Efficient reaction kettle for magnetorheological fluid production

By introducing pre-stirring components and secondary stirring components into the reactor for magnetorheological liquid production, and adopting a multi-stage stirring structure, the problem of insufficient suspension uniformity of magnetorheological liquid is solved, and the suspension uniformity is significantly improved.

CN222034755UActive Publication Date: 2024-11-22GUANGZHOU PEGARUN SPECIAL LUBRICANT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421116779.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-21
Publication Date
2024-11-22
Estimated Expiration
2034-05-21

AI Technical Summary

Technical Problem

Common reactors for magnetorheological fluid production lack multi-stage stirring structure, resulting in the problem that the suspension uniformity of magnetorheological fluid needs to be improved.

Method used

A high-efficiency reactor is designed, including a pre-mixing assembly and a secondary stirring assembly. The pre-mixing assembly is used to pre-mix the vapor phase silica and hydroxy iron powder. The secondary stirring assembly is used to stir the synthetic oil and solid raw materials. The grade stirring structure improves suspension uniformity.

Benefits of technology

Through multi-stage stirring, the suspension uniformity of the magnetorheological liquid is significantly improved, and the problem of insufficient suspension uniformity in common reactors is solved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222034755U_ABST
    Figure CN222034755U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of magnetorheological fluid production, in particular to an efficient reaction kettle for magnetorheological fluid production. The technical problems that according to a common reaction kettle for magnetorheological fluid production, raw materials are usually fed into a container, all the raw materials are stirred through a stirring structure, a multi-stage stirring structure is lacked, and consequently the suspension uniformity of magnetorheological fluid needs to be improved are solved. According to the technical scheme, the efficient reaction kettle for producing the magnetorheological fluid comprises a reaction kettle main body. According to the device, fumed silica and hydroxyl iron powder are pre-stirred through the pre-stirring assembly, then synthetic oil and solid raw materials are stirred through the secondary stirring assembly, and the suspension uniformity of magnetorheological fluid is improved through multi-stage stirring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of magnetorheological fluid production, in particular to a high-efficiency reaction kettle for magnetorheological fluid production. Background Art

[0002] Magnetorheological fluid is a smart material that can controllably change its properties under the action of an external magnetic field. Magnetorheological fluid is a two-phase fluid. In the absence of an external magnetic field, magnetorheological fluid will behave like a Newtonian fluid and its shear strength increases linearly with the increase of shear rate. Under the action of an external magnetic field, the magnetic particles in the magnetorheological fluid form a fibrous structure along the direction of the magnetic field lines.

[0003] Common reactors for producing magnetorheological fluids usually feed raw materials into a container and stir all the raw materials through a stirring structure. The lack of a multi-stage stirring structure leads to the problem that the suspension uniformity of the magnetorheological fluid needs to be improved.

[0004] Therefore, the problem that the reactor for producing the magnetorheological fluid lacks a multi-stage stirring structure, resulting in the suspension uniformity of the magnetorheological fluid to be improved, needs to be solved urgently to improve the usage scenario. Utility Model Content

[0005] In order to overcome the problem that the common reactor for producing magnetorheological fluid lacks a multi-stage stirring structure, the suspension uniformity of the magnetorheological fluid needs to be improved.

[0006] The technical solution of the utility model is: a high-efficiency reactor for magnetorheological fluid production, comprising a reactor body, a first fixed pipe is installed on the top of the left end of the reactor body, a solenoid valve is arranged in the middle of the first fixed pipe, the upper end of the first fixed pipe is connected with a processing tank, the upper end of the front side of the processing tank is connected with a first feed pipe, the upper end of the back side of the processing tank is installed with a second feed pipe, a pre-stirring component is arranged in the middle of the processing tank, a secondary stirring component is connected in the middle of the reactor body, a mounting frame is arranged on the right side of the reactor body, and a conveying component is installed on the mounting frame.

[0007] Preferably, the fumed silica and hydroxy iron powder are pre-mixed by a pre-mixing component, and then the synthetic oil and solid raw materials are mixed by a secondary mixing component. The suspension uniformity of the magnetorheological fluid is improved by multi-stage mixing to solve the problem that the common reactor for magnetorheological fluid production usually feeds the raw materials into the container and all the raw materials are mixed by a mixing structure, but lacks a multi-stage mixing structure, resulting in the problem that the suspension uniformity of the magnetorheological fluid needs to be improved.

