Slurry box structure attached to steel pipe pile

By designing a floating mud box attached to steel pipe piles, it uses the buoyancy of water to carry mud and gravel, the problems of low efficiency and pollution of gravel cleaning in steel pipe piles are solved, and efficient gravel cleaning and environmental protection are achieved. Mud recycling.

CN222083554UActive Publication Date: 2024-11-29ZHEJIANG ROAD & BRIDGE CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420733510.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-10
Publication Date
2024-11-29
Estimated Expiration
2034-04-10

AI Technical Summary

Technical Problem

During the construction of steel pipe piles, when blocks or rocks are encountered, the conventional mud circulation system cannot effectively clean up the gravel, resulting in the accumulation of gravel in the steel pipe piles, affecting the impact efficiency. Moreover, due to the small diameter of the steel pipe piles, the conventional The mud pump cannot be placed, causing the mud mixture to overflow and pollute the environment.

Method used

A circular mud box attached to steel pipe piles was designed. The steel pipe piles were connected to the water surface through a clasp, and the buoyancy of the water was used to carry the weight of mud and gravel. The mixture of mud and gravel flowed directly into the mud through the round hole. In the box, avoid spillage and pollution and realize the recycling of mud.

Benefits of technology

It improves the efficiency of cleaning gravel, avoids mud spills and pollutes the environment, solves the problem of slurry storage and bearing capacity of mud boxes, realizes the recycling of mud, and improves construction efficiency and environmental protection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222083554U_ABST
    Figure CN222083554U_ABST
Patent Text Reader

Abstract

The utility model relates to a slurry box attached to a steel pipe pile, the slurry box is in a circular ring shape and comprises a pair of symmetrically arranged semi-circular ring boxes, the ends, making contact with the steel pipe pile, of the semi-circular ring boxes are provided with hoops attached to the steel pipe pile, and the pair of semi-circular ring boxes are connected through the hoops; a round hole right opposite to the semicircular box is formed in the upper portion of the joint of the steel pipe pile and the semicircular box. According to the actual height of the steel pipe pile exposed out of the water surface, the device can be correspondingly installed at the most appropriate position on the steel pipe pile, the slurry flowing distance is shortened, the rock ballast cleaning efficiency is greatly improved, slurry and rock ballast mixtures in the steel pipe pile directly flow into the slurry box through the round holes, and the situation that the slurry overflows or leaks to pollute the environment is avoided; meanwhile, the slurry injected into the slurry box can be recycled, and waste is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of building construction, and in particular to a mud box attached to a steel pipe pile. Background Art

[0002] Before constructing an underwater bridge, it is often necessary to build a construction trestle and platform with steel pipe piles as the supporting foundation. When the steel pipe piles are driven into the ground, if they encounter boulders or rocks at the bottom, they need to be crushed before they can be driven in. Sinking the steel pipe piles after crushing the rock layer inside the steel pipe piles can greatly improve efficiency and accuracy, but the slag will accumulate inside the steel pipe piles, affecting the impact efficiency.

[0003] The common solution is to use the mud circulation system of the bridge pile foundation drilling hole to clean the slag. First, the mud pipe is extended into the bottom of the steel pipe pile, and then high-pressure mud is transported into the mud pipe to stir the slag at the bottom of the steel pipe pile, so that the mud mixed with the slag is suspended and rises. However, the diameter of the steel pipe pile is small, and the conventional mud pump cannot be placed in the steel pipe pile, resulting in the mud circulation system being unusable. The mixed mud can only overflow from the top of the steel pipe pile and be discharged, polluting the environment. Utility Model Content

[0004] Based on this, it is necessary to provide a mud box attached to the steel pipe pile to overcome the defects mentioned in the above background technology.

[0005] The mud box attached to the steel pipe pile is in the shape of a ring and includes a pair of symmetrically arranged semi-circular ring boxes. The contact ends of the semi-circular ring boxes and the steel pipe piles are provided with clamps that fit the steel pipe piles. The pair of semi-circular ring boxes are connected to each other through the clamps. A circular hole facing the semi-circular ring box is provided above the connection between the steel pipe pile and the semi-circular ring box.

