Tunnel-first and station-second overground and underground communicating structure

By using rotary excavators to drill holes and pour concrete into connecting holes during the subway construction of tunnels and then stations, the problem of difficulty in outbound earth transportation in the central urban area of ​​the city was solved, rapid outbound earth transportation of foundation pits was achieved, and construction efficiency was improved.

CN222044272UActive Publication Date: 2024-11-22GUANGZHOU METRO CONSTR MANAGEMENT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420638068.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-29
Publication Date
2024-11-22
Estimated Expiration
2034-03-29

AI Technical Summary

Technical Problem

During the subway construction in the urban central urban area, it is difficult to transport the earth from the foundation pit of the tunnel first and then the station, especially the strict environmental noise control, which leads to major defects in the construction.

Method used

The structure of tunneling and then stationing above and underground is adopted. The reserving hole is formed by drilling holes by rotary excavator, and the earth-cutting pipe and grouting pipe are installed. The concrete is cast and sealed to form communication holes. The shield tunnel has been constructed. Earth is transported outside.

Benefits of technology

It has achieved convenient and rapid transportation of soil from foundation pits, solved the problem of difficult transportation of soil from earth, and improved construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222044272U_ABST
    Figure CN222044272U_ABST
Patent Text Reader

Abstract

The utility model discloses a tunnel-first station-second overground and underground communicating structure, which relates to the field of subway station construction and comprises a duct piece positioned on the outer side of a tunnel and a preformed hole formed after drilling by a rotary drilling machine, the rotary drilling machine is used for drilling holes, the preformed holes are formed after drilling, the earthwork discharging pipes are placed in the preformed holes, the grouting pipes are arranged in the preformed holes, gaps are reserved between the bottom ends of the earthwork discharging pipes and the hole bottoms of the preformed holes, and the centers of the earthwork discharging pipes correspond to the middle positions of the two annular pipe pieces. The rotary drilling machine is used for drilling holes, the preformed holes are formed after drilling, and the earthwork discharging pipes are placed in the preformed holes; a water drill is adopted in a tunnel hole to break a shield segment below an earthwork discharging pipe, after the segment is broken, a soil body and a concrete layer below the earthwork discharging pipe are broken, a communicating hole communicating with the earthwork discharging pipe is formed, and earthwork obtained after foundation pit excavation falls onto a transport vehicle in the tunnel through the earthwork discharging pipe and the communicating hole. Earthwork is transported outwards through the constructed shield tunnel, so that foundation pit earthwork is transported outwards more conveniently and quickly.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of subway station construction, and in particular relates to a ground-underground connecting structure with a tunnel first and a station later. Background Art

[0002] In the construction of urban subway projects, the large-scale demolition of urban village shantytowns involves the conversion of collective land to agricultural use, the demonstration and selection of resettlement housing plans, as well as rush construction and illegal construction. The demolition workload is large, the demolition is difficult, and the land cannot be demolished and handed over on time. As a result, stations and sections cannot be started as planned, and are even seriously delayed, affecting the goal of achieving the node of full line connection.

[0003] For example, Chinese patent publication number CN110424969 B discloses an open-cut station construction method of tunneling first and then stationing. The shield machine is used to excavate through the station range first, which solves the problem that the station is affected by land acquisition and demolition and does not have the conditions for construction, and cannot provide the starting and receiving conditions for the shield machine; it solves the problem that the section can be penetrated first and the station can be constructed later.

[0004] However, the above patent does not address the problem of difficulty in transporting earth from station foundation pits, especially in construction in central urban areas where environmental noise control is relatively strict and the time for transporting earth is limited, resulting in major defects in the construction of station foundation pits with tunnels first and stations later.

[0005] Therefore, we propose a tunnel-first, station-later ground-underground connecting structure to solve the above problems. Utility Model Content

[0006] The above-mentioned patent does not address the problem of difficulty in transporting earthwork from station foundation pits, especially in construction in city center areas, where environmental noise control is relatively strict and the time for transporting earthwork is limited, resulting in the problem that the construction of station foundation pits with tunnels first and stations later still has major defects. The utility model provides a ground-underground connecting structure with tunnels first and stations later.

[0007] The utility model adopts a solution to solve the technical problem: a ground and underground connecting structure with a tunnel first and a station later, comprising a pipe segment located outside the tunnel and a reserved hole formed by drilling with a rotary drilling machine.

[0008] It also includes an earthwork feeding pipe and N grouting pipes. The earthwork feeding pipe is located in the reserved hole, and a gap is left between the bottom end of the earthwork feeding pipe and the bottom of the reserved hole. The center of the earthwork feeding pipe corresponds to the middle position of the two ring segments.

[0009] N grouting pipes are located in the reserved holes and are arranged around the earthwork feeding pipe.

