Combined bent cap support
By introducing steel pier components into the cover beam bracket, the problem of excessive pier column spacing when the cover beam spans the underground shield double-line interval and insufficient bearing capacity of the clamp is solved, and the safety and utilization rate of the bracket are improved, reducing construction costs.
Patent Information
- Application Number
- CN202420556036.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-21
- Publication Date
- 2025-03-28
- Estimated Expiration
- 2034-03-21
AI Technical Summary
When the cover beam spans the underground shield double-line interval, the distance between the pier columns is too large, resulting in insufficient bearing capacity of the hoop, which cannot meet the requirements of the upper load, and has great limitations.
A combined cover beam bracket is designed, including a steel clamping assembly and a steel pier assembly. The steel clamping assembly is installed on the bridge pier column, and the steel clamping assembly is set at the center between adjacent pier columns to reduce the upper load on the clamps on both sides.
By setting up a steel pier assembly, the upper load borne by the steel clamp assembly is reduced, the safety and utilization rate of the bracket are improved, the construction cost is reduced, and the economic and social benefits are good.