remote control system further comprises: an adjustment device; the adjustment device is connected to the first timing device and the second timing device respectively; The data processing system detects a first timing accuracy of the first timing device and a second timing accuracy of the second timing device; If the first timing accuracy or the second timing accuracy does not meet the preset accuracy requirement, the data processing system sends an adjustment instruction to the adjustment device; The adjusting device adjusts the accuracy of the first timing device or the second timing device according to the adjusting instruction, so that the first timing accuracy and the second timing accuracy both meet the accuracy requirement.

[0044] The first acquisition device acquires the first time of the first timing device and the second time of the second timing device at the target time; wherein the target time is the completion time after the remote control system starts the business processing from the initial time, including: The first acquisition device acquires a plurality of the first times and the corresponding second times; The data processing system determines a target service delay time for service processing by the remote control system according to a plurality of the first times and the second times.

[0045] The data processing system determines the sub-service delay of each service device in the remote control system; The service device to be debugged in the remote control system is determined according to the target service delay time and the sub-service delay.

[0046] like Figure 4 As shown, an embodiment of the present application provides an electronic device for executing the parameter testing method of the remote control system in the present application, the device includes a memory, a processor, a bus, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the parameter testing method of the remote control system when executing the computer program.

[0047] Specifically, the above-mentioned memory and processor may be general-purpose memory and processor, which are not specifically limited here. When the processor runs the computer program stored in the memory, the above-mentioned parameter testing method of the remote control system can be executed.

[0048] Corresponding to the parameter testing method of the remote control system in the present application, an embodiment of the present application also provides a computer-readable storage medium, on which a computer program is stored. When the computer program is run by a processor, the steps of the above-mentioned parameter testing method of the remote control system are executed.

[0049] Specifically, the storage medium can be a general storage medium, such as a mobile disk, a hard disk, etc. When the computer program on the storage medium is run, the above-mentioned parameter testing method of the remote control system can be executed.

[0050] In the embodiments provided in the present application, it should be understood that the disclosed systems and methods can be implemented in other ways. The system embodiments described above are merely schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some communication interfaces, indirect coupling or communication connection of systems or units, which can be electrical, mechanical or other forms.

[0051] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, and may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0052] In addition, each functional unit in the embodiments provided in the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.

[0053] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a personal computer, server, or network device, etc.) to execute all or part of the steps of the method described in each embodiment of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM), random access memory (RAM), disk or optical disk, and other media that can store program codes.

[0054] It should be noted that similar numbers and letters represent similar items in the following figures. Therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description and are not to be understood as indicating or implying relative importance.

[0055] Finally, it should be noted that the above-described embodiments are only specific implementation methods of the present application, which are used to illustrate the technical solutions of the present application, rather than to limit them. The protection scope of the present application is not limited thereto. Although the present application is described in detail with reference to the above-mentioned embodiments, ordinary technicians in the field should understand that any technician familiar with the technical field can still modify the technical solutions recorded in the above-mentioned embodiments within the technical scope disclosed in the present application, or can easily think of changes, or make equivalent replacements for some of the technical features therein; and these modifications, changes or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present application. They should all be included in the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the protection scope of the claims.

Claims

1. A parameter testing device for a remote control system, characterized in that: The remote control system includes a remote control system and a local control system; The parameter testing device comprises: a first timing device, a second timing device, a time synchronization module, a first acquisition device and a data processing system; there is a preset distance interval between the remote control system and the local control system; during parameter acquisition, the first timing device and the remote control system are arranged at the same position, and the second timing device and the local control system are arranged at the same position; The time synchronization module is used to synchronize the time of the first timing device and the second timing device, so that the first timing device and the second timing device both start timing from a preset initial time; The first collecting device is used to collect the first time of the first timing device and the second time of the second timing device at a target time; wherein the target time is the completion time after the remote control system starts the business processing from the initial time; The data processing system is used to display the second time of the second timing device, and is also used to determine the target service delay time for the remote control system to perform service processing based on the first time and the second time.