[0008] Preferably, the pre-mixing assembly includes a first motor and a first coupling; the first motor is installed in the middle position of the upper end of the processing tank, and the lower end of the first motor is connected to the first coupling. After the gas-phase silica and hydroxyl iron powder are respectively added through the first feed pipe and the second feed pipe, the first motor is started and the first coupling rotates.

[0009] Preferably, the pre-mixing assembly includes a rotating rod and a stirring rod; a rotating rod is installed at the bottom of the first coupling, and a plurality of stirring rods are evenly arranged on the outside of the rotating rod. The rotation of the first coupling drives the rotating rod and the stirring rod to rotate, thereby pre-mixing the gas-phase silica and hydroxyl iron powder.

[0010] Preferably, the secondary stirring assembly includes a second motor and a second coupling; a second motor is arranged in the middle of the top of the reactor body, and a second coupling is connected to the bottom of the second motor. When the second motor is started, the second coupling rotates.

[0011] Preferably, the secondary stirring assembly includes a connecting rod and stirring blades; a connecting rod is installed at the lower end of the second coupling, and a number of stirring blades are evenly installed on the outside of the connecting rod. The second coupling drives the connecting rod and the stirring blades to rotate, and the stirring blades complete the stirring of the synthetic oil and the solid raw materials, thereby improving the suspension uniformity of the magnetorheological fluid through multi-stage stirring.

[0012] Preferably, the delivery assembly includes a delivery pump and a liquid inlet pipe; the delivery pump is connected to the top of the right end of the mounting frame, a liquid inlet pipe is provided at the front end of the delivery pump, the front end of the liquid inlet pipe is connected to the external oil supply pipeline, and the delivery pump is started.

[0013] Preferably, the conveying assembly includes a second fixed pipe and a connecting pipe; a second fixed pipe is arranged near the right end of the top of the reactor body, and the top of the delivery pump is connected to the upper end of the second fixed pipe through the connecting pipe, and the synthetic oil is pumped into the reactor body through the connecting pipe and the second fixed pipe.

[0014] Beneficial effects of the utility model:

[0015] 1. The pre-stirring component is used to pre-stir the fumed silica and hydroxy iron powder, and then the synthetic oil and solid raw materials are stirred by the secondary stirring component. The suspension uniformity of the magnetorheological fluid is improved by multi-stage stirring to solve the problem that the common reactor for magnetorheological fluid production usually feeds the raw materials into the container and stirs all the raw materials by the stirring structure, but lacks a multi-stage stirring structure, resulting in the problem that the suspension uniformity of the magnetorheological fluid needs to be improved;

[0016] 2. After respectively feeding the fumed silica and hydroxy iron powder through the first feeding pipe and the second feeding pipe, start the first motor and the first coupling to rotate. The rotation of the first coupling drives the rotating rod and the stirring rod to rotate, and pre-mixes the fumed silica and the hydroxy iron powder. Then, open the solenoid valve and complete the pumping of the synthetic oil. Start the second motor and the second coupling to rotate. The second coupling drives the connecting rod and the stirring blade to rotate. The stirring blade completes the mixing of the synthetic oil and the solid raw materials, and improves the suspension uniformity of the magnetorheological fluid through multi-stage mixing. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 What is shown is a three-dimensional structural schematic diagram of a high-efficiency reaction kettle for producing magnetorheological fluid of the utility model;

[0018] Figure 2 The present invention shows a schematic diagram of the installation structure of a high-efficiency reaction kettle pre-stirring assembly for magnetorheological fluid production;

[0019] Figure 3 Shown is a schematic diagram of the installation structure of a secondary stirring assembly of a high-efficiency reactor for magnetorheological fluid production of the utility model;

[0020] Figure 4 What is shown is a schematic diagram of the installation structure of a high-efficiency reactor conveying component for magnetorheological fluid production of the utility model.

