A construction method of cylindrical coal shed net shell vertical gable starting with a transfer station crossing a hole

By dividing the vertical gable wall into six starting units, using double-layer guy ropes for layered anchoring, and employing auxiliary lifting equipment for temporary load-bearing closure, the construction difficulties caused by the top transfer station passing through the opening in a large-span bolted spherical reticulated shell structure were solved. This approach shortened the construction cycle, improved safety, and enhanced installation accuracy. It is suitable for columnar coal shed reticulated shells with transfer stations passing through openings and other large-span incomplete reticulated shell structures.

CN122406869APending Publication Date: 2026-07-17MCC (SHANGHAI) STEEL STRUCTURE TECHNOLOGY CORP LTD
View PDF 4 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
MCC (SHANGHAI) STEEL STRUCTURE TECHNOLOGY CORP LTD
Filing Date
2026-05-27
Publication Date
2026-07-17

AI Technical Summary

Technical Problem

Existing technologies cannot effectively address the problems of structural discontinuity, long construction period, unstable hoisting, weak wind resistance, and low installation accuracy caused by the top transfer station crossing the opening, especially in the initial construction of the gable wall of a large-span bolted spherical shell structure.

Method used

The method employs a six-section vertical gable wall starting unit, with different attitudes for hoisting, double-layer guy ropes for layered anchoring, temporary support and closure of auxiliary hoisting equipment, and full-process precision control. This includes steps such as dividing the construction area with the structural expansion joint as the boundary, dividing the vertical gable wall starting unit into six sections and hoisting it with different attitudes, double-layer guy ropes for layered anchoring, temporary support and closure of auxiliary hoisting equipment, and deflection monitoring.

Benefits of technology

It significantly shortens the construction period, improves hoisting safety and structural stability, enhances wind resistance and installation accuracy, and is suitable for columnar coal shed reticulated shells with transfer stations passing through the openings on the top, as well as other large-span incomplete reticulated shell structures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN122406869A_ABST
    Figure CN122406869A_ABST
Patent Text Reader

Abstract

本发明公开了一种带转运站穿越洞口的柱面煤棚网壳垂直山墙起步施工方法,解决现有技术无法应对顶部洞口区域结构不连续、施工周期长、吊装风险高的问题。该方法包括:以伸缩缝为界划分两个施工区从两端山墙同步施工;将山墙起步单元划分为六个分块,前五个分块地面拼装后吊装,第六分块高空散装,翻身与正式吊装分姿态验算并设倒链及安全备用钢丝绳;设置双层缆风绳分层锚固,第一层内侧绑扎于第2球节点、外侧绑扎于第3球节点,第二层内侧绑扎于第4球节点、外侧绑扎于第5球节点,采用活动锚碇配重;逐层高空散装;在洞口区域经有限元分析确定吊点位置,用辅助起重设备持力合拢;成型后监测挠度。
Need to check novelty before this filing date? Find Prior Art

Citation Information

Patent Citations

  • Transfer station across the original coal transport trestle and construction method

    CN110255208B

  • A method for installing a curved steel grid shell structure with a gradually changing gable span.

    CN111809893B

  • Construction method of large-span columnar bolt-sphere joint grid

    CN114164934A

  • Large-span bolt-sphere net rack gable wall mounting method

    CN116065836A