Concrete modular rapid construction cofferdam

CN224858882UActive Publication Date: 2026-10-16NANJING CHANGJIANG WATERWAY ENG BUREAU +1
0 Cites 0 Cited by

Patent Information

Application Number
CN202522522138.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-27
Publication Date
2026-10-16
Estimated Expiration
2035-11-27

AI Technical Summary

Technical Problem

2、 在航道施工阶段,航道水深不满足大型水上机械进场施工条件;

Benefits of technology

本申请通过利用对拉钢筋及水下钢管桩,将预制混凝土构件拼接成适应任意特定地形及水动力场的水下单元框格,在单元格内浇筑水下混凝土形成围堰整体结构,模板免拆除,采用水下分序、分格进行浇筑,极大地避免了使用常规模板水下作业历时长、施工难度大等问题,同时减少单次浇筑量,提高了水下混凝土的施工效率。

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The utility model proposes a kind of concrete modularization rapid construction cofferdam, including prefabricated component, the horizontal position of prefabricated component is fixedly installed with reinforcing bar, the vertical position of prefabricated component is fixedly installed with steel pipe, the inside of two rows prefabricated component is surrounded with concrete pouring area, wherein the inside pouring of concrete pouring area is provided with underwater concrete block, the top pouring of underwater concrete block is provided with overwater concrete block, it is related to concrete cofferdam technical field.The utility model is by using to pull reinforcing bar and underwater steel pipe pile, and prefabricated concrete component is spliced into underwater unit frame suitable for any specific terrain and underwater unit frame of hydrodynamic field, and underwater concrete is formed cofferdam overall structure in cell, formwork is exempted from demolition, and it is poured using underwater sequence, and it greatly avoids the problem, such as long duration, great construction difficulty of using conventional formwork underwater operation, while reducing single pouring amount, improve the construction efficiency of underwater concrete.
Need to check novelty before this filing date? Find Prior Art