2. The parameter testing device for a remote control system according to claim 1, characterized in that: The time synchronization module is used to synchronize the time of the first timing device and the second timing device so that both the first timing device and the second timing device start timing from a preset initial time, including: The time synchronization module is used to generate an initial time in response to a time setting operation; and control the first timing device and the second timing device to start timing with the initial time as a starting point; Alternatively, the data processing system is used to generate a time control instruction according to the current third time of the first timing device and the current fourth time of the second timing device; The time synchronization module is used to synchronize the first timing device and the second timing device according to the time control instruction, so that the first timing device and the second timing device both start timing with a preset initial time as the starting point.

3. The parameter testing device for a remote control system according to claim 2, characterized in that: The time control instructions include time keeping instructions and time synchronization instructions; The data processing system is used to generate a time control instruction according to the current third time of the first timing device and the current fourth time of the second timing device, including: If the interval between the third time and the fourth time is less than or equal to a preset interval threshold, a time keeping instruction is generated; wherein the time keeping instruction is used to control the first timing device and the second timing device to maintain their own timing states; If the interval between the third time and the fourth time is greater than a preset interval threshold, a time synchronization instruction is generated; wherein the time synchronization instruction is used to control the first timing device and the second timing device to start timing from a preset initial time.

4. The parameter testing device for a remote control system according to claim 3, characterized in that: If the interval between the third time and the fourth time is greater than a preset interval threshold, a time synchronization instruction is generated; wherein the time synchronization instruction is used to control the first timing device and the second timing device to start timing from a preset initial time, including: determining a transmission delay between the first timing device and the second timing device; Generate a first time synchronization instruction for the first timing device according to the preset time and the transmission delay; wherein the first time synchronization instruction is used to control the first timing device to start timing as a preset initial time; A second time synchronization instruction for the second timing device is generated according to the preset time, wherein the second time synchronization instruction is used to control the second timing device to start timing with the preset initial time as the starting point.

5. The parameter testing device for a remote control system according to claim 1, characterized in that: The parameter testing device of the remote control system further comprises: an adjustment device; the adjustment device is connected to the first timing device and the second timing device respectively; The data processing system is used to detect a first timing accuracy of the first timing device and a second timing accuracy of the second timing device; If the first timing accuracy or the second timing accuracy does not meet the preset accuracy requirement, the data processing system is used to send an adjustment instruction to the adjustment device; The adjustment device is used to adjust the accuracy of the first timing device or the second timing device according to the adjustment instruction, so that the first timing accuracy and the second timing accuracy both meet the accuracy requirement.

6. The parameter testing device for a remote control system according to claim 1, characterized in that: The first collecting device is used to collect the first time of the first timing device and the second time of the second timing device at a target time; wherein the target time is the completion time after the remote control system starts the business processing from the initial time, including: The first acquisition device is used to obtain a plurality of the first times and the corresponding second times; The data processing system is used to determine a target service delay time for service processing by the remote control system according to a plurality of the first times and the second times.

7. The parameter testing device for a remote control system according to claim 1, characterized in that: The data processing system is further used to debug the remote control system based on the target service delay time so that the remote control system meets service requirements.

8. A parameter testing method for a remote control system, characterized in that: A parameter testing device applied to a remote control system, wherein the remote control system comprises a remote control system and a local control system; The parameter testing device comprises: a first timing device, a second timing device, a time synchronization module, a first acquisition device and a data processing system; there is a preset distance interval between the remote control system and the local control system; the first timing device and the remote control system are arranged at the same position, and the second timing device and the local control system are arranged at the same position; the method comprises: The time synchronization module performs time synchronization on the first timing device and the second timing device, so that both the first timing device and the second timing device start timing from a preset initial time; The first collecting device collects the first time of the first timing device and the second time of the second timing device at the target time; wherein the target time is the completion time after the remote control system starts the business processing from the initial time; The data processing system displays the second time of the second timing device, and determines the target service delay time for the remote control system to perform service processing according to the first time and the second time.

9. An electronic device, characterized in that: include: A processor, a memory and a bus, wherein the memory stores machine-readable instructions executable by the processor, and when the electronic device is running, the processor and the memory communicate via the bus, and when the machine-readable instructions are executed by the processor, the steps of the parameter testing method of the remote control system as described in claim 8 are performed.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the parameter testing method of the remote control system as claimed in claim 8 are executed.