[0021] In the figure: 1. Reactor body; 2. First fixed pipe; 3. Solenoid valve; 4. Processing tank; 5. First feed pipe; 6. Second feed pipe; 7. Pre-mixing assembly; 8. Secondary mixing assembly; 9. Mounting frame; 10. Conveying assembly; 701. First motor; 702. First coupling; 703. Rotating rod; 704. Stirring rod; 801. Second motor; 802. Second coupling; 803. Connecting rod; 804. Stirring blade; 1001. Conveying pump; 1002. Liquid inlet pipe; 1003. Second fixed pipe; 1004. Connecting pipe. DETAILED DESCRIPTION

[0022] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0023] See also Figure 1The utility model provides an embodiment: a high-efficiency reactor for magnetorheological fluid production, including a reactor body 1, a first fixed pipe 2 is installed on the top of the left end of the reactor body 1, a solenoid valve 3 is arranged in the middle of the first fixed pipe 2, a treatment tank 4 is connected to the upper end of the first fixed pipe 2, a first feed pipe 5 is connected to the upper end of the front side of the treatment tank 4, a second feed pipe 6 is installed at the upper end of the back side of the treatment tank 4, a pre-stirring component 7 is arranged in the middle of the treatment tank 4, a secondary stirring component 8 is connected in the middle of the reactor body 1, a mounting frame 9 is arranged on the right side of the reactor body 1, and a conveying component 10 is installed on the mounting frame 9.

[0024] See also Figure 2 In this embodiment, the pre-mixing component 7 includes a first motor 701 and a first coupling 702; the first motor 701 is installed in the middle position of the upper end of the processing tank 4, and the lower end of the first motor 701 is connected to the first coupling 702. After the fumed silica and hydroxy iron powder are respectively added through the first feeding pipe 5 and the second feeding pipe 6, the first motor 701 is started, and the first coupling 702 rotates. The pre-mixing component 7 includes a rotating rod 703 and a stirring rod 704; the rotating rod 703 is installed at the bottom of the first coupling 702, and a plurality of stirring rods 704 are evenly arranged on the outside of the rotating rod 703. The rotation of the first coupling 702 drives the rotating rod 703 and the stirring rod 704 to rotate, so as to pre-mix the fumed silica and the hydroxy iron powder.

[0025] See also Figure 3 In this embodiment, the secondary stirring assembly 8 includes a second motor 801 and a second coupling 802; a second motor 801 is arranged at the middle position of the top of the reactor body 1, and a second coupling 802 is connected to the bottom of the second motor 801. When the second motor 801 is started, the second coupling 802 rotates, and the secondary stirring assembly 8 includes a connecting rod 803 and a stirring blade 804; a connecting rod 803 is installed at the lower end of the second coupling 802, and a plurality of stirring blades 804 are evenly installed on the outside of the connecting rod 803. The second coupling 802 drives the connecting rod 803 and the stirring blade 804 to rotate, and the stirring blade 804 completes the stirring of the synthetic oil and the solid raw material, and the suspension uniformity of the magnetorheological fluid is improved through multi-stage stirring.

[0026] See also Figure 4In this embodiment, the delivery component 10 includes a delivery pump 1001 and a liquid inlet pipe 1002; the delivery pump 1001 is connected to the top of the right end of the mounting frame 9, and the front end of the delivery pump 1001 is provided with a liquid inlet pipe 1002, and the front end of the liquid inlet pipe 1002 is connected to the external oil supply pipeline. The delivery pump 1001 is started, and the delivery component 10 includes a second fixed pipe 1003 and a connecting pipe 1004; a second fixed pipe 1003 is provided near the right end of the top of the reactor body 1, and the top of the delivery pump 1001 is connected to the upper end of the second fixed pipe 1003 through the connecting pipe 1004, and the synthetic oil is pumped into the reactor body 1 through the connecting pipe 1004 and the second fixed pipe 1003.