[0010] After pouring concrete through the grouting pipe, the bottom of the reserved hole is sealed, and a concrete layer is formed after solidification.

[0011] The bottom end of the earthwork feeding pipe is located in the concrete layer.

[0012] A connecting hole is provided at a position of the pipe segment corresponding to the earthwork feeding pipe. The connecting hole passes through the soil body and extends to the concrete layer and is connected with the inner cavity of the earthwork feeding pipe, so that the material in the earthwork feeding pipe can fall into the pipe segment through the connecting hole.

[0013] Preferably, the diameter of the reserved hole is 8-12 cm larger than the diameter of the earthwork feeding pipe.

[0014] Preferably, a gap of 8-12 cm is left between the bottom end of the earthwork feeding pipe and the bottom of the reserved hole.

[0015] Preferably, the earthwork feeding pipe is assembled from multiple steel pipes.

[0016] Preferably, the thickness of the concrete layer is 40-60 cm.

[0017] Preferably, backfill soil is provided in the reserved hole, and the backfill soil is located outside the earth feed pipe.

[0018] Compared with the prior art, the beneficial effects of the utility model are:

[0019] 1. The utility model uses a rotary drilling machine to drill a hole, and a reserved hole is formed after drilling. An earth feeding pipe is placed in the reserved hole, and the shield pipe segment below the earth feeding pipe is broken by a water drill in the tunnel hole. After breaking the pipe segment, the soil and concrete layer below the earth feeding pipe are broken to form a connecting hole connected with the earth feeding pipe. The earth after the foundation pit excavation falls through the earth feeding pipe and the connecting hole to the transport vehicle in the tunnel, and the earth is transported out of the foundation pit by using the completed shield tunnel, making it more convenient and quick to transport the foundation pit earth out. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a schematic diagram of the structure of the utility model;

[0021] Figure 2 For this utility model Figure 1 The enlarged structural diagram at A in the middle;

[0022] Figure 3 For this utility model Figure 1 Schematic diagram of the enlarged structure from top view.

[0023] In the figure: 1 pipe segment, 2 reserved hole, 3 earth discharge pipe, 4 grouting pipe, 5 concrete layer, 6 soil body, 7 connecting hole. DETAILED DESCRIPTION

[0024] The utility model is further described below in conjunction with the accompanying drawings and embodiments.

[0025] See also Figure 1-3 The utility model provides a technical solution for the ground-underground connecting structure of tunnel first and station later:

[0026] Embodiment 1:

[0027] according to Figure 1-3 As shown, it includes a segment 1 located outside the tunnel and a reserved hole 2 formed after drilling by a rotary drilling machine. The drilling depth of the reserved hole 2 is the shield tunnel top elevation plus 20 cm.

[0028] It also includes an earthwork discharge pipe 3 and N grouting pipes 4. The earthwork discharge pipe 3 is assembled from multiple steel pipes. The earthwork discharge pipe 3 is located in the reserved hole 2, and a gap is left between the bottom end of the earthwork discharge pipe 3 and the bottom of the reserved hole 2. A gap of 8-12 cm is left between the bottom end of the earthwork discharge pipe 3 and the bottom of the reserved hole 2. In this embodiment, the reserved gap is 10 cm.

[0029] The diameter of the reserved hole 2 is 8-12 cm larger than the diameter of the earthwork feeding pipe 3. In this embodiment, the diameter of the reserved hole 2 is 10 cm larger than the diameter of the earthwork feeding pipe 3, ensuring that the earthwork feeding pipe 3 can be smoothly lowered into place, and the center of the earthwork feeding pipe 3 corresponds to the middle position of the two ring segments 1.

[0030] In this embodiment, the number of grouting pipes 4 is four, and the four grouting pipes 4 are located in the reserved hole 2 and are arranged around the earthwork feeding pipe 3. C15 concrete is poured into the bottom of the reserved hole 2 through the grouting pipes 4.

[0031] After pouring concrete through the grouting pipe 4, the bottom of the reserved hole 2 is sealed, and a concrete layer 5 is formed after solidification. The thickness of the concrete layer 5 is 40-60 cm. In this embodiment, the thickness of the concrete layer 5 is 50 cm.

[0032] The bottom end of the earthwork feeding pipe 3 is located in the concrete layer 5 , and the earthwork feeding pipe 3 is fixed by the concrete layer 5 to ensure the stability of the earthwork feeding pipe 3 in the reserved hole 2 .

[0033] A connecting hole 7 is provided at a position of the pipe segment 1 corresponding to the earthwork feeding pipe 3 . The connecting hole 7 passes through the soil 6 and extends to the concrete layer 5 and is connected to the inner cavity of the earthwork feeding pipe 3 , so that the material in the earthwork feeding pipe 3 can fall into the pipe segment 1 through the connecting hole 7 .