[0006] As a preferred embodiment of the mud box attached to the steel pipe pile in the utility model, the clamp is arranged along the inner ring of the semicircular ring box, and includes a connecting piece and a pull piece. The connecting piece is arc-shaped, and the pull piece is provided with bolt holes. A pair of the pull pieces are arranged on both sides of the connecting piece.

[0007] As a preferred embodiment of the mud box attached to the steel pipe pile in the utility model, the diameter of the circular hole is greater than 0.15m.

[0008] As a preferred embodiment of the mud box attached to the steel pipe pile in the utility model, the distance between the bottom of the circular hole and the top of the semicircular ring box is not less than 0.3m.

[0009] As a preferred embodiment of the mud box attached to the steel pipe pile in the utility model, the semicircular ring box has a cavity opening upward.

[0010] As a preferred embodiment of the mud box attached to the steel pipe pile in the utility model, the bottom of the semicircular ring box is connected to the water surface.

[0011] Beneficial effects of the utility model:

[0012] 1. The utility model can be installed at the most suitable position on the steel pipe pile according to the actual height of the steel pipe pile exposed above the water surface, shortening the mud flow distance and greatly improving the efficiency of cleaning slag.

[0013] 2. The utility model floats on the water surface and ingeniously uses the buoyancy of water to bear most of the weight of mud and slag, thus solving the defects of having nowhere to place the mud box and requiring high bearing capacity. At the same time, the annular structure arranged around the steel pipe piles is evenly stressed.

[0014] 3. The mud and slag mixture of the steel pipe pile in the utility model flows directly into the mud box through the circular hole, thereby preventing mud from overflowing or leaking and polluting the environment. At the same time, the mud injected into the mud box can be recycled without causing waste. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0016] Figure 1 This is one of the structural schematic diagrams when the mud box is connected to the steel pipe pile in the embodiment of the present application;

[0017] Figure 2 This is the second structural schematic diagram of the mud box and the steel pipe pile when they are connected in the embodiment of the present application;

[0018] Figure 3 This is the third structural schematic diagram of the mud box and the steel pipe pile when they are connected in the embodiment of the present application;

[0019] Description of reference numerals:

[0020] 1. Semicircular ring box; 2. Steel pipe pile; 3. Hoop; 31. Connecting piece; 32. Pull piece; 4. Round hole. DETAILED DESCRIPTION

[0021] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present application. However, the present application can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present application, so the present application is not limited by the specific embodiments disclosed below.

[0022] In the description of the present application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0023] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0024] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0025] In the present application, unless otherwise clearly specified and limited, a first feature being “above” or “below” a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being “above”, “above”, and “above” a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being “below”, “below”, and “below” a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0026] It should be noted that when an element is referred to as being "fixed to" or "disposed on" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "upper", "lower", "left", "right" and similar expressions used herein are for illustrative purposes only and are not intended to be the only implementation method.

[0027] Example

[0028] This embodiment provides a mud box attached to a steel pipe pile, such as Figure 1 to Figure 3 As shown, the mud box is in a circular ring shape, which floats on the water surface and its inner ring is connected to the steel pipe pile 2. The mud box includes a pair of symmetrically arranged semi-circular ring boxes 1, and the contact end of the inner ring of the semi-circular ring box 1 and the steel pipe pile 2 is provided with a clamp 3 that fits the steel pipe pile 2. The pair of semi-circular ring boxes 1 are connected to each other through the clamp 3, and a circular hole 4 facing the semi-circular ring box 1 is provided above the connection between the steel pipe pile 2 and the semi-circular ring box 1.

[0029] In this embodiment, the hoop 3 is arranged along the inner ring of the semicircular ring box 1, and includes a connecting piece 31 and a pull piece 32. The connecting piece 31 is arc-shaped, and the pull piece 32 is provided with a bolt hole. A pair of pull pieces 32 are arranged on both sides of the connecting piece 31. A pair of the semicircular ring boxes 1 are connected to each other by bolts passing through the bolt holes. The diameter of the circular cavity formed by the pair of connecting pieces 31 is not greater than the outer diameter of the steel pipe pile 2, so as to better fix the mud box.