[0027] During operation, after the fumed silica and hydroxy iron powder are respectively fed in through the first feeding pipe 5 and the second feeding pipe 6, the first motor 701 is started, the first coupling 702 rotates, and the rotation of the first coupling 702 drives the rotating rod 703 and the stirring rod 704 to rotate, and the fumed silica and the hydroxy iron powder are pre-mixed. Then, the solenoid valve 3 is opened to allow the pre-mixed raw materials to enter the reactor body 1, and the delivery pump 1001 is started to pump the synthetic oil into the reactor body 1 through the connecting pipe 1004 and the second fixed pipe 1003. Then, the second motor 801 is started, the second coupling 802 rotates, and the second coupling 802 drives the connecting rod 803 and the stirring blade 804 to rotate. The stirring blade 804 completes the stirring of the synthetic oil and the solid raw materials, and the suspension uniformity of the magnetorheological fluid is improved through multi-stage stirring.

[0028] Through the above steps, the gas phase silica and hydroxy iron powder are pre-mixed by the pre-mixing component 7, and then the synthetic oil and the solid raw materials are mixed by the secondary mixing component 8. The suspension uniformity of the magnetorheological fluid is improved by multi-stage mixing to solve the problem that the common reactor for magnetorheological fluid production usually feeds the raw materials into the container and all the raw materials are mixed by the mixing structure, but lacks a multi-stage mixing structure, resulting in the problem that the suspension uniformity of the magnetorheological fluid needs to be improved.

[0029] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of those skilled in the art without departing from the purpose of the present invention.

Claims

1. A high-efficiency reactor for producing magnetorheological fluid, comprising a reactor body (1), characterized in that: A first fixed pipe (2) is installed at the top of the left end of the reactor body (1), a solenoid valve (3) is arranged in the middle of the first fixed pipe (2), the upper end of the first fixed pipe (2) is connected to a processing tank (4), the upper end of the front side of the processing tank (4) is connected to a first feed pipe (5), the upper end of the back side of the processing tank (4) is installed with a second feed pipe (6), the middle of the processing tank (4) is provided with a pre-stirring component (7), the middle of the reactor body (1) is connected with a secondary stirring component (8), a mounting frame (9) is arranged on the right side of the reactor body (1), and a conveying component (10) is installed on the mounting frame (9).

2. The high-efficiency reactor for producing magnetorheological fluid according to claim 1, characterized in that: The pre-mixing assembly (7) comprises a first motor (701) and a first coupling (702); the first motor (701) is installed at the middle position of the upper end of the processing tank (4), and the lower end of the first motor (701) is connected to the first coupling (702).

3. The high-efficiency reactor for producing magnetorheological fluid according to claim 2, characterized in that: The pre-mixing assembly (7) comprises a rotating rod (703) and a stirring rod (704); the rotating rod (703) is installed at the bottom of the first coupling (702), and a plurality of stirring rods (704) are evenly arranged on the outside of the rotating rod (703).

4. The high-efficiency reactor for producing magnetorheological fluid according to claim 1, characterized in that: The secondary stirring assembly (8) comprises a second motor (801) and a second coupling (802); the second motor (801) is arranged at the middle position of the top of the reactor body (1), and the bottom of the second motor (801) is connected to the second coupling (802).

5. The high-efficiency reactor for producing magnetorheological fluid according to claim 4, characterized in that: The secondary stirring assembly (8) comprises a connecting rod (803) and stirring blades (804); the connecting rod (803) is installed at the lower end of the second coupling (802), and a plurality of stirring blades (804) are evenly installed on the outer side of the connecting rod (803).

6. The high-efficiency reactor for producing magnetorheological fluid according to claim 1, characterized in that: The delivery assembly (10) comprises a delivery pump (1001) and a liquid inlet pipe (1002); the delivery pump (1001) is connected to the top of the right end of the mounting frame (9); the front end of the delivery pump (1001) is provided with a liquid inlet pipe (1002); and the front end of the liquid inlet pipe (1002) is connected to an external oil supply pipeline.

7. The high-efficiency reactor for producing magnetorheological fluid according to claim 6, characterized in that: The conveying assembly (10) comprises a second fixed pipe (1003) and a connecting pipe (1004); the second fixed pipe (1003) is arranged near the right end of the top of the reactor body (1), and the top of the conveying pump (1001) is connected to the upper end of the second fixed pipe (1003) via the connecting pipe (1004).