Substation starting auditing method and device and storage medium
By modeling the substation equipment, simulating the wiring diagram and conducting simulation review of the verification and startup process, the problems of large audit workload and safety accident risks caused by the complex startup steps of the substation are solved, and efficient and accurate startup audit is achieved.
CN119740398APending Publication Date: 2025-04-01GUANGDONG POWER GRID CO LTD +1
0 Cites 0 Cited by
Patent Information
- Application Number
- CN202411951709.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-27
- Publication Date
- 2025-04-01
AI Technical Summary
Technical Problem
The startup steps of the substation are complex, resulting in large workloads of manual review, which is prone to errors and leakage due to visual fatigue or memory deviations, increasing the risk of safety accidents.
Method used
By modeling the equipment in the substation, an electrical interval model, a simulation wiring diagram, and a verification wiring diagram are generated. If passed, a simulation review of the startup process will be carried out to provide an automated audit framework.
Benefits of technology
It greatly reduces the workload of manual review, improves the accuracy and efficiency of review, effectively prevents safety accidents during the start-up of the substation, and ensures the safety of startup.
✦ Generated by Eureka AI based on patent content.
Abstract
The invention discloses a starting auditing method and device for a transformer substation and a storage medium, and the method comprises the steps: carrying out the modeling of primary equipment in the transformer substation, and obtaining an electrical interval model; simulating wiring of primary equipment according to the electrical interval model so as to construct a primary wiring diagram for the transformer substation; verifying the primary wiring diagram according to the equipment specification of the transformer substation; and if the primary wiring diagram passes the verification, simulating the process of starting the transformer substation according to the primary wiring diagram so as to check the process of starting the transformer substation. According to the embodiment of the invention, a user is automatically assisted in auditing the starting process of the transformer substation, and the auditing accuracy of the starting process of the transformer substation is improved, so that the auditing efficiency of the starting process of the transformer substation is greatly improved, safety accidents caused in the starting process of the transformer substation are effectively prevented, and the user experience is improved. And the starting safety of the substation is ensured.