[0034] Backfill soil is arranged in the reserved hole 2 , and the backfill soil is located outside the earthwork feeding pipe 3 .

[0035] When used specifically, the utility model provides a tunnel-first-station-later ground-underground connecting structure, comprising the following steps:

[0036] S1. Measurement and positioning: according to the layout of the shield tunnel segments 1, the center of the earthwork feed pipe 3 is selected in the middle of the two ring segments 1, and accurate positioning is performed on the ground;

[0037] S2. Calculate the drilling depth, which is the shield tunnel top elevation plus 20cm, and then use it as the drilling depth;

[0038] S3, use a rotary drilling machine to drill a hole, the diameter of the hole is 10cm larger than the diameter of the buried earthwork feeding pipe 3, to ensure that the earthwork feeding pipe 3 can be smoothly lowered into place;

[0039] S4. Use mud to protect the wall during drilling to avoid hole collapse;

[0040] S5. After drilling to the calculated depth, the earthwork feeding pipe 3 is hoisted. The earthwork feeding pipe 3 is hoisted in sections and connected at the opening of the reserved hole 2. The earthwork feeding pipe 3 is hoisted to 10 cm above the bottom of the reserved hole 2;

[0041] S6, after the earthwork feeding pipe 3 is hoisted into place, four grouting pipes 4 are pre-buried around it;

[0042] S7, pour C15 concrete through the grouting pipe 4 to seal the bottom 50 cm of the reserved hole 2, and pour the concrete to a height of 50 cm;

[0043] S8, after the concrete solidifies to form a concrete layer 5, backfill the surroundings of the earthwork feed pipe 3;

[0044] S9. After the concrete strength age reaches the requirement, grouting is performed around the earthwork feeding pipe 3 through the pre-buried grouting pipe 4 to ensure that the soil layer is sealed to avoid air leakage during the excavation process;

[0045] S10, after the shield tunneling passes through the position of the earthwork feeding pipe 3, the position of the buried earthwork feeding pipe 3 is laid out at the position of the pipe segment 1 in the tunnel;

[0046] S11, placing a water pump under the earthwork feeding pipe 3 on the ground to drain the mud in the earthwork feeding pipe 3;

[0047] S12, in the tunnel, a water drill is used to break the shield segment 1 below the earthwork feeding pipe 3. The breaking range of the segment 1 is 5 cm smaller than the diameter of the earthwork feeding pipe 3. After breaking the segment 1, the soil 6 below the earthwork feeding pipe 3 and the bottom concrete are broken to form a connecting hole 7;

[0048] S13. The earthwork after foundation pit excavation falls through the earthwork discharge pipe 3 and the reserved hole 2 to the transport vehicle in the shield tunnel, and the earthwork is transported out using the completed shield tunnel.

Claims

1. A tunnel-first-station-later ground-underground connecting structure, comprising a pipe segment located outside the tunnel and a reserved hole formed by drilling with a rotary drilling machine, characterized in that: It also includes an earthwork feeding pipe and N grouting pipes. The earthwork feeding pipe is located in the reserved hole, and a gap is left between the bottom end of the earthwork feeding pipe and the bottom of the reserved hole. The center of the earthwork feeding pipe corresponds to the middle position of the two ring segments. N grouting pipes are located in the reserved holes and are arranged around the earthwork feeding pipe; After pouring concrete through the grouting pipe, the bottom of the reserved hole is sealed, and a concrete layer is formed after solidification; The bottom end of the earthwork feeding pipe is located in the concrete layer; A connecting hole is provided at a position of the pipe segment corresponding to the earthwork feeding pipe. The connecting hole passes through the soil body and extends to the concrete layer and is connected with the inner cavity of the earthwork feeding pipe, so that the material in the earthwork feeding pipe can fall into the pipe segment through the connecting hole.

2. The tunnel-first-station-later ground-underground connecting structure according to claim 1 is characterized in that: The diameter of the reserved hole is 8-12 cm larger than the diameter of the earthwork feeding pipe.

3. The tunnel-first-station-later ground-underground connecting structure according to claim 1 is characterized in that: There is a gap of 8-12 cm between the bottom end of the earthwork feeding pipe and the bottom of the reserved hole.

4. The tunnel-first-station-later ground-underground connecting structure according to claim 1 is characterized in that: The earthwork feeding pipe is assembled from a plurality of steel pipes.

5. The tunnel-first-station-later ground-underground connecting structure according to claim 1 is characterized in that: The thickness of the concrete layer is 40-60 cm.

6. The tunnel-first-station-later ground-underground connecting structure according to claim 1 is characterized in that: Backfill soil is arranged in the reserved hole, and the backfill soil is located outside the earthwork feeding pipe.