[0030] In this embodiment, the diameter of the circular hole 4 is greater than 0.15 m, so that the slag can flow out of the circular hole 4 easily.

[0031] In this embodiment, the distance between the bottom of the circular hole 4 and the top of the semicircular ring box 1 is not less than 0.3m.

[0032] In this embodiment, the semicircular ring box 1 has a cavity opening upward, and a mud pump is arranged in the cavity to transport the mud carrying slag in the mud box to the mud sedimentation tank for recycling after treatment.

[0033] The utility model can be installed at the most suitable position on the steel pipe pile 2 according to the actual height of the steel pipe pile 2 exposed above the water surface, shortening the mud flow distance and greatly improving the efficiency of cleaning slag.

[0034] In the conventional positive circulation mud circulation system, the mud flows out from the end of the steel casing and then flows back to the mud sedimentation tank, or the mud is pumped out and transported to the sedimentation tank by the mud pump in the steel casing. In this embodiment, since the steel pipe pile 2 is longer than the steel casing, the amount of mud flowing out from the end must be huge, and during the long flow process, the slag will inevitably settle into the steel pipe pile 2, affecting the slag removal efficiency. In addition, there is no space for the mud pump to be placed in the steel pipe pile 2 with a smaller diameter than the steel casing. The mud box in this embodiment floats on the water surface, using the buoyancy of water to carry most of the weight of the mud and slag, solving the problem of having nowhere to place the mud box and requiring high bearing capacity. According to the actual height of the steel pipe pile 2 above the water surface, the mud box can be installed at the most suitable position on the steel pipe pile 2 accordingly, shortening the mud flow distance and greatly improving the efficiency of cleaning the slag. The mud and slag mixture in the steel pipe pile 2 flows directly into the mud box through the circular hole to avoid mud overflow or leakage and polluting the environment.

[0035] The utility model floats on the water surface and cleverly uses the buoyancy of water to bear most of the weight of mud and slag, thereby solving the defects of having nowhere to place the mud box and requiring high bearing capacity. At the same time, the annular structure arranged around the steel pipe pile 2 is evenly stressed and there is no risk of overturning.

[0036] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0037] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be construed as limiting the scope of the patent application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent application shall be subject to the attached claims.

Claims

1. A mud box attached to a steel pipe pile, characterized in that: The mud box is in the shape of a ring, and comprises a pair of symmetrically arranged semi-circular ring boxes (1). The contact ends of the semi-circular ring boxes (1) and the steel pipe piles (2) are provided with clamps (3) that fit the steel pipe piles (2). The pair of semi-circular ring boxes (1) are connected to each other through the clamps (3). A circular hole (4) facing the semi-circular ring boxes (1) is provided above the connection between the steel pipe piles (2) and the semi-circular ring boxes (1).

2. The mud box attached to the steel pipe pile according to claim 1, characterized in that: The hoop (3) is arranged along the inner ring of the semicircular ring box (1), and comprises a connecting piece (31) and a pull piece (32). The connecting piece (31) is arc-shaped, and the pull piece (32) is provided with bolt holes. A pair of the pull pieces (32) are arranged on both sides of the connecting piece (31).

3. The mud box attached to the steel pipe pile according to claim 1, characterized in that: The diameter of the circular hole (4) is greater than 0.15 m.

4. The mud box attached to the steel pipe pile according to claim 3, characterized in that: The distance between the bottom of the circular hole (4) and the top of the semicircular ring box (1) is not less than 0.3 m.

5. The mud box attached to the steel pipe pile according to claim 1, characterized in that: The semicircular ring box (1) has a cavity opening upward.

6. The mud box attached to the steel pipe pile according to claim 5, characterized in that: The bottom of the semicircular ring box (1) is connected to the